Professional Documents
Culture Documents
Progress Tracking Sheet-Piping Fabrication: Enter % Complete For Each Work Step
Progress Tracking Sheet-Piping Fabrication: Enter % Complete For Each Work Step
Progress Tracking Sheet-Piping Fabrication: Enter % Complete For Each Work Step
Spool
Weld map Full Non Surface
Withdrew Welding Assemble Final Deliver at
drawing welding Destructive preparation
material preparation and tack Inspection site
preparation execution Examination and coating
weld
Work Pack
Weighting
Individual
(Dia-inch)
Man hour
Progress
Progress
Drawing
Project
Overall
Quantity
Area
Item
1 ISO-011 A WP-001 80.0 450 0.03 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 0.032
2 ISO-012 A WP-001 90.0 600 0.04 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 0.043
3 ISO-013 A WP-001 50.0 260 0.02 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 0.019
4 ISO-014 A WP-001 38.3 210 0.02 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 0.015
5 ISO-015 A WP-001 44.5 250 0.02 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 0.018
6 ISO-016 A WP-001 100.0 520 0.04 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 0.037
7 ISO-017 A WP-02 120.0 709 0.05 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 0.051
8 ISO-018 A WP-02 181.0 1000 0.07 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 0.071
9 ISO-019 A WP-02 200.0 1300 0.09 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 0.093
10 ISO-020 A WP-02 96.0 701 0.05 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 0.050
11 ISO-021 B WP-02 200.0 1250 0.09 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 0.089
12 ISO-022 B WP-02 231.0 1280 0.09 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 0.091
13 ISO-023 B WP-02 100.0 550 0.04 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 0.039
14 ISO-024 B WP-02 230.0 1200 0.09 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 0.086
15 ISO-025 B WP-03 200.0 1025 0.07 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 0.073
16 ISO-026 B WP-03 120.0 600 0.04 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 0.043
17 ISO-027 B WP-03 150.0 750 0.05 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 0.054
18 ISO-028 B WP-03 20.5 103 0.01 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 0.007
19 ISO-029 B WP-03 42.0 210 0.02 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 0.015
20 ISO-030 B WP-04 120.0 600 0.04 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 0.043
21 ISO-031 B WP-04 27.0 135 0.01 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 0.010
22 ISO-032 B WP-04 59.5 298 0.02 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 0.021
Progress Summary by Project Area-Piping Fabrication Progress Summary by Work Pack-Piping Fabrication
Work Pack)
Weighting(
Enter % complete for
Work Pack
Weighting
(Dia-inch)
Man hour
Progress
Progress
Progress
Progress
by Work
by Area
Project
Overall
Overall
Quantity
Pack
Area