Towards Last Planner System Implementation in Gaza Strip

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 19

International Journal of Construction Management

ISSN: 1562-3599 (Print) 2331-2327 (Online) Journal homepage: http://www.tandfonline.com/loi/tjcm20

Towards Last Planner System Implementation in


Gaza Strip, Palestine

Osama Abusalem

To cite this article: Osama Abusalem (2018): Towards Last Planner System Implementation
in Gaza Strip, Palestine, International Journal of Construction Management, DOI:
10.1080/15623599.2018.1484861

To link to this article: https://doi.org/10.1080/15623599.2018.1484861

Published online: 01 Oct 2018.

Submit your article to this journal

View Crossmark data

Full Terms & Conditions of access and use can be found at


http://www.tandfonline.com/action/journalInformation?journalCode=tjcm20
INTERNATIONAL JOURNAL OF CONSTRUCTION MANAGEMENT
https://doi.org/10.1080/15623599.2018.1484861

Towards last planner system implementation in Gaza Strip, Palestine


Osama Abusalem
Department of Engineering Management and Enterprise, University of Debrecen, Debrecen, Hungary

ABSTRACT KEYWORDS
The Gaza Strip’s construction industry in Palestine is suffering from the existence of unreliable control; lean construction;
production plans with great variability. One of the innovative solutions to avoid, eliminate or at last planner system;
least reduce plan variation is the adoption of last planner system (LPS). This research highlights planning; workflow
the importance of eliminating plan variation in the production planning and control process in
Gaza Strip as a key improvement in the delivery process of construction projects through the
use of LPS. This research applies a survey strategy that uses two data collection methods,
including questionnaire and interview. The results show that several elements of LPS already
exist in Gaza Strip. Nevertheless, these elements do not follow the same approach of LPS. The
main challenge is the involvement of many subcontractors. The primary variation cause is the
unavailability of materials. The critical success factor is the top management support.

Introduction can be achieved by improving management practices


(Ballard 2000; Koskela 2000). One significant initiative
The construction industry has an extremely complex
has been the adoption of lean construction (LC).
and dynamic nature. This nature can be attributed to
Since 1992, LC has evolved as a new way to manage
the interaction of multiple variables and diverse work-
construction projects more efficiently and effectively.
flows. These two traits resulted in uncertainty as an
LC was taken from lean production (LP) that can be
inherent feature of construction (Ballard 2000;
traced to Toyota production system (TPS; Ballard
Koskela 2000). Linguistically, uncertainty means the
2000). LC is ‘a way to design production systems to
‘presence of doubt, changeability, lack of assurance or
minimize waste of materials, time, and effort in order
reliability’ (Hornby 1974) . The uncertainty compro-
to generate the maximum possible amount of value in
mises the reliability of planning and control methods construction’ (Koskela 2000). Diverse LC techniques
by making the construction projects more susceptible have been developed and successfully applied to sim-
to variation (Ballard and Howell 1994). Variation is ple and complex construction projects. The most
‘the difference between what was planned and what remarkable LC technique is last planner system (LPS),
actually happened’ (Wambeke et al. 2012). The vari- which is a production planning and control system to
ation leads to overdue of project delivery, cost over- improve workflow reliability (Ballard 2000). Many
run, less productivity and decreasing the value of the studies all over the world have been carried out to
overall project outputs by increasing the amount of study the applications of LC, especially LPS.
waste (Howell et al. 1993; Ballard and Howell 1994; Nevertheless, the literature review shows no evidence
Howell and Ballard 1994a; Hopp and Spearman 1996; of existing research or practical applications regarding
Ballard 2000; Koskela 2000; Vrijhoef and Koskela LPS in Gaza Strip, Palestine. Therefore, this is the
2000; London and Kenley 2001; Alves 2005; Green first comprehensive academic research that addresses
et al. 2005). Causes of unreliable production plans the implementation of LPS in this territory. This
cluster around two issues: (1) project environment research highlights the importance of eliminating plan
factors: are uncontrollable external factors that have variation in the production planning and control pro-
to be taken as given in any construction project and cess in Gaza Strip as a key improvement in the deliv-
(2) management factors: are controllable internal fac- ery process of construction projects through the use
tors and efforts should be directed towards minimiz- of LPS. It contributes to help the contracting firms to
ing their impact. Arguably, controlling such causes establish new strategies and policies to improve their

CONTACT Osama Abusalem o.abusalem@hotmail.com


ß 2018 Informa UK Limited, trading as Taylor & Francis Group
2 O. ABUSALEM

managerial practices by using the findings of this 1994). Assignments are ‘a directive or order given to a
research as a reference. Moreover, it forms a basis for worker or workers directly producing or contributing to
the development of further researches in the area of the production of design or construction’ (Ballard
LPS. This research has three main objectives: (1) pro- 2000). The LPS argues that since last planners are famil-
vides a broader overview of the actual state of LPS iar with the construction production process and closer
implementation worldwide, (2) investigates the extent to the site, it is more appropriate that they provide
of implementing the LPS in Gaza Strip and (3) inputs into WWP through adding details and commit-
assesses the challenges, variation causes and critical ment to what can actually be achieved in the upcoming
success factors (CSFs) that may affect the future week (Ballard 1994). The results indicated that the fre-
implementation of LPS in Gaza Strip. quency and severity of uncertainty significantly increase
as one moves from project manager to superintendent
to foreman (Russell et al. 2013).
Literature review
The LPS learns from past failures and successes by
The LPS was originated by Glenn Ballard and following the Shewhart plan-do-check-act cycle (made
Gregory Howell in 1992, in the discovery that only an popular by W. Edwards Deming) for a continuous
average of 54% of tasks on weekly plans was com- improvement process (Ballard 2000).
pleted from over 450 weeks of numerous projects in Kim and Ballard (2010) argued that the LPS
both design and construction of seven highly regarded appears to reflect managing-by-means thinking rather
construction companies (Ballard and Howell 1998). than managing-by-results thinking based on the fol-
The LPS has five principles: (1) plans in greater detail lowing: (1) assuming that scheduled tasks include
as you get closer to doing the work, (2) produces plans uncertainty and constraints and highly interdepend-
collaboratively with those who will do the work, (3) ent, (2) monitoring focuses on planning reliability,
reveals and removes constraints on planned tasks as a not on financial metrics and (3) management deci-
team, (4) makes and secures reliable promises and (5) sions are based on planning reliability, a prerequisite
learns from breakdowns (Ballard et al. 2009). to cost and progress measures.
The LPS classifies tasks into four categories: (1) The LPS consists of four levels hierarchy of planning,
SHOULD: represents tasks that need to be done, (2) including the master plan, phase plan, look-ahead plan
CAN: represents tasks made ready from what and WWP, not to mention the several tools and metrics
SHOULD be done, (3) WILL: represents tasks com- (Ballard 2000). The master plan sets milestones and key
mitted to be done from what CAN be done and (4) dates. The phase plan specifies handoffs between trades.
DID: represents tasks completed from what WILL be The look-ahead plan makes tasks ready. The WWP
done (Ballard 2000). specifies individual assignments. The percent plan com-
The LPS has two levels of control: (1) production plete (PPC) tracks progress.
unit control aims to progressively make better assign-
ments to direct workers through continuous learning
Methodology
and corrective actions, that is, as in the weekly work
plan (WWP) and (2) workflow control seeks to pro- This research consists of three stages. The first stage
actively cause work to flow across production units in represents the secondary data collection stage. This
the best achievable sequence and rate, that is, as in stage conducts an intensive review of the available lit-
the look-ahead plan (Ballard 2000). erature to determine the benefits, challenges, variation
The production control has two primary approaches for causes and CSFs associated with LPS implementation
controlling the workflow in the production systems: (1) in diverse environments around the world. The
push approach releases materials or information into a sys- author argues that a single study is extremely valuable
tem based on preassigned due dates from the master pro- when researching typical studies that serve a demon-
duction schedule and (2) pull approach releases materials strative purpose. Nevertheless, it is not appropriate
or information into a system based on the state of the sys- for researchers and construction professionals to build
tem (the ability to do the work; Hopp and Spearman 1996). their conclusions based on the results of a single
The name of LPS was inspired from the ‘last study for their projects and their specific implementa-
planner’, typically the foreman (Ballard 2000). The last tion of LPS. Consequently, this stage summarizes the
planner is ‘the person or group of people accountable findings of 34 studies around the world to offer a
for production unit control’. This means completion of broader overview of the actual state of LPS implemen-
individual assignments at the operational level (Ballard tation in construction projects (Table 1). The second
Table 1. List of studies.
Study Reference Methodology Description
S1 Adamu and Howell (2012) Case study Implementing LPS on 50 housing units in Damaturu, Nigeria
S2 Ahiakwo et al. (2013) Action research with different data collection Implementing LPS on one of four prototype hostel buildings
methods (questionnaire, interview, observation and of a federal university in the North Central region of Nigeria
documentary analysis)
S3 AlSehaimi et al. (2014) Action research with different data Implementing LPS on two large state-owned construction projects in Saudi Arabia
collection methods (questionnaire, interview and
observation)
S4 Brady et al. (2011) Literature review Examining the barriers to LPS implementation
S5 Cervero-Romero et al. (2013) Action research with different data collection Implementing LPS on seven case studies in Mexico
methods (questionnaire, interview and observation)
S6 Daniel et al. (2014) Questionnaire and interview Analysing the non-value adding activities by conducting 40 questionnaires and three
interviews with the registered contractors and construction professionals in the aca-
demia in Lagos Metropolis, Nigeria
S7 Enshassi and Abu Zaiter (2014) Questionnaire Investigating the implementation of lean tools in construction projects and its impact
on safety conditions by distributing 31 questionnaires on contractors and clients in Gaza
Strip, Palestine
S8 Fauchier and Alves (2013) Observation Observing 15 teams applied LPS on nine projects in Northern and Southern California
between 2010 and 2013
S9 Fernandez-Solis et al. (2013) Literature review and questionnaire The literature review covers the benefits and challenges of 26 case studies. The ques-
tionnaire assesses the challenges faced by senior and mid-level management during the
implementation of LPS
S10 Fuemana and Puolitaival (2013) Interview Six interviews with three large main contracting companies having an average of 5
years of experience with LPS in Auckland, New Zealand
S11 Gao and Low (2014) Interview Interviews with 27 experienced Chinese building professionals from 16 large Chinese
construction firms between February and May of 2011 to identify the strengths, weak-
nesses, opportunities and threats factors of LPS implementation
S12 Hamzeh (2009) Case study and simulation The case study applies LPS on a hospital rehabilitation project in San Francisco,
California. The analytical simulation model analyses the look-ahead planning process
S13 Hamzeh (2011) Literature review and action research The literature review covers the challenges of LPS implementation. The action research
involves three case studies (a health care project, a research facility and an administra-
tion building) of applying LPS
S14 Hamzeh and Aridi (2013) Modelling Studying the relationship between tasks anticipated (TA), tasks made ready and PPC
by analysing LPS data collected over 2 years from several branches of a construction
company in the United States
S15 Hamzeh and Langerud (2011) Simulation Investigating the impact of improving the TA in look-ahead planning process on the
reliability of WWP expressed as PPC
S16 Hamzeh et al. (2015) Simulation Exploring the relationship between improving the TA in look-ahead planning and overall
project duration
S17 Issa (2013) Case study Implementing LPS on an industrial project in Egypt
S18 Khan and Tzortzopoulos (2014) Action research Implementing the WWP of LPS on two building information modelling-based building
design projects
S19 Koskela et al. (2010) Comparative analysis Comparing LPS and critical chain in construction management
S20 Koskenvesa and Koskela (2012) Literature review Evaluating and summarizing the diffusion of LPS in Finland through analysing pilot
projects, education offerings and company policies from 2003 to 2011
S21 Leigard and Pesonen (2010) Interview Interviewing experts in human behaviour and implementation with an experience in
implementing LPS on over 60 projects in a construction company in Finland between
2008 and 2010
S22 Leino and Elfving (2011) Action research with different data Applying LPS on three construction sites in Finland between 2007 and 2010
INTERNATIONAL JOURNAL OF CONSTRUCTION MANAGEMENT

