Professional Documents
Culture Documents
Short Circuit Levels Adequation by Network Topology Modifications Using Genetic Algorithms
Short Circuit Levels Adequation by Network Topology Modifications Using Genetic Algorithms
Short Circuit Levels Adequation by Network Topology Modifications Using Genetic Algorithms
net/publication/265932155
CITATIONS READS
0 145
4 authors, including:
Some of the authors of this publication are also working on these related projects:
Models for optimal pricing of electricity and demand side scheduling View project
All content following this page was uploaded by Alberto Urdaneta on 23 September 2014.
Abstract-- A new methodology is proposed to adequate the In this work an automatic methodology is proposed that
short-circuit levels on the buses of an electrical power system allows to adapt the short-circuit levels in busbars and the
as well as to control the fault current contributions through maximum fault current contributions by their ties, through
the bus ties, using a genetic algorithm to optimize the the optimized modification of the system topology using a
network topology by positioning and controlling the genetic algorithm [1], [2], [3].
operation of the bus-tie breakers. The problem is stated as an The problem is stated as an optimization problem, with the
optimization problem, formulated as to maximize the number objective function defined to maximize the reliability of the
of closed bus-tie breakers, subject to the short-circuit system. The problem restrictions are given mainly by the
capabilities of the equipment and the normal operation maximum short-circuit levels in busbars and the maximum
constraints. The problem is of combinatorial nature for which contributions of fault currents, as well as those limits on the
the genetic algorithm constitutes a powerful tool for its operation variables associated to permissible system
solution. The methodology was successfully applied to the operation conditions in steady state. The operation states of
electrical power system of AES Venezuela - C.A. La the bus-tie breakers are chosen as control variables for the
Electricidad de Caracas consisting of eight (8) 230 kV definition of new topologies. Based on the evaluation of the
substations and seventeen (17) 69 kV substations connected previous operating conditions of the breakers, the genetic
to 30 kV and 12.47 kV. networks. algorithm promotes changes on their state and determines the
"fitness" of each resultant topology as a solution, and direct
Key Words -- Genetic algorithms, network topology, the search towards the best network configuration, if it does
optimization, power systems, short-circuit level adequation, exists.
switching. The main difficulty of the problem lies in its combinatorial
nature and its increasing dimensionality with the size of the
system under study. The search of an adequate solution is not
I. INTRODUCTION trivial and to the authors knowledge no mathematical
The short-circuit levels in busbars of an electrical power methodology has been proposed so far to approach this
system can be changed by modifying the state of operation problem, except for the "trial and error" option.
(switching) of the bus-tie breakers. By this means, the
possibility of adapting the short-circuit levels of a power II. STATEMENT OF THE PROBLEM
system as well as the maximum fault current contributions
from busbar ties appears, by changing the network topology As previously mentioned, the problem of adequating the
through operations of the existing bus-tie breakers, power system buses short-circuit levels by network topology
maintaining the system operative limits and appropriate changes reached through operations on the existing bus-tie
reliability indices. breakers, can be outlined as an optimization problem.
The high short-circuit levels not only affect the substations From the theoretical point of view, the objective function
breakers but other substation equipment. The replacement of is defined as the maximization of the reliability of the
any of these devices of the system due to the increase of the electrical network, which is a function of the network
short-circuit levels, could lead to the need of high topology.
investments. The costs of greater capacity equipment, mainly The problem can be outlined as:
breakers, could be deferred in the time if the short-circuit
levels could be adjusted through changes in the network Maximize F(I) , (1)
topology. This could represent important savings if it is Subject to: g(I )≤ 0
achieved without reducing the reliability level required in the
network. 4 where
F(I): is the “System Reliability Level”, and
g(I): represents the problem constraints. They depend
C. M. Dacchille and J. Dupouy are with AES Venezuela-Electricidad de basically on the system short-circuit levels and system
Caracas, Venezuela (e-mail: cesar.dacchille@grupoedc.com) .
A. J. Urdaneta and R. Villasana Soto are with Universidad Simón Bolívar,
Aptdo. 89000, Caracas, Venezuela (e-mail: alberto@usb.ve).
369-124
operating conditions (equipment loading, voltage levels, etc.), Ii,j Fault current contribution through the switch located
which at the same time are function of the bus-tie breakers in substation i that flows from the extreme j
state, that is, the system topology.
I: binary array with the states of the candidate bus-tie • Power flow by transmission lines or transformers.
breakers. (1 = closed, 0 = open) Maximum and minimum voltages allowance:
From an engineering point of view, the term reliability is
used to indicate the quality and continuity of the electrical Sbranch k ≤ 100 % (7)
service. In general, the calculation methods and the selection Vmin≤V≤Vmax (8)
of an adequate reliability index depend upon several factors.
The reliability indices of the power system can be evaluated where
using different techniques proposed in the literature [4], [5], S Apparent power.
[6], [7], [8]; however they require the use of time consuming min minimum allowed value.
digital programs that manage relatively complex algorithms. max maximum allowed value.
In this work, to simplify the statement of the problem as V Vector of bus voltage
well as the solution process, without loss of generality, the
number of closed bus-tie breakers for a given network The voltage restriction can also be relaxed including only
topology was chosen as the index to be maximized instead. those buses with critical voltage problems.
