Welding Procedure For Steel Structure Welding
Welding Procedure For Steel Structure Welding
Page 1 of 6
2. Full Penetration Welding of 30mm thick flange
30 30 30 30
mm mm mm mm
3-4 mm
30 mm
Doubler
L=14mm
Plate
(Leg
Length)
30 mm
Flange
Page 2 of 6
4. Full Penetration Welding of 30mm Base Plate to 30mm Flange
L=8mm
40 40
40 40
mm mm
mm mm
R= 2-4mm
Page 3 of 6
Welding Parameters (Welding Position 1G/4G):
Pass/Layer Size of filler Current Voltage Current Polarity Travel speed
material (A) (V) (mm/min)
Root 1.2mm 140-180 25-28 DC+ve 80-120
Filling 1.2mm 160-240 26-29 DC+ve 120-200
Capping 1.2mm 160-240 26-29 DC+ve 140-200
Back gouge from other side up to the sound metal & then complete the capping.
Capping 1.2mm 160-240 26-29 DC+ve 140-200
L=10mm
20 mm 20mm
Page 4 of 6
7. 30mm flange full penetration welding (Column to Beam Welding)
L= 6mm
F=2-3 mm
7mm
15mm
15mm
30mm 30mm
Page 5 of 6
Welding Parameters (Welding Position 3G/3F):
Pass/Layer Size of filler Current Voltage Current Polarity Travel speed
material (A) (V) (mm/min)
Root 1.2mm 140-180 25-28 DC+ve 80-120
Filling 1.2mm 160-220 26-29 DC+ve 120-200
Capping 1.2mm 160-220 26-29 DC+ve 140-200
Back gouge from other side up to the sound metal & then complete the capping.
Filling 1.2mm 160-220 26-29 DC+ve 120-200
Capping 1.2mm 160-220 26-29 DC+ve 140-200
Page 6 of 6