Construction of Marawi Filipino-Chinese Friendship Dome Proposed Construction Schedule - Level 3 06 March 2020

Marawi City, Lanao Del Sur, Mindanao


Activity ID Activity Name Original Start Finish Budgeted Material Budgeted Labor Budgeted Total CostQ Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q QQ
Duration Cost Cost

Marawi Filipino-Chinese Friendship Dome 624 24-Feb-20 08-Nov-21 Php140,739,463.38 Php59,260,469.77 Php199,999,933.15 08-Nov-21, Marawi Filipino-Chinese Friendship Dom
Milestones 612 06-Mar-20 08-Nov-21 Php0.00 Php0.00 Php0.00 08-Nov-21, Milestones
MS1000 Complete Submission of Final 0 06-Mar-20 Php0.00 Php0.00 Php0.00 Complete Submission of Final Quotation,
Quotation
MS1005 Complete Receipts of Award & 0 13-Mar-20 Php0.00 Php0.00 Php0.00 Complete Receipts of Award & Proceed Notices,
Proceed Notices
MS1008 Start Design & Engineering - Phase I 0 16-Mar-20 Php0.00 Php0.00 Php0.00 Start Design & Engineering - Phase I, 16-Mar-20

MS1010 Complete Design & Engineering - 0 16-May-20 Php0.00 Php0.00 Php0.00 Complete Design & Engineering - Phase I,
Phase I
MS1030 Start Construction of Dome Stadium - 0 18-May-20 Php0.00 Php0.00 Php0.00 Start Construction of Dome Stadium - Phase II, 18-May-20
Phase II
MS1035 Complete Siteworks 0 29-Dec-20 Php0.00 Php0.00 Php0.00 Complete Siteworks,
MS1040 Complete Civil Works 0 02-Oct-21 Php0.00 Php0.00 Php0.00 Complete Civil Works,
MS1050 Complete Steel Works 0 05-Apr-21 Php0.00 Php0.00 Php0.00 Complete Steel Works,
MS1060 Complete Architectural Works 0 25-Oct-21 Php0.00 Php0.00 Php0.00 Complete Architectural Works,

MS1062 Complete Electrical Works 0 08-Nov-21 Php0.00 Php0.00 Php0.00 Complete Electrical Works,
MS1064 Complete Auxiliary Works 0 01-Nov-21 Php0.00 Php0.00 Php0.00 Complete Auxiliary Works,
MS1065 Complete Plumbing Works 0 30-Oct-21 Php0.00 Php0.00 Php0.00 Complete Plumbing Works,
MS1080 Complete Mechanical Works 0 08-Nov-21 Php0.00 Php0.00 Php0.00 Complete Mechanical Works,
MS1100 Complete Others 0 08-Nov-21 Php0.00 Php0.00 Php0.00 Complete Others,
MS1110 Complete Project Closing 0 08-Nov-21 Php0.00 Php0.00 Php0.00 Complete Project Closing,
MS1120 Complete Demobilization 0 08-Nov-21 Php0.00 Php0.00 Php0.00 Complete Demobilization,
Contract Negotiation 11 24-Feb-20 06-Mar-20 Php0.00 Php0.00 Php0.00 06-Mar-20, Contract Negotiation
CN1000 Submission of Final Quotation and 11 24-Feb-20 06-Mar-20 Php0.00 Php0.00 Php0.00 Submission of Final Quotation and other Documents
other Documents

Notice of Award & NTP 7 06-Mar-20 13-Mar-20 Php0.00 Php0.00 Php0.00 13-Mar-20, Notice of Award & NTP
NA1000 Evaluation of Final Quotation and 6 06-Mar-20 12-Mar-20 Php0.00 Php0.00 Php0.00 Evaluation of Final Quotation and Receipt of Notice of Award
Receipt of Notice of Award

NA1010 Receipt of Notice To Proceed 1 13-Mar-20 13-Mar-20 Php0.00 Php0.00 Php0.00 Receipt of Notice To Proceed
Phase I - Design & Engineering 54 16-Mar-20 16-May-20 Php210,000.00 Php2,290,000.00 Php2,500,000.00 16-May-20, Phase I - Design & Engineering

