Professional Documents
Culture Documents
Reach 1 - Variations 26.03.2020
Reach 1 - Variations 26.03.2020
Revised Cost as
OLD APPROVAL REFERENCE Already approved Excess Savings Remarks
proposed now
Variations/Extra Items
B Additional cost due to variations
Administrativily approved cost for sub-structure due to aditional NHAI Loading (1st
1
Variation proposal)
NMRCL/CPM-R1/VIA/NCC/CORRES/1/1882 503,200,000.00 503,200,000.00
3a Vartion on account of Rahate colony station BOQ (1st Variation proposal) NMRCL/CPM-R1/VIA/NCC/CORRES/1/1882 111,164,074.00 114,114,545.31 2,950,471.31
Vartion on account of Congress Nagar station concourse loading (1st Variation
3b
proposal)
NMRCL/CPM-R1/VIA/NCC/CORRES/1/1882 120,136,780.00 124,928,408.46 4,791,628.46
6 Compound Wall in Jail Area (1st Variation proposal) NMRCL/CPM-R1/VIA/NCC/CORRES/1/1882 64,047,493.00 64,047,493.00
7 RCC work in Medians (1st Variation proposal) NMRCL/CPM-R1/VIA/NCC/CORRES/1/1882 73,099,370.00 78,326,896.26 5,227,526.26
8 VVIP Road (1st Variation proposal) NMRCL/CPM-R1/VIA/NCC/CORRES/1/1882 13,085,173.00 10,292,619.86 2,792,553.14
9 Jail Road (1st Variation proposal) NMRCL/CPM-R1/VIA/NCC/CORRES/1/1882 84,204,943.00 117,176,429.17 32,971,486.17
Rehabilitation of 02 Nos of structures falling in the Jail Road alignment (1st
10
Variation proposal)
NMRCL/CPM-R1/VIA/NCC/CORRES/1/1882 4,637,845.00 4,637,845.00
11 Extra Spans (Pocket Track) P151-PJ1(Superstructure) NMRCL/CPM-R1/VIA/NCC/CORRES/1/1882 14,635,827.00 14,965,757.66 329,930.66
12 Reflective Light Extra quantity NMRCL/CPM-R1/VIA/NCC/CORRES/1/1882 1,013,637.00 1,013,637.00
13 Additional expenditure incurred in Survey and Soil Investigation NMRCL/CPM-R1/VIA/NCC/CORRES/1/1882 6,297,867.00 6,297,867.00
14 Aditional aveage depth of pile in Jail Area over and above the linear variation cost NMRCL/CPM-R1/VIA/NCC/CORRES/1/1882 31,863,602.00 31,863,602.00
15 Additional steel and Concrete for OHE Mast foundations at extra locations NMRCL/CPM-R1/VIA/NCC/CORRES/1/1882 22,256,151.00 22,256,151.00
20 HILTI make OHE Holding Down Bolts (2nd Variation proposal) NMRCL/CPM-R1/VIA/NCC/CORRES/1/1945 3,358,656.00 3,358,656.00
Approval for NS item proposal of Stainless Steel Hand Railing to M/s NCC Ltd.
21
(3rd Variation proposal)
NMRCL/CPM-R1/VIA/NCC/CORRES/1/1969 91,828,598.00 102,163,600.00 10,335,002.00
Current variation due to increse in scope of items of work like additional
22 concrete,steel,HT strands .holding down bolts,Paitings etc,due to introduction of NMRCL/CPM-R1/VIA/NCC/CORRES/1/2170 29,551,597.00 27,270,913.03 2,280,683.97
FOB Loadings at Sitabuldi (4th Variation proposal)
Extra implication of Design fees (Nalla span) and on Extra items rates adopted in NCCL/NAGPUR/METRO-R1/2018-2019/1019 and
23
Reach 1 (5th Variation proposal) NCCL/NAGPUR/METRO-R1/2018-2019/1228
7,225,161.00 7,225,161.00
Proposed now.
Administrative approval
24 LINK BRIDGE VS NORMAL NHAI PIER ARM 9,702,160 9,702,160 placed at SN/…
Proposed now.
Administrative approval
25 Extra items on account of Balance work of stations 70,474,975 70,474,975 placed at SN/…
Extra items on account of composite girder fabrication and installation in Congress PD GC note no: GC/NMRP/PDO/CON/EDR/2019/3478 dated:
26
Nagar station (6th variation proposal) 03.08.2019
100,779,375.00 104,810,550.00 4,031,175.00
Proposed now.
28 Ajni Station stressing works 2,697,606.70 2,697,607 Administrative approval
placed at SN/…
CLAIMS APPROVED
APPROVAL FOR CLAIM OF EXTRA QUANTITIES OF CONCRETE AND NMRCL letter No: NMRCL/ED/Proc/NCC/Reach
30
REINFORCEMENT INCURRED DUE TO INCREASE IN RSI VALUE 1/Claims/2019/1478 dated: 31.07.2019
74,497,500 74,497,500
Claim for NHAI pier arm staging 4 sets procurred for use in Ujwal nagar,
33 Jayaprakash nagar, Chatrapathi station as pier cap is combined with pier arm, as - -
insisted by client for only 1 Use.
Claim for Metro Pier arm staging extra 4 sets procurred for use at Rahate colony ,
34
congress nagar as insisted by client for only 1 use.
- -
Claim of extra staging for facilitating college entry at Congress nagar CN-7 by
35
providing add / support columns & beams.
- -
Claim for pier cap staging at Nallah span P-42-P-43 as the size of pier caps are
36
different.
