HSE Daily REPORT

Rig : 5005 Date: 2019 12 19 Days LTI Free: 526 Rig Manager

HF0287-
Well M0287H1
Date operation start: 2019/10/08 Petrochina DSV

ANTON Days since last


526 HSE Supervisor
recordable case
PERMIT TO WORK
POB Details STOP CARD
Cold Work : 1 Hot Work : 0 LIFTING 0 CSE 0

Bed Capacity Total Cards Percentage AT807

Total POB 69 0%
PCH 3 0%
ANTON 34 1 3%
Third Party 35 0%

UA
UC 1
SC
SA

JHA 1 Off load Diesel

TBT 1 Off load Diesel

Daily Inspections 1

Audits 0

Drill 0

Finding 1

Training 1 Well Control

Near miss 0

Incident 0

Activity 1

Monthly Safety Theme. Energy Isolation


STOP CARDS HIGHLIGHT (Top 5 Cards)
No. Observation Action

4
Huang Wei

Yao Zhixiang / Zhang Diansheng

Umer Farooq

TOTAL: 1

Action
DRILLING CONTRACTOR UAUC OBSERVATION 2019

No. Date Location Area Company Classification Observation

1 12/1/2019 HF-0287 Rig site AT5005 UC UC Fire hoses are not properly covered and placed inside the box

2 12/1/2019 HF-0287 Rig site AT5005 UA UA Floormen were working at rig floor without safety glasses

Grounding with the mud tank#7 is not installed yet, meanwhile, power junction box
3 12/2/2019 HF-0287 Rig site AT5005 UC UC
observed without grounding

4 12/2/2019 HF-0287 Rig site AT5005 UC UC Forklift operator cabin observed full of rubbish and cigarates butts

Fire Extenguisher on the rig floor duty room found empty, meanwhile, another F.E
5 12/2/2019 HF-0287 Rig site AT5005 UC UC
found empty inside the forklift operator cabin

6 12/3/2019 HF-0287H1 Rig site AT5005 UC UC One chemical sack found damage and chemical is leaking

Welder was doing welding job without arrangement of DCP fire extinguisher near to
7 12/3/2019 HF-0287H1 Rig site AT5005 UA UA
him

8 12/4/2019 HF-0287H1 Rig site AT5005 UC UC Manual slips handles observed without green color

9 12/4/2019 HF-0287H1 Rig site AT5005 UA UA Welder was doing welding job without welding PPE

10 12/5/2019 HF-0287H1 Rig site AT5005 UC UC Some safety signs on rig floor damaged or not posted at all

Crane operator was performing the lifting operation without barricade the crane
11 12/5/2019 HF-0287H1 Rig site AT5005 UA UA
radius area

12 12/6/2019 HF-0287H1 Rig site AT5005 UA UA Mud boy was mixing the chemical without wearing the google

Walk way on the flow line is not properly covered, chance of fell down from height is
13 12/6/2019 HF-0287H1 Rig site AT5005 UC UC
quite possible
14 12/6/2019 HF-0287H1 Rig site AT5005 UC UC Body wash station on mud tank is not connected yet with clean water line

15 12/7/2019 HF-0287H1 Rig site AT5005 UA UA Welder is doing grinding job near to workshop without PPE

16 12/7/2019 HF-0287H1 Rig site AT5005 UC UC Aftet cleaning the tank, mud tank lid was not closed, chance of fell down inside

17 12/8/2019 HF-0287H1 Rig site AT5005 UA UA some garbage observed inside the rig floor duty room

18 12/8/2019 HF-0287H1 Rig site AT5005 UC UC One SCBA have an air leakage problem

19 12/9/2019 HF-0287H1 Rig site AT5005 UA UA Mechanic was working without hard hat and also was smoking near gas cylinders

20 12/9/2019 HF-0287H1 Rig site AT5005 UC UC Forklift reverse alarm is not functioning and operator cabin is full of rubbish

21 12/10/2019 HF-0287H1 Rig site AT5005 UC UC Bad housekeeping observed inside the workshop and surrounding area

