Professional Documents
Culture Documents
Safety of Offshore Topside Processing Facilities: The Era of Fpsos and Flngs
Safety of Offshore Topside Processing Facilities: The Era of Fpsos and Flngs
Contents
1. Introduction 269
2. Offshore Topside Facilities 270
3. Floating Production, Storage, and Offloading Vessels 272
3.1 FPSO 272
3.2 FLNG 278
4. Conclusions 285
References 285
1. INTRODUCTION
The need for more fossil energy resources has resulted in an ever-
increasing offshore operations including drilling, extraction, producing,
and processing of oil and natural gas. Forced by the extraction and depletion
of the most of shallow water recourses, the pursuit of oil and gas resources
has shifted toward deep water and ultradeep water operations.
The depth of water, which in most cases makes it impossible to employ
fixed platforms, from one hand and the remote locations of deep-water off-
shore operations, which are hundreds of kilometers away from shore, from
the other hand have resulted in an outgrowth of floating production, stor-
age, and offloading vessels. Such vessels, depending on the type of substances
they process, i.e., crude oil or natural gas, are usually referred to FPSO and
FLNG vessels, respectively.
FPSOs have been in operation for almost two decades now (Leonhardsen,
Ersdal, & Kvitrud, 2001), but the first FLNG, Shell’s Prelude FLNG, just came
B
SPAR Platform Floating Production Shuttle Floating Production, Storage,
(SPAR) System Tanker and Offloading System
(FPS) (FPSO)
Subsea System
(SS)
1 5 4 4 3 7 7
2 1 9
3 4 7 6 8
6 8
which is separated on the deck into oil, gas, and water. The oil is then
offloaded to an oil tanker. The produced gas is exported, reinjected, or
combusted (Suardin et al., 2009). Compared to other offshore platforms
depicted in Fig. 1, an FPSO is faster to build, can operate at different water
depths, and can easily be relocated (Shimamura, 2002).
Fires and explosions have been identified as major potential hazards for
FPSO (Table 1), and thus similar safety measures and fire protection systems
used at offshore oil and gas facilities (HSE, 2009) can presumably be used to
prevent and mitigate fires and explosions. However, limitations in the space
and weight of the FPSO may pose more constraints on the type and siting of
safety measures (e.g., the design and sizing of fire water pumps as pointed out
by Suardin et al., 2009). Besides, fire safety systems need to be able to cope
with the forces caused by the FPSO’s movements, need to have a certain
level of flexibility, and must meet stringent anticorrosion requirements.
Passive fire protection (PFP), also known as fireproof coating, is the most
common way used to protect main structural elements that support walk-
ways, open escape routes, and process vessels containing hydrocarbon
(Friebe, Beom-Seon, & Yanlin, 2014; HSE, 2009). As identified by HSE
(2009), PFP is aimed at providing up to 2 h fire resistance for fire and blast
walls, including covered escape routes such as tunnels on FPSO’s, especially
in case of jet fires and pool fires.
PFP technically takes priority over active fire protection systems such as
sprinkler systems and water deluge systems due to their passive performance
(no need for detection and actuation systems, and thus lower failure rates),
and lower maintenance and inspection costs. However, fireproof coating
materials are susceptible to physical damage and water ingress which may
decrease their efficiency (lower fire resistance) or lead to complete
unavailability (HSE, 2009; Landucci, Argenti, Tugnoli, & Cozzani, 2015).
274 Nima Khakzad and Genserik Reniers
Table 1 FPSO Modules in Fig. 3 and Relevant Accident Scenarios (Suardin et al., 2009)
Module Equipment Included Hazards
Oil treatment Separators and pumps Jet fire, pool fire,
explosion
Glycol regeneration/fuel Separators, contractor, and Jet fire
gas system/metering compressors
Power generation Natural gas power generation Jet fire, pool fire,
and diesel powered explosion
Flare system High pressure and low pressure Jet fire, pool fire,
scrubber for oil and gas explosion
Gas compression systems Compressors Jet fire, pool fire,
explosion
Flash gas compression Scrubbers and compressors Jet fire, pool fire,
explosion
Risers Oil and gas risers Jet fire, pool fire,
explosion
where ttf is the time to failure (s); Q is the received heat radiation (kW/m2);
V is the process vessel’s volume (m3); Y is the probit value; Pr is the failure
probability of the vessel; Φ(.) is the cumulative standard normal distribution.
