Professional Documents
Culture Documents
Foundation Problems
Foundation Problems
TABLE OF CONTENTS
4
PROF. MOHAMMED AWAD
ENG. LUAY QRENAWI ENG. RANA JABER
SOLVED PROBLEMS IN FOUNDATION ENGINEERING
ACKNOWLEDGMENTS
Our thanks are due also to our sincere students, who helped us in
preparing this work.
1
SOLVED PROBLEMS IN FOUNDATION ENGINEERING
2
SOLVED PROBLEMS IN FOUNDATION ENGINEERING
PREFACE
This book was prepared to cover the urgent need of the student of
Civil Engineering Department at the Islamic University of Gaza to a
reference gathering solutions to problems that may arise in the field of
work and to help them to pass the course of Foundation Engineering
(ECIV 4352) successfully.
3
SOLVED PROBLEMS IN FOUNDATION ENGINEERING
BY:
Prof. MOHAMMED A. AWAD (Dean, Faculty of
)Engineering, Islamic University
Eng. LUAY I. QRENAWI (Teaching Assistant, Islamic
)University
Eng. RANA M. JABER (Teaching Assistant, Islamic
)University
First Edition
May – 2004
الطبعة األولى
مايو – 4002
1
SOLVED PROBLEMS IN FOUNDATION ENGINEERING
Problem # (1)
The subsoil profile of a very large area consists of a 6.0-m thick dense coarse
sand layer overlaying a 9.0-m thick stratum of normally consolidated clay which in
turn rests on a bed rock.
At a distance of 3.0-m and 6.0-m above the bed rock, the clay stratum contains
thin horizontal layers of sand. It is expected that the sand layers provide free drainage
for the clay above and below. The water table is 1.0-m below the ground surface. The
coarse sand has a specific gravity (Gs) of 2.68 and porosity (n) of 0.3. The physical
properties of clay layers are given below:
Over this area the following constructional operations are proposed and
planned:
1. The ground water table is to be lowered to a depth of 5-m below the existing
ground surface (Unit weight of water = 9.80-kN/m3), coarse sand above water
table is assumed to be dry.
2. A compacted granular fill is to be constructed over this large area with a unit
weight of 20-kN/m3 and a height of 2.5-m.
3. A warehouse of 20 * 40 m2 is to be erected on the top of the new fill. A
uniform load of 60-kN/m2 is to be applied due to the construction of the
warehouse.
4. The operation has been completed in 2-months period, which is very short, so
that the loading can be considered instantaneous. Settlement of dense sand is
not considered.
5
PROF. MOHAMMED AWAD
ENG. LUAY QRENAWI ENG. RANA JABER
SOLVED PROBLEMS IN FOUNDATION ENGINEERING
Useful formulas:
C H P P
S c log o
1 eo Po
For normally consolidated clay :
C c 0.009 ( LL 10)
Tv H dr
2
Cv
t
d (1 n) G s w
Gs w e w
sat
1 e
(G s 1) w
sub
1 e
n
e
1 n
6
PROF. MOHAMMED AWAD
ENG. LUAY QRENAWI ENG. RANA JABER
SOLVED PROBLEMS IN FOUNDATION ENGINEERING
Where;
Po is the present overburden pressure
P added vertical pressure that causes settlement
LL is the liquid limit
Cc is the compression index
Cv is the coefficient of consolidation
Tv is the time factor