Actual Level of Effort Remaining Work Date Revision Checked Approved


Page 1 of 6
06-Mar-20 Proposed Construction Schedule for FCFD ver. 1.0 JAA RGC
Actual Work Critical Remaining Work
Standel Corporation
Construction of Marawi Filipino-Chinese Friendship Dome Proposed Construction Schedule - Level 3 06 March 2020
Marawi City, Lanao Del Sur, Mindanao
Activity ID Activity Name Original Start Finish Budgeted Material Budgeted Labor Budgeted Total CostQ Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q QQ
Duration Cost Cost

Project Definition & Scope Devt. Phase 10 16-Mar-20 26-Mar-20 Php0.00 Php0.00 Php0.00 26-Mar-20, Project Definition & Scope Devt. Phase
DE1000 Initial Site Visit 2 16-Mar-20 17-Mar-20 Php0.00 Php0.00 Php0.00 Initial Site Visit
DE1010 Meeting w/ Client's Mgt. to define 3 18-Mar-20 20-Mar-20 Php0.00 Php0.00 Php0.00 Meeting w/ Client's Mgt. to define Scope of Works
Scope of Works
DE1020 Perform Material Testing & 7 19-Mar-20 26-Mar-20 Php0.00 Php0.00 Php0.00 Perform Material Testing & Geotechnical Services, Special Inspections, C
Geotechnical Services, Special
Inspections, Contingency & Draft
Design
Schematic Design Phase 11 24-Mar-20 04-Apr-20 Php0.00 Php0.00 Php0.00 04-Apr-20, Schematic Design Phase
DE1030 Approval & Installation of Informational 3 24-Mar-20 26-Mar-20 Php0.00 Php0.00 Php0.00 Approval & Installation of Informational Signage at Project Site
Signage at Project Site

DE1040 Preparation & Approval of Schematic 10 25-Mar-20 04-Apr-20 Php0.00 Php0.00 Php0.00 Preparation & Approval of Schematic Design Documents & a Revised Es
Design Documents & a Revised
Estimate of Probable Total Project Cost

Design Development Phase 36 06-Apr-20 16-May-20 Php210,000.00 Php2,290,000.00 Php2,500,000.00 16-May-20, Design Development Phase
A1000 Develop the Detailed Construction 36 06-Apr-20 16-May-20 Php210,000.00 Php2,290,000.00 Php2,500,000.00 Develop the Detailed Construction Drawings & Specifications & the Upda
Drawings & Specifications & the
Updated Construction Schedule

General Requirements 463 18-May-20 08-Nov-21 Php2,305,033.31 Php1,104,643.09 Php3,409,676.40 08-Nov-21, General Requirements
GR1000 Permits, Bonds and Licenses 60 18-May-20 25-Jul-20 Php382,051.46 Php0.00 Php382,051.46 Permits, Bonds and Licenses
GR1010 Construction Safety and Health 463 18-May-20 08-Nov-21 Php682,143.65 Php204,643.09 Php886,786.74 Construction Safety and Health

GR1020 Offices & Laboratories for Engineers 463 18-May-20 08-Nov-21 Php1,240,838.20 Php0.00 Php1,240,838.20 Offices & Laboratories for Engineers

GR1030 Security Services 463 18-May-20 08-Nov-21 Php0.00 Php900,000.00 Php900,000.00 Security Services
Procurement 290 17-Mar-20 17-Feb-21 Php0.00 Php0.00 Php0.00 17-Feb-21, Procurement
Local Purchases 290 17-Mar-20 17-Feb-21 Php0.00 Php0.00 Php0.00 17-Feb-21, Local Purchases
PL1010 Start of Canvass & Issuing of 150 17-Mar-20 07-Sep-20 Php0.00 Php0.00 Php0.00 Start of Canvass & Issuing of Purchase Requests to Local Supplier
Purchase Requests to Local Suppliers