Ideally, ttfp ¼ 120 min (rating time), but the fireproof coating deteriorates
over time due to fire exposure, environmental and chemical activities (expo-
sure to sea water and humidity), and thus not maintaining its initial protec-
tion integrity.
In case of low performance fireproof coating or deteriorated coating, a
percentage α of ttfp is usually considered as fire resistance (e.g., α ¼ 0.25 in
Khakzad, Landucci, Cozzani, Reniers, & Pasman, 2018). The impact of fire-
proof coating on exposed structures and process vessels can be modeled
using an event tree in Fig. 4 (Khakzad et al., 2018).
Water deluge is an active fire protection system aimed at providing
a spray curtain (usually salt water, which causes nozzle blockage and
internal corrosion) in order to shield the target vessel from a primary fire
(HSE, 2009). Similar to other active fire protection systems, a water
deluge consists of a gas, heat and flame detection, logic solver, and an
actuation system, each with their own reliability, availability, and effi-
ciency. In addition to the previous components of a water deluge system,
large pumps and pipework add more complexity to the system compared
with PFP.
As pointed out in HSE (2009), on installations with minimum facilities
and limited space (FPSOs implied), a general area protection system such as
water deluge will provide a higher level of personnel protection than other
Fig. 5 Performance evaluation of water deluge system used to protect a target equip-
ment from external heat radiation (Khakzad et al., 2018).
Safety of Offshore Topside Processing Facilities 277
Maximum water required for deluge system for each module in FPSO
10,000 Back to Water
Calculation
9000
Risers
Water application rate (m3/hr)
8000
Flash gas compression
7000 package
Gas compression system
6000
Flare system
5000
Power generation
4000
1000
Oil treatment
0
FPSO
Fig. 6 Water required by water deluge systems on FPSO (Suardin et al., 2009).
een
all betw
Blast W d Utility
a n
Process
een
all betw
Blast W c ess
nd Pro
Turret a
Fig. 7 Separation of process area from the other areas using blast walls (Kang, Choi,
Choi, Ryu, & Lee, 2017).
Aside from the fire and explosion hazards, collisions, green water inci-
dents, mooring line failures, pitting corrosion in cargo tanks, cracking of rails
in turret area, and loss of heading control have been reported as other incidents
for FPSOs. Fig. 8 depicts the collision frequency of FPSOs compared to other
278 Nima Khakzad and Genserik Reniers
0.15
0.1
0.05
0
ket
s
uni
ts S' ys Us
Jac le GB buo /FS
obi ng PS
O
M Loadi F
Fig. 8 Collision frequencies in the Norwegian Continental Shelf from 1982 to 2000
(Leonhardsen et al., 2001).
3.2 FLNG
Many natural gas resources are located in remote offshore fields, where sub-
sea pipelines structures do not exist or are not economically viable. Floating
liquefied natural gas (FLNG) vessels have been designed to facilitate the pro-
duction, liquefaction, and storage of natural gas at sea (Fig. 9).
The first FLNG begins operations this year off the coast of Northern
Australia over Shell’s Prelude natural gas field. FLNG pumps up natural
gas, storing it within massive storage tanks at the temperature of 162°C.
On a regular basis, storage tanks are off-loaded to gas tankers. When fully
Safety of Offshore Topside Processing Facilities 279
Refrigerant LNG
compression –161°C
Pipeline
feeds gas To ships
loaded, the FLNG may contain 600,000 t of liquefied natural gas (LNG).
