IMS

ELEMENT

1. Contract 1-Lease, moore, Install and operate 45kbopd 3-phase separation MOPU (Critical for 1st Oil)
2. Contract 2-Lease, moore, Install & operate 600Kbbls 50-man FSO & 70Kbbls Shuttle Tanker (Cr 1st Oil)
3. Contract 3-Flexible Hoses connecting MOPU to WHP, MOPU to FSO, FSO to Shuttle Tank
4. Contract 4-Procurement and installation of LACT unit and PD Meters (Critical for 1st Oil)
5. Contract 5- KCDP-A Re-vamp
6. Contract 6-Revamp KCDP-B
7. Contract 10-Marine Support Vessels (SEWOP, PSV, FSIV & Security Vessel, etc)
8. Contract 11-Procur & instal 2no. multi wellhead control panels, ea. for KCDP-A & B wells (Cr 1st Oil)
9. Contract 13: Slickline Unplugging_ SGBHP_Eline RMT) on KCDP-A and KCDP-B
10. Contract 14: Supply of wellhead manifolds for KCDP-A & KCDP-B1
11. Contract 15: Design and fabrication of sacrificial anode for kalaekule field OML 72
12. Contract 16: Structural Assessment, DESKTOP (KCDP-A & KCDP-B)
13. Contract 17: Structural Assessment, Visual Underwater Inspections (KCDP-A & B)

KCDP-A REVAMP

1. Duration: 95 days (3-months)


2. Time frame: 15-Dec-2 to 19th-March-2021
3. 1st oil comes up by 19-Mar-2021

KCDP-B Safe Access to KCDP-B

1. Duration: 19 days for offshore activities


2. Time frame: 12-Feb-2021 to 3rd March-2021
3. 2nd oil comes up by 30-Apr-2021