Al Wissam Showroom /Update To (03-Dec-2020) Plan TASK filters: One Month Lookahead Works, WBS_1.

Activity ID Activity Name Original Activity % Start Finish


Duration Complete 2020 2021
Jul A S O N D J F M A M J Jul
205 01-Aug-20 A 03-Jan-21 03-Jan-21, Al Wissam Sho
Al Wissam Showroom Plan
203 01-Aug-20 A 01-Jan-21 01-Jan-21, General Requirement
General Requirement
Milestone 203 01-Aug-20 A 01-Jan-21 01-Jan-21, Milestone
A1000 Permit Approval 30 100% 01-Aug-20 A 31-Aug-20 A Permit Approval
A1080 Mobilization 7 100% 02-Sep-20 A 10-Sep-20 A Mobilization
A1010 Site Delivery 0 100% 07-Sep-20 A Site Delivery
A1690 Architectural Design Drawings Submission 0 100% 11-Nov-20 A Architectural Design Drawings Su
A1710 Architectural Design Drawings Approval 0 100% 16-Nov-20 A Architectural Design Drawings Approval
A1020 Requirement ARB Fit Out Design 0 100% 16-Nov-20 A Requirement ARB Fit Out Design
A1040 Structural Design Drawings Submission 0 100% 18-Nov-20 A Structural Design Drawings Submission
A1030 Structural Design Drawings Approval 0 100% 21-Nov-20 A Structural Design Drawings Approval
A1060 Down Payment 0 0% 03-Dec-20 Down Payment
A1700 MEP Design Drawings Submission 0 0% 08-Dec-20 MEP Design Drawings Submission
A1720 MEP Design Drawings Approval 0 0% 08-Dec-20 MEP Design Drawings Approval
A1120 Finish till Slab on Grade 0 0% 01-Jan-21 Finish till Slab on Grade
124 12-Sep-20 A 03-Jan-21 03-Jan-21, Execution Works
Execution Works
Civil Works 124 12-Sep-20 A 03-Jan-21 03-Jan-21, Civil Works
Sub Structure 124 12-Sep-20 A 03-Jan-21 03-Jan-21, Sub Structure
Under Ground Works 122 12-Sep-20 A 01-Jan-21 01-Jan-21, Under Ground Works
UG&T-0010 Excavation 11 100% 12-Sep-20 A 26-Sep-20 A Excavation
UG&T-0020 Termite Control 1st Step 1 100% 29-Sep-20 A 29-Sep-20 A Termite Control 1st Step
UG&T-0030 Blinding Concrete 4 100% 30-Sep-20 A 03-Oct-20 A Blinding Concrete
UG&T-0080 Concrete Isolated Footing 6 100% 22-Nov-20 A 03-Dec-20 A Concrete Isolated Footing
UG&T-0050 Columns neck 5 0% 07-Dec-20 11-Dec-20 Columns neck
UG&T-0160 Earthing Works ( Ranging within column necks) 3 0% 08-Dec-20 10-Dec-20 Earthing Works ( Ranging wit
UG&T-0170 Curing works 3 0% 12-Dec-20 14-Dec-20 Curing works
UG&T-0120 Waterproofing 1 0% 15-Dec-20 15-Dec-20 Waterproofing
UG&T-0130 Backfilling 1st Step 4 0% 16-Dec-20 19-Dec-20 Backfilling 1st Step
UG&T-0040 Grade Beams 4 0% 20-Dec-20 23-Dec-20 Grade Beams

Actual Work
Prepared by: Senior Planning & Cost Manager
Remaining Work Fady F. El Aawar
Critical Remaining Work Al Wissam Showroom /Update To (03-Dec-2020)
Milestone Page 1 of 2
Summary
Al Wissam Showroom /Update To (03-Dec-2020) Plan TASK filters: One Month Lookahead Works, WBS_1.

Activity ID Activity Name Original Activity % Start Finish


Duration Complete 2020 2021
Jul A S O N D J F M A M J Jul
UG&T-0150 MEP Embedded Items (Ranging within GB & SOG) 7 0% 22-Dec-20 28-Dec-20 MEP Embedded Items (Ra
UG&T-0070 Backfilling 2nd Step 2 0% 24-Dec-20 25-Dec-20 Backfilling 2nd Step
UG&T-0140 Termite Control 2nd Step 1 0% 26-Dec-20 27-Dec-20 Termite Control 2nd Step
UG&T-0110 Slab on Grade 4 0% 28-Dec-20 01-Jan-21 Slab on Grade
Water & Septic Tank Works 25 10-Dec-20 03-Jan-21 03-Jan-21, Water & Septic
UG&T-0250 Excavation Work 6 0% 10-Dec-20 15-Dec-20 Excavation Work
UG&T-0190 Blinding Work 2 0% 17-Dec-20 18-Dec-20 Blinding Work
UG&T-0200 Waterproofing under Tank 2 0% 19-Dec-20 20-Dec-20 Waterproofing under Tank
UG&T-0060 Concrete Rafts for Tanks 5 0% 21-Dec-20 25-Dec-20 Concrete Rafts for Tanks
UG&T-0090 Concrete Walls for Tanks 6 0% 25-Dec-20 30-Dec-20 Concrete Walls for Tanks
UG&T-0230 MEP Embedded Items 2 0% 26-Dec-20 27-Dec-20 MEP Embedded Items
UG&T-0260 Testing for 48 hours 2 0% 28-Dec-20 29-Dec-20 Testing for 48 hours
UG&T-0100 Concrete Cover Slab for Tanks 4 0% 31-Dec-20 03-Jan-21 Concrete Cover Slab for Tanks

Electrical Works 9 11-Dec-20 19-Dec-20 19-Dec-20, Electrical Works


Power Networks 4 16-Dec-20 19-Dec-20 19-Dec-20, Power Networks
E-W-0025 Panel Boards Installation 4 0% 16-Dec-20 19-Dec-20 Panel Boards Installation
Lightning & Earthing Systems 6 11-Dec-20 16-Dec-20 16-Dec-20, Lightning & Earth
E-W-0100 1st Fix (Cabling) 6 0% 11-Dec-20 16-Dec-20 1st Fix (Cabling)

Actual Work
Prepared by: Senior Planning & Cost Manager
Remaining Work Fady F. El Aawar
Critical Remaining Work Al Wissam Showroom /Update To (03-Dec-2020)
Milestone Page 2 of 2
Summary