It also produces around 3.6 million tonnes per year of LNG.
FLNG vessels makes it possible to transfer LNG directly from the floating
facility to a variety of consumers around the world via waterways. The LNG
liquefaction process in onshore LNG plants and FLNG vessel are all but the
same (Fig. 10). The process includes:
• to separate condensates from gas. The gases such as methane, ethane, pro-
pane, and butane are then compressed and sent to the liquefaction unit.
• impurities such as carbon dioxide and hydrogen sulfide are removed
through acid-gas removal column.
• water and mercury are removed from the remaining natural gas through
absorber and regeneration column.
280 Nima Khakzad and Genserik Reniers
A1. Slug A2. Gas/liquid B1. Acid gas B4. Liquefaction B6. Cooling B7. Heating
catcher separation C1~C4 removal system system system
C5~C6 C1~C4
A3. B8. Inert B9. N2
B2. Dehydration B5. Fractionation gas supply supply
Stabilization
C5~C6
B3. Mercury B10. HPU
A4. Condensate removal
Fig. 11 Schematic of a typical FLNG’s module layout (Dan, Lee, Park, Shin, & Yoon, 2014).
confined area
Dispersion in
Immediate
Delayed
medium
Spillage
ignition
ignition
Water Rapid phase
transition
Pool fire/jet
Yes
LNG spillage fire
Yes
Ground
Flash fire
No
explosion
No
Dispersion into
No
air
the accident scenarios, rapid phase transition (RPT), also known as cold
explosion, is a phenomenon specific to cryogenic chemicals such as LNG,
where LNG vaporizes violently upon contact with water causing a physical
explosion. During a cold explosion there is no combustion but a huge
amount of energy is released in the form of heat.
Dan et al. (2014) assessed the risk of fire and explosion in a FLNG with a
focus on the LNG liquefaction process units. They considered a number of
release scenarios with the LNG and refrigerant leakages from valves as the
most probable scenarios causing fire and explosion. Risk contours of fire
and explosion for the considered release scenarios have been depicted in
Fig. 13.
Despite the similarities between onshore and offshore LNG plants in
terms of both operations and accident scenarios, the safety of the latter seems
more challenging as, due to usually compact structures and limited space,
application of onshore safety measures such as inherently safer design tech-
niques and safety distances (Khan & Amyotte, 2002), is not easily possible.
Aside from accident scenarios such as fires and explosions which are
common between LNG plants onshore and FLNGs (Dan et al., 2014), there
are several scenarios which can be envisaged mainly due to the floatation of
FLNGs. Among others, the grounding of FLNGs, their collision with
282 Nima Khakzad and Genserik Reniers
´ 10–4
5
4.5
3.5
2.5
1.5
0.5
0
Fig. 13 Risk contours for fire and explosion at FLNG (Dan et al., 2014).
Safety of Offshore Topside Processing Facilities 283
shuttle tankers during offloading operation, and failure of loading arms are
worth noting (Yeo et al., 2016). However, it should be noted that since the
application of FLNGs is quite new, compared to some 158 accidents
recorded for LNG tankers since 1959 (Vanem, Antao, Østvik, & de
Comas, 2008), there has been no accident reported for FLNGs as the first
FLNG was put into operation just in 2017. According to Vanem et al.
(2008), collision and grounding have accounted for around 90% of total
accidents reported for LNG tankers. Likewise, as reported in Yeo et al.
(2016), Lloyds shipping accident database (Blake, 1960), collision, leakage
of LNG, and foundering have been among the most feared accident scenar-
ios during offloading operations.
A collision can occur between an FLNG and a shuttle tanker or between
the FLNG and the port. A poorly designed mooring system or the failure of
the mooring system can result in instability of FLNG (and also shuttle tanker)
due to either the environmental forces such as wind, waves, and tides or
waves generated by other passing ships. A mooring system consists of
breasting, mooring dolphins, and a loading platform (Yeo et al., 2016). Large
tankers use steel wires or steel wires with nylon tails as mooring lines. Several
safety barriers are employed to dampen the impact of collisions among
which fenders are very common. Fig. 14 depicts a rubber fender for this pur-
pose, being placed between the LNG carrier and the port berth.