- -
NMRCL letter No: NMRCL/ED/Proc/NCC/Reach
1/Claims/2019/1631/15823 dated: 28.08.2019
APPROVAL FOR CLAIM TOWARDS SUPERSTRUCTURE ERECTION BY GLS
37
IN JAIL AREA
28,464,200 28,464,200
Claim towards providing additional LG system for Double Decker for Metro Spans
39
From P62 to P78
- -
Variation claim towards 10 sample location drawing and design comparision with NMRCL/ED/Proc/NCC/Reach-1/Claims.2020/87 dated:
43
NHAI loading and Without NHAI loading 27.01.2020
28,463,361 28,463,361
NMRCL/CPM-R1/VIA/NCC/CORRES/1/2170,
4 Quantity variation for ramjhula Section Reach-4
NMRP/CPM/R4/RJ/VARIATION/2018/0341
-10,044,212.00 -10,044,212.00
Total amount of viaduct contract including approved extra items(A+B+C) 5,015,985,429 5,165,306,410 154,394,218 5,073,237
SUBSTRUCTURE
Providing and installing cast-in-situ vertical bored piles of required depth as
per approved GFC drawings of 1200mm dia. with M35 grade Design Mix
Cement Concrete using 20mm graded crushed stone aggregate using PPC/
PSC grade 53 cement including extra cement in all soil strata including
boulders and kankar and soft rock/ weathered rock as per TS. The cost shall
also include the cost of empty boring with MS temporary liner as per site
requirement. The cost shall also include built up of pile up to the required
level (Measurement shall be from theortical cut-off level to founding Toe
level) as per drg. The rate includes all operations required for installation of
1 pile such as installation of rig, shifting of hydraulic rig, construction of
approach temporary road/ bridge for piling rig etc. Any reason for idling of
rig will not be payable. The item includes disposal of earth, muck, slush
released from piles, top cut portion of pile at dumping ground for all leads.
Rate shall include cost of using required dosage of admixture in concrete
for obtaining required workability as per approval of engineer in charge.
Drilling shall be done by use of hydraulic rig using temporary casing of
required depth (min. of 4.5 mtr). Polymer slurry to be used and as directed
by the Engineer. (Use of Bentonite slurry is not permitted). Reinforcement
will be paid seperately. Rate shall also include cost of polymer to be used
for stabilisation of bore.
i) For 1200mm dia Pile RMT 255.502 82.366 15110.18 3860681 1244565 -2616116
Excavation below ground level in all strata upto 2 m except in hard rock for
2 pilecap including disposal of material and including dewatering if CUM 304.301 304.301 459.51 139829 139829 0
necessary.
Providing M 15/20 concrete for Minimum 100mm thick PCC below pile
cap, open foundation slabs and ramp foundations extending 100mm all
3 around beyond pile cap, open foundation slabs. Rate shall include cost of CUM 10.570 11.746 7271.29 76859 85409 8550
using required dosage of admixture in concrete for obtaining required
workability as per approval of Engineer.
Providing and laying M40/20 grade concrete for pile cap using 20mm
4 downgrade metal including necessary shuttering, centering, compaction by CUM 188.946 204.466 9127.31 1724569 1866225 141656
vibrating, curing etc. In all respects. (Excluding reinforcement)
6 Backfilling foundation trenches with granular material. CUM 101.045 101.045 128.08 12942 12942 0
Page 2 of 46
P207 to P213 BOQ (Due to FOB)
Providing and applying epoxy based paint of approved colour and shade to
exterior surface in two or more coats including scaffolding preparing the
surface to receive paint etc.Complete. Rate includes preparation of surface,
8 application of one or more coats of primer as per manufacture's SQM 691.839 600.480 407.03 281601 244415 -37186
recommandation
10 Extra for using HDPE sheathing pipe instead of CRCA sheating pipes RMT 419.836 419.836 84.70 35560 35560 0
12 Providing and Fixing of J Bolt, Bearing plate & Base Plate as per the 0
followig inventory
a 32mm x 850mm L bolt with two nut each 416.000 384 1050.053 436822 403220 -33602
b 600mm x 475mm x 25mm Base plate each 52.000 48 7175.138 373107 344407 -28701
c 600mm x 475mm x 25mm Outer plate each 52.000 48 7175.138 373107 344407 -28701
d Consumables like welding rod, welding machine, binding wire, etc pier 7.000 6 3380.10 23661 20281 -3380
e Labour for installation pier 7.000 6 17238.50 120670 103431 -17239
Total Payable Amount 29,551,897 27,270,913 (2,280,984)
Page 3 of 46
VARIATION STATEMENT ON ACCOUNT OF TRAFFIC MARSHALLS
Name of the work : Design and construction of viaduct in Reach-1 between new airport and sitabuldi stations from CH6790 to CH14400 including viaduct in five Elevated station portion also,
on NORTH - SOUTH Corridor of Nagpur Metro Rail Project
Contractor : M/s NCC Limited
Work Order No: NMRCL/CIVIL(D&B)/02/2015/4006 Dated: 28/11/2015
Variation
SR. As per Contract Already Approved Anticipated Now
ITEM NO Descrption of Item Unit W.R.T Saving Excess Remarks
NO SCHEDULE – B-1 Quantity Rate (Rs). Amount (Rs) Quantity Rate (Rs). Amount (Rs) Quantity Amount (Rs)
individual
MISCELLANEOUS ITEMS FOR WORKS NOT
INCLUDED IN LUMP-SUM COMPONENT (Non-DSR
ITEMS) There is an
I. MISC WORKS OF excess of Rs.
BARRICADING & TRAFFIC 54.35 lakhs
MANANGEMENT WORKS with respect to
the earlier
Deployment of adequate
approved
manpower for 8 hrs. shift for
quantities as
day and night management of
the stipulated
traffic in intersections,
duration of
roadway influenced by
3 work has got
contractor and traffic
extended.
diversions at various levels.
