Professional Documents
Culture Documents
Master Technical File and QAWP Catagory 4 - 4 1-4 2
Master Technical File and QAWP Catagory 4 - 4 1-4 2
4.1 4.1.4 It is never too late to start a master technical file with an historical record section
4.1 4.1.5 The master technical file may be hard copy and/or digital
4.1 4.1.6 All master technical files require an historical record section to use for reference when
planning for the upcoming shutdown work packages
4.1 4.1.7 All shutdown final master work packages should be able to be developed from
information contained in a master technical file with an historical records section
4.1 4.1.8 For master technical files without historical records such as plant facility’s first shutdown,
the number of work package planning labour hours is extensive, however, the historical
record section retains the value of this labour expended
4.1 4.1.10 The master technical file should contain any drawing changes, including copies of the up-
to-date drawings, as well as a copies of the original drawings, complete with As-Builts
and any engineering variances
4.1 4.1.11 The master technical file should contain all of the manufacturer’s specifications, original
manufacturer’s record book (MRB) including original inspection reports, and a copy of
the original operation, service and start up documentation
4.1 4.1.12 Name plate rubbings should be added to the master technical file where applicable
4.1 4.1.13 When ordering new plant assets, the contract order should include a full inspection set
of reports, such as wall thickness, opening measurements on tubes, dimensions, weights
etc. and be included in the master technical file
4.1 4.1.14 All fabrications, material components, etc. should be photographed after they are off-
loaded on the plant site and approved by Quality Assurance/ Engineering and those
pictures kept in the master technical file
4.1 4.1.15 Third party inspection reports, including digital pictures, should indicate if the
manufacture or fabrication is to the Engineering drawings, scope and specifications
4.1 4.1.16 All master technical files should contain a complete bill of materials and any upgrades
4.1 4.1.17 Master technical files for piping systems should contain a complete set of piping
isometrics plus the fabrication cut sheets
4.1 4.1.18 Many plants are using a ‘TML’ drawing (thickness measurement drawing)
4.1 4.1.19 The master technical file should retain all historical shutdown master work packages and
in many cases the sub work packages given to the contractors
This next section will deal with what should be in a shutdown master work package
historical record
4.1 4.1.22 The master work package should contain the following for file administration:
4.1 4.1.22.1 Engineering file number
4.1 4.1.22.2 Equipment or tag number
4.1 4.1.22.3 Work order number
4.1 4.1.22.4 Work breakdown structure
4.1 4.1.22.5 Organizational breakdown structure
4.1 4.1.22.6 Cost control and activity code identifier list
4.1 4.1.22.7 Cost control tracking and reporting documentation forms
4.1 4.1.22.8 Copies of purchase orders
4.1 4.1.22.9 Copy of relevant section of shutdown Master Execution Schedule
4.1 4.1.22.10 Original schedule estimate with task duration and activity resource loading per shift
4.1 4.1.23.16 Procurement – required paper work at time of delivery i.e. MTR’s, MRB
4.1 4.1.23.17 Procurement – specific material identification needs i.e. vessel number, name
4.1 4.1.23.18 Installation: Code requirements are activities that need to be scheduled and budgeted
for, and should be filed by name only as actual information will be found in QA files
which may or may not be part of this master technical file, such as heat treating, non
destructive examination reports, pressure tests, jurisdictional witness and reporting
requirements
4.1 4.1.23.19 Copies of special safety work permits such as confined space, number of safety watches,
special equipment, special precautions – x-ray no other work is allowed in immediate
area, fire hydrant, road closure
4.1 4.1.23.20 Temporary utility requirements such as plant air, water, power, nitrogen, instrument air
4.1 4.1.26.6 Actual cost of the work package plus any definable variances
Estimated Actual
Task Required Person Completion Completion
Yes/No Responsible Date Date
Additional Comments
4.2 4.2.5 Has a general work description been written by Engineering and/or Quality Assurance
4.2 4.2.6 Has the work scope been conveyed to the shutdown planner
4.2 4.2.7 Has the shutdown planner developed the initial Quick Action Work Package, complete
with a budget and schedule for the task and activities, to present to the turnaround team
at the predetermined quick action meeting
4.2 4.2.8 Have all turnaround team members reviewed the Quick Action Work Package
4.2 4.2.9 Has the turnaround team and a senior management representative agreed on the Quick
Action Work Package, work scope, work procedure, safety and quality assurance
requirements, budget and schedule
4.2 4.2.10 Are there budget funds available (contingency) or does the turnaround team senior
manager have to secure them before work can start
4.2 4.2.11 Has the accepted Quick Action Work Package been sent to the shutdown planner to
develop the bill of materials and sub work packages to the contractor
4.2 4.2.12 Has the shutdown scheduler a copy of the Quick Action Work Package to update the
shutdown master execution schedule
4.2 4.2.13 Has the cost control budget been updated with the found work
Additional Comments
Task Required Person Responsible Estimated Actual
Yes/No Completion Date Completion Date