Project Integration Simulation

(PMPG-5502 ON)

Assignment-4
(Project Lessons Learned & Final Status Reports)

Group Member names-


1)Conrado Oliveira
2)Mahyar Zandrahimi
3)Chahat Preet Kaur

Group Number- 02
Submission date- April 05, 2020
Final Project Status Report

Date: 2020-04-05 Project Number: N/A


Project Name: MS Society - London to Grand Bend Tour Project Sponsor: Hamza Qazi
Project Manager: Sarah Mann

Scope Status
Final Deliverables Acceptance Criteria Criteria Met/Comment

1. Find Alternative The new route must be safe, Yes, the new route was safe,
routes in good condition and the in good condition, with
distance should be similar to similar distances and as an
the previous route. extra, the view was
breathtaking.

2. Get Permits The cities involved had to Yes, permits were issued on
review the new tour route time.
and approve them.

3. Contact Emergency Contact all the stakeholders Yes, all the required services
Services necessary for a safe tour, and were there when needed.
request their services on the
designated days.

4. Set Checkpoints Following the previously The checkpoints were


defined specifications, a installed according to the
checkpoint had to be put in initial plan.
place to assist the
participants of the tour.

5. Draw Detailed Maps A comprehensive map had to Yes, the map included all the
and list of locations draw, in order to provide necessary information for all
guidance for the stakeholders parties.
and participants

6. Print High-Quality The maps have to be printed Yes, the quality was
Maps in high-quality for the satisfactory and there was no
participants of the tour. complaints

7. Distribute Maps, Every participant, Yes, everyone had access to


Emergency Contact stakeholder needed to be the information.
Numbers handed the necessary
information regarding the
route and emergency
contacts.

Schedule Status
Final Deliverables Approves Dates Actual completion dates
(d/m/y) (d/m/y)

1. Met the timeline ( 21


days) Mon 25-06-18 Wed 25-07-18

2. Printing maps
Fri 18-07-20 Fri 18-07-20

3. Get permits from


council Thu 18-07-05 Thu 18-07-05

4. Setting checkpoints
Mon 18-07-09 Mon 18-07-09

5. Verify Road
Conditions Tue 18-07-10 Tue 18-07-10

6. Distribute maps
and route Mon 18-07-23 Mon 18-07-23
descriptions for
cyclists

7. Distribute maps
and route Tue 18-7-19 Tue 18-7-19
descriptions for
volunteers and staff

8. Distribute map and


route descriptions for Mon 18-07-23 Mon 18-07-23
cyclists
9. Contact all
emergency services Mon 02-07-18 Wed 04-07-18

Effort and Spending Status


- Approved Amounts Actual Amounts

Effort (Hours)/Days 21 23

Spending (Money) $ 15,000.00 $10280

Changes to Plan (Total Changes)


- Baseline Approved Changes Final Approved Amounts

Deliverables 7 0 7

Deadlines N/A
Tue 18-07-24 Tue 18-07-24

Efforts Our team was We were given 5 We ended up with 4 team


consisted of us volunteers to help members, the PM, and 5
3, Sarah Mann us with project volunteers.
(PM) and an work.
extra team
Member,
which we
called
Elizabeth

Spending $5000 Additional $10,000 $15,000.00


Explain all differences: This project was significantly under budget, because the project team
ended using more volunteers than what was on the project plan. The Scope and Schedule were
not impacted and did not suffer any major change. There were some changes pushed by the
Sponsor regarding the quality of some deliverables, but they were handled without any impact
to the project outcome.

Lessons Learned Recommendations


Date: 2020-04-05 Project Number: N/A
Project Name: MS Society - London to Grand Bend Tour Project Sponsor: Hamza Qazi
Project Manager: Sarah Mann
Project Objectives Worked/Continue Did not work/ Modify

Scope We understood the Scope Be Careful with other sources


since day one of the project. of information for this
Our recommendation is to project. This scope is very
ask as many questions as specific and does not include
possible to your Sponsor. several things from the
He/She will provide very project case study (E.G:
detailed documentation, but Refreshments for the day of
still really useful to ask the tour). Make sure to work
questions and confirm some on a brand new WBS for this
information. The Scope of the assignment. We make
project may seem simple and corrections in the WBS, as
straightforward, but it's not. the resources column and
We founded the new stakeholders were not
gentative route for the required .
project within the given time,
cost and resources , quality.