8 3(a) In- Charge Shift 2000.00 566.24 1132477.20 6615.37 566.24 3745877.85 7021.00 3975561.21 351.05 3745877.85
9 3(b) Supervisor Shift 6000.00 534.78 3208685.40 14007.37 534.78 7490873.94 14430.00 7716888.39 240.50 7490873.94
Traffic Guards
10 3(c) Shift 50000.00 511.48 25573945.00 208619.88 511.48 106704666.74 229005.00 117131225.49 458.01 106704666.74
1 Supplying, Fabrication and fixing of SS Hand meter 13932 15500 6591.2 91828598.4 102163600
Railing made up of 38mm outer diameter SS 304
pipe with 1.6mm thickness in combination of
16mm outer dia as per approved pattern shown
in the drawings (Sheet 1 to 6). Size of each railing
shall be 3m wide and 0.7m high. Weight of each
Art work railing as per drawing shall be in the
range of 22-23 kg and remaining letter railings as
per drawing shall be in the range of 21 to 23 kg.
All SS pipes, tubes, art work shall be of SS 304
grade. SS Hollow tubes, pipes, plates etc shall be
cut as per approved drawing and installed in
ROB Parapet. Bottom plates are to be provided
with necessary holes as per the approved
sample.
Providing and laying M60 or M70 grade prestressed / Reinforced cement concrete in pedestal,
seismic restrainer, Pier, Pier cap, Extended Pier cap etc.. Using 20mm and down grade metal
including necessary shuttering, centering, compaction by vibrating, curing etc.. Complete in all
2 respects excluing cost of reinforcement, prestressing arrangements and HT strands. CUM 395.48 16850.25 6,663,954
(i) The removal of inside shutters must be carried out using semi automatic hydraulic equipment
ITEM ESTIMATED ESTIMATED
DESCRIPTION UNIT RATE REMARKS
NO QTY AMOUNT
(ii) At the end of the work all the infrastructure facilities provided in casting yard may be taken
back by the Contractor.
Loading, transporting precast segments from casting yard to work site, launching and erection
in position with launching girder, including the erection and shifting of launching girder, cost of
all temporary supports, launching girder, erection equipment, transporting etc, applying epoxy- LAR rate of Manish
based bonding agent on end surfaces of segments after dry matching includingtemporary nagar flyover of
prestressing required during its curing period and positioning on bearings etc. M/s NCC item no
6 MT 292.50 -3236.31 (946,621)
3.2.1 plus 05%
price escalation for
three years
Prestressing HT steel cables providing fabricating and fixing in position to exact design profile,
prestressing HT cables of all classification made from lower relaxation strands confirming to IS
14268:1995 in prestressed concrete girder/slabs etc.. including supplying cutting making into
cables with necessary spacers , colour coding, protecting with water soluble oil at all times,
anchoring of cables,supplying and placing spiral corrugated type galvanised metal steel duct
sheathing made up of cold rolled cold annealed mild steel confirming to IS 513 of required
diameter bar thickness, vent pipe ,placing , bending,routing,fixing,stressing and grouting of Approved rate for
7 cable ducts with cement grout , anchorage sets in required numbers with proviison for future MT 2.48 -132912.39 (330,154) Rahate extra item
prestressing if any including all lead and lift with contractor's own materials,labour,equipments no 13
etc,.. complete as per drawing and specification. Rate also includes covering,anchorage pads
with epoxy mortar of approved quality to avoid corrosion.
Extra for using HDPE sheathing pipe instead of CRCA sheating pipes
Approved rate for
8 MT 405.00 -84.70 (34,304) Rahate extra item
no 14
(i) The removal of inside shutters must be carried out using semi automatic
hydraulic equipment.
(ii) At the end of the work all the infrastructure facilities provided in casting
yard may be taken back by the Contractor.
Loading, transporting precast segments from casting yard to work site,
launching and erection in position with launching girder, including the
erection and shifting of launching girder, cost of all temporary supports,
launching girder, erection equipment, transporting etc, applying epoxy-based
bonding agent on end surfaces of segments after dry matching
2 includingtemporary prestressing required during its curing period and MT 866.80 888.83 2512.72 2,178,021 2,233,377
positioning on bearings etc.
Providing and applying epoxy based paint of approved colour and shade to
exterior surface in two or more coats including scaffolding preparing the
surface to receive paint etc.Complete. Rate includes preparation of surface,
5
application of one or more coats of primer as per manufacture's
SQM 930.00 930.00 407.03 378,540 378,540
recommandation
Provinding and fixing strip seal expansion joints: Providing and fixing
inpositon of standard performed sealed and slab type or strip sealed
elastomeric type expansion joints for Railway bridge or Road over Bridge as
per apporved drawing and latest MOST/IRC specifation. Rates are inclusive
7 of suppying and fixing with contractor's own materials for ex.inserts RMT 34.00 34.00 18728.41 636,766 636,766
bolts,socket,tubes,neoprene sheets/caps etc.. equipments ,machineries, labour
all tax royalties,all lead and lift,transport,testing,surface preparartion
complete.
Extra for using HDPE sheathing pipe instead of CRCA sheating pipes
This item was missed out in
earlier estimate but is
executed at site no. Rate as
8 RMT 0.00 480.00 84.70 - 40,656 per already approved rate of
Extra items for Rahate
station work in this contract.
NOTES:-
1) Steel (Plates and Rolled sections) should conform to
IS: 2062-2011. It shall have Sub quality “B0‟ & Grade
E350. Plates shall be fully killed and fully normalized /
controlled cooled.
Page 10 of 46
VARIATION STATEMENT 6
Design and Construction of Viaduct in Reach-1 between New-Airport and Sitabuldi stations from Ch.6790 to 14400 including viaduct in five elevated
station portion also, on North-South Corridor of Nagpur Metro Rail Project
L.O.A No : . NMRCL/CIVIL(D&B)/02/2015/4008, dated 28.11.2015
6th VARIATION STATEMENT FOR COMPOSITE GIRDERS IN CONGRESS NAGAR
12/24/2020
Previously
Already approved Anticipated
Sr. No Description of item Unit Rate approved Anticipated Now Remarks
Amount Amount
Qty
11) The Block required shall be arranged by
NMRCL.The duration of the block shall be as
approved by Engineer.The required duration of block
will be arranged by NMRCL.
