JABAL OMAR DEVELOPMENT PROJECT


Hill International

Received By Recipient Date


Copy Distribution
0 Jabal Omar Development Co ~ Hill International 0

- -------------------------------------------------
- - - - - - · - - - - -------·-· -------------···

IIIII
Hill International JABAL OMAR DEVELOPMENT PROJECT

TITLE: ULMA System for Slabs SUBMmAL NO: 883-4-Z04-W04Z -C-CN12-RCC-SBT-C0-0111


TO: EHAF Consulting Engineers REV. NO.: 01
FROM: Ruwad Civil Construction (RCC) DATE: 26 Aug-2014
ATTN: Mr. Ahmed Atta (CRE) ORIG. REF::-

D PQD - Pre-Qualification
D SDS - Shop Drawing Schedule D SMP -Samples D OMM - Operating & Maintenance Manuals
D SCE - Program I Schedule [gl SHD - Shop Drawings D QPP - Quality Plans & Procedures -
D ITP -Inspection & Test Plan D MUP - Mock Ups & QC Panels D INC - Insurance Certificates
[gJ MST - Method Statement D TST - Test reports D PBW - Bonds, Guarantees, Warranties
D MPD- Product & Materials Data D ABO - As Built Drawings
[gl OTH -Others- Calculations

[gl C-Civil D S-Structural D A-Architectural D E-Eiectrical OM-Mechanical D G-General D a-Coordination


D !-Interior Design D T-Sections D U-Urban I Master Planning
ULMA System for Slabs (Method Statement, Calculations & Drawings) Rev-01

~ A-Approval D R-Review & Comments D Q-As Requested D !-Information I Records Only D N-Action D 0-0thers

Engr. Nabil Abdul Samad


Submitted By Contractor's Rep.: (Sr. Construction Manager) Signature:

Name: Signature:
------------------- Date: ----------

'-
Name: Signature:
-------------------- Date: ----------
D A-Approved D 8 -Approved As Noted, Work May D C- Approved With Comments, D D- Rejected D N-Noted
. Proceed - Incorporate Comments Work May Not Proceed,
& Resubmit Within ...... Days Revise-& Resubmit
D R-Reviewed As Compliant D S- Reviewed As Noted, lncorp. Comments D T- Reviewed With Comments, Revise I Resubmit

For & On behalf


Name: Signature: Date:

Page 1 of 1 Doc./Form No: PSA-883-PP-02-06-FM Rev.2