Professional Documents
Culture Documents
Case Study - BCD Construction Company
Case Study - BCD Construction Company
In partial fulfillment
of the course
Quantitative Methods for Decision Making
In MSC530M
Submitted by:
Submitted to:
Dr. Enrico Cordoba
March 7, 2020
I. Background
1
BCD Construction Company is a relatively small entity which earns mostly from local
job contracts. Management agreed to send a proposal to construct a mile-long extension to the
central sewage network in a rural town that used septic tanks to this day. This project is
considered crucially important for many, as anyone who wins this offer will have an advantage
in securing a P100 million contract that will be given by the city later in the year. Taking the
project’s importance into consideration, BCD project managers are tasked to make decisions to
In accordance with common practices of construction firms in the area, BCD employs
people from union pools. There is a good possibility that the local Excavators Union would go
on a strike on the start date of the project which could adversely impact its profitability. There
was an agreement at a project management conference to use the possibility of such a strike for
contingency purposes at 80 per cent. If a strike does occur, direct costs would stay unchanged,
because the problem concerned was not that of wages; however, indirect costs would rise in
What recommendation should the project manager make regarding the number of shifts
to be employed and the exact bid amount for the sewerage project?
A. To determine the optimal number of shifts that would result in the lowest cost for the
project, which, in turn, would yield a competitive bid for BCD Construction Company.
municipal government.
2
IV. Areas of Consideration and Methodology
A. Point of View
The group will take the point of view of the BCD Construction Company’s
B. Methodology
The group utilized Program Evaluation Review Technique / Critical Path Method
(PERT/CPM) to compute for the total project days/completion date and total project
costs.
Annex 1 shows the time and cost estimates of BCD’s engineers for the project.
V. Analysis
The trunk sewer extension is to be laid in a tunnel for 1/3 its length; the remaining 2/3 is
to be constructed in trenches. To build the tunnel, a primary shaft must be excavated first, then
the secondary shafts can be driven and the tunnel can be dug simultaneously. The trench is to be
started at the same time as the primary shaft. Another crew of workers follows the trench
workers, laying pipes, pouring concrete, and refilling trenches as far as they have been
excavated. The excavators lose no time as a result of this follow up. A third group would be
3
performing a similar function in the tunnel. Based on the above, we came up with the precedence
table below:
Based on our analysis, the group has determined the critical path as A - D - G - I - F - K -
L regardless of the number of shifts to be selected. The critical path is illustrated as follows:
(Please see Annex 2 for the detailed analysis per number of shifts):
4
Below is the estimated total number of working days per shift based on the identified critical
path:
No. of days
Activity Description
One Shift Two Shifts Three Shifts
A Move in machinery/equipment 12 6 4
G Pipe-laying in trenches 50 25 17
K Landscape 10 8 6
L Move out 6 3 2
C. Project Costing
5
One Shift Two Shifts Three Shifts
ACTIVITY
Days Cost (P) Days Cost (P) Days Cost (P)
A Move in machinery/equipment 12 3,000 6 3,300 4 3,600
B Excavate primary shaft 12 6,950 12 6,950 12 6,950
C Excavate secondary shafts 60 6,250 24 6,600 12 6,950
D Excavate trenches 300 33,700 150 42,500 100 44,700
E Excavate tunnel 305 36,150 155 39,100 105 40,000
F Backfill (trenches only) 50 1,000 25 1,500 17 2,000
G Pipe-laying in trenches 50 7,500 25 8,200 17 8,900
H Pipe-laying in tunnel 46 5,500 25 5,700 16 6,000
I Pour concrete in trenches 70 11,400 35 11,650 25 11,850
J Pour concrete in tunnel 60 11,000 30 11,250 20 11,500
K Landscape 10 2,000 8 2,900 6 3,000
L Move out 6 500 3 750 2 1,000
Total Direct Cost 124,950 140,400 146,450
Since there is a strong chance that the local Excavators Union will strike on the project’s
inception date, we also computed for the additional indirect costs during strike days. See below
6
Length of Strike Days with
Probability
(Days) Strike
20 25% 5
30 25% 7.5
40 50% 20
Total 32.5
80% Consensus Rate 26 Days
Per the project estimates, general and administrative costs are 40% of the sum of
direct and indirect costs. See below for the detailed computation:
7
Indirect Costs 69,720 40,320 30,780
Strike Costs 3,640 4,160 4,680
Total Costs 198,310 184,880 181,910
G&A Percentage 40% 40% 40%
Total G&A 79,324 73,952 72,764
To determine the exact bid to be submitted to the municipal government, we will evaluate
the following ACAs which considers the high chance that a strike will happen:
8
One Shift Two Shifts Three Shifts
Direct Costs 124,950 140,400 146,450
Indirect Costs 73,360 44,480 35,460
G&A Expenses 79,324 73,952 72,764
Total Costs 277,634 258,832 254,674
Target Margin (10% of cost) 27,763 25,883 25,467
Bid Price 305,397.40 284,715.20 280,141.40
Estimated No. of Days to
498 252 171
Complete
a. Decision Criteria
Decision criteria are the items which BCD Company should view as important to
determine the exact bid to be submitted to the municipal government. The following criteria
1. Total project cost considering the high percentage that a strike will occur (25%)
3. Project Length - Total estimated number of days to complete the project (25%)
Project Cost
25% 12.50% 25% 25%
Higher than the average of all three ACAs - 12.5%
Lower - 25%
Bid Price
25% 12.50% 25% 25%
9
Higher than the average of all three ACAs - 12.5%
Lower - 25%
Project Length
The third ACA (Three shifts) gained the highest score, and is, therefore, the recommendation of
the group.
After carefully understanding and analyzing the case of BCD Construction Company, the
group concludes that the third alternative course of action would be the overall best way to
implement this project. Consequently, the group also concluded that the exact bid price to be
submitted is Php 280,141.40. The group employed the PERT CPM model and found that,
regardless of the number of shifts selected, the critical path of the project is A - D - G - I - F -
K - L. From the critical path, the group determined that it would take 498, 252, and 171 days to
complete the project through employing one, two and three shifts, respectively. Subsequently,
the group was able to derive the the total costs of the different work shift alternatives by
considering direct costs, indirect costs, general administrative and strike costs. The three shift
alternative resulted in the lowest cost at Php 254,674. Lastly, the group was able to select the
best alternative course of action with the help of a decision criteria that takes into account the
total cost, projected bid price, project length and profit. The third alternative emerged as the
overall best.
10
Given these points, the group, being the assigned project manager of this crucial project,
recommend the management of BCD company to submit an exact bid of Php 280,141.40 to the
prospective municipal client. The project manager also recommends employing a three shift
schedule, should the company win and bag the said project.
Annex 1
11
Annex 2
12
One Shift
Two Shifts
Three Shifts
13
14