Page 11 of 46
JAIL ROAD (From Ch 9335.83 to Ch 8596.429m) (800m length)
Item Description ORIGINAL ORIGINAL
Sr. ANTICIPATED ANTICIPATED
Referen unit APPROVED
QTY
APPROVED RATE APPROVED
AMOUNT
SAVING EXCESS Remarks
no QTY AMOUNT
ce
Earth work in excavation by mechanical means (Hydraulic Actual quanitites
excavator) / manual means over areas (exceeding 30cm in executed at site
depth. 1.5 m in width as well as 10 sqm on plan) including plus service
disposal of excavated earth, lead upto 50m and lift upto Road quantities
1 2.6 1.5m, disposed earth to be levelled and added extra
neatly dressed.
2.6.1 All kinds of soil cum 22500 16524.43 178.94 4,026,150 2,956,882 1069268.4958 0.00
Disposal of building rubbish / malba / similar unserviceable, Actual quanitites
dismantled or waste materials by mechanical means, executed at site
including loading, transporting, unloading to approved plus service
2 15.6 municipal dumping ground or as approved by Engineer-in- cum 22500 17324.43 142.255 3,200,738 2,464,487 736250.71035 0.00 Road quantities
charge, beyond 50 m initial lead, for all leads including all added extra
lifts involved.
Preparation and consolidation of sub grade with power road Actual quanitites
roller of 8-12T capacity after excavation earth to an average of executed at site
22.5cm depth dressing to camber and consolidating with plus service
3 16.1 road roller including making good the undulation etc. and re- Road quantities
rolling the sub grade and disposal of surplus earth with lead added extra
upto 50m.
(i) For Jail Road Sqm 22500.00 20465.88 93.44 2,102,344 1,912,281 190063.0875 0.00
(i) For Jail Road Cum 11925 13260.307 488.81 5,829,029 6,481,738 0 652708.08
JAIL ROAD (From Ch 9335.83 to Ch 8596.429m) (800m length)
Item Description ORIGINAL ORIGINAL
Sr. ANTICIPATED ANTICIPATED
Referen unit APPROVED
QTY
APPROVED RATE APPROVED
AMOUNT
SAVING EXCESS Remarks
no QTY AMOUNT
ce
Construction of granular sub-base by providing close graded Actual quanitites
Material conforming to specifications, mixing in a executed at site
mechanical mix plant at OMC, carriage of mixed material by plus service
tippers to work site, for all leads & lifts, spreading in uniform Road quantities
layers of specified thickness with motor grader on prepared added extra
6 16.78 surface and compacting with vibratory power roller to achieve
the desired density, complete as per specifications and
directions of Engineerin- Charge.
Average LAR
rates of (i) On granular surface treated with primer and on hungry Actual quanitites
8a
Manish bituminous surface @2.5 to 3.0 kg/10 sq.m. sqm 11250 30416.5 24.17 271,913 735,167 0 463254.31 executed at site
Nagar, Depot, plus service
IL&FS and
ITD contracts
Road quantities
(ii) On Bituminous surface @ 2.0 to 2.5 Kg/10 sq.m. added extra
8b sqm 11250 30416.5 22.60 254,250 687,413 0 433162.90
Providing and Fixing Concertina Coil Fencing:Providing and RMT 0 900 354.7938 319314.42 0 319314.42 This item was
Fixing Concertina Coil Fencing with punched tape concertina missed out in
coil 600mm dia 10 metre openable length (total length 90M) the earlier
having 50 nos rounds per 6metre lenght, upto 3metre height estimate but is
of wall with existing angle iron 'Y' shaped 3 m apart and with being executed
9 horizontal R.B.T. reinforced barbed wire, stud tied with GI at site. Rate as
staples and GI clips to retain horizontal including necessary per At-grade
bolt or GI barded wire tied to angle iron all complete as per contract BOQ
direction of Engineer Incharge with reinforced barbed tape item 2 of
(R.B.T.)/ Spring core (2.5mm thick) wire of high tensile Section 3. LOA
strength of 165kg/MMsq with tape (0.52 mm Thick) and of At-grade
weight 43.478gm/metre (Cost of angle, CC contract is
blocks shall be paid separately) dated
Rate as 30.05.2015. 5%
price escalation
per LAR
12 per annum has
At-grade
been
contract of
considered for 4
NCC
years to bring
the rate atpar
with presenent
rate.
JAIL ROAD (From Ch 9335.83 to Ch 8596.429m) (800m length)
Item Description ORIGINAL ORIGINAL
Sr. ANTICIPATED ANTICIPATED
Referen unit APPROVED
QTY
APPROVED RATE APPROVED
AMOUNT
SAVING EXCESS Remarks
no QTY AMOUNT
ce
Steel work in built up tubular trusses including cutting, Kg 0 8400 104.88555 881038.62 0 881038.62 This item was
hoisting, fixing in position and applying a priming coat of missed out in
approved steel primer welded and bolted including special the earlier
shaped washers etc complete. Hot finished welded type tubes estimate but is
as per approved drawing for concertina coil fixing along the being executed
compound wall. at site. Rate as
per approved
extra item of
At-grade
contract.
Rate as Approval
per LAR accorded in Jan
13 At-grade 2018. 5% price
contract of index applied to
NCC bring at-par
with present
rate.
Providing laying Gaivanization by applying Zinc coating to kg 0 8400 45.99 386316 0 386316 This item was
MS Tube welded Frames which is placed on compound wall missed out in
for concertina coil fixing the earlier
estimate but is
being executed
at site. Rate as
per approved
extra item of
At-grade
contract.
Rate as Approval
per LAR accorded in Jan
14 At-grade 2018. 5% price
contract of index applied to
NCC bring at-par
with present
rate.