collection methods (meeting, discussion and personal survey)


(continued)
3
4
O. ABUSALEM

Table 1. Continued.
Study Reference Methodology Description
S23 McConaughy and Shirkey (2013) Action research with different 250 questionnaires, an interview with LC expert of 40 years of experience in construc-
data collection methods tion and 9 years of experience in LC coaching and consulting and observations of three
(questionnaire, interview and observation) construction projects implementing LPS
S24 Mota et al. (2010) Simulation Simulating LPS with systems dynamic model
S25 Nieto-Morote and Ruz-Vila (2012) Case study Applying LPS on a chemical plant construction project in Spain
S26 Ochoa (2014) Case study Investigate the effectiveness of using LPS method in reducing plan variations in a
sustainable building project consists of two towers in Hong Kong
S27 Porwal et al. (2010) Literature review Identifying the challenges faced by construction professionals during the implementa-
tion and use of LPS at organizational and project levels
S28 Priven and Sacks (2013) Case study Applying LPS on the interior finishing works of eight residential building construc-
tion projects
S29 Rosas (2013) Case study and modelling Integrating the design structure matrix and the LPS into building design for building
over 430 residential houses among other non-residential buildings in the Peruvian
Andes zone
S30 Russell et al. (2013) Questionnaire Distributing 180 questionnaires on 36 different companies, including both general
contractors and subcontractors, throughout the United States to study the application
of time buffers to construction project task durations
S31 Russell et al. (2015) Case study Two case studies (a mechanical contractor, who uses the traditional management and a
general contractor, who uses the LPS) to investigate the allocation and reduction of
time buffer
S32 Seppanen et al. (2010) Literature review, workshop and interview Combining LPS and location-based management system by using Skanska Finland’s
practical experience, a series of workshops conducted at Cathedral Hill hospital project
in San Francisco, interviewing three California general contractors with some expertise
in both systems
S33 Viana et al. (2010) Questionnaire and interview Conducting questionnaire and interview surveys with the site engineers, foremen and
crew leaders from 16 construction companies that implement LPS in the South of Brazil
S34 Wambeke et al. (2012) Case study Using LPS and a risk assessment matrix to reduce variation in mechanical-related con-
struction tasks by comparing two separate but similar projects, one of them uses LPS
INTERNATIONAL JOURNAL OF CONSTRUCTION MANAGEMENT 5

and third stages represent the primary data collection questionnaire survey is 139 contracting firms with a per-
stage. The second stage investigates the extent of imple- centage of 64% of the population. About 150 question-
menting the LPS in Gaza Strip. The third stage employs naires were distributed randomly with only one copy for
the findings of the first stage to assess the challenges, each contracting firm. However, some of the contracting
variation causes and CSFs that may affect the future firms had no interest in contributing to this research.
implementation of LPS in Gaza Strip. This research Therefore, 145 valid questionnaires were received back
applies a survey strategy that uses two data collection from the contracting firms. The contribution of every fac-
methods, including questionnaire and interview. This is tor to each table in the questionnaire was examined and
in line with the recommendations of Saunders et al. the ranking of the items regarding their importance as
(2016), who suggested that this strategy is best suited to comprehended by the respondents was done by using the
exploratory research. The survey strategies that utilize relative importance index (RII). The use of questionnaire
questionnaires are widespread as they facilitate the col- has some limitations, such as it must contain simple ques-
lection and comparison of standardized data from a tions, there is no control over respondents and it forces
sizeable population in an extremely economical manner respondents to choose from available alternatives that may
(Saunders et al. 2016). The questionnaire consists of not be the true reflection of their opinions (Saunders et al.
three main parts: (1) background of respondents, (2) 2016). Therefore, a personal, semi-structured, and open-
investigation of the extent of implementing LPS and (3) ended interview survey was conducted in order to obtain
assessment of the challenges, variation causes and CSFs further and more in-depth information that cannot easily
that may affect the future implementation of LPS. The be captured by the questionnaire survey. The interview
questionnaire uses a self-administration mode with survey allows to have a comprehensive analysis and to
closed-ended and open-ended questions. The closed- cross validate the results of the collected quantitative data
ended questions are as follows: (1) Likert-style rating (Saunders et al. 2016). The minimum sample size for semi-
questions (strongly disagree, disagree, neutral, agree and structured and in-depth interviews should be within the
strongly agree), (2) rating questions (very low, low, range from 5 to 25 (Saunders 2012). Thereby, 25 interviews
medium, high and very high), (3) dichotomous ques- were conducted with 5 company directors, 10 project man-
tions (yes or no) and (4) multiple-choice questions. The agers and 10 site engineers from different contracting firms
questionnaire uses the five-point scale because the with more than 5 years of experience in construction. The
respondents find it difficult to distinguish between val- duration of an interview ranged from 1 to 2 hours. The
ues when the rating is more than five points (Saunders topics covered in the interview survey are the same topics
et al. 2016). A pilot study was conducted by distributing addressed in the questionnaire survey. The author could
the initial questionnaire to a panel of eight experts. Five not apply an action research strategy. This limitation is due
of these experts are academics, whereas three of them to the lack of time and resources.
are construction professionals with more than 10 years
of experience. The purpose of the pilot study is to iden- Findings
tify the strength and weakness points in the question-
naire to make the necessary changes and to ensure First stage: review
valuable feedbacks (Saunders et al. 2016). The investi- Via its implementation in many countries and the
gated population by both the questionnaire and interview rapid development of this decentralized system of
surveys is limited to the classified contracting firms under production planning and control, the LPS has proven
all classifications and disciplines that have a valid registra- to be a powerful system for the management of con-
tion in the Palestinian Contractors Union in Gaza Strip. struction projects and has won recognition from prac-
The number of registered and classified contracting firms titioners all over the world (Table 2). Researchers and
is 217 firms. The minimum sample size of the construction professionals reported several challenges

Table 2. Summary of the benefits of LPS.