PL1020 Issuances of Purchase Orders to Local 260 21-Apr-20 17-Feb-21 Php0.00 Php0.00 Php0.00 Issuances of Purchase Orders to Local Suppliers
Suppliers
Importation 180 17-Mar-20 12-Oct-20 Php0.00 Php0.00 Php0.00 12-Oct-20, Importation

Actual Level of Effort Remaining Work Date Revision Checked Approved


Page 2 of 6
06-Mar-20 Proposed Construction Schedule for FCFD ver. 1.0 JAA RGC
Actual Work Critical Remaining Work
Standel Corporation
Construction of Marawi Filipino-Chinese Friendship Dome Proposed Construction Schedule - Level 3 06 March 2020
Marawi City, Lanao Del Sur, Mindanao
Activity ID Activity Name Original Start Finish Budgeted Material Budgeted Labor Budgeted Total CostQ Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q QQ
Duration Cost Cost

PI1000 Identification of Long Lead Items 30 17-Mar-20 20-Apr-20 Php0.00 Php0.00 Php0.00 Identification of Long Lead Items

PI1010 Start Placing of Orders via Bank's 90 30-Jun-20 12-Oct-20 Php0.00 Php0.00 Php0.00 Start Placing of Orders via Bank's Letter of Credit
Letter of Credit
Mobilization 30 18-May-20 20-Jun-20 Php0.00 Php889,840.00 Php889,840.00 20-Jun-20, Mobilization
MO1000 Start Mobilization of Manpower, Tools & 30 18-May-20 20-Jun-20 Php0.00 Php889,840.00 Php889,840.00 Start Mobilization of Manpower, Tools & Equipment
Equipment
Phase II - Construction 532 26-May-20 08-Nov-21 Php138,224,430.07 Php54,594,626.66 Php192,819,056.73 08-Nov-21, Phase II - Construction
Siteworks 187 26-May-20 29-Dec-20 Php4,560,976.63 Php6,531,678.19 Php11,092,654.82 29-Dec-20, Siteworks
SW1000 Structure Excavation and Earthworks 60 26-May-20 03-Aug-20 Php0.00 Php5,163,385.19 Php5,163,385.19 Structure Excavation and Earthworks

SW1010 Embankment, Backfilling, Compaction 90 08-Sep-20 21-Dec-20 Php4,266,100.85 Php1,279,830.26 Php5,545,931.11 Embankment, Backfilling, Compaction including Hauling & Disp
including Hauling & Disposal of Debri

SW1030 Termite Control Work 7 22-Dec-20 29-Dec-20 Php294,875.78 Php88,462.74 Php383,338.52 Termite Control Work
Civil Works 365 04-Aug-20 02-Oct-21 Php23,124,875.05 Php6,937,462.51 Php30,062,337.56 02-Oct-21, Civil Works
Pre-cast Pre-stressed Concrete Piles, Driven 200 04-Aug-20 24-Mar-21 Php13,730,843.91 Php4,119,253.17 Php17,850,097.08 24-Mar-21, Pre-cast Pre-stressed Concrete Piles, Driven
CW1000 Concrete Works for Support Structures 140 04-Aug-20 13-Jan-21 Php9,200,463.51 Php2,760,139.05 Php11,960,602.56 Concrete Works for Support Structures & for Seating Sections
& for Seating Sections

CW1005 Installation of Pre-cast Concrete Planks 60 14-Jan-21 24-Mar-21 Php4,530,380.40 Php1,359,114.12 Php5,889,494.52 Installation of Pre-cast Concrete Planks

Slab Inside Stadium, Driveway & Parking Areas 165 25-Mar-21 02-Oct-21 Php4,906,228.46 Php1,471,868.54 Php6,378,097.00 02-Oct-21, Slab Inside Stadium, Driveway & Parking A
CW1020 Concrete Works for Slab Inside 165 25-Mar-21 02-Oct-21 Php4,906,228.46 Php1,471,868.54 Php6,378,097.00 Concrete Works for Slab Inside Stadium, Driveway/Pa
Stadium, Driveway/Parking Areas