JAIL ROAD (From Ch 9335.83 to Ch 8596.429m) (800m length)
Item Description ORIGINAL ORIGINAL
Sr. ANTICIPATED ANTICIPATED
Referen unit APPROVED
QTY
APPROVED RATE APPROVED
AMOUNT
SAVING EXCESS Remarks
no QTY AMOUNT
ce
Precasting and placing in position 125 mm dia Bollards 600 This item was
mm high of required shape, including providing M.S. Pipe missed out in the
Sleeve 50 mm dia 300 mm long in the Bollard and M.S. Pipes earlier estimate
40 mm dia and 450 mm long with 150x150x6mm M.S. plate but is being
welded at bottom and embedded 150 mm in cement concrete executed at site.
DSR 2014 1:3:6 (1 Cement : 3 coarse sand : 6 graded stone aggregate 20 (Rate as per
15 item no mm nominal size), including necessary excavation of size 250 Each 0 50 628.65 - 31,432 0 31432.38 DSR 2014 plus
4.9 x 250 x 450 mm deep for the same in bitumen/concrete 15% above as
pavement at specified spacing. per schedule B)
(i) For VVIP Road (Shoul Sqm 3408.75 0.00 93.44 318505 0
5b (ii) On Bituminous surface @ 2.0 to 2.5 Kg/10 sq.m. sqm 7508.34 11250 22.60 169688 254250
13.61.1 Two or more coats on new work sqm 100 0 85.56 8556 0
13085173 10292620
CONGRESS NAGAR BOQ
DESCRIPTION ORIGINAL
ORIGINAL ANTICIPATED APPROVED ANTICIPATED
ITEM NO UNIT APPROVED SAVING EXCESS Remarks
APPROVED QTY QTY RATE AMOUNT
AMOUNT
SUBSTRUCTURE
Providing and installing cast-in-situ vertical bored piles of required
depth as per approved GFC drawings of 1200mm dia. with M35 grade
Design Mix Cement Concrete using 20mm graded crushed stone
aggregate using PPC/ PSC grade 53 cement including extra cement in
all soil strata including boulders and kankar and soft rock/ weathered
rock as per TS. The cost shall also include the cost of empty boring
with MS temporary liner as per site requirement. The cost shall also
include built up of pile up to the required level (Measurement shall be
from theortical cut-off level to founding Toe level) as per drg. The rate
includes all operations required for installation of pile such as
installation of rig, shifting of hydraulic rig, construction of approach
temporary road/ bridge for piling rig etc. Any reason for idling of rig
will not be payable. The item includes disposal of earth, muck, slush
released from piles, top cut portion of pile at dumping ground for all
1
leads. Rate shall include cost of using required dosage of admixture in
concrete for obtaining required workability as per approval of engineer
in charge. Drilling shall be done by use of hydraulic rig using
temporary casing of required depth (min. of 4.5 mtr). Polymer slurry to
be used and as directed by the Engineer. (Use of Bentonite slurry is not
permitted). Reinforcement will be paid seperately. Rate shall also
include cost of polymer to be used for stabilisation of bore.
i) For 1200mm dia Pile RMT 1069.92 1046.4 15110.18 16,166,684 15,811,292 355391.4336 0.00
Providing 2 m high temporary barricade (all contractor's materials and
arrangement for traffic diversion such as traffic signals during
construction at site,for day and night as per requirement and drawings.
During Construction , barricading arrangement for traffic diversion has
to be kept continuously and maintained properly till the completion of
all activities , the construction barricade will have different width in
2 (a) RMT 65 0 3145.77 204,475 - 204475.05 0.00
different portion of the alignment as directed by the engineer keeping in
view the movement of traffic at the ground level and the minimum
inconvience to the safety of public.
Dismantling and re-erecting the above barricading (item No 2(a)) and Item being proposed
2 (b) other arrangements at the new location as per instructions of Engineer. now as old barricades
re-erected at site and
BOQ rate is considered.
Note : The payment schedule for item No. 1(a) & (b) shall be as
follows: Payment stages (i) 70% on installation (ii) 30% on removal/ RMT 0 65 349.53 - 22,719 0 22719.45
shift
CONGRESS NAGAR BOQ
DESCRIPTION ORIGINAL
ORIGINAL ANTICIPATED APPROVED ANTICIPATED
ITEM NO UNIT APPROVED SAVING EXCESS Remarks
APPROVED QTY QTY RATE AMOUNT
AMOUNT
Excavation below ground level in all strata upto 2 m except in hard rock
3 for pilecap including disposal of material and including dewatering if CUM 2329.75 2319.7 459.51 1,070,543 1,065,925 4618.0755 0.00
necessary.
Providing M 15/20 concrete for Minimum 100mm thick PCC below
pile cap, open foundation slabs and ramp foundations extending 100mm
all around beyond pile cap, open foundation slabs. Rate shall include
4 cost of using required dosage of admixture in concrete for obtaining CUM 58.3 54.35 7271.29 423,916 395,195 28721.5955 0.00
required workability as per approval of Engineer.