No. Benefit Study
1 Improving planning and control reliability S3, S5, S6, S9, S10, S18, S19, S20, S23, S24, S25, S26, S29, S31, S33, S34
2 Increasing of PPC S1, S2, S3, S12, S14, S15, S17, S24, S25, S26, S29, S31, S32
3 Reducing the time of project delivery S1, S2, S3, S6, S9, S10, S16, S17, S31, S32
4 Improving information flow S3, S5, S6, S8, S9, S18, S23, S28, S31
5 Reducing project cost S2, S6, S9, S19, S31, S34
6 Improving productivity S9, S10, S19, S26, S34
7 Improving health and safety S7, S19, S22
8 Reducing time buffers S30, S31
6 O. ABUSALEM

faced by them during LPS implementation. These classifications, such as the first A, first B and second
challenges limited the potential capabilities and bene- in buildings and roads as well as the first, second and
fits that could be gained from the full application of third in water and sewer and electro-mechanical.
LPS. Regardless of these challenges, the implementa-
tion of LPS is on the rise. The existence of these chal- Planning system
lenges does not indicate a deficiency within LPS.
About 100% of the respondent contracting firms use
Most likely, it reflects a failure to follow the same
only the traditional planning and control systems (i.e.
approach of LPS. This is mainly because of the
not the LPS). This result confirms that the LPS is a
attempts to implement LPS within poor environ-
new concept to the Gaza Strip’s construction industry
ments, where the necessary conditions for the max-
in Palestine.
imum utilization of the inherent potentials of LPS are
missing (Table 3). Understanding and addressing the
Levels of planning
causes of variation (reasons for incomplete assign-
ments according to what has been planned during the Master plan. 100% of the respondent contracting
project) will help us to avoid, eliminate or at least firms use a similar master plan to the LPS. As discov-
reduce their occurrence and associated adverse impact ered from the interviews, planning is mainly based on
(Table 4). The successful full implementation of LPS a master plan presented on a bar chart. The master
requires a set of CSFs that can serve as a guiding map plan is provided as a mandatory requirement for the
throughout the use of the system (Table 5). Although bidding documents to the client before the com-
there are likely additional benefits, challenges, vari- mencement of the project. One interviewee clari-
ation causes and CSFs regarding the implementation fied that
of LPS, this study addresses only those specifically
Master plan cannot be heavily relied upon alone in
reported by previous researchers from the litera- meeting the requirements of planning. It just sets the
ture review. milestones and key dates without going into details.
Therefore, at this level of planning, there is a great
likelihood of generating uncertainty that leads to
Second stage: investigation plan variation.
Background of respondents Phase plan. 63.9% of the respondent contracting
Table 6 shows the background of 145 respondents, firms use a phase plan. As pointed out by the inter-
who returned back valid questionnaires. The numbers viewees, the used phase plan does not follow the same
indicate that the size of contracting firms and projects approach of the phase plan in LPS. Although the used
in Gaza Strip is small compared to other countries. phase plan generates more detailed and manageable
The following promotes the validity of the obtained plan covering each project phase based on targets and
results: (1) the close percentages of the job title since milestones from the master plan, it is not a collabora-
LPS depends on the decentralization of the produc- tive planning practice. Specifying handoffs between
tion planning and control process through involving specialists, including the rules for releasing work to
parties from different levels of the hierarchy of man- move from one activity to the next, is missing. They
agement, (2) 91.7% of the respondent contracting do not apply the pull approach from successor mile-
firms have sufficient experience in construction with stones by using the reverse phase scheduling.
over than 5 years and (3) the percentages of classifica- Moreover, they do not use ‘stickies on a wall’ tech-
tion since, arguably, the contracting firms that have a nique to develop the network of activities required to
high likelihood to implement LPS are those with high complete the phase.

Table 3. Summary of the challenges of LPS.


No. Challenge Study
1 Lack of culture, commitment and attitude S2, S3, S4, S6, S13, S21, S27, S33
2 Lack of training on LPS and LC S4, S9, S13, S20, S27, S33
3 Organizational inertia and lengthy approval process S3, S4, S5, S13
4 Lack of leadership S9, S13, S27
5 Contractual issues S9, S20
6 Lack of participation of low-level parties (subcontractors, foreman and works) S4, S11
7 Lack of improvement analysis S4, S23
8 Lack of participation of suppliers S4, S31
9 Involvement of many subcontractors S3
10 The long time spent on making the plans S33
Table 4. Summary of the variation causes of LPS in a descending order based on the frequency of occurrence.
S2 S3 S6 S26 S31
First project Second project
1 Material 1 Prerequisite work 1 Labour 1 Long approval process 1 Lack of continuity (pre- 1 Over commitment by
requisite work the trade contractors
not completed)
2 Prerequisite work 2 Material 2 Material 2 Design changes 2 Moves to another work 2 Incomplete prerequis-
area (priority change) ite work
3 Labour supply 3 Approval 3 Approval 3 Design errors 3 Waiting for workers, tools 3 Change in work plan
or equipment or priorities
4 Submittal 4 Changed priority 4 Prerequisite work 3 Waiting for other crews to 4 Unavailability
complete their task Others: of materials

4 Rework 5 Labour 5 Late request 3 Delay from suppliers  Waiting for materials from Others:
for inspection the warehouse
4 Incomplete design 5 Equipment 5 Incomplete information 4 Equipment breakdown  Waiting for materials from  Crew inefficiencies and
information the supplier lack of skilled labour
5 Equipment 5 Design 6 Equipment 5 Waiting for inspection  Lack of access  Material concerns (late
materials, incorrect
quantities and receiv-
ing dam-
aged materials)
6 Poor weather 5 Overestimate of 7 Changed priority 6 Disagreement and  Equipment breakdowns  Changes in scope
achievement disputes on site and priority
6 Incomplete information 8 Overestimate of 7 Waiting for instruction  Changes or redoing work  Overcrowded or clut-
achievement (design errors) tered work area
6 Defects require reworking 8 Defects require reworking 8 Construction errors  Changes or redoing work  Design quality
(site errors)
6 Interface with 8 Weather 9 Congestion on site  Waiting for information  Coordination with
other packages other trades, commu-
nication and informa-
tion flow
7 Scheduling/coordination 9 Design 10 Rework  Overcrowded
working areas
8 Space 9 Interface with 11 Excessive transport  Inclement weather
other packages of material
8 Weather 10 Scheduling/coordination 12 Waiting for equipment
8 Other (technical 10 Space 13 Excessive
specification) labour movement
8 Other (rock under floor) 10 Other (technical
specification)
9 Late request 10 Other (rock under floor)
for inspection
INTERNATIONAL JOURNAL OF CONSTRUCTION MANAGEMENT
7
8 O. ABUSALEM

Table 5. Summary of the CSFs of LPS.


No. CSF Study
1 Continuous improvement through training and learning S3, S5, S13, S20, S31
2 Improving information flow S2, S3, S5, S13, S31
3 Involvement of all stakeholders S3, S5, S13, S20, S31
4 Top management support S3, S5, S13, S20, S31
5 Enhancing culture and awareness S2, S3, S5, S13
6 Close relationship with suppliers S3, S31
7 Clear definition of roles and responsibilities S5, S13
8 Motivating people to make change S3, S15
9 Formation of policies to suit LC adoption S2

Table 6. Background of respondents.


No. Item Percentage (%)
1 Job title Site engineer Project manager Company director
40.3 31.9 27.8
2 Years of company’s experience 5 or less 6–10 11–20 Over 20
8.3 37.5 40.3 13.9
3 Permanent employees 5 or less 6–10 11–20 Over 20
20.8 44.4 22.2 12.5
4 Annual average value of projects Less than $250k–less $500k–less $1m and
$250k than $500k than $1m more
11.1 25 25 38.9
5 Classification First A First B Second Third Fourth Fifth
Buildings 32.8 28.4 23.9 10.4 4.5 0.0
Roads 18.0 29.5 26.2 11.5 8.2 6.6
Water and sewer 28.0 32.0 26.0 10.0 4.0
Electromechanical 23.9 32.6 28.3 8.7 6.5