Masonry Works 150 14-Jan-21 07-Jul-21 Php4,487,802.68 Php1,346,340.80 Php5,834,143.48 07-Jul-21, Masonry Works
CW1010 Masonry Works 150 14-Jan-21 07-Jul-21 Php4,487,802.68 Php1,346,340.80 Php5,834,143.48 Masonry Works
Steel Works 210 08-Sep-20 05-Apr-21 Php23,361,334.36 Php7,008,400.31 Php30,369,734.67 05-Apr-21, Steel Works
Roof Trusses 210 08-Sep-20 05-Apr-21 Php23,361,334.36 Php7,008,400.31 Php30,369,734.67 05-Apr-21, Roof Trusses
RT1000 Structural Roof Trusses 120 08-Sep-20 25-Jan-21 Php10,240,115.20 Php3,072,034.56 Php13,312,149.76 Structural Roof Trusses
RT1005 Steel Works for Seat Frames & 60 13-Jan-21 14-Mar-21 Php4,871,142.36 Php1,461,342.71 Php6,332,485.07 Steel Works for Seat Frames & Railings
Railings
RT1010 Roofing System 60 26-Jan-21 05-Apr-21 Php8,250,076.80 Php2,475,023.04 Php10,725,099.84 Roofing System
Architectural Works 250 18-Feb-21 25-Oct-21 Php31,314,530.31 Php9,394,359.10 Php40,708,889.41 25-Oct-21,Architectural Works
Installation of Seating 30 15-Mar-21 17-Apr-21 Php4,846,153.85 Php1,453,846.15 Php6,300,000.00 17-Apr-21, Installation of Seating

Actual Level of Effort Remaining Work Date Revision Checked Approved


Page 3 of 6
06-Mar-20 Proposed Construction Schedule for FCFD ver. 1.0 JAA RGC
Actual Work Critical Remaining Work
Standel Corporation
Construction of Marawi Filipino-Chinese Friendship Dome Proposed Construction Schedule - Level 3 06 March 2020
Marawi City, Lanao Del Sur, Mindanao
Activity ID Activity Name Original Start Finish Budgeted Material Budgeted Labor Budgeted Total CostQ Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q QQ
Duration Cost Cost

AR1010 Supply & Installation of Bleachers 30 15-Mar-21 17-Apr-21 Php4,846,153.85 Php1,453,846.15 Php6,300,000.00 Supply & Installation of Bleachers Fixed Seats (High-Back)
Fixed Seats (High-Back)

Basketball & Volleyball Court 90 18-Feb-21 02-Jun-21 Php4,488,666.28 Php1,346,599.88 Php5,835,266.16 02-Jun-21, Basketball & Volleyball Court
AR1020 Construction of Basketball & Volleyball 90 18-Feb-21 02-Jun-21 Php4,488,666.28 Php1,346,599.88 Php5,835,266.16 Construction of Basketball & Volleyball Court
Court

Function & Changing Rooms, Offices, Toilets, etc 120 25-Mar-21 11-Aug-21 Php7,407,023.05 Php2,222,106.92 Php9,629,129.97 11-Aug-21, Function & Changing Rooms, Offices, Toile
AR1030 Construction of Construction of 120 25-Mar-21 11-Aug-21 Php7,407,023.05 Php2,222,106.92 Php9,629,129.97 Construction of Construction of Function Rooms, Chang
Function Rooms, Changing Rooms,
Kiosks, Media Coverage Rooms, Rest
Rooms, etc.
Gates, Doors & Windows 107 12-Apr-21 27-Jul-21 Php5,080,364.04 Php1,524,109.22 Php6,604,473.26 27-Jul-21, Gates, Doors & Windows
AR1035 Fabrication & Installation of Doors & 90 28-Apr-21 27-Jul-21 Php3,253,422.79 Php976,026.84 Php4,229,449.63 Fabrication & Installation of Doors & Windows
Windows
AR1040 Fabrication & Installation of 60 12-Apr-21 19-Jun-21 Php1,826,941.25 Php548,082.38 Php2,375,023.63 Fabrication & Installation of Performers/Guest Gates & Oth
Performers/Guest Gates & Others

