Professional Documents
Culture Documents
Storage of Materials: Engineering Encyclopedia Project Management Managing Materials During Construction
Storage of Materials: Engineering Encyclopedia Project Management Managing Materials During Construction
• A Place to Work
In order to have the correct material available when needed, the material must arrive at jobsite, be
inspected and protected, stored where it can be found, issued to the right person, and used where
it was intended. Field material control encompasses the remaining steps from receipt to end use.
The construction warehouse/storage function is responsible for material control from receipt to
issue.
Storage of Materials
With materials representing over 40% of the costs of a typical project the proper handling and
storage can impact the success of the project. The Project Engineer should pay particular
attention to the maintenance and record keeping associated with the storage of materials at the
jobsite. Remember, it is just as important to keep the incorrect material out of the project, as it is
to get the correct material into the project.
Maintenance
The proper maintenance of project materials not only prior to being installed but prior to the on-
stream date are important to assuring the material will function properly when required to do so.
Protective maintenance should be continued after release from warehouse control and when
material or equipment is installed in the final location. Following is a list of items which the
Project Engineer will want to become familiar with.
• Materials should be kept off the ground on pallets, sleepers, dunnage, temporary
concrete slabs, etc.
• Lube oil in machinery should be checked periodically for level and cleanliness.
• Piping should be capped to keep out dirt and debris and to protect ends.
• Paints and other highly flammable materials should be kept in segregated storage
and at safe distance. Responsible personnel must be clearly designated and
reporting requirements established.
Record Keeping
Job Procedure should cover protective maintenance of materials and equipment at the jobsite from
time of receipt until such materials or equipment are turned over ready for commissioning.
Protection includes protection from weather, environment, physical damage and any other
potential damage or deterioration. Periodic inspections should be made of materials in open
storage.
Accurate records must be kept to record the acceptance and issue of materials from the jobsite
storage area to the jobsite. The loss of almost any item can jeopardize the completion of the
project. Objectives of field material record keeping are:
• That claims are filed promptly for items damaged in shipment or shortages in
shipments
Introduction
A well executed project should have no more than 3% or 4% material surplus or excess at the end
of commissioning. Excessive materials which are surplus or excess are usually an indication of
unsatisfactory material control or significant late changes in the scope of work.
New or good-as-new DC surplus material can be turned in to DC surplus inventory for full credit
by completing Form A-7287 provided the material:
• Is not shown on the list “Materials not acceptable for DC surplus inventory”; and
Items with a line item value of $1,000 or less are transferred to Dhahran Reclamation Yard for no
credit by use of Form A-112 “Reclamation Receipt."
There are three exceptions to the above limitation of $1,000 or less value. They are:
• Portions of a major assembly which have already been accepted for DC surplus
inventory; or
• Specialized fittings for items which have already been accepted for DC surplus
inventory.
DC material which is not acceptable for turn-in to DC surplus inventory but is salable is
transferred to the Auction Yard with Form A-8764 “New or Good-as-New Material Disposition”
at appraised value, based on the return obtained on similar material at recent auctions.
DC material with a line item value greater than $1,000 that is in new or good-as-new and
unsalable is transferred to Reclamation with Form A-8764 at zero value.
DC material with a line item value greater than $1,000 that is not new or good-as-new and
unsalable is transferred to Reclamation with Form A-112 at zero value.
Material that has been previously issued to users from DC surplus inventory is returned by users
for credit equal to the original issue cost. Users that want to return material to DC surplus
inventory must provide R&DCU with a copy of the original issue document.
Material which is no longer in new or good-as-new condition is not accepted for return but is
transferred to Reclamation with Form A-112 at zero value. Material which has been modified
after issue is rarely accepted for return to DC surplus inventory.
• SAMS material
• Ferrous scrap
• Gas cylinders
• Gaskets