Although it is not a reliability index itself, there is a close
relationship between the number of closed bus-tie breakers of
the system for a given network topology and its reliability. III. SOLUTION METHODOLOGY
Under this premises, the problem to be solved can be The proposed methodology is based upon the application
written as: of a genetic algorithm as optimization technique, interacting
Maximize F(I) = Σ i∈ B Ii (2)
with a load flow and a short-circuit calculation modules. The
calculations are performed for a set of relevant scenarios,
considered as representative of the system, and selected
where under certain previously established rules and criteria with
i represents the index of each candidate bus-tie the advise of system experts.
breaker Fig.1 illustrates general solution procedure. It consists of
B is the set of candidate bus-tie breakers three layers:
Using a relaxed approach, the constraints g(I) are stated - a top level where the system experts have the task of
only for those devices or equipment were the allowable limits selecting the relevant scenarios,
are being violated as well as for those elements in the - an intermediate or optimization level, which solves the
proximity of the violation of such limits. They include problem of finding the bus-tie breaker positions by a
restrictions of the type: genetic algorithm for the selected scenarios, and
- a bottom layer or simulation level where the behavior
• Short-circuit Levels: indices and optimization constraints are evaluated [9],
[12].
Ncc1ϕ≤ Ncc1ϕmax (3) The optimization block selects the network topology; that
Ncc13ϕ≤ Ncc13ϕmax (4) is, the position of the bus-tie breakers, considering that the
number of bus-tie breakers that remain closed will be
where maximized.
Ncc short-circuit level The combinatorial nature of the problem is handled by
max maximum allowed value means of the genetic algorithm with the advice of system
i buses with short-circuit level exceeded or near experts. It searches the solution between multiple network
to be exceeded. topologies which are evaluated by the simulation block as a
1φ, 3φ Upper index of “Single Phase” and “Three Phase” calculation subprocess based upon computational programs
. devised to calculate the load flow solution, the short-circuit
levels of the system and the fault current contributions [15],
• Fault Current Contributions: [16].
A. The Genetic Algorithm
Ii,j1ϕ≤ Ii,j1ϕmax (5)
The genetic algorithms technique, have been widely used
Ii,j3ϕ≤ Ii,j3ϕmax (6) in engineering and in particular in the power systems area
[9], [10], [11], [12], [13], [14]. They represent relatively a
where simple alternative to deal effectively with problems of a
i Terminal where the fault occurs. combinatorial nature, like the one outlined in this paper.
j Terminal from where the fault current By means of a direct analogy with natural evolution
contribution flows. processes, each potential problem solution is represented as
an individual with its particular characteristics, which are the genetic algorithm will adapt the short-circuit levels of the
strictly determined by a set of chromosome genes. The system and the maximum fault current contributions, while
individuals are subject to the natural selection process, where enforcing the operation constraints.
In this application, the constraints associated with the
power flow limits through transmission lines and
i: 1 2 3 4 5 6 . . . . . . . . n
1 0 1 1 0 1 . . . . . 0
EXP ERTS
SYSTEM
STUDY CASE DEFINITION
Fig. 2. General structure of a chromosome
OPTIMIZATION
GENETIC circuit levels at busbars and maximum fault current
ALGORITHM contributions are treated as "hard" feasibility constraints.
They were managed by punishing the unfeasible
"individuals", with very large penalty factors.
C.R.Z. Plant
69 kV 33 Boyacá 69 kV Convento 69 kV 11 12 13
15 Arrecifes Guaira 69 kV
17 16
69 kV
24
4 5 6
Chacao 69 kV Convento 30 kV
32 19
20 21 22 Magallanes
69 kV Tarzilandia 69 kV
2 3 Curupao 69 kV
Catia 30 kV
25
Cota Mil
69 kV
LEYENDA:
Prado de María 30 kV
Equivalent
7 Generator
Bambues 30 kV
230/69 kV
31 1 Transformer
Prado de María
8 9 10
69 kV 69/30 kV
Barbecho 69 kV Santa Rosa 30 kV Transformer
28
27 Boulevard 69 kV 765/230 kV
Panamericana Auto-
69 kV
Transformer
Antimano 69 kV Pedrera 69 kV
30
Bus-Tie
26 23 Breaker
30 kV Network
Pedrera
230 kV
14 18 Papelón 69 kV
Junquito 69 kV 29
OAM 69 kV
OAM Plant
69 kV Papelón 230 kV
Junquito 230 kV
Fig. 3. Transmission system of the C.A La Electricidad de Caracas Used as Test Case
For the test case, the obtained solutions correspond to six stage, the production of new qualified individuals decreases
(6) topologies (individuals) which satisfy all the constraints since the population is limited.
with a maximum historical value for the adaptability function In average, the historical maximum was reached after 24
of thirty (30), i.e., with the 3 bus-tie breakers open. generations.
Analyzing the results, the best solutions are based on the
opening of the combinations of three bus-tie breakers in the 35
whole system. These are: bus-tie breakers No. 2 or No. 3 in 30
the substation Catia 30 kV; bus-tie breakers No. 8, No. 9 or
Fitness Function
25
Average of the