22 12/10/2019 HF-0287H1 Rig site AT5005 UA UA Many cigarette butts and rubbish observed inside the mud engineer lab

23 12/11/2019 HF-0287H1 Rig site AT5005 UC UC Casing lay down on ground without placing on casing rack

24 12/11/2019 HF-0287H1 Rig site AT5005 UA UA Mud boy and mud engineer were mixing chemical without proper PPE

25 12/12/2019 HF-0287H1 Rig site AT5005 UC UC One SCBA found with low air pressure

26 12/12/2019 HF-0287H1 Rig site AT5005 UA UA Link was lifted up by crane without tag line and bankman

27 12/13/2019 HF-0287H1 Rig site AT5005 UC UC Camp fire pump is not switing on due to have low battery problem

28 12/13/2019 HF-0287H1 Rig site AT5005 UC UC Mud spillage observed around the trip tank
29 12/14/2019 HF-0287H1 Rig site AT5005 UA UA AD started the mud tank cleaning job without PTW

30 12/14/2019 HF-0287H1 Rig site AT5005 UC UC Eye wash station on mud tank found empty

31 12/15/2019 HF-0287H1 Rig site AT5005 UA UA Crew were working on the mud pump with out proper PPE

32 12/16/2019 HF-0287H1 Rig site AT5005 UA UA Electrician was working on electrical installation without electrical PPE

33 12/17/2019 HF-0287H1 Rig site AT5005 UC UC Chemcial spillage on the walkway of mud tank cause slippery hazard

34 12/18/2019 HF-0287H1 Rig site AT5005 UC UC One Mud tank's lid found open wide, it may cause of fell down inside the tank

35 12/19/2019 HF-0287H1 Rig site AT5005 UC UC Fire extenguisher is not available in public toilet

36

37

38

39

40

41

42

43

45
46

47

48

49

50

51

52

53

54

55

56

57

58
OBSERVATION 2019
Closed Status Recorded
Action taken Immediately Observed By
Date O/C by

Keep protect the fire hoses inside the box to prevent from
HSE 12/2/2019 O HSE
damage by harsh weather

Advise them about to wear all PPE while at work place HSE 12/1/2019 C HSE

Informed RM and responsible person for connecting the


HSE 12/2/2019 O HSE
grounding with the identified tank and power junction box

Advise forklift operator about to keep clean the operator


HSE 12/2/2019 C HSE
cabin

Arrange new DCP fire extinguishers and place at respective


HSE 12/2/2019 C HSE
places

Informed Mud engineer about to immediately stop and


HSE 12/3/2019 C HSE
remove the chemical leakage from the sack and
Advise him about to arrange DCP class fire extinguisher and
HSE 12/3/2019 C HSE
place near to him for safe welding job

Informed RM about to appoint someone for doing paint


HSE 12/4/2019 O HSE
green color work with all manual slips handles

Advise him about to wear all welding PPE before to do


HSE 12/4/2019 C HSE
welding job

New safety signs have been arranged and will posted within
HSE 12/6/2019 C HSE
due date

Advise crane operator about to barricade the crane radius


HSE 12/5/2019 C HSE
area

Give him new google and request him to wear all time while
HSE 12/6/2019 C HSE
mixing the chemical

Advise AD about to protect the expose area of walkway


HSE 12/6/2019 O HSE
where chance of fell down from height is quite possible
Advise AD about to immediately connect the body wash
HSE 12/6/2019 C HSE
station with clean water line on mud tanks

Advise him about to wear all grinding related PPE HSE 12/7/2019 C HSE

Advise mud boy about to close the lid of mud tank after
HSE 12/7/2019 C HSE
finish cleaning tank

Advise all crew on rig floor about to keep clean the entire rig
HSE 12/8/2019 C HSE
floor

Informed RM about to fix the air leakage problem with SCBA HSE 12/8/2019 C HSE

Give him last warning regarding smoking violation and


HSE 12/9/2019 C HSE
Advise him about to wear all PPE at his work place

Informed RM about to give instruction to mechanic for


HSE 12/9/2019 O HSE
installing of new reverse, advise operator for cleaning cabin

