Professional Documents
Culture Documents
Kansai Airport Settlement Report
Kansai Airport Settlement Report
② The settlement has been monitored with utmost care and it was
re-
re-confirmed by a recent measurement to be within the estimate
except
exce pt a few areas and the settlement is stabilizing.
* To solve the severe noise problem of the former international airport in Kansai region,
Itami Airport located in a densely populated area, construction of a new noise-free and
24 hour operational airport was started in 1987, 5 km off the Senshu district
district, southern
part of Osaka Prefecture, see the map below, where the sea is 18 meters deep and the
seabed is extremely soft.
Lake
Biwa
Nagoya
○
ITAMI Kyoto
AIRPORT ○
Kobe ●
○ ○ Osaka
○Nara
Awajishima KANSAI
Island ● AIRPORT
○ Wakayama
Shikoku
Island
Pacific Ocean
2
* The formation under the sea of the airport consists of the very soft Holocene clay layer,
the Pleistocene clay layer and the Tertiary deposit, as illustrated below.
* Of these layers, the Holocene clay layer can be artificially improved to be solid enough
to support a heavy structure by the sand drain method,
method which is explained in the next
page.
* This is the reason why utmost attention was paid to make a correct estimate about the
settlement, especially about the Pleistocene layer, as precise as possible, and also the
settlement has been carefully monitored.
300 - 500m
about 800m
[the
the Lower Pleistocene clay layer
layer]
more than 900m
[the
the Tertiary deposit]
deposit
[Granite
Granite]
Granite
4
Sand Drain Method
① This method strengthens the seabed by draining water from the Holocene clay layer
and accelerates its settlement.
② After lying and spreading a thin sand blanket
blanket, sand piles are driven through to the
Holocene clay layer.
③ With the weight of spread soil, water contained in the Holocene clay layer is forced out
through the sand piles into the sea.
pull up
piling
sand sea level
Sand
blanket
. .
seabed
sand pile . .
left water water settled
[the Holocene clay layer] (solid)
4
The settlement has been monitored with utmost care and it was
re-
re-confirmed by a recent measurement to be within the estimate
except
excep t a few areas and the settlement is stabilizing.
* The recent measurement carried out at the end of 2000 reconfirmed that the
settlement of the KIX airport island is within the estimate except a few areas: 11.7
meters were measured on average, while about 12.0 meters had been estimated for
the total settlement from the beginning of reclamation.
* Of those 11.7 meters of settlement, 9.8 meters settled during the period of land
reclamation and facilities construction before opening. The settlement which
progressed after the opening is 1.9 meters, settling 3∼
3∼4 centimeters less every year.
year
Thus the progress of stabilization is on course, as shown below.
Stabilization of Settlement
Average settlement
(cm/y)
60
50
50 ① 43
30 31
0
'94 '95 '96 '97 '98 '99 '00
(KIX opened.)
5
Measures are being taken by constructing diaphragm walls around
* Level of grounds
grounds,
rounds except for a few areas, is high enough for a safe and normal airport
operation as shown below.
* A few areas which exceeded the estimate around the fuel storage tanks and the
passenger terminal are now to be protected by the diaphragm walls walls, see the
illustration of its mechanism on the next page, against extremely high tide which
might occur every 50 years so that the underground water within the walls could be
controlled artificially by being pumped out.
6
Mechanism of Control of Underground Water
by Diaphragm Wall
Terminal
Facility
Level of underground
Water (controlled)
water water
permeable permeable
to water diaphragm wall to water
① In case of extremely high tide, which might occur every 50 years, as the seawall is
permeable to water
water, level of underground water comes up to the same level as that of
high tide.
② As this phenomenon may break basement structures of the facilities,
facilities the diaphragm
walls are to be constructed around such facilities as fuel storage tanks and the
passenger terminal facilities, so that the level of underground water within the walls
could be controlled by being pumped out. out
7
Operation of KIX has been and
and will be safely maintained by timely
unique jack-
jack-up systems equipped to each pillar of the passenger