Leakage of LNG due to the failure of loading arms is another envisaged
accident scenario. Loading arms are to connect the manifolds of the LNG
carriers so as to transport LNG from one to another. A loading arm comprises
the Straits of Gibraltar in June 1979. The tanker suffered heavy bottom dam-
age over the whole length of the cargo spaces, as well as flooding to the star-
board double bottom and wing ballast tanks. However, the membrane cargo
containment was not breached, and no liquefied natural gas was spilled
(GlobalSecurity.org, n.d.).
4. CONCLUSIONS
There is a number of key features in the process and layout for (LNG)
floating production, storage, and offloading vessels that require different or
modified approaches for hazard identification and safety assessment. This is
mainly due to the size and the variation in the release scenarios from one
hand, and floatation of such vessels from the other hand which in turn
can give rise to issues such as collision and grounding.
Although the accident scenarios such as mooring failure, grounding, and
collision and ensuing hydrocarbon release are among likely scenarios (com-
parable with other mobile units and loading buoys), fires and explosions
are the most feared accident scenarios at topside facilities, including FPSOs
and FLNGs, due to a variety of extremely flammable and explosive hydro-
carbons. In addition to fires and explosions, in the case of FLNGs, an spill of
LNG on water can also give rise to RPT—also known as cold explosion—
with a huge amount of heat release.
Taking into account the design, size, and novel and inherently different
features compared to other offshore facilities, safety risk assessment and man-
agement of FPSO and FLNG vessels demand for approaches that account for
varying environmental forces and operating conditions in addition to pre-
viously well-established design practices and risk assessment techniques.
For FLNG, especially due to the young technology and lack of historical
data, dynamic techniques, for example, based on Bayesian belief network,
would be needed so that the level of risk can be updated in a real-time fash-
ion as precursor data in form of equipment malfunction, collisions, minor
release, environmental changes, etc., becomes available.
REFERENCES
Americas Offshore Energy. n.d. Available online from: http://www.americasoffshoreenergy.
com/#/?section¼producing-offshore.
Blake, G. (1960). Lloyd’s register of shipping, 1760–1960. Lloyd’s Register.
Cole, W. (2009). Navy ship grounding detailed. The Honolulu Advertiser.
286 Nima Khakzad and Genserik Reniers
Cozzani, V., Antonioni, G., Khakzad, N., Khan, F., Taveau, J., & Reniers, G. (2013). Quan-
titative assessment of risk caused by domino accidents. In: G. Reniers & V. Cozzani
(Eds.), Domino effects in the process industries, (pp. 208–228). UK: Elsevier.
Dan, S., Lee, C. J., Park, J., Shin, D., & Yoon, E. S. (2014). Quantitative risk analysis of fire
and explosion on the top-side LNG-liquefaction process of LNG-FPSO. Process Safety
and Environmental Protection, 92, 430–441.
Encyclopedia of Cleveland History, n.d., Indiana University Press. Available from: https://
case.edu/ech/articles/e/east-ohio-gas-co-explosion-and-fire/.
Finucane, M., & Pinkney, D. (1988). Reliability of fire protection and detection systems, SRD
R431. Edinburgh (UK): United Kingdom Atomic Energy Authority, University of
Edinburgh.
Friebe, M., Beom-Seon, J., & Yanlin, J. (2014). A parametric study on the use of passive fire
protection in FPSO topside module. International Journal of Naval Architecture and Ocean
Engineering, 6(4), 826–839.
GlobalSecurity.org. n.d. LNG Tanker Safety. Available online from: https://www.
globalsecurity.org/military/systems/ship/tanker-lng-safety.htm.