Schedule This was the project major As per our PTB Report, we
constraint, so everyone knew didn't meet the schedule
the schedule very well. The timeline, as we took most of
instructions regarding the the tasks with optimistic
Three Point Estimation duration.There were some
technique will be very tasks that had taken 2-3 days
helpful. Make sure to and we couldn't change their
understand how to use it and days to less than allocated.
confirm the information with Instead of getting the 21 days
your sponsor. Also, have for the whole project, we got
100% clear what are your 23 days.
available human and physical
resources for the projects. As
per simulation, Our actual
duration was 23 days

Cost We accurately distributed the We were afraid to be above


cost of each task and budget, so we ended up using
resources so that we stick to more volunteers than the
the budget to not get over original plan, which ended up
budget then the actual having the opposite factor.
budget we got in target. We were under budget by
roughly 33% percent.

Effort In the PTB Report scenario, Despite that, volunteers'


there were 3 listed efforts probability to show up in the
that we achieved project was less than 60%, so
1) Number of team we had to assign them few
members tasks that were not so
2) Given more important . But for us, it took
volunteers time to assemble the
3) Reduced 1 team volunteers for task on which
member. they will not hamper their
Here, we achieved all of progress while running the
the criterias according to PTB scenario.
fulfill the Project deadline
and work/ effort.
The Probability of the
volunteers in the project
was less than other
resources . it was 60% and
the main tasks were listed
and assigned to other
resources like we as team
and sarah mann to not
break the PTB Scenario.
Volunteers were only
called up for the task
whenever they needed it
because they didn't have
any cost assigned with
them.

Project Area Worked/Continue Did not work/ Modify

Project Initiation As per the project charter In the Project purpose and
was developed, Major background, we wrote the
Constraints were kept in duration for the project as for
consideration regarding cost, 22 days.In the schedule/
time workers/volunteers.For Timeline area, we forgot to
cost, some activities required add 2-3 tasks in the MS
more budget like permits, project and we modified
safety and kits etc where we them by adding all remaining
had to properly distribute the tasks in the Final project
money according to the areas management plan.
where it will get more utilized
and needed more.

Project Management Plan For the overall project In the project management
management plan, the areas plan, WBS needed
like Background, Network modification as we
diagram,Cost allocation for unnecessarily added the
each expenses, Quality of the information for marketING,
project, Resources assigned Stakeholders as WBS does
to each task were properly not include resources.So, we
worked as per we distributed didn't add them into the final
for the project. project management plan.

Project Execution N/A The project execution was


not achieved because we
didn't meet few targets
including quality
requirement, Total Cost and
Idle cost.

Project Closeout N/A N/A

Communication Plan In the Project management There were no


plan, We assigned different communication modifications
modes of communication done in the entire project.As,
tools for specific resources/ we accurately distributed all
Person and even we provided the tools and modes for each
the medium by which they resource in the project
will communicate and management plan.
enlisted the possible barriers.

Team Membership As working in a team of 3 , N/A


we all coordinated with the
work really well. In the
beginning we distributed the
tasks among all of us and we
achieved the team work. We
committed to accurately
distribute work so everyone
can complete the work prior
to the deadline easily.We
managed responsibility, had
excellent communication
skills

Risk Analysis Earlier in the Project charter, In the Final Presentation


we followed the template for plan, we modified the risk
risk management plan that register by adding a few more
included risk description, parameters like risk ID,
assessment level and Probability, Impact, Owner,
mitigation strategy. Cause.

Quality Plan Our quality plan was N/A


impacted by the changes
requested by our sponsor.
However, his instructions
were very clear, and the new
quality requirements were
achieved without any major
impact to cost, schedule or
scope.We would recommend
leaving some buffer
(resources and time),
because you may have to
choose longer or more
expensive tasks due to
quality requirements.

Procurement Plan We used a table format that We used documentation


all the members would put from older projects to help us
their needs/thoughts and with our procurement plan,
then we consolidate and we ended up adding
everything together. This was more than we needed. Don’t
a great approach. use any other documents
than the ones provided by
our Sponsor.

Project Change Management Documenting every change in Saving all the PTB
plan the deliverables (Project submissions information in a
Charter, Project Plan) in the document would have helped
same format is a good way to us a lot, but we only started
keep track of everything. The doing so on a later stage of
team has to agree on a the process.
format and use it.
Afterwards, you can control
and check all of them without
much effort.
Recommendations:
1. Our most important advice is to ask as many questions as you can to your sponsor and
clarify everything before putting information into deliverables, especially the early ones,
Project Charter and Project Plan. We wrote without understanding 100% and it ended
up costing us a lot of time to fix it on a later stage of the project.
2. This process is very iterative. It may seem confusing in the beginning, but everything will
come together in the end. The first contact with the simulation tool may seem scary, but
there’s a lot of video and tutorials. Make sure to check them thoroughly before starting
working with the tool.
3. Before the execution of the project,the entire team should go through the work again so
that they can evaluate the durations of the activities as per the tasks allocated. If the
duration gets misaligned , then the whole project can reach over schedule or under
schedule.
4. The parameters like Idle cost, Penalty needs very serious consideration while running
the scenarios.