The PTB Simulation Report

User: Chahat Preet


User Email: N01352883@humbermail.ca
Scenario: Medium Radar Development
Created at: Friday, January 24, 2020 9:18:51 PM
Last simulation run result: Scenario finished
Simulation Time: 15
Target Date: 15
Target Cost: 41000
Simulation Cash: 137900
Total Cost: 32100
Benefit: 83.86
Estimated Cost: 21750
Estimated Finish Period: 15
Scenario Information:
Project Name Number of Target Date Initial Cash Bonus per Penalty per
Tasks Period Period

Project1 5 15 100000 10000 20000

Resource Information:
Name Availa Availa Cost/ Idle Firing Hiring Show Firing Hiring Minim Maxim
ble ble Period Cost/ Cost Cost Up Lead Lead um um
Units Units Period Proba Time Time Units Units
in bility
Lead (%)
Time

Engin 6 6 100 50 50 50 80 1 1 1 30
eers

Techni 6 6 50 10 40 20 85 1 1 2 50
cians

Quality Requirements:
The PTB Simulation Report

Name Formula Importanc Minimum Desired Maximum Best Mode Evaluation


e Value Value Value

Range Pow([TP]* 7 10 12 40 Maximum 11.07


[RS]*[AG],
0.25)

Quality [SEQ]*[QT 8 0 75 100 Maximum 73.74


]*[QR]*[Q
A]*[QI]*1
00

Reliability [AR]*[IR]* 6 0 65 100 Maximum 65.61


[TR]*[RR]
*100

Task Information:
The PTB Simulation Report

Project Task Name Cost of Actual Actual Income Current Selected


Name Split Start Finish Status Mode

Project1 Systems 20 0 4 50000 Finished Large


Engineerin Team
g

Mode Optimisti Most Pessimist Fixed Engineers Technicia System Reliabilit


Name c Likely ic Cost Needed ns Engineeri y of
Duration Duration Duration Needed ng System
Quality Design
(SEQ) (DR)
(SEQ) (DR)

Small 5 7 10 2000 1 0 0.8 0.8


Team

Large 3 4 5 4000 3 1 0.99 0.9


Team
The PTB Simulation Report

Project Task Name Cost of Actual Actual Income Current Selected


Name Split Start Finish Status Mode

Project1 Transmitte 20 4 9 0 Finished Reengineer


r Design

Mode Optimist Most Pessimi Fixed Enginee Technici Transmi Transmi Transmi
Name ic Likely stic Cost rs ans tter tter tter
Duratio Duratio Duratio Needed Needed Quality Power Reliabili
n n n (QT) (TP) ty (TR)
(QT) (TP) (TR)

Reengin 3 5 8 5000 2 1 0.99 50 0.9


eer

New 7 9 11 10000 4 2 0.95 100 0.8


Design
The PTB Simulation Report

Project Task Name Cost of Actual Actual Income Current Selected


Name Split Start Finish Status Mode

Project1 Receiver 20 4 11 0 Finished Reengineer


Design

Mode Optimist Most Pessimi Fixed Enginee Technici Receive Receive Receive
Name ic Likely stic Cost rs ans r Quality r r
Duratio Duratio Duratio Needed Needed (QR) Sensitivi Reliabili
n n n (QR) ty (RS) ty (RR)
(RS) (RR)

Reengin 3 5 9 2000 2 1 0.95 30 0.9


eer

New 8 10 11 15000 3 1 0.8 200 0.99


Design
The PTB Simulation Report

Project Task Name Cost of Actual Actual Income Current Selected


Name Split Start Finish Status Mode

Project1 Antenna 20 4 11 0 Finished Reengineer


Design

Mode Optimist Most Pessimi Fixed Enginee Technici Antenna Antenna Antenna
Name ic Likely stic Cost rs ans Quality Gain
Duratio Duratio Duratio Needed Needed (QA) (AG) Reliabili
n n n (QA) (AG) ty (AR)
(AR)

Reengin 3 7 9 3000 3 2 0.8 10 0.9


eer

New 6 7 9 7000 5 2 0.99 30 0.9


Design
The PTB Simulation Report

Project Task Name Cost of Actual Actual Income Current Selected


Name Split Start Finish Status Mode

Project1 Integratio 10 11 15 20000 Finished In-House


n and
Testing

Mode Optimisti Most Pessimist Fixed Engineers Technicia Integrati Reliabilit


Name c Likely ic Cost Needed ns on y of
Duration Duration Duration Needed Quality Integrati
(QI) (QI) on (IR)
(IR)

In-House 3 4 5 4000 3 3 0.99 0.9

Subcontr 2 4 6 6000 1 0 0.9 0.99


act