Professional Documents
Culture Documents
Case Study Group 2
Case Study Group 2
COLLEGE OF ENGINEERING
MEMBERS:
The purpose of this case study is to determine the factors that are
involved to complete the project within the given time extension and monetary
requirements.
From the assessment made by the team, the challenging factors are
being determined by interviewing the contractor as per Qualitative Analysis.
In this case study, utilizing the qualitative data gathering and analysis
posed a great deal in helping complete construction projects.
The Project consists of the construction of the 20-meter bridge
superstructure and elements with 9.7-meter width, 230-meter approaches that
includes slope protection, concrete pavement and wearing surface, and earth
and river works. The budgetary requirement is 10, 170, 000.00 pesos. The
Project implementation activities started May 2020 and is supposed to be
finished on November 2020. However, the project is delayed by 5 months due
to extension of time (EOT) brought about by issues such as weather
disturbances, right-of-way issues and traffic management, thus, extended until
April 2021. The Location is within Region VII of the Republic of the
Philippines.
Based on individual Relative Weights, it is evident that Item 505(2)a
Grouted Riprap Class A and Item 506 Stone Masonry are the critical activities
since they hold the highest duration among all the activities (12.38%).
The second most critical activities are Item 508 Hand-laid Rock
Embankment and Item 311(1)e Portland Cement Concrete Pavement
(11.14%).
Largest contributor to the delay of project is the ROW problem.
The implication that there is a lapse in coordination between contractor and
the client with regards to the issue.
The pre-construction stage is the most important stage in a
construction project. It does not only determine possible risk but also help
minimize and eliminate the negative effects these risks may bring.
Reports are the most important tool in project management,
control and monitoring. A well-detailed report may provide a database for the
selection of the best technique in keeping the project in its time and cost
requirements.
INTRODUCTION
Risk Optimization
Planning and Identification of
Scheduling and Construction
Assessment Phase
Figure 1. Pre-construction Process Flow Chart
Decision Criteria
` Time requirement such that the project avoids any delay in order to
accomplish the due date.
Assumptions
An attempt to establish a process of achieving goals was mention in
our project management subject. Assumptions in this project is vital for us
to meet our goals, plan ahead, and to prepare for possible problems to
encounter. The assumption is that the solution that we are about to come
up will help in the scheduling and management of the project up to its
completion.
Data Analysis
1. Pre-construction Phase
Risk Optimization
Planning and Identification of
Scheduling and Construction
Assessment Phase
Figure 1. Pre-construction Process Flow Chart
The items included in the program of works are presented on
Table 1 which shows the individual Relative Weight of each items.
Relative Weight is computed as individual duration divided by the total
number of days for all items multiplied by 100.
310(1) Bituminous Concrete Wearing Course, Hot Laid (thk. = 50mm) 5 1.24
310(1) Bituminous Concrete Wearing Course, Hot Laid (thk. = 50mm) 5 1.24
Outcome
From the assessment made by the team, the challenging factors are
being determined by interviewing the contractor as per Qualitative
Analysis.
CONCLUSION
https://scad.gov.ph/build-build-build/
https://www.pmi.org/about/learn-about-pmi/what-is-project-management
https://www.apm.org.uk/resources/what-is-project-management/
www.informaticsjournals.com/index.php/mvpjes/index.
www. ppiaf.org/sites/ppiaf.org/files/documents/toolkits/highwaystoolkit/6/pdf-
version/3-12-3.pdf
www.en.wikipedia.org/wiki/Transportation_in_the_Philippines