Look-ahead plan. 59.7% of the respondent con- look-ahead plan after removing all constraints and
tracting firms use a look-ahead plan. As learned from providing all prerequisites. There is an absence in
the interviews, the term of look-ahead plan is not examining the assignments against the quality criteria
prevalent among the contracting firms. The equivalent of definition, sequence, soundness, size and learning.
name for the look-ahead plan is the monthly plan. They do not stabilize the workflow between the pro-
However, the used monthly plan does not follow the duction units by making and keeping commitments to
same approach of the look-ahead plan of LPS. There what will be done. Additionally, they do not use the
is an absence in breaking down tasks into the level of PPC or other metric tools to track the progress of
processes and then to the level of operations, identify- projects. They do not specify the root reasons for
ing and removing constraints to make tasks ready for incomplete assignments as scheduled by using the five
execution and designing operations through first run why’s or any other technique to analyse them in the
studies. They do not use the screening and pulling meetings and take actions that would prevent them
approaches to detect and remove constraints. They do from recurring. Although the contracting firms usually
not examine the assignments against the quality crite- consult the last planners and subcontractors about dif-
ria of definition, sequence, soundness, size and learn- ferent issues, empowering them to take ownership in
ing before inclusion in the WWP. Further, they do the planning and control process remains limited.
not use any metrics to measure the performance of Based on the above discussion, the levels of project
the monthly planning process. As the results show, planning adopted by the Gaza Strip’s construction
the monthly plan is the most absent plan among the industry have the same structural hierarchy of the
other plans used by the contracting firms. LPS. However, these levels of project planning do not
WWP. 68.1% of the respondent contracting firms follow the same approach of LPS. Furthermore, these
use a WWP. As revealed by the interviewees, the used levels of project planning are not adopted by all of
WWP does not follow the same approach of the the contracting firms.
WWP in LPS. The used WWP is not an ‘assignment-
Meetings
level schedule’ and does not contain high level of
details required to deliver the production process. Table 7 illustrates that 100% of the respondent con-
They do not shield production units from upstream tracting firms conduct meetings to discuss the pro-
uncertainty by selecting only those assignments that gress of projects with the work team. The percentages
are ready to be done from a workable backlog in the show that there is a wide use of different frequencies
INTERNATIONAL JOURNAL OF CONSTRUCTION MANAGEMENT 9

Table 7. Meetings. routine procedures requested by the client and


No. Item Percentage (%) stipulated in the contract.
1 No meetings 00.0
2 Monthly 44.4
3 Weekly 41.7 Parties involved in the planning process
4 Daily 18.0
5 According to the need 51.4 Table 9 shows that there is a wide involvement of dif-
ferent parties in the planning process. The project
of meetings. According to the need, meeting came in manager is the most involved party with a high per-
the first place. This result reflects that the absence of centage of 91.7%. As pointed out by the interviewees,
the prior determination of date and time is the dom- the project manager is the responsible person for the
inant feature of meetings in Gaza Strip. As explained successful completion of projects. His primary role is
by the interviewees, the main reason for this is the to ensure achieving the predetermined project objec-
complex and dynamic nature of construction process. tives of time, cost, quality and safety. The project
Generally, meetings are informal, where there are no manager is the best candidate for this job because of
session minutes that contain the date and time of his rich experience in construction and the solid know-
meetings, list of attendees, issues to be discussed and ledge in management. Additionally, the focus should
decisions to be taken. One interviewee states that be directed towards the foreman since he is typically
Usually, our meetings are informal in their nature.
considered as the last planner. There is a considerable
We do not always have a fixed schedule to discuss percentage of 33.3% from the respondent contracting
the work progress. Sometimes, we use the phone as a firms that involve the foreman in the planning process.
way of communication, coordination, ordering This reflects the awareness of these firms to the signifi-
materials, staying continuously informed on the cant role of foreman’s participation to reduce the pos-
course of events, and consulting about the problems sible plan variation. Even these firms that involve the
facing us at the work site that need to be solved
immediately. All team members can meet at any time
foreman in the planning process do not entirely
at the work site or office. Furthermore, holding a empower him to develop the weekly plans.
huddle meeting whenever summoned the need for it.
Participation of the foreman
Improving plans Table 10 shows that there is a considerable percentage
of 68.1% from the respondent contracting firms that
Table 8 shows that the vast majority of the respond-
agree that the foreman is qualified to add details and
ent contracting firms review, analyse and update
commitment to the planning and control process. The
plans. However, this did not improve the planning
majority of the interviewees clarified that consulting
and control reliability. The proof of this is the exist-
with the foreman about the works that need to be
ence of unreliable production plans that led to a high
accomplished in the upcoming week is essential
level of plan variation. The underlying truth behind
because he is familiar with the construction produc-
these results was revealed during the interviews. The
tion process and closer to the site. This result reflects
majority of the interviewees clarified that reviewing,
the extent of accepting one fundamental pillar of LPS
analysing and updating plans were done informally.
represented in empowering the foreman to take
The systematic review of project plans that were
drawn in a bar chart format was found to be rare or Table 9. Parties involved in the
absent. One interviewee commented that planning process.
Usually, we do not heavily rely on the developed No. Item Percentage (%)
plans in the execution process. Hence, there are no 1 Project manager 91.7
2 General contractor 77.8
further attempts to update the produced plans in the 3 Site engineer 77.8
beginning of the project, even if changes occur. 4 Subcontractor 19.4
Sometimes, updating plans that have been created are 5 Foreman 33.3
meaningless, mere ink on papers. They are just for
Table 10. Participation of the foreman.
No. Item Percentage (%)
Table 8. Improving plans.
1 Strongly disagree 11.1
No. Item Percentage (%) 2 Disagree 00.0
1 Reviewing plans 93.1 3 Neutral 20.8
2 Analyzing plans 94.4 4 Agree 52.8
3 Updating plans 88.9 5 Strongly agree 15.3
10 O. ABUSALEM

ownership in the planning and control process. The lack of commitment and attitude from the fore-
Nevertheless, 31.9% of the respondent contracting man came in the fifth place. One interviewee stated that
firms disagree or stand on neutral. Actually, the foreman is not ready to exert additional
efforts to prepare the weekly plan, commit to implement
Reasons for lack of participation of the foreman it and assume all responsibility in case of failure. He
prefers to stay in the safe zone, where he can lay the
Table 11 presents the reasons for lack of participation of the blame on the plan produced by the project manager.
foreman. These reasons are based on the literature review
of LPS. The results indicate that the overall reasons for lack
of participation of the foreman are approximately medium Adoption of the LPS
since the average (2.7) is just less than the hypothesized After a brief explanation of LPS, the respondent con-
value 3, with an RII of 54.9%. As mentioned previously, tracting firms were requested to answer if they would
33.3% of the respondent contracting firms involve the fore- like to adopt the LPS and explain the reasons in case
man in planning and 68.1% agree that the foreman is quali- of rejection. The results show that 84.7% of the
fied to add details and commitment to the planning and respondent contracting firms expressed their willing-
control process. One interviewee expressed that ness to adopt the LPS. This encouraging result reflects
I think there is no significant reason that could the pressing need of the Gaza Strip’s construction
prevent the contracting firms from participating the professionals to eliminate the plan variation. This
foreman in the planning and control process, just forms a fertile environment and a solid platform to
this is how the things have been. launch from it towards the full implementation of
However, there is a considerable percentage of con- LPS in the future. The reasons for objecting to adopt-
struction professionals who agree on these reasons. ing the LPS are as follows: (1) the harsh circumstan-
This is the same conclusion that was obtained from ces of Gaza Strip, such as the lack of materials and
the interviews. The lack of culture and awareness came the excessive rise of materials prices due to the Israeli
in the first place. The unwillingness of the construction siege and (2) the size of construction projects in Gaza
professionals to involve other low-level parties came in Strip does not require this level of detailed plans. One
the second place. These results emphasize that empow- interviewee commented that
ering the foreman to take ownership in the planning In normal conditions, implementing LPS would be
and control process needs huge efforts to change the extraordinary since I experienced such this system when I
mentality and culture of all parties in Gaza Strip. The was working in the United Arab Emirates (UAE).
poor capabilities of foreman came in the third place. However, the implementation of LPS would be to some
extent difficult due to the harsh circumstances endured by
One interviewee mentioned that Gaza Strip. Furthermore, who use these systems are huge
The planning and control process needs a scientific contracting firms that operate in complex projects and
based approach in order to establish schedules, have an engineering staff specialized only in planning and
allocate resources, analyse plans and specify control on a daily basis.
constraints. This is not available at most of the low-
level parties, such as the foreman.
The lack of trust in the foreman came in the fourth Third stage: assessment
place. One interviewee explained that Current situation
Unfortunately, many foremen work within their own This section assesses the current situation of the Gaza
narrow scope. They do not believe in the unity of the
Strip’s construction industry by covering only the
team and that the project’s success or failure depends
on the combined efforts of the work crews to deliver the aspects improved by the LPS that have been previ-
project. All that matter is the accomplishment of their ously addressed as its benefits in Table 2. All of the
work as agreed upon in order to claim their wages. interviewees agreed that increasing the planning and

Table 11. Reasons for lack of participation of the foreman.