Advise mechanic for maintaining good houekeeping inside


HSE 12/10/2019 C HSE
and outside of workshop

Give verbal warning to mud engineer and told him about to


HSE 12/10/2019 C HSE
smoke cigarettes at smoking designated area only

Informed responsible person for proper placement of casing


HSE 12/11/2019 C HSE
on casing rack

Advise them about to wear all PPE while mixing the chemical HSE 12/11/2019 C HSE

Fill the SCBA and put back at respective place HSE 12/12/2019 C HSE

Advise crane operator and TP about to banksman must


HSE 12/12/2019 C HSE
wear vest jacket and must use tag-line with each load

Informed rig manager about to fix the problem with the camp
HSE 12/13/2019 C HSE
fire pump

Advise AD and mud boys to clean the mud sillage around


HSE 12/13/2019 C HSE
the trip tank
Advise him about to prepare PTW and then start the
HSE 12/14/2019 C HSE
cleaning the mud tank

Advise AD about to fill the eye wash station with fresh and
HSE 12/14/2019 C HSE
clean water

Advise all crew about to wear all PPE before before to start
HSE 12/15/2019 C HSE
the work

Request him about to wear electrical PPE HSE 12/16/2019 C HSE

Informed mud engineer about to immediately clean the


HSE 12/17/2019 C HSE
walkway of mud tank

advise all crew about to keep close the all tank lids after the
HSE 12/18/2019 C HSE
end of work

Arrange new DCP fire extinguishers and place at respective


HSE 12/19/2019 C HSE
place
PERSONNEL ON BOARD AT5005
Halfaya 2019年12月19日

NO. Name company Position Nationality D\N Shift Room N Date In Date out

Petrochina

1 Yao Zhixiang PCH DSV Chinese D


2 Zhang Diansheng PCH DSV Chinese D
3 Liu Jun PCH Geologist Chinese D
Antonoil Drilling Crew
1 Huang Wei Anton Rig Manager Chinese D
2 He Shanfei Anton Operation Manager Chinese D
3 Sun Peng Anton HR Manager Chinese D
4 Chen xue feng Anton Drilling Engineer Chinese D
5 Li Wen Jie Anton Toolpusher Chinese D
6 Wu De Hua Anton Assistant Driller Chinese D
7 Li de zhong Anton Motor man Chinese D
8 Chen Shu Liang Anton Mechanic Chinese D
9 Chu Shuqing Anton Electrician Chinese D
10 Sun Guang Fa Anton Driller Chinese D
11 Nie Shen Min Anton Crane operator Chinese D
12 Xu Hua Qing Anton TDS Engineer Chinese D
13 Umer Farooq Anton HSE Engineer Pakistani D
14 Zhang Hui Anton Driller Chinese N
15 Zhang Li Heng Anton Assistant Driller Chinese N
16 Zhao Jichao Anton Toolpusher Chinese N
17 Ali Salah Anton Assist HSE Iraqi D
18 Karar Abbas Anton D.M Iraqi D
19 Muhammad Adnan Anton D.M Iraqi D
20 Ali Hashim Anton F.M Iraqi D
21 Mustafa Hussain Anton F.M Iraqi D
22 Jafar Mohsin Anton F.M Iraqi D
23 Haider Aity Anton M.B Iraqi D
24 Haider Jasim Anton M.B Iraqi D
25 Hani Anton D.M Iraqi N
26 Hassan Ouda Anton D.M Iraqi N
27 Ali Dinar Anton F.M Iraqi N
28 Mohsin Anton F.M Iraqi N
29 Muhammad Anton F.M Iraqi N
30 Kazim Kibar Anton F.M Iraqi N
31 Hassan Anton M.B Iraqi N
32 Ahmed Anton M.B Iraqi N
33 Salman Anton M.B Iraqi N
34 Ali Ganim Anton Crane operator Iraqi D
35 Adel Khalaf Anton Crane operator Iraqi N
36 Kazim Jabar Anton Pickup Driver Iraqi D
37 Ahmed Jabbar Anton Rig medic Iraqi D
38 Maithem Anton Gate Man Iraqi D
GWDC Mud logging
1 Javaid Akhtar GWDC Data Engineer Pakistani N
2 Afrashiab Khattak GWDC Mud Logger Pakistani N
3 Imtaiz Ahmed GWDC Data Engineer Pakistani D
4 Ghulam Kebria GWDC Mud Logger Pakistani D
5 Ali Rabi GWDC Sample catcher Iraqi N
6 Hadi GWDC Sample catcher Iraqi D
Power Mud
1 Zhang Ping Power Petroleum Mud Engineer Chinese D
2 Lv Zhi qiang Power Petroleum Mud Engineer Chinese N
Catering Crew
1 Sajeev TPC Camp Boss Indian D/N
2 Wang Qiujun TPC Cook Chinese D
3 Manivarnan Ramallngum TPC Assitant Cook/ Chinese Indian D
4 Mustafa TPC Cook/ Iraqi Iraqi D
5 Ali TPC Waiter / iraqi Iraqi D
6 Ajit Veigas TPC Cleaning Indian D
7 Robiul Jabed TPC Clean boy Bangladesh D
8 Md Afsar TPC Clean boy Bangladesh D
9 Mohammad Mammun TPC Kitchen clean boy Bangladesh D
10 Imran TPC Laundry man Bangladesh D
Security Crew
1 David Olweny REED Supervisor Uganda D/N
2 Mousa Kadhim REED Guard Iraqi N
3 Mousa REED Guard Iraqi N
4 Haider REED Guard Iraqi N
5 Abbas Adnan REED Guard Iraqi D
6 Jabbar REED Guard Iraqi D
7 Jassim Muhammad REED Guard Iraqi D
OPF
1 Hashem OPF OPF Iraqi D/N
2 Thamer OPF OPF Iraqi D/N
3 Mohammad OPF OPF Iraqi D/N
12/19/2019
S.No POB Man Hour UA UC POSITIVE CWP HWP FAC MTC Near Miss

