Professional Documents
Culture Documents
Bushing Present Load On Aux. Transformer-4:450 KW To 500 KW Present Load On Aux. Transformer-4:120 KW To 150 KW
Bushing Present Load On Aux. Transformer-4:450 KW To 500 KW Present Load On Aux. Transformer-4:120 KW To 150 KW
Objective-We planned to take shutdown of Aux. Transformer-4 to attend the oil leakage of LT
bushing
Present load on Aux. Transformer-4:450 KW to 500 KW
Present load on Aux. Transformer-4:120 KW to 150 KW
Risk involved:
1. Tripping of 25 MW STG, in case of tripping of Aux transformer-5.
2. Breaking of porcelain bushing while tightening
Mitigation Plan:
1. Checking the healthiness of Tr 5 before changeover ( check list available with electrical team).
2. OEG senior team will monitor the performance of TR 5 during the activity.
3. In worst case if 25MW TG is tripped, senior Operation team will be available to save 30MW
Turbine.( SOP available in control room).
4. Proper precaution will be taken while tightening the bush.
Personnel responsible for above activities:
1. Mr. R. Krishnamurthy
2. Mr. Bimal Upadhyay
3. Mr. Vikas Bhandare
4. Mr. Santosh Prushty