Providing and laying M40/20 grade concrete for pile cap using 20mm
downgrade metal including necessary shuttering, centering, compaction
5 by vibrating, curing etc. In all respects. (Excluding reinforcement) CUM 1752.1 1758.46 9127.31 15,991,960 16,050,010 0 58049.69
Providing and applying epoxy based paint of approved colour and shade
to exterior surface in two or more coats including scaffolding preparing
10 the surface to receive paint etc.Complete. Rate includes preparation of SQM 2236.84 1600 407.0325 910,467 651,252 259214.5773 0.00
surface, application of one or more coats of primer as per manufacture's
recommandation
SUPERSTRUCTURE - 0 0.00
CONGRESS NAGAR BOQ
DESCRIPTION ORIGINAL
ORIGINAL ANTICIPATED APPROVED ANTICIPATED
ITEM NO UNIT APPROVED SAVING EXCESS Remarks
APPROVED QTY QTY RATE AMOUNT
AMOUNT
Providing and laying M50/20 Grade cement concrete for Concreting
and curing precast segments of all spans (straight or curved) in the
casting yard, bolt holes for fixation of Blisters for temporary Pre-
Stressing, provision for future external Pre-Stressing arrangement,
lifting the segments from the mould and shifting the same to the
stacking yard. The cost shall be inclusive of the cost proportionate
treatment for each cubic meter of concrete for having provided all
infrastructure in the casting yard, gantry cranes, moulds, casting beds,
mobile cranes, stores, concrete batching plant, establishing labs, cut-
outs, shear keys, bulkheads, end block in situ concrete after stressing
etc. where specified, all curing arrangements as required, all handling
etc. complete. Reinforcement steel shall be paid separately under
11 relevant BOQ item. Payment for Prestressing system (includes strands, cum 176 195.82 14912.82 2,624,656 2,920,228 0 295572.04
anchorages, sheathing, vent pipe ..etc) will be measured under relevant
BOQ item. Rate shall include the cost of required dosage of admixture
in concrete for obtaining required workability as per specification and
approval of Engineer. The Rate shall also include UPV testing (by
approved NABL and as approved and directed by Engineer) for all end
segments.
(i) The removal of inside shutters must be carried out using semi
automatic hydraulic equipment. -
(ii) At the end of the work all the infrastructure facilities provided in
casting yard may be taken back by the Contractor. -
Extra for using HDPE sheathing pipe instead of CRCA sheating pipes
14 RMT 4807 4600 84.7 407,153 389,620 17532.9 0.00
Providing and applying epoxy based paint of approved colour and shade
to exterior surface in two or more coats including scaffolding preparing
15 the surface to receive paint etc.Complete. Rate includes preparation of SQM 445.25 1650 407.0325 181,231 671,604 0 490372.40
surface, application of one or more coats of primer as per manufacture's
recommandation
Provinding and fixing strip seal expansion joints: Providing and fixing
inpositon of standard performed sealed and slab type or strip sealed
elastomeric type expansion joints for Railway bridge or Road over
Bridge as per apporved drawing and latest MOST/IRC specifation.
Rates are inclusive of suppying and fixing with contractor's own
17 materials for ex.inserts bolts,socket,tubes,neoprene sheets/caps etc.. RMT 17 34 18458.27 313,791 627,581 0 313790.59
equipments ,machineries, labour all tax royalties,all lead and
lift,transport,testing,surface preparartion complete.
CONGRESS NAGAR BOQ
DESCRIPTION ORIGINAL
ORIGINAL ANTICIPATED APPROVED ANTICIPATED
ITEM NO UNIT APPROVED SAVING EXCESS Remarks
APPROVED QTY QTY RATE AMOUNT
AMOUNT
Supply of ordinary portland cement for Grouting of HT strand item as
mentioned above. Item was not
18 MT 0 49 6177 - 302,673 0 302673.00 considered in earlier
proposal. Rate
considered as per At-
grade BOQ rate.
Providing and supplying in standard lengths ISI mark rigid Rate as per PWD
unplasticised PVC pipes suitable for potable water with solvent cement Pradhikaran schedule
joints including cost of couplers, as per IS specification no. 4985 / 1988 18-19 rates
excluding GST levied by GOI and GOM in all respect, including
transportation, freight charges, inspection charges, loading, unloading,
conveyance
to the departmental stores and stacking the same in closed shed duly
protected from sun rays and rains including cost of jointing material i.e.
solvent cement, etc. complete (selffit type to be jointed with cement
19 solvent). Rmt 0 31 332.808 - 10,317 0 10317.05
Note : 1) 10% of cost of pipes shall be considered for cost of PVC
specials for estimate purpose only.
2) One coupler and required cement solvent shall be provided with each
full length pipe cost
of which is included in rates below.
Working pressure 4kg/sqcm and 160mm dia PVC pipe
Lowering, laying and jointing with P.V.C. pipes and specials of Rate as per PWD
following class and diameter including cost of conveyance from stores Pradhikaran schedule
to site of works including cost of all labour, material, except cement 18-19 rates
20 solvent, rubber ring, as per IS code, etc. complete (with cement solvent Rmt 0 31 44.688 - 1,385 0 1385.33
joint / ring fit joint). Working pressure 4kg/sqcm and 160mm dia
PVC pipe
Drainage. Providing and fixing of rigid HDPE rain water pipe in Rate as per LAR of
superstructure diaphragm (end segment) and downtake pipes, bends, Reach 2 Viaduct.
couplers, upper receiving caps, etc upto bottom of pier through shear
21 key/ upto road incl. All accessories such as pipe clamps, GI grating, RMT 0 30 556.5 - 16,695 0 16695.00
collection chamber, anchor straps and its connections, etc as specified
in drawings incl all accessories.
Providing and fixing MS drainage spout with grill in deck slab with Hot Rate as per LAR of
22 dipped galvanizing @ 650 gms per square meter after welding as per Nos 0 6 1470 - 8,820 0 8820.00 Reach 2 Viaduct.
specifications and drawings.
CONGRESS NAGAR BOQ
DESCRIPTION ORIGINAL
ORIGINAL ANTICIPATED APPROVED ANTICIPATED
ITEM NO UNIT APPROVED SAVING EXCESS Remarks
APPROVED QTY QTY RATE AMOUNT
AMOUNT
Supplying and fixing DI Circular cover with Square frame Heavy duty Material rate as per Tax
Grade C 250 Wt 85 KG with Hinges. invoice plus freight and
fixing charges @ 10%,
plus GST @ 12% &
23 Nos 2 9986.4765 - 19,973 0 19972.95 contractors overhead
and profit @ 12.5%
i) For 1200mm dia Pile RMT 1004.39 1004.744 15110.18 15,176,514 15,181,863 0 5349.00
Providing 2 m high temporary barricade (all contractor's
materials and arrangement for traffic diversion such as traffic
signals during construction at site,for day and night as per
requirement and drawings. During Construction , barricading
arrangement for traffic diversion has to be kept continuously and
maintained properly till the completion of all activities , the
2 (a) construction barricade will have different width in different RMT 155 0 3145.77 487,594 - 487594.35 0.00
portion of the alignment as directed by the engineer keeping in
view the movement of traffic at the ground level and the
minimum inconvience to the safety of public.