Finishing Works 180 28-Apr-21 25-Oct-21 Php9,492,323.09 Php2,847,696.93 Php12,340,020.02 25-Oct-21, Finishing Works
AR1050 Ceiling, Floor & Wall Tilings, Partitions, 180 28-Apr-21 25-Oct-21 Php9,492,323.09 Php2,847,696.93 Php12,340,020.02 Ceiling, Floor & Wall Tilings, Partitions, etc. & Painting
etc. & Painting Works

Electrical Works 276 22-Dec-20 08-Nov-21 Php21,856,751.68 Php9,511,889.63 Php31,368,641.31 08-Nov-21, Electrical Works
Earthing Works 60 22-Dec-20 01-Mar-21 Php2,948,269.65 Php884,480.89 Php3,832,750.54 01-Mar-21, Earthing Works
EW1000 Grounding & Lighting Arrester 60 22-Dec-20 01-Mar-21 Php2,948,269.65 Php884,480.89 Php3,832,750.54 Grounding & Lighting Arrester

Power & Lighting System 210 08-Jan-21 09-Sep-21 Php9,322,484.12 Php2,796,745.23 Php12,119,229.35 09-Sep-21, Power & Lighting System
EW1010 Electrical Conduit, Pipes & Fittings 120 08-Jan-21 27-May-21 Php4,405,944.82 Php1,321,783.44 Php5,727,728.26 Electrical Conduit, Pipes & Fittings

EW1020 C.O., Switches, Receptacles & Lighting 60 28-May-21 05-Aug-21 Php2,643,566.89 Php793,070.07 Php3,436,636.96 C.O., Switches, Receptacles & Lighting Outlets
Outlets

EW1030 Lighting Fixtures 60 02-Jul-21 09-Sep-21 Php2,272,972.41 Php681,891.72 Php2,954,864.13 Lighting Fixtures
Electrical Equipment 131 09-Jun-21 08-Nov-21 Php9,585,997.91 Php5,830,663.51 Php15,416,661.42 08-Nov-21, Electrical Equipment
EW1040 Panelboards & Circuit Breakers 60 09-Jun-21 17-Aug-21 Php1,379,432.07 Php413,829.62 Php1,793,261.69 Panelboards & Circuit Breakers

EW1050 Electrical Equipment 90 12-Jun-21 24-Sep-21 Php8,078,917.22 Php2,423,675.17 Php10,502,592.39 Electrical Equipment

Actual Level of Effort Remaining Work Date Revision Checked Approved


Page 4 of 6
06-Mar-20 Proposed Construction Schedule for FCFD ver. 1.0 JAA RGC
Actual Work Critical Remaining Work
Standel Corporation
Construction of Marawi Filipino-Chinese Friendship Dome Proposed Construction Schedule - Level 3 06 March 2020
Marawi City, Lanao Del Sur, Mindanao
Activity ID Activity Name Original Start Finish Budgeted Material Budgeted Labor Budgeted Total CostQ Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q QQ
Duration Cost Cost

EW1060 Tapping Connection for Electricity 30 25-Sep-21 29-Oct-21 Php127,648.62 Php38,294.59 Php165,943.21 Tapping Connection for Electricity

EW1070 Testing & Commissioning for Electrical 120 22-Jun-21 08-Nov-21 Php0.00 Php2,954,864.13 Php2,954,864.13 Testing & Commissioning for Electrical System
System
Auxiliary System 240 26-Jan-21 01-Nov-21 Php10,049,368.00 Php4,486,608.00 Php14,535,976.00 01-Nov-21,Auxiliary System
CATV System 60 26-Jan-21 05-Apr-21 Php1,740,228.00 Php522,068.40 Php2,262,296.40 05-Apr-21, CATV System
AS1000 Installation of CATV System 60 26-Jan-21 05-Apr-21 Php1,740,228.00 Php522,068.40 Php2,262,296.40 Installation of CATV System

