Progress Tracking Sheet-Piping Fabrication: Enter % Complete For Each Work Step

You might also like

Download as xls, pdf, or txt
Download as xls, pdf, or txt
You are on page 1of 1

Progress Tracking Sheet-Piping Fabrication

Spool
Weld map Full Non Surface
Withdrew Welding Assemble Final Deliver at
drawing welding Destructive preparation
material preparation and tack Inspection site
preparation execution Examination and coating
weld

Work Pack

Weighting

Individual
(Dia-inch)

Man hour

Progress

Progress
Drawing

Project

Overall
Quantity
Area
Item

4% 3% 20% 25% 20% 6% 15% 4% 3%

1 ISO-011 A WP-001 80.0 450 0.03 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 0.032
2 ISO-012 A WP-001 90.0 600 0.04 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 0.043
3 ISO-013 A WP-001 50.0 260 0.02 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 0.019
4 ISO-014 A WP-001 38.3 210 0.02 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 0.015
5 ISO-015 A WP-001 44.5 250 0.02 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 0.018
6 ISO-016 A WP-001 100.0 520 0.04 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 0.037
7 ISO-017 A WP-02 120.0 709 0.05 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 0.051
8 ISO-018 A WP-02 181.0 1000 0.07 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 0.071
9 ISO-019 A WP-02 200.0 1300 0.09 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 0.093
10 ISO-020 A WP-02 96.0 701 0.05 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 0.050
11 ISO-021 B WP-02 200.0 1250 0.09 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 0.089
12 ISO-022 B WP-02 231.0 1280 0.09 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 0.091
13 ISO-023 B WP-02 100.0 550 0.04 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 0.039
14 ISO-024 B WP-02 230.0 1200 0.09 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 0.086
15 ISO-025 B WP-03 200.0 1025 0.07 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 0.073
16 ISO-026 B WP-03 120.0 600 0.04 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 0.043
17 ISO-027 B WP-03 150.0 750 0.05 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 0.054
18 ISO-028 B WP-03 20.5 103 0.01 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 0.007
19 ISO-029 B WP-03 42.0 210 0.02 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 0.015
20 ISO-030 B WP-04 120.0 600 0.04 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 0.043
21 ISO-031 B WP-04 27.0 135 0.01 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 0.010
22 ISO-032 B WP-04 59.5 298 0.02 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 0.021

Progress Summary by Project Area-Piping Fabrication Progress Summary by Work Pack-Piping Fabrication

Work Pack)
Weighting(
Enter % complete for

Work Pack
Weighting
(Dia-inch)

Man hour

Progress

Progress

Progress

Progress
by Work
by Area
Project

Overall

Overall
Quantity

each work step

Pack
Area

A 1000 6000 0.43 100% 42.9% WP-001 0.164 100% 16%


B 1500 8000 0.57 100% 57.1% WP-02 0.571 100% 57%
WP-03 0.192 100% 19%
WP-04 0.074 100% 7%
Total 2500 14000 1.00 100.0% 1.00 100%