Dismantling and re-erecting the above barricading (item No Item being proposed now
2 (b) 2(a)) and other arrangements at the new location as per as old barricades re-erected
instructions of Engineer. at site and BOQ rate is
considered.
RAHATE COLONY BOQ Item being proposed now
ORIGINAL as old barricades re-erected
ORIGINAL ANTICIPATED APPROVED ANTICIPATED
ITEM NO DESCRIPTION UNIT APPROVED SAVING EXCESS Remarks
at site and BOQ rate is
APPROVED QTY QTY RATE AMOUNT
AMOUNT considered.
Note : The payment schedule for item No. 1(a) & (b) shall be as
follows: Payment stages (i) 70% on installation (ii) 30% on RMT 0 155 349.53 - 54,177 0 54177.15
removal/ shift
Excavation below ground level in all strata upto 2 m except in
3 hard rock for pilecap including disposal of material and CUM 1700.272 1700.272 459.51 781,292 781,292 0 0.00
including dewatering if necessary.
Providing M 15/20 concrete for Minimum 100mm thick PCC
below pile cap, open foundation slabs and ramp foundations
extending 100mm all around beyond pile cap, open foundation
4 slabs. Rate shall include cost of using required dosage of CUM 46.774 46.774 7271.29 340,107 340,107 0 0.00
admixture in concrete for obtaining required workability as per
approval of Engineer.
Providing and laying M40/20 grade concrete for pile cap using
20mm downgrade metal including necessary shuttering,
5 centering, compaction by vibrating, curing etc. In all respects. CUM 1250.984 1287.557 9127.31 11,418,119 11,751,932 0 333813.11
(Excluding reinforcement)
SUPERSTRUCTURE - 0 0.00
RAHATE COLONY BOQ
ORIGINAL
ORIGINAL ANTICIPATED APPROVED ANTICIPATED
ITEM NO DESCRIPTION UNIT APPROVED SAVING EXCESS Remarks
APPROVED QTY QTY RATE AMOUNT
AMOUNT
Providing and laying M50/20 Grade cement concrete for
Concreting and curing precast segments of all spans (straight or
curved) in the casting yard, bolt holes for fixation of Blisters for
temporary Pre-Stressing, provision for future external Pre-
Stressing arrangement, lifting the segments from the mould and
shifting the same to the stacking yard. The cost shall be
inclusive of the cost proportionate treatment for each cubic
meter of concrete for having provided all infrastructure in the
casting yard, gantry cranes, moulds, casting beds, mobile cranes,
stores, concrete batching plant, establishing labs, cut-outs, shear
keys, bulkheads, end block in situ concrete after stressing etc.
where specified, all curing arrangements as required, all
handling etc. complete. Reinforcement steel shall be paid
11 separately under relevant BOQ item. Payment for Prestressing cum 440 440 14912.82 6,561,640 6,561,640 0 0.00
system (includes strands, anchorages, sheathing, vent pipe ..etc)
will be measured under relevant BOQ item. Rate shall include
the cost of required dosage of admixture in concrete for
obtaining required workability as per specification and approval
of Engineer. The Rate shall also include UPV testing (by
approved NABL and as approved and directed by Engineer) for
all end segments.
(i) The removal of inside shutters must be carried out using semi
automatic hydraulic equipment. -
Lowering, laying and jointing with P.V.C. pipes and specials of Rate as per PWD
following class and diameter including cost of conveyance from Pradhikaran schedule 18-19
stores to site of works including cost of all labour, material, rates
except cement solvent, rubber ring, as per IS code, etc. complete
20 (with cement solvent joint / ring fit joint). Working pressure Rmt 0 100 44.688 - 4,469 0 4468.80
4kg/sqcm and 160mm dia PVC pipe
RAHATE COLONY BOQ
ORIGINAL
ORIGINAL ANTICIPATED APPROVED ANTICIPATED
ITEM NO DESCRIPTION UNIT APPROVED SAVING EXCESS Remarks
APPROVED QTY QTY RATE AMOUNT
AMOUNT
Drainage. Providing and fixing of rigid HDPE rain water pipe in Rate as per LAR of Reach 2
superstructure diaphragm (end segment) and downtake pipes, Viaduct.
bends, couplers, upper receiving caps, etc upto bottom of pier
through shear key/ upto road incl. All accessories such as pipe
21 clamps, GI grating, collection chamber, anchor straps and its RMT 0 100 556.5 - 55,650 0 55650.00
connections, etc as specified in drawings incl all accessories.
Providing and fixing MS drainage spout with grill in deck slab Rate as per LAR of Reach 2
22 with Hot dipped galvanizing @ 650 gms per square meter after Nos 0 20 1470 - 29,400 0 29400.00 Viaduct.
welding as per specifications and drawings.
Supplying and fixing DI Circular cover with Square frame Material rate as per Tax
Heavy duty Grade C 250 Wt 85 KG with Hinges. invoice plus freight and
fixing charges @ 10%, plus
23 Nos 5 9986.4765 - 49,932 0 49932.38 GST @ 12% & contractors
overhead and profit @
12.5%
5 16.3.2 Supplying and stacking at site. 53 mm to 22.4 mm size stone Cum 530.25 598.25 1354.00 717959 810031
6 16.3.9 aggregate
Supplying and stacking at site. Good Earth Cum 7743.98 8746.98 320.90 2485043 2806906
Partial Only laying and Spreading the stacked material including
7 item of compaction with watering and ramming. Cum 8274.23 9345.23 313.98 2597943 2934215
16.4
Revised Medain cost of Viaduct Reach-1 (Including Pocket track median portion)
Description
DSR 2014 Approved Anticipated Approved Approved Anticipated
Sr.no Unit Remark
Item No. Quantity Qty Rate Amount Amount
10 13.4.2 12 mm cement plaster of mix : Sqm 707.00 839.00 158.40 111989 132898
Dismantling manually/ by mechanical means including
stacking of serviceable material and disposal of unserviceable
11 15.43.2 material within 50 metres lead as per direction of Engineer-in- Sqm 9000.00 9300.00 159.05 1431450 1479165
charge bituminous road
Lifting and placing of 1.5m x 0.9m x 0.3m size kerb stones and
Analysis of jointing with cement mortar 1:3 with joint thickness of mortar
rate based approximately 10mm.