Solution:
1. UNIT WEIGHTS OF SAND:
dry = (1- 0.3) * 2.68 * 9.80 = 18.4 kPa
sub = 18.4 + (0.3 * 9.81) - 9.80 = 11.54 kPa
4. COMPRESSION INDEX:
Clay Layer Cc = 0.009 (LL – 10)
The upper Cc = 0.009 (60 – 10) = 0.45
The middle Cc = 0.009 (80 – 10) = 0.63
The lower Cc = 0.009 (70 – 10) = 0.54
7
PROF. MOHAMMED AWAD
ENG. LUAY QRENAWI ENG. RANA JABER
SOLVED PROBLEMS IN FOUNDATION ENGINEERING
20 m
8
PROF. MOHAMMED AWAD
ENG. LUAY QRENAWI ENG. RANA JABER
SOLVED PROBLEMS IN FOUNDATION ENGINEERING
6. SETTLEMENT:
6.1 SETTLEMENT BENEATH THE CENTER
Layer Po P (kPa) Settlement beneath the center (m)
0.45 3.0 92.6 125.6
Upper 92.60 27.6 + 50.0 + 48.0 = 125.6 S log 0.34
1 0 .5 92.6
0.63 3.0 123.6 119.1
Middle 123.6 27.6 + 50.0 + 41.5 = 119.1 S log 0.33
1 0 .7 123.6
0.54 3.0 154 113.1
Lower 154.0 27.6 + 50.0 + 35.5 = 113.1 S log 0.24
1 0 .6 154
7. TOTAL SETTLEMENT:
Upper Layer Middle Layer Lower Layer Total (m)
Center 0.34 (m) 0.33 (m) 0.24 (m) 0.91
Corner 0.27 (m) 0.27 (m) 0.20 (m) 0.74
8. DIFFERENTIAL SETTLEMENT:
S = 0.91 – 0.74 = 0.17 m
9. COEFFICIENT OF CONSOLIDATION:
Tv H dr
2
Layer Hdr (cm) t50 (min) Tv Cv cm 2 / min
t
Upper 2.54 / 2 = 1.27 6.0 0.197 0.0530
Middle 2.54 / 2 = 1.27 7.0 0.197 0.0454
Lower 2.54 / 2 = 1.27 5.0 0.197 0.0635
9
PROF. MOHAMMED AWAD
ENG. LUAY QRENAWI ENG. RANA JABER
SOLVED PROBLEMS IN FOUNDATION ENGINEERING
01
PROF. MOHAMMED AWAD
ENG. LUAY QRENAWI ENG. RANA JABER
SOLVED PROBLEMS IN FOUNDATION ENGINEERING
Problem # (2)
Site investigation is to be made for a 40-m diameter and 20-m high water tank.
The tank will be built on a thick clay layer. Depth of rock is about 100-m while the
water table is at the ground surface. What is the approximate depth of boreholes?
Saturated unit weight (sat) of soil is 17-kN/m3.
Circular Tank
v
Bed Rock
Solution:
Let D1 & D2 to be the assumed depths of the borehole
q The pressure caused by the weight of water
q H w
w 10 kN / m 3
Then; q 20 10 200 kN / m 2
Depth of the boreholeis the smallest of D1 or D2 , where;
1
D1 : Is the depth at which q
10
q 200 kN/m 2
Weight
; the area will be calculated besed on 2-vertical:1-horizontal concept
Area
(40 2 ) 20 10
3.2 105
Then; 4
(40 D1 ) 2
(40 D1 ) 2
4
3.2 10 5
1
200 20
(40 D1 ) 2
10
D1 80D1 14400 0.0
2
D1 86.49m 11
PROF. MOHAMMED AWAD
ENG. LUAY QRENAWI ENG. RANA JABER
Then; 4
(40 D1 ) 2
(40 D1 ) 2
4
3.2 10 SOLVED
5
1 PROBLEMS IN FOUNDATION ENGINEERING
200 20
(40 D1 ) 2
10
D1 80D1 14400 0.0
2
D1 86.49m
5
D 2 : Is the depth at which 'v
100
'v ' H ( sat w ) D2 (17 10) D 2 7 D2 kN/m 2
3.2 105 5
7 D2
(40 D2 ) 2
100
D2 80D2 1600D 2 914285.7 0.0
3 2
11
PROF. MOHAMMED AWAD
ENG. LUAY QRENAWI ENG. RANA JABER
SOLVED PROBLEMS IN FOUNDATION ENGINEERING
Ground Surface
Problem # (3)
The borehole shown is in a
Ground Water Table
silty soil.
Given that;
hw ho 12.24m Time = t3
h3
t1 24hr Time = t2
t 2 48hr h2
Time = t1
h1 1.2m
h1
h2 0.86m
Time = to
h3 0.60m
Determine:
1. (hw) the depth of water table.