Voice & Data System 60 06-Apr-21 14-Jun-21 Php1,600,228.00 Php480,068.40 Php2,080,296.40 14-Jun-21, Voice & Data System
AS1020 Installation of Voice & Data System 60 06-Apr-21 14-Jun-21 Php1,600,228.00 Php480,068.40 Php2,080,296.40 Installation of Voice & Data System

Fire Detection & Alarm System 90 15-Jun-21 27-Sep-21 Php2,236,304.00 Php670,891.20 Php2,907,195.20 27-Sep-21, Fire Detection & Alarm System
AS1040 Installation of FDAS 90 15-Jun-21 27-Sep-21 Php2,236,304.00 Php670,891.20 Php2,907,195.20 Installation of FDAS
CCTV System 60 06-Apr-21 14-Jun-21 Php1,747,228.00 Php524,168.40 Php2,271,396.40 14-Jun-21, CCTV System
AS1070 Installtion of CCTV System 60 06-Apr-21 14-Jun-21 Php1,747,228.00 Php524,168.40 Php2,271,396.40 Installtion of CCTV System

Background Music & Paging System 60 08-Jul-21 15-Sep-21 Php1,607,228.00 Php482,168.40 Php2,089,396.40 15-Sep-21, Background Music & Paging System
AS1100 Installation of BMPS 60 08-Jul-21 15-Sep-21 Php1,607,228.00 Php482,168.40 Php2,089,396.40 Installation of BMPS
Clock System 60 15-Jun-21 23-Aug-21 Php1,118,152.00 Php335,445.60 Php1,453,597.60 23-Aug-21, Clock System
AS1120 Installation of Clock System 60 15-Jun-21 23-Aug-21 Php1,118,152.00 Php335,445.60 Php1,453,597.60 Installation of Clock System

Testing & Commissioning for Auxiliary System 90 20-Jul-21 01-Nov-21 Php0.00 Php1,471,797.60 Php1,471,797.60 01-Nov-21, Testing & Commissioning forAuxiliary Sy
AS1130 Testing & Commissioning forAuxiliary 90 20-Jul-21 01-Nov-21 Php0.00 Php1,471,797.60 Php1,471,797.60 Testing & Commissioning for Auxiliary System
System
Plumbing Works 269 22-Dec-20 30-Oct-21 Php7,310,660.00 Php3,489,360.00 Php10,800,020.00 30-Oct-21, Plumbing Works
PW1000 Plumbing Pipes & Fittings 120 22-Dec-20 10-May-21 Php2,162,902.00 Php648,870.60 Php2,811,772.60 Plumbing Pipes & Fittings
PW1010 Plumbing Fixtures 60 06-Apr-21 14-Jun-21 Php1,665,006.00 Php499,501.80 Php2,164,507.80 Plumbing Fixtures
PW1020 Pumps Installation 30 15-Jun-21 19-Jul-21 Php883,792.00 Php265,137.60 Php1,148,929.60 Pumps Installation
PW1025 Sewer System 60 11-May-21 19-Jul-21 Php1,237,110.00 Php371,133.00 Php1,608,243.00 Sewer System
PW1030 Waterline Connection 30 20-Jul-21 23-Aug-21 Php1,361,850.00 Php408,555.00 Php1,770,405.00 Waterline Connection
PW1050 Testing for Plumbing Works 89 20-Jul-21 30-Oct-21 Php0.00 Php1,296,162.00 Php1,296,162.00 Testing for Plumbing Works
Mechanical Works 276 22-Dec-20 08-Nov-21 Php6,408,218.50 Php4,163,554.27 Php10,571,772.77 08-Nov-21, Mechanical Works
Fire Protection Pipings & Accessories 120 22-Dec-20 10-May-21 Php4,485,752.95 Php1,922,465.55 Php6,408,218.50 10-May-21, Fire Protection Pipings & Accessories