Gomez-Mares, M., Tugnoli, A., Landucci, G., & Cozzani, V. (2012). Performance assess-
ment of passive fire protection materials. Industrial and Engineering Chemistry Research,
51(22), 7679–7689.
HSE. (2009). Provision of active fire protection on offshore installations offshore information sheet no.
5/2009. Available online from http://www.hse.gov.uk/offshore/infosheets/is5-2009.htm.
Jones C. Lessons learnt from completing formal safety assessments for FLNG facilities.
Hazards 24, Edinburgh, UK, 7–9 2014.
Kang, K. Y., Choi, K. H., Choi, J. W., Ryu, Y. H., & Lee, J. M. (2017). Explosion induced
dynamic responses of blast wall on FPSO topside: Blast loading application methods.
International Journal of Naval Architecture and Ocean Engineering, 9, 135–148.
Khakzad, N., Landucci, G., Cozzani, V., Reniers, G., & Pasman, H. (2018). Cost-effective
fire protection of chemical plants against domino effects. Reliability Engineering & System
Safety, 169, 412–421.
Khan, F., & Amyotte, P. (2002). Inherent safety in offshore oil and gas activities: A review of
the present status and future directions. Journal of Loss Prevention in the Process Industries, 15,
279–289.
Landucci, G., Argenti, F., Tugnoli, A., & Cozzani, V. (2015). Quantitative assessment of
safety barrier performance in the prevention of domino scenarios triggered by fire. Reli-
ability Engineering and System Safety, 143, 30–43.
Leonhardsen, R. L., Ersdal, G., & Kvitrud, A. (2001). In Experience and risk assessment of
FPSOs in use on the Norwegian continental shelf: Descriptions of events. Proceedings of the
11th international offshore and polar engineering conference, o1. 1. 309-314 (ISOPE). Stavanger,
Norway. June (pp. 17–22).
Professional Mariner. (2010). LNG carrier damages coral reef in Puerto Rico grounding. Available
online from http://www.professionalmariner.com/March-2010/LNG-carrier-damages-
coral-reef-in-Puerto-Rico-grounding/.
Reuters. (2015). UPDATE 1-tanker grounded off Nigeria may siphon LNG to break free. Available
online from http://www.reuters.com/article/lng-nigeria/update-1-tanker-grounded-
off-nigeria-may-siphon-lng-to-break-free-idUSL6N0US41320150113.
Roberts, T. A. (2004). Directed deluge system designs and de-termination of the effective-
ness of the currently recommended minimum deluge rate for the protection of LPG
tanks. Journal of Loss Prevention in the Process Industries, 17, 103–109.
Seamanship, W. (2008). LNG Shipping Knowledge: Support Systems. Standard operations:
Vol. 4. Witherby Seamanship International Ltd.
Shimamura, Y. (2002). FPSO/FSO: State of the art. Journal of Marine Science and Technology, 7,
59–70.
Safety of Offshore Topside Processing Facilities 287
Suardin, J., McPhate, J., Jr., Sipkema, A., Childs, M., & Mannan, S. (2009). Fire and explo-
sion assessment on oil and gas floating production storage offloading (FPSO): An effec-
tive screening and comparison tool. Process Safety and Environmental Protection, 87(3),
147–160.
The Maritime Executive. (2015). LNG Carrier Aground in Nigeria. Available online from
https://maritime-executive.com/article/lng-carrier-aground-in-nigeria.
Vanem, E., Antao, P., Østvik, I., & de Comas, F. D. C. (2008). Analysing the risk of LNG
carrier operations. Reliability Engineering & System Safety, 93, 1328–1344.
Yeo, C., Bhandari, J., Abbassi, R., Garanya, V., Chai, S., & Shomali, B. (2016). Dynamic risk
analysis of offloading process in floating liquefied natural gas (FLNG) platform using
Bayesian network. Journal of Loss Prevention in the Process Industries, 41, 259–269.