No. Item SD (%) D (%) N (%) A (%) SA (%) Avg s RII (%) Rank
1 Lack of culture and awareness 13.9 20.8 31.9 23.6 9.7 2.9 1.2 58.9 1
2 Unwillingness of construction professionals to involve other low-level parties 15.3 23.6 22.2 31.9 6.9 2.9 1.2 58.3 2
3 Poor capabilities of the foreman 13.9 26.4 34.7 25.0 0.0 2.7 1.0 54.2 3
4 Lack of trust in the foreman 16.7 31.9 25.0 25.0 1.4 2.6 1.1 52.5 4
5 Lack of commitment and attitude from the foreman 13.9 41.7 25.0 16.7 2.8 2.5 1.0 50.6 5
Overall reasons 2.7 1.1 54.9
INTERNATIONAL JOURNAL OF CONSTRUCTION MANAGEMENT 11

control reliability is extremely difficult within a com- that is, by being released upon completion of prede-
plex and dynamic environment, such as the construc- cessor activities. In case of the unavailability of all
tion industry. The construction projects are usually prerequisites on time, those available will wait in a
planned by specifying the set of activities required to queue or buffer for the assembly of the rest to be
deliver the projects, estimating their durations, identi- ready as a single entity, this so-called ‘matching parts’.
fying dependencies between them and allocating and Starting the work with an incomplete set of prerequi-
leveling resources for each activity. The schedule is sites compromises the workflow between crews and
developed by calculating the earliest and latest start thus adversely affects the productivity. When the
and finish dates of each activity using the critical path missing prerequisites are identified during the on-site
method. The resulting schedule is typically called work, it is too late to prevent delays. Therefore, rigor-
master schedule or master plan (Tommelein and ously adhering to the initial schedule may not be the
Ballard 1997). The prevailing practice in the construc- best approach for successful project completion, as
tion industry is to develop highly detailed plans to the status of prerequisites may change from those
reduce the discretion of those performing the sched- were assumed when generating that schedule
uled work and to facilitate micro-management (Tommelein 1998).
(Ballard and Tommelein 2012). However, all plans are The traditional approaches to construction project
forecasts, and all forecasts are wrong. Forecasting fur- management are dominated by the flexibility strategy
ther into the future and forecasting at a high level of for managing production in the case of high workflow
details significantly increase the likelihood of forecast uncertainty. Mainly, this is because the traditional
error (Nahmias 1989). The recommended practice is approaches do not provide a conceptual basis or prac-
to plan in greater details as we approach the execu- tical tools for controlling production. The flexibility
tion date (Ballard et al. 2009). This stems from the strategy is about mobilizing all available resources suf-
fact that scheduling developed nearer in time to exe- ficiently to perform any work which emerges on the
cution benefits from more reliable information. surface. The flexibility strategy sacrifices the product-
Hence, the master schedule must be kept at the level ivity and cost for the sake of schedule. This makes
of phase milestones. This level of details often the workflow uncertainty much worse (Howell and
referred to in the construction industry as the pro- Ballard 1996). A superior alternative is to improve the
posal schedule (Ballard and Tommelein 2012). Upon reliability of production planning and control systems.
project execution, activities are expected to commence Ballard and Howell (1998) confirmed that 30% less
at their earliest possible date in order not to delay the labour is required when planning reliability reaches
following activities or the whole project. All stake- levels higher than 50%. Howell et al. (2001) concluded
holders must adhere to the resulting schedule to that reducing variation by improving planning reli-
deliver the project on time. In this type of planning, ability from 50% to 70% can theoretically increase
it is assumed that all prerequisites required to execute productivity to 30%. The managers can improve the
any activity will be indeed available at that activity’s overall performance of a company by utilizing its pro-
early start time, this so-called ‘push’ approach. duction capacity to the optimum level. This can be
Although the push approach is essential at the early achieved through employing all resources in an effect-
stage of the project to set the major milestones and ive and efficient manner to get the best possible out-
key dates for delivery, it is inefficient to be followed puts from the same amount of inputs. The effective
throughout the progress of the project, particularly and efficient utilization of company’s resources leads
during the production stage (Hopp and Spearman to lower production cost and increased profits. The
1996; Tommelein 1998). This approach has low flexi- secret behind this extraordinary productivity is the
bility, entail high inventory levels and have the ten- hard-working attitude and commitment of the work-
dency to increase the amount of waste (Tommelein force to achieve timely completion. One interviewee
and Weissenberger 1999). Variation is closely associ- stated that: ‘There is no room for delivering projects
ated with schedules throughout project progress due on time without the hard-working attitude and com-
to the uncertainty in durations, dependencies and mitment of the workforce to get the slipped schedule
prerequisites of activities. During the planning phase, back on the right track as soon as possible’. However,
it may be possible to model this uncertainty. the employees are often undervalued and treated as
However, the actual manifestation of uncertainty is machines, even though they are the most significant
only known upon plan execution. Each activity must asset in the company. Sometimes, they have to work
passively wait for its prerequisites to become available, overtime for long hours, on weekends, and during the
12 O. ABUSALEM

official holidays to catch up with the schedule. Thus, tendency of people to waste time buffer by starting their
achieving timely completion can be a heavy burden tasks later than the planned start or even as late as pos-
on the shoulders of employees. sible without impacting the next scheduled task or
As clarified by the interviewees, occupational their deadline.
health and safety are crucial in improving productiv- Another significant deficiency in the current practi-
ity and reducing plan variations. Accidents and inci- ces is the poor communication, coordination, collabor-
dents reduce the efficiency of the production process ation, commitment and trust. These conventional plans
through hindering the workflow and wasting the pro- are developed and pushed by using top–down approach
duction time and costly resources. One interviewee rather than bottom–up approach without taking any
commented that considerations to the frontline foremen and workers.
The injured worker costs the company lost working The experience and knowledge of those responsible for
hours, increased insurance rates, compensation doing the work are not incorporated to yield schedules
premiums, and possible litigation. The production with higher anticipation and better sequencing of tasks.
time is wasted when other workers have to stop the These plans are generated by a wishful thinking and in
work to deal with the injury. Even after the injured
worker has been sent to the home or taken to the
the absence of reliable promises (Ballard and Howell
hospital, other workers may be distracted or need to 1994). As a result, the current managerial practices are
take time off from work in the aftermath of not able to provide a smooth and accurate transmission
the accident. of information. As clarified by the interviewees, the con-
The production systems must be able to absorb vari- tracting firms heavily depend on the cumulative know-
ation to avoid loss of productivity, wasted capacity, ledge of their employees, suppliers, customers and other
inflated cycle times, long lead times, larger inventory key stakeholders. The accurate knowledge about the
levels and poor customer service. Therefore, construc- complex aspects that create problems, new ideas and
tion personnel naturally tend to compensate for the new approaches is essential for developing innovative
uncertainty in the construction environment by adding practical solutions. This knowledge is only obtained
buffers as cushions that pad or shield activities against by a free flow of information among stakeholders.
variability and disruptions in production systems Limiting the sharing of information across the com-
(Howell et al. 1993; Howell and Ballard 1994a, 1996; pany leads to information gaps. Therefore, the need for
Ballard and Howell 1995; Hopp and Spearman 1996; knowledge to become more widely spread is essential.
Tommelein and Weissenberger 1999; Tommelein 2003; Delivering the right information to the right people at
Alves 2005). Nevertheless, these buffers cast a heavy bur- the right time requires from the knowledge producers
den on projects concerning extra cost, wasted time and to overcome many barriers. One interviewee com-
low productivity. Ohno (1988) and Womack and Jones mented that
(1996) argued that the use of buffers is waste since they Each work crew thinks that every task or package is
do not directly add value to projects even though they independent and they just need to complete their job
allow downstream operations to continue. Vrijhoef and away from the rest of the teams. The inefficient
Koskela (2000) emphasized the impracticality of communication and poor collaboration lead to late or
improving supply chain reliability through buffering. incomplete information, misunderstandings or even
disputes among parties, resulting in compromising
Russell et al. (2015) concluded that there is an urgent
the workflow.
need to add larger time buffers in complex and intensive
labour trades in construction projects, such as the mech- Command and control are dominating the current
anical trade. However, the importance lies in the fact practices in construction projects so that tasks are
that buffers only mask the sources of uncertainty. assigned as orders and reinforced by contractual pen-
Increasing time buffer seems to be responsible for alties. Commitments from work crews are neither
decreasing productivity. Lechler et al. (2005) explained requested nor given. Accurate information about the
that the time buffer added to tasks is usually subjected to actual performance of planning and progress status
either Parkinson’s law or student syndrome. Parkinson’s can only be available when those charged with plan-
law states that people will always use this time buffer ning and performing the work can say ‘Won’t Do’.
because the task will grow to take as long as the time Having the right to say ‘no’ guarantees reliable com-
allotted for it to be done. For example, the work will mitments to perform the work as scheduled (Howell
expand to fill the time allotted by working more slowly and Ballard 1994b).
or rechecking work multiple times before declaring its It is unlikely that we will be perfect planners in a
completeness. The student syndrome is based on the complex and dynamic environment, such as the
INTERNATIONAL JOURNAL OF CONSTRUCTION MANAGEMENT 13