2. Determine h2
3. Determine h3
Solution:
(h1 ) 2 (1.2) 2
ho 4.24m
h1 h 2 1.2 0.86
(h2 ) 2 (0.86) 2
h2 2.175m
h1 h 2 1.2 0.86
(h3 ) 2 ( 0 . 6) 2
h3 1.385m
h 2 h 3 0.86 0.60
hw h o 12.24m (Given)
hw 12.24 4.24 8m
31
PROF. MOHAMMED AWAD
ENG. LUAY QRENAWI ENG. RANA JABER
SOLVED PROBLEMS IN FOUNDATION ENGINEERING
Problem # (4)
For the soil profile shown below; standard penetration numbers in a clay soil
layer were given. Determine and plot the variation of Cu and OCR with depth.
Saturated Clay
Sat= 17.2 kN/m
NF = 4
NF = 3
NF = 3
Solution: Sand Layer
41
PROF. MOHAMMED AWAD
ENG. LUAY QRENAWI ENG. RANA JABER
SOLVED PROBLEMS IN FOUNDATION ENGINEERING
CONVERSION TABLE
Force:
1 lb = 4.4482 N
1 U.S. ton = 8.896 kN
I lb/ft = 14.593 N/m (Force per unit length)
1 N = 0.2248 lb
Stress:
1 lb/ft2 = 47.88 N/m2
1 U.S. ton/ft2 = 95.76 kN/m2
1 kip/ft2 = 47.88 kN/m2
1 lb/in2 = 6.895 kN/m2
Unit weight:
1 lb/ft3 = 0.1572 kN/m3
1 lb/in3 = 271.43 kN/m3
Length:
1 ft = 30.48 cm
1 in = 25.4 mm
1 ft = 12 in
1 mi = 5280 ft
1 mi = 1.609 km
61
PROF. MOHAMMED AWAD
ENG. LUAY QRENAWI ENG. RANA JABER
SOLVED PROBLEMS IN FOUNDATION ENGINEERING
Problem # (5)
A solid concrete bridge pier is to be constructed on very dense sand – gravel
deposit .Determine the width and length of the footing.
-
Gross allowable bearing value of soil (allowable base pressure) = 300kN/m2
71
PROF. MOHAMMED AWAD
ENG. LUAY QRENAWI ENG. RANA JABER
SOLVED PROBLEMS IN FOUNDATION ENGINEERING
Loads:
D : Dead load L : Live load
W: Wind load IC: Ice thrust
Load Groups:
Group 1: DL + SF + LL
Group 2: DL + SF + W
Group 3: DL + SF + EQ
Group 4: DL + SF + LL + IC
Group 5: DL + SF + W + IC
Group 6: DL + SF + LL + LF + F + WL + 0.3W
Solution:
Assume B = 14 m, L = 26 m
Total dead load (DL) = weight of pier + weight of footing + weight of soil +
dead load from the superstructure
- Weight of pier = (6×18×7×24) + ((6×18×10) × (24-10)) + (9×21×2× (24-10))
= 38,556 kN
= 8,620 kN
- Dead load from the superstructure = 3×7000 = 21,000 kN
DL 83464 - 0 - -
LL 9000 - 0 - -
SF - 240 11 2640 -
W - 400 27 10800 -
WL - 300 25 7500 -
IC - 3000 15 45000 -
LF - 1000 25 - 25000
F - 2000 23 - 46000
Q 6e 6e
q 1 x y
BL L B
Group 1 : DL + SF + LL
Q 92,464kN
M y 2,640kN.m
My 2,640
ex 0.029m
Q 92,464
Q 6e 92,464 6 0.029 255.7 kN / m2
max
q min 1 x 1 2 300kN / m
2
BL L 14 26 26 252.3kN / m
71
PROF. MOHAMMED AWAD
ENG. LUAY QRENAWI ENG. RANA JABER
SOLVED PROBLEMS IN FOUNDATION ENGINEERING
Group 2 : DL + SF + W
Q 83,464kN
M y 2,640 10,800 13,440kN .m
My 13,440
ex 0.16m
Q 83,464
83,464 6 0.16 237.8kN / m2
max
q min 1 300kN / m 2
14 26 26 220.8 kN / m 2
02
PROF. MOHAMMED AWAD
ENG. LUAY QRENAWI ENG. RANA JABER
SOLVED PROBLEMS IN FOUNDATION ENGINEERING
So, dimensions of the pier footing are perfectly alright for both structural safety and
economical point of view.
07
PROF. MOHAMMED AWAD
ENG. LUAY QRENAWI ENG. RANA JABER
SOLVED PROBLEMS IN FOUNDATION ENGINEERING
Problem # