PM 300 SECOND ASSIGNMENT

Due Date: 14 days After handover

The diagram below represents a resource bar chart for a project with 6 activities.

Activity Mon Tues We Thu Fri Satu Sun Mon Tue Wed
Number d
1 2 4 5 6 7 8 9 10
3

3 3
100

200 4 4

5 5
300

400 3 3

500 2 2 2 2 2

600 5

a) What do you understand by resource-limited resource scheduling? Using the figure above, perform
resource limited scheduling. Assume that you have only 5 workers available at any given time. Does
the resource scheduling affect the completion date of the project? (50 marks)
b) What do you understand by the term time-limited resource scheduling? Using the figure above,
perform a time limited resource scheduling. Assume that you only have 7 workers (50 marks)