construction industry. We sometimes break our prom- Challenges


ises in everyday life, despite thoughtful consideration of
The respondent contracting firms were asked to assess
our capability to perform before committing. Even
the challenges that may affect the future implementa-
though, we can aspire never to make the same mistake
tion of LPS listed in Table 12. The results show that
twice. This needs learning from our plan failures, our
the overall challenges are medium since the average
broken promises. Most practices that obsessively focus
(3.1) is slightly higher than the hypothesized value 3,
on objectives fail to track the progress of the project,
with an RII of 62.5%. The involvement of many sub-
identify the root causes of plan failures, learn from these
contractors came in the first place. As revealed from
failures, prevent recurring and update the schedule. The the interviews, the subcontracting strategy is widely
strong temptation is to clean up the mess and move on, used by almost all contracting firms in the construc-
although doing that virtually ensures a repetition of the tion industry to mitigate the heavy burden placed on
same breakdown in the future (Ballard and Tommelein their shoulders. The non-adoption of subcontracting
2012). Furthermore, there is no distinction between the strategy requires great assets of human resources,
plan quality failure and plan execution failure. It is materials and equipment to perform the work.
assumed that all failures are plan execution failures Consequently, they try to reduce the number of acti-
because the quality characteristics of plans are not expli- vates in the construction process and eliminate part
cit. The findings indicate that the majority of failures to of the costs with welfare taxes by transferring a sig-
complete the work as scheduled are rooted plan quality nificant part of the work to third parties.
failures (Ballard and Howell 1994). Nevertheless, the involvement of many subcontractors
All of these concerns made plan execution poses a great challenge to the planning and control
extremely hard and doomed for failure. Accordingly, methods. Contracting with multiple parties of differ-
the traditional mentality of planning and control is ent and sometimes conflicting goals and scopes to
inefficient and ineffective to achieve the optimal per- perform a set of activities required to deliver the pro-
formance. Given the uncertain and sometimes unpre- ject can noticeably reduce the efficiency of informa-
dictable environment of construction projects, the tion flow among these parties; subsequently,
planning process should be dynamic and iterative increasing the amount of uncertainty, misunderstand-
rather than static and deterministic (Smith 2003). The ings, disputes and workflow instability. Moreover,
successful planning must be a continuous adaptive adopting the subcontracting strategy minimizes the
iterative process in the quest for value. It is expected profit margin of contracting firms because they will
to reduce risk, manage and reduce uncertainty, sup- lose the advantage of securing all profits resulting
port sound decision-making, establish trust and share from each subgroup of work. The subcontractors,
information (Cohn 2005). This can be achieved who are not responsible for supplying the whole
through a holistic approach to production planning resources, may waste a large amount of them because
and control system that promotes different levels of they only worry about finishing their work without
detailed schedules, collaboration between all stake- taking into consideration the optimal utilization of
holders, removing constraints from planned tasks, these resources. The insecure or temporary relation-
securing reliable commitments, and a continuous ship between the subcontractors and contracting firms
improvement process of eliminating waste, maximiz- may reduce the motivation of subcontractors’ crews
ing value and learning from failures. These results to produce a larger amount of work with high quality.
promote the urgent need for the implementation of This result is similar to the findings of AlSehaim
LPS in the Gaza Strip’s construction industry. et al. (2014), who ranked this challenge in the first

Table 12. Challenges of the future implementation of LPS.


No. Challenges VL (%) L (%) M (%) H (%) VH (%) Avg s RII (%) Rank
1 Involvement of many subcontractors 5.6 13.9 33.3 31.9 15.3 3.4 1.1 67.5 1
2 Organizational inertia and lengthy approval process 4.2 19.4 37.5 27.8 11.1 3.2 1 64.4 2
3 Contractual issues 2.8 16.7 48.6 25 6.9 3.2 0.9 63.3 3
4 Lack of participation of suppliers 4.2 16.7 44.4 27.8 6.9 3.2 0.9 63.3 3
5 Lack of training on the new and innovative management techniques 1.4 25 33.3 37.5 2.8 3.2 0.9 63.1 4
6 Lack of culture, commitment and attitude 13.9 12.5 33.3 34.7 5.6 3.1 1.1 61.1 5
7 Lack of improvement analysis 5.6 12.5 58.3 18.1 5.6 3.1 0.9 61.1 5
8 The long time spent on making the plans 4.2 22.2 44.4 23.6 5.6 3 0.9 60.8 6
9 Lack of participation of low-level parties (subcontractors, foreman or works) 5.6 23.6 40.3 23.6 6.9 3 1 60.6 7
10 Lack of leadership 4.2 29.2 34.7 29.2 2.8 3 0.9 59.4 8
Overall challenges 3.1 1.0 62.5
14 O. ABUSALEM

place. The organizational inertia and lengthy approval even cost overrun, delay in delivering the projects on
process came in the second place. The majority of the time, less productivity, and poor performance at
interviewees explained that the approval process is all levels.
time-consuming and causes significant delays in deci- The unavailability of materials came in the first
sion-making and in approval of the purchase of mate- place. This result demonstrates that providing the
rials. Furthermore, the roles and assigned right materials on time is the most significant factor
responsibilities are vague, resulting in slowing the in delivering the construction projects. As explained
pace of the workflow. This result is consistent with by all interviewees, this result is attributed to the lack
the findings of AlSehaim et al. (2014), who ranked of materials and excessive rise of materials prices,
this challenge in the second place. The lack of leader- especially the cement and steel reinforcement, due to
ship was ranked eighth in the last place. However, the Israeli siege on Gaza Strip. This meaning for the
this challenge is medium since the average (3) is equal unavailability of materials is an uncontrollable exter-
to the hypothesized value 3. The leadership is a fun- nal factor that has to be taken as given in any con-
damental aspect of the culture of any successful com- struction project. Nevertheless, there are other
pany. The good leader should be able to influence the meanings falling under the name of unavailability of
thoughts and actions of others by providing direc- materials that can be controlled. As mentioned by the
tions, implementing plans and motivating people to interviewees, these meanings include overdue of mate-
achieve the predetermined goals. One interviewee rials delivery by suppliers, waiting for materials from
mentioned that the warehouse, wrong materials and defective materi-
The good leadership can achieve success through als. This result matches the findings of Ahiakwo et al.
organizing the work and allocating the duties, (2013), who ranked the unavailability of materials in
responsibilities, and authorities. Furthermore, giving the first place. The incomplete prerequisite works
instructions to ensure that the agreed policies are came in the second place. This result reflects the
carried out, checking the performance of the plan,
absence of identifying and removing constraints from
taking corrective actions, motivating people to do an
excellent job rather than an adequate job, future assignments to ensure all prerequisites before
encouraging them to share ideas and opinions and being assigned to the work crews. Resulting in creat-
rewarding creativity. ing an unreliable workflow that prevents the contract-
ing firms from doing the works is as planned. This
Variation causes result is compatible with the findings of Ahiakwo
et al. (2013) and Russell et al. (2015), who ranked the
The respondent contracting firms were asked to assess incomplete prerequisite works in the second place.
the variation causes that may affect the future imple- The lack of labour supply or skilled labour was
mentation of LPS listed in Table 13. The results reveal ranked 11th in the last place. This variation cause
that the overall variation causes are medium since the stands between the low and medium levels since the
average (3.1) is slightly larger than the hypothesized average (2.6) is roughly in the middle between the
value 3, with an RII of 62.1%. One interviewee hypothesized values 2 and 3. This result implies the
said that availability of sufficient workforce with hard-working
Variation largely exists in construction projects. It attitude and commitment that can meet the project
leads to reducing the contractor profit margin or needs. By contrast, lack of labour supply or skilled

Table 13. Variation causes of the future implementation of LPS.


No. Variation causes VL (%) L (%) M (%) H (%) VH (%) Avg s RII (%) Rank
1 Unavailability of materials 5.6 5.6 22.2 25 41.7 3.9 1.2 78.3 1
2 Incomplete prerequisite works 4.2 15.3 36.1 33.3 11.1 3.3 1 66.4 2
3 Long approval process and waiting for information or instructions 1.4 25 34.7 25 13.9 3.3 1 65 3
4 Late requests 5.6 15.3 40.3 29.2 9.7 3.2 1 64.4 4
5 Changes in scope, priorities or strategies of the project 4.2 23.6 34.7 22.2 15.3 3.2 1.1 64.2 5
6 Over commitment 4.2 18.1 43.1 27.8 6.9 3.2 0.9 63.1 6
7 Unavailability of equipment or equipment breakdowns 4.2 20.8 51.4 16.7 6.9 3 0.9 60.3 7
8 Design-related issues (errors, changes incompleteness) 6.9 30.6 29.2 25 8.3 3 1.1 59.4 8
9 Poor weather 11.1 26.4 30.6 23.6 8.3 2.9 1.1 58.3 9
10 Defects requiring rework 11.1 29.2 31.9 19.4 8.3 2.8 1.1 56.9 10
11 Overcrowded working areas 8.3 29.2 36.1 22.2 4.2 2.8 1 56.9 10
12 Lack of labour supply or skilled labour 20.8 23.6 36.1 15.3 4.2 2.6 1.1 51.7 11
Overall variation causes 3.1 1.1 62.1
INTERNATIONAL JOURNAL OF CONSTRUCTION MANAGEMENT 15

Table 14. CSFs of the future implementation of LPS.