Actual Level of Effort Remaining Work Date Revision Checked Approved


Page 5 of 6
06-Mar-20 Proposed Construction Schedule for FCFD ver. 1.0 JAA RGC
Actual Work Critical Remaining Work
Standel Corporation
Construction of Marawi Filipino-Chinese Friendship Dome Proposed Construction Schedule - Level 3 06 March 2020
Marawi City, Lanao Del Sur, Mindanao
Activity ID Activity Name Original Start Finish Budgeted Material Budgeted Labor Budgeted Total CostQ Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q QQ
Duration Cost Cost

MW1000 Fire Protection Pipe, Fittings, Supports 120 22-Dec-20 10-May-21 Php4,485,752.95 Php1,922,465.55 Php6,408,218.50 Fire Protection Pipe, Fittings, Supports and Brackets
and Brackets

Automated Fire Sprinkler System 173 02-Apr-21 20-Oct-21 Php1,922,465.55 Php823,913.81 Php2,746,379.36 20-Oct-21,Automated Fire Sprinkler System
MW1010 Installation of Automatic Fire Sprinkler 120 02-Apr-21 19-Aug-21 Php1,281,643.70 Php549,275.87 Php1,830,919.57 Installation of Automatic Fire Sprinkler Heads & Fire Hos
Heads & Fire Hose Cabinets w/
Accessories

MW1020 Valves for Fire Protection, Flow & 120 03-Jun-21 20-Oct-21 Php640,821.85 Php274,637.94 Php915,459.79 Valves for Fire Protection, Flow & Monitoring Switches
Monitoring Switches

Testing & Commissioning for Mechanical 120 22-Jun-21 08-Nov-21 Php0.00 Php1,417,174.91 Php1,417,174.91 08-Nov-21, Testing & Commissioning for Mechanica
MW1030 Testing & Commissioning for 120 22-Jun-21 08-Nov-21 Php0.00 Php1,417,174.91 Php1,417,174.91 Testing & Commissioning for Mechanical System
Mechanical System
Other Works 456 26-May-20 08-Nov-21 Php10,237,715.54 Php3,071,314.65 Php13,309,030.19 08-Nov-21, Other Works
OW1010 Formworks & Scaffolding 354 08-Sep-20 25-Oct-21 Php3,523,961.57 Php1,057,188.47 Php4,581,150.04 Formworks & Scaffolding
OW1015 Temporary Perimeter Fence 402 26-May-20 06-Sep-21 Php1,955,530.88 Php586,659.26 Php2,542,190.14 Temporary Perimeter Fence

OW1020 Waterproofing Works 90 29-Apr-21 11-Aug-21 Php1,779,238.47 Php533,771.54 Php2,313,010.01 Waterproofing Works
OW1030 Softscape & Hardscape 55 06-Sep-21 08-Nov-21 Php1,629,492.31 Php488,847.69 Php2,118,340.00 Softscape & Hardscape
OW1040 Murals & Signages 55 06-Sep-21 08-Nov-21 Php1,349,492.31 Php404,847.69 Php1,754,340.00 Murals & Signages
Project Closing 55 06-Sep-21 08-Nov-21 Php0.00 Php0.00 Php0.00 08-Nov-21, Project Closing
PC1000 Complete All Works, T&C, Close Out 55 06-Sep-21 08-Nov-21 Php0.00 Php0.00 Php0.00 Complete All Works, T&C, Close Out Docs., Ready fo
Docs., Ready for Initial Acceptance &
Inspection
Demobilization 55 06-Sep-21 08-Nov-21 Php0.00 Php381,360.02 Php381,360.02 08-Nov-21, Demobilization
DW1000 Demobilization of Manpower, Tools & 55 06-Sep-21 08-Nov-21 Php0.00 Php381,360.02 Php381,360.02 Demobilization of Manpower, Tools & Equipment
Equipment

Actual Level of Effort Remaining Work Date Revision Checked Approved


Page 6 of 6
06-Mar-20 Proposed Construction Schedule for FCFD ver. 1.0 JAA RGC
Actual Work Critical Remaining Work
Standel Corporation