Weekly Working Report

Assigned Section: Export


Date: 16/11/2020 to 21/11/2020
Prepared by: Shayan Ahmed Raghib

Sr.
Task Description Details Section Status
#
Various ideas and targets Discussions were carried out.
Analysis of Export were discussed with Rustam Further working on (i) Press Shop
Export
Production with Sb. to increase and capacity (ii) Export Line Station
1. Assembly +
respect to Prior and streamline export wise capacity (iii) Human
Press Shop
Subsequent Sections production. Press Shop Resources reqd. for production
output will be analyzed. increase

Assembly lines processes


Analysis of assembly were observed, discussed
2. Assembly Assembly Report completed.
line working. and improvement
suggestions were reported.

Fin Machine and Tube Machine


instructions compiled and
Work Instructions of all
Compilation and discussed with
process on the production
3. Display of Work Overall operators/supervisors. Will
floor are to be written and
Instructions submit for review after all
displayed.
feeding section processes are
done.

Monitoring and recording


Introduction of OEE
system of KPIs that highlight Report Completed and Shared
4. based KPIs for Overall
runtime, performance and with respective personnel.
production
quality.

Time can be saved if fin


dressing comb length is Sample provided to operator.
Increasing size of fin
5. increased. Samples of this Process Hall Currently making time study
dressing combs
are to be made. To perform report to highlight results.
trials and test.
Feasibility of adding a drain
Adding drain hole/pipe Discussed with maintenance, will
valve or hole to the
6. to the chemical Process Hall be applied when FPR (repair) will
chemical application was
application tanks be done next time
investigated.

New quality reports for


Press Shop Report being used.
7. Quality Reports rework, scrap and press Overall
Press Shop scrap report provided.
shop.

Use of register for the


After implementation on trial
approval of size and A proper register for this
basis, proper implementation will
dimensions by Quality purpose will provide better
8. Feeding start from next month. New
Inspector, instead of record keeping than small
register will be provided through
the piece of paper pieces of paper.
LPR.
currently used.