13 rmt 15000.00 16000.00 180.00 2700000 2880000
on DSR
2014 items
Total amount in Schedule B-2 add 15.00 % for above quoted in the tender Total amount = 73099369.80 78326896.26
AS PER BOQ
Item No Description Approved
Unit Qty Total Amount Total Amount
Rate
Supplying and post threading uncoated stress relieved low relaxation steel
conforming to IS: 14268, class-2 in standard pier cap / rib slabs incl.
providing 107 mm ID for (19K15) or 86 mm ID (for 12K15), corrugated HDPE
duct (both sides) 3.3 mm thick in case of 19K15 and 2.8 mm incase of 12K15
with cpouplers & vent pipes, spacers, anchorages,stressing using 19K15 or
1
12K15 system and grouting , epoxy protection of anchorages, sealing of Pt
Average LAR rates considered:
anchorage recess with concrete (same grade as structure) and all related
operations to complete the work. (Note : the details shown on the drawing all
R-4 ITD Viaduct rate= 106216,
likely to change and nothing extra will be paid to the contractor on this IL&FS rate = Rs. 166558.72,
account) R-4 ITD Station rates =
Rs.95092.2, R-3 ITD Station =
Rs.162401.25, Avg = Rs.
i) Strands MT 20.349 132567.04 2,697,607 132567.04
ii) Corrugated HDPE Pipe 107 mm ID RM - NA NA
iii) Corrugated HDPE Pipe 86 mm ID RM - NA NA
iv) Anchorages for 19K15 cable. Nos. - NA NA
iv) Anchorages for 12K15 cable. Nos. - NA NA
TOTAL 2,697,607
“Design and construction of viaduct in Reach-1 between new airport and sitabuldi stations from CH 6790 to 14400 including viaduct in five Elevated station portions also, on NORTH-SOUTH Corridor of
Name of Work : Nagpur Metro Rail Project”.
Contractor M/s. NCC Limited.
Aggrement No : NMRCL/Procure/47 Dated:- 12/01/2016
Work Order No: NMRCL/CIVIL(D&B)/02/2015/4006 Dated:- 28/11/2015
Bill Period : 27/12/2018 TO 15/03/2020
Statement: FINACIAL IMPLICATION STATEMENT OF EXTRA ITEMS FOR BALANCE IL&FS STATIONS WORKS EXECUTED IN REACH 1 VIADUCT AGREEMENT
Extra item no Item Description Unit Total Anticipated Qty Rate Total Anticipated Amount Remarks
Extra items for Machinery Deployment on Hire from NCC for
1 various works like I-Girder Dispatch from IL&FS casting yard
and Erection at site.
3 Labour Charges
“Design and construction of viaduct in Reach-1 between new airport and sitabuldi stations from CH 6790 to 14400 including viaduct in five Elevated station portions also, on NORTH-SOUTH Corridor of
Name of Work : Nagpur Metro Rail Project”.
Contractor M/s. NCC Limited.
Aggrement No : NMRCL/Procure/47 Dated:- 12/01/2016
Work Order No: NMRCL/CIVIL(D&B)/02/2015/4006 Dated:- 28/11/2015
Bill Period : 27/12/2018 TO 15/03/2020
Statement: FINACIAL IMPLICATION STATEMENT OF EXTRA ITEMS FOR BALANCE IL&FS STATIONS WORKS EXECUTED IN REACH 1 VIADUCT AGREEMENT
Extra item no Item Description Unit Total Anticipated Qty Rate Total Anticipated Amount Remarks
6 Elastomeric bearing
Providing and laying M60 grade concrete in pedestal, seismic Rate as per actual work order placed at
restrainer etc.. Using 20mm and down grade metal including SN/………………………………………………. The
7 Cum 16.750 16850.25 282241.69
necessary shuttering, centering, compaction by vibrating, total anticipated Qty sheet is placed at
curing etc.. Complete in all respects excluding reinforcement. SN/………………………………………………….
“Design and construction of viaduct in Reach-1 between new airport and sitabuldi stations from CH 6790 to 14400 including viaduct in five Elevated station portions also, on NORTH-SOUTH Corridor of
Name of Work : Nagpur Metro Rail Project”.
Contractor M/s. NCC Limited.
Aggrement No : NMRCL/Procure/47 Dated:- 12/01/2016
Work Order No: NMRCL/CIVIL(D&B)/02/2015/4006 Dated:- 28/11/2015
Bill Period : 27/12/2018 TO 15/03/2020
Statement: FINACIAL IMPLICATION STATEMENT OF EXTRA ITEMS FOR BALANCE IL&FS STATIONS WORKS EXECUTED IN REACH 1 VIADUCT AGREEMENT
Extra item no Item Description Unit Total Anticipated Qty Rate Total Anticipated Amount Remarks
Providing and applying epoxy based paint of approved colour Rate as per actual work order placed at
and shade to exterior surface in two or more coats including SN/………………………………………………….
scaffolding preparing the surface to receive paint The total anticipated Qty sheet is placed
11 Cum 93.280 407.03 37967.76
etc.Complete. Rate includes preparation of surface, application at
of one or more coats of primer as per manufacture's SN/………………………………………………………
recommandation ……………...………………………………