No. CSFs VL (%) L (%) M (%) H (%) VH (%) Avg s RII (%) Rank
1 Top management support 0 9.7 19.4 43.1 27.8 3.9 0.9 77.8 1
2 Enhancing culture and awareness 0 2.8 29.2 51.4 16.7 3.8 0.7 76.4 2
3 Involvement of all stakeholders 0 8.3 25 45.8 20.8 3.8 0.9 75.8 3
4 Clear definition of roles and responsibilities 0 5.6 27.8 48.6 18.1 3.8 0.8 75.8 3
5 Close relationship with suppliers 0 4.2 36.1 44.4 15.3 3.7 0.8 74.2 4
6 Continuous improvement through training and learning 0 6.9 36.1 40.3 16.7 3.7 0.8 73.3 5
7 Motivating people to make change 0 4.2 40.3 47.2 8.3 3.6 0.7 71.9 6
8 Improving information flow 6.9 11.1 19.4 43.1 19.4 3.6 1.1 71.4 7
9 Formation of policies to suit the adoption of the new and innovative management techniques 0 11.1 34.7 41.7 12.5 3.6 0.9 71.1 8
Overall CSFs 3.7 0.9 74.2

labour came in the top variation causes in many stud- management, it is the only one that is able to move the
ies, such as Ahiakwo et al. (2013), AlSehaim et al. wheel of change in the field of construction.
(2014), and Ochoa (2014). The top six variation causes
in Table 13 are consistent with the top variation causes
reached by Ahiakwo et al. (2013), AlSehaim et al. Conclusion
(2014), Daniel et al. (2014), Ochoa (2014), and Russell The Gaza Strip’s construction industry in Palestine
et al. (2015) with a slight disparity in the order. requires creative initiatives to solve the growing problem
of planning and control reliability, such as adopting the
Critical success factors LPS. The results of the questionnaire and interview sur-
veys show that several elements of LPS already exist in
The respondent contracting firms were asked to assess the
Gaza Strip. However, these elements do not follow the
CSFs that may affect the future implementation of LPS
same approach of LPS. About 84.7% of the respondent
listed in Table 14. The results indicate that the overall CSFs
contracting firms expressed their willingness to adopt
are relatively high since the average (3.7) is just below than
the LPS. This forms a fertile environment and a solid
the hypothesized value 4, with an RII of 74.2%. This result
platform to launch from it towards the full implementa-
highlights the extent of the significant influence of these
tion of LPS in the future. Nevertheless, the future imple-
CSFs on the future implementation of LPS. In addition,
mentation of LPS may face several challenges and
this result implies the extent of the absence of these CSFs
variation causes. Therefore, the author recommends the
and the efforts that desperately need to be exerted to pro-
contracting firms to apply the CSFs as a comprehensive
vide them. The top management support came in the first
strategy to better plan and organize their efforts in
place. This result is similar to the findings of Cervero-
implementing LPS, increase the chances of successful
Romero et al. (2013) and AlSehaim et al. (2014), who
implementation and sustain this success. The author rec-
ranked the top management support in the first place. The
ommends the following future research: (1) evaluating
enhancing culture and awareness came in the second place.
the challenges, variation causes and CSFs that may affect
This result is consistent with the findings of AlSehaim et al.
the future implementation of LPS in Gaza Strip to intro-
(2014), who ranked enhancing culture and awareness in
duce the necessary adjustments, (2) conducting case
the second place. These two CSFs emphasize that the
studies to obtain more in-depth feedback about the
future implementation of LPS needs huge efforts to change
implementation of LPS in Gaza Strip and (3) studying
the mentality and culture of all parties in the Gaza Strip’s
other LC techniques to form a comprehensive vision
construction industry. The formation of policies to suit the
about the implementation of LC in Gaza Strip.
adoption of the new and innovative management techni-
ques ranked eighth in the last place. However, this CSF lies
between the medium and high levels since the average Disclosure statement
(3.6) is almost in the middle between the hypothesized val- No potential conflict of interest was reported by the author.
ues 3 and 4. One interviewee commented that
Formation of policies by the state or authorities to
References
oblige the contracting firms to adopt new management
systems, such as LPS, will be a significate initiative. Adamu I, Howell G. 2012. Applying last planner in the
Nevertheless, the commitment to implement these Nigerian construction industry. In: Tommelein ID,
systems must come from the inside of the companies, Pasquire CL, editors. 20th Annual Conference of the
from the desire for change and to achieve the ideal International Group for Lean Construction; Jul 18–20;
performance. The real change starts from the top San Diego (CA). http://iglc.net/.
16 O. ABUSALEM

Ahiakwo O, Oloke D, Suresh S, Khatib J. 2013. A case International Group for Lean Construction; Jul 31–Aug
study of last planner system implementation in Nigeria. 2; Fortaleza (Brazil). p. 559–568.
In: Formoso CT, Tzortzopoulos P, editors. 21th Annual Fernandez-Solis J, Porwal V, Lavy S, Shafaat A, Rybkowski
Conference of the International Group for Lean Z, Son K, Lagoo N. 2013. Survey of motivations, benefits,
Construction; Jul 31–Aug 2; Fortaleza (Brazil), p. 699–707. and implementation challenges of last planner system
AlSehaim AO, Fazenda PT, Koskela L. 2014. Improving con- users. J Constr Eng Manage. 139(4):354–360.
struction management practice with the last planner system: Fuemana J, Puolitaival T. 2013. Last planner system – a step
a case study. Eng Constr Archit Manage. 21(1):51–64. towards improving the productivity of New Zealand con-
Alves TDCL. 2005. Buffering practices in HVAC supply struction. In: Formoso CT, Tzortzopoulos P, editors. 21th
chains [Ph.D. Dissertation]. Berkeley (CA): Civil and Annual Conference of the International Group for Lean
Environmental Engineering, University of California. Construction; Jul 31–Aug 2; Fortaleza (Brazil). p. 679–688.
Ballard G. 1994. The last planner. Spring Conference of the Gao S, Low SP. 2014. The last planner system in China’s
Northern California Construction Institute; Apr 22–24; construction industry – a SWOT analysis on implemen-
Monterey, California, USA. tation. Int J Project Manage. 32(7):1260–1272.
Ballard G. 2000. The last planner system of production con- Green SD, Fernie S, Weller S. 2005. Making sense of supply
trol [Ph.D. Dissertation]. Birmingham, (UK): School of chain management: a comparative study of aerospace
Civil Engineering, University of Birmingham. and construction. Constr Manage Econ. 23(6):579–593.
Ballard G, Howell G. 1994. Implementing lean construction: Hamzeh FR. 2009. Improving construction workflow – the
stabilizing the work flow. 2nd Annual Conference of the role of production planning and control [Ph.D.
International Group for Lean Construction; September; Dissertation]. Berkeley (CA): Civil and Environmental
Santiago (Chile): Pontifical Catholic University of Chile; Engineering Department, University of California.
p. 101–110. Hamzeh FR. 2011. The lean journey: implementing the last
Ballard G, Howell G. 1995. Toward construction JIT. planner system in construction. In: Rooke J, Dave B, edi-
Association of Researchers in Construction Management tors. 19th Annual Conference of the International Group
Conference; Sheffield (UK). for Lean Construction; Jul 13–15; Lima (Peru).
Ballard G, Howell G. 1998. Shielding production: essential Hamzeh FR, Aridi OZ. 2013. Modeling the last planner sys-
step in production control. J Constr Eng Manage. tem metrics: a case study of an AEC company. In:
124(1):11–17. Formoso CT, Tzortzopoulos P, editors. 21st Annual
Ballard G, Tommelein I. 2012. Lean management methods Conference of the International Group for Lean
for complex projects. Eng Project Organiz J. 2(1–2): Construction; Jul 31–Aug 2; Fortaleza (Brazil). p. 599–608.
85–96. Hamzeh FR, Langerud B. 2011. Using simulation to study
Ballard G, Hammond J, Nickerson R. 2009. Production con- the impact of improving Lookahead planning on the reli-
trol principles. In: Cuperus Y, Hirota EH, editors. 17th ability of production planning. Proceedings of the 2011
Annual Conference of the International Group for Lean Winter Simulation Conference; Dec 11–14; Phoenix
Construction; Jul 15–17; Taipei (Taiwan). p. 489–500. (AZ). p. 3431–3442.
Brady D, Tzortopoulos P, Rooke J. 2011. An examination Hamzeh FR, Saab I, Tommelein ID, Ballard G. 2015.
of the barriers to last planner implementation. In: Rooke Understanding the role of “tasks anticipated” in look-
J, Dave B, editors. 19th Annual Conference of the ahead planning through simulation. Autom Constr.
International Group for Lean Construction; Jul 13–15; 49(Part A):18–26.
Lima (Peru). Hopp WJ, Spearman ML. 1996. Factory physics: founda-
Cervero-Romero F, Napolitano P, Reyes E, Teran L. 2013. tions of manufacturing management. Chicago (IL): Irwin
Last planner system and lean approach process experien- Professional.
ces from implementation in Mexico. In: Formoso CT, Hornby, A. 1974. Oxford advanced learner’s dictionary of
Tzortzopoulos P, editors. 21th Annual Conference of the current English. Oxford, UK: Oxford University Press.
International Group for Lean Construction; Jul 31–Aug Howell, G, Ballard G. 1994a. Implementing lean construc-
2; Fortaleza (Brazil). p. 709–718. tion: reducing inflow variation. 2nd Annual Conference
Cohn M. 2005. Agile estimating and planning. Upper of the international group for Lean Construction.
Saddle River (NJ): Prentice Hall Professional Technical Santiago (Chile): Catolica Universidad de Chile.
Reference. Howell G, Ballard G. 1994b. Lean production theory: mov-
Daniel EI, Pasquire C, Ameh OJ. 2014. The magic of the ing beyond “Can-Do”. In: Alarcon L, editor. Lean con-
last planner system for Nigerian construction. In: Kalsaas struction; Leiden (Netherlands): Balkema. p. 17–24.
BT, Koskela L, Saurin TA, editors. 22nd Annual Howell G, Ballard, G. 1996. Managing uncertainty in the
Conference of the International Group for Lean piping process. Austin (TX): Construction Industry
Construction; Jun 25–27; Oslo (Norway). p. 605–616. Institute, University of Texas. Technical Report No. 47.
Enshassi A, Abu Zaiter M. 2014. Implementation of lean Howell G, Ballard G, Hall J. 2001. Capacity utilization and
tools on safety in construction projects in Palestine. In: wait time: a primer for construction. In: Ballard G, Chua
Kalsaas BT, Koskela L, Saurin TA. editors. 22nd Annual D, editors. 9th Annual Conference of the International
Conference of the International Group for Lean Group for Lean Construction; Aug 6–8; Singapore:
Construction; Jun 25–27; Oslo (Norway). p. 1205–1218. University of Singapore.
Fauchier D, Alves TDCL. 2013. Last planner system is the Howell GA, Laufer A, Ballard G. 1993. Interaction between
gateway to lean behaviors. In: Formoso CT, sub cycles: one key to improved methods. J Constr Eng
Tzortzopoulos P, editors. 21th Annual Conference of the Manage. 119(4):714–728.
INTERNATIONAL JOURNAL OF CONSTRUCTION MANAGEMENT 17

Issa UH. 2013. Implementation of lean construction techni- Walsh K, Alves T, editors. 18th Annual Conference of
ques for minimizing the risks effect on project construc- the International Group for Lean Construction; Jul
tion time. Alexandria Eng J. 52(4):697–704. 14–16; Haifa, Israel. p. 548–556.
Khan S, Tzortzopoulos P. 2014. Effects of the interactions Priven V, Sacks R. 2013. Social network development in
between LPS and BIM on workflow in two building last planner system implementations. In: Formoso CT,
design projects. In: Kalsaas BT, Koskela L, Saurin TA, Tzortzopoulos P, editors. 21th Annual Conference of the
editors. 22nd Annual Conference of the International International Group for Lean Construction; Jul 31–Aug 2;
Group for Lean Construction; Jun 25–27; Oslo (Norway). Fortaleza, Brazil. p. 537–548.
p. 933–944. Rosas E. 2013. Integrating the design structure matrix and
Kim Y, Ballard G. 2010. Management thinking in the the last planner system into building design. In: Formoso
earned value method system and the last planner system. CT, Tzortzopoulos P, editors. 21th Annual Conference of
J Manage Eng. 26(4): 223–228. the International Group for Lean Construction; Jul
Koskela L. 2000. An exploration towards a production the- 31–Aug 2; Fortaleza, Brazil. p. 389–398.
ory and its application to construction [Ph.D. disserta- Russell M, Howell G, Hsiang S, Liu M. 2013. Application of
tion]. Helsinki (Finland): Helsinki University of time buffers to construction project task durations. J
Technology, VTT Publications. 408. Constr Eng Manage. 139(10):04013008. doi:10.1061/
Koskela L, Stratton R, Koskenvesa A. 2010, Last planner (ASCE)CO.1943-7862.0000735.
and critical chain in construction management: compara- Russell M, Liu M, Howell G, Hsiang S. 2015. Case studies of the
tive analysis. In: Walsh K, Alves T, editors. 18th Annual allocation and reduction of time buffer through use of the
Conference of the International Group for Lean last planner system. J Constr Eng Manage. 141(2):04014068.
Construction; Jul 14–16; Haifa, Israel. p. 538–547. doi:10.1061/(ASCE)CO.1943-7862.0000900.
Koskenvesa A, Koskela L. 2012. Ten years of last planner in Saunders M, Lewis P, Thornhill A. 2016. Research methods
Finland – where are we? In: Tommelein ID, Pasquire CL, for business students. London (UK): Pearson Publishing.
editors. 20th Annual Conference of the International Saunders MNK. 2012. Choosing research participants. In:
Group for Lean Construction; Jul 18–20; San Diego (CA). Symons G, Cassell C, editors, Qualitative organizational
Lechler T, Ronen B, Stohr E. 2005. Critical chain: a new research: core methods and current challenges. London
project management paradigm or old wine in new bot- (UK): Sage Publishing; p. 35–52.
tles? Eng Manage J. 17(4):45–58. Seppanen O, Ballard G, Pesonen S. 2010. The combination
Leigard A, Pesonen S. 2010. Defining the path: a case study
of last planner system and location-based management
of large scale implementation of last planner. In: Walsh
system. In: Walsh K, Alves T, editors. 18th Annual
K, Alves T, editors. 18th Annual Conference of the
Conference of the International Group for Lean
International Group for Lean Construction; Jul 14–16;
Construction; Jul 14–16; Haifa, Israel. p. 467–476.
Haifa, Israel. p. 396–405.
Smith SF. 2003. Is scheduling a solved problem? 1st
Leino A, Elfving J. 2011. Last planner and zero accidents
International Conference on Multidisciplinary
program integration – workforce involvement perspec-
Scheduling: Theory and Applications (MISTA 03); Aug
tive. In: Rooke J, Dave B, editors. 19th Annual
13–15; Nottingham (UK). p. 3–17.
Conference of the International Group for Lean
Tommelein ID. 1998. Pull-driven scheduling for pipe-spool
Construction; Jul 13–15; Lima, Peru.
London KA, Kenley R. 2001. An industrial organization installation: simulation of lean construction technique. J
economic supply chain approach for the construction Constr Eng Manage. 124(4):279–288.
industry: a review. Constr Manage Econ. 19(8):777–788. Tommelein ID. 2003. Acknowledging variability and uncer-
McConaughy T, Shirkey D. 2013. Subcontractor collaboration tainty in product and process development. In: Issa RRA,
and breakdowns in production: the effects of varied LPS Flood I, O’Brien WJ, editors. 4D CAD and Visualization
implementation. In: Formoso CT, Tzortzopoulos P, editors. in Construction: Developments and Applications; A.A.
21th Annual Conference of the International Group for Lean Balkema Publishers. p. 165–193.
Construction; Jul 31–Aug 2; Fortaleza, Brazil. p. 649–658. Tommelein ID, Ballard G. 1997. Look-ahead planning:
Mota BP, Viana DD, Isatto EL. 2010. Simulating the last screening and pulling. Berkeley (CA): Construction
planner with systems dynamic. In: Walsh K, Alves T, Engineering and Management Program, Civil and
editors. 18th Annual Conference of the International Environmental Engineering Department, University of
Group for Lean Construction; Jul 14–16; Haifa, Israel. p. California. Technical Report No. 97-9.
487–496. Tommelein ID, Weissenberger M. 1999. More just-in-time:
Nahmias S. 1989. Production and operations analysis. location of buffers in structural steel supply and con-
Chicago (IL): Irwin Professional Publishing. struction processes. 7th Annual Conference of the
Nieto-Morote A, Ruz-Vila F. 2012. Last planner control International Group for Lean Construction; Jul 26–28;
system applied to a chemical plant construction. J Constr Berkeley (CA). p. 109–120.
Eng Manage. 138(2):287–293. Viana DD, Mota B, Formoso CT, Echeveste M, Peixoto
Ochoa JJ. 2014. Reducing plan variations in delivering sus- M, Rodrigues CL. 2010. A survey on the last planner
tainable building projects. J Cleaner Prod. 85:276–288. system: impacts and difficulties for implementation in
Ohno T. 1988. Toyota production system: beyond large- Brazilian companies. In: Walsh K, Alves T, editors.
scale production. Portland (OR): Productivity Press. 18th Annual Conference of the International Group
Porwal V, Fernandez-Solıs J, Lavy S, Rybkowski ZK. 2010. for Lean Construction; Jul 14–16; Haifa, Israel. p.
Last planner system implementation challenges. In: 497–507.
18 O. ABUSALEM

Vrijhoef R, Koskela L. 2000. The four roles of supply chain mechanical related construction tasks. J Constr Eng
management in construction. Eur J Purchasing Supply Manage. 138(4):491–498.
Manage. 6(3–4):169–178. Womack J, Jones D. 1996. Lean thinking: banish waste and
Wambeke B, Liu M, Hsiang S. 2012. Using last planner and create wealth in your corporation. New York (NY):
a risk assessment matrix to reduce variation in Simon and Schuster.

You might also like