ECM366

`SUBJECT : CIVIL ENGINEERING QUANTITIES & ESTIMATION

COURSE CODE : ECM366

ASSIGNMENT : 2 (CHAPTER 4)

ESTIMATION
Learning outcome:
At the end of this session, students should be able to:
 Show cost estimation using appropriate technique and engineering tools with an awareness of
limitation (CO2PO5)

Guideline:
Students may go to the field experience during the Week Without Walls (WWW) as implemented by
HEA from 7th to 11th May 2018.

Synopsis:
This assignment is to test student’s abilities in estimation for brick walls and tiles works only. Students
are required to work in groups to carry out the task given. The time given for this assignment is only 1
week from the date of assignment instruction.

Topic: Estimation

1. Estimating of Brick Works


2. Estimating of Tiling Works

Instruction:
The students required to visit the site (location is based on the opinion given by the respective Lecturer)
and each group needs to measure the area of the location given. The students required to provide a
figure/drawings of walls & tiles and use the appropriate elevation to indicates the size of area where
needed to show clearly dimension in millimetres (mm). Estimates the overall costs for the works based
on the price rate given in Appendix.

Deadline:
Students should submit in the hardcopy report latest before 11 MAY 2018 (Friday) 5.00pm

Format:
Hardcopy report using Microsoft Words and maximum is 10 pages. Please records (picture or video)
during the activities as evidence of the attendance and should be attached in the report.

Marks Distribution –10% (CO2PO5)


ECM366

Appendix

Assumption:

 Assume the wall as a half brickwall.


 Expected duration for the tiling works will be 2 days
 Tile with 20mm thick of cement
 Allow 15% profit for both works

DATA:

1) Cost of Mixer:
Mini Concrete Mixer = RM4500
Interest rate = 10% per annum
Life Span = 3 years
Output per day = 15 m3
2) Mixer Operator, Skilled = RM 70 / day
3) Mixer Operator, Semiskilled = RM 56 / day
4) Bricklayer, Skilled = RM 97.45 / day
5) Bricklayer, Semiskilled = RM 75.60 / day
6) Tiler, Skilled = RM 101.70 / day
7) Tiler, Unskilled = RM 65 / day
8) Diesel = RM2.4 / liter
9) Lubricating oil = RM10 / liter
10) Ordinary Portland Cement, 50 kg = RM 16 / bag
11) Normal Mining Sand = RM 33 / m3
12) Plain Homogeneous Floor Tiles
Std Light colour, Grade 1
(300 mm x 300 mm x 8 mm) = RM 2.75 / pc
13) Common Clay Brick = RM 0.40 / pc