1 79 948 1 1 0 2 0 0 0 0
2 78 936 0 3 0 1 1 0 0 0
3 74 888 1 1 0 0 1 0 0 0
4 75 900 1 1 0 1 1 0 0 0
5 73 876 1 1 0 2 2 0 0 0
6 70 840 1 2 0 0 0 0 0 0
7 69 828 1 1 0 1 0 0 0 0
8 69 828 1 1 0 0 0 0 0 0
9 68 816 1 1 0 0 0 0 0 0
10 69 828 1 1 0 0 0 0 0 0
11 66 792 1 1 0 0 1 0 0 0
12 75 900 1 1 0 1 0 0 0 0
13 78 936 0 2 0 1 0 0 0 0
14 72 864 1 1 0 3 1 0 0 0
15 67 804 1 0 3 0 0 0 0
16 67 804 1 0 0 1 0 0 0 0
17 67 804 0 1 0 0 0 0 0 0
18 68 816 0 1 0 0 0 0 0 0
19 69 828 0 1 0 1 0 0 0 0
20 0 0 0 0 0 0 0 0 0 0
21 0 0 0 0 0 0 0 0 0 0
22 0 0 0 0 0 0 0 0 0 0
23 0 0 0 0 0 0 0 0 0 0
24 0 0 0 0 0 0 0 0 0 0
25 0 0 0 0 0 0 0 0 0 0
26 0 0 0 0 0 0 0 0 0 0
27 0 0 0 0 0 0 0 0 0 0
28 0 0 0 0 0 0 0 0 0 0
29 0 0 0 0 0 0 0 0 0 0
30 0 0 0 0 0 0 0 0 0 0
31 0 0 0 0 0 0 0 0 0 0
Total 1353 16236 14 21 0 17 7 0 0 0
12/19/2019
Inspection Drills

1 0
1 0
1 0
1 0
1 1
1 1
1 0
1 0
1 0
1 0
1 0
1 1
1 0
1 1
1 1
1 0
1 0
1 0
1 1
0 0
0 0
0 0
0 0
0 0
0 0
0 0
0 0
0 0
0 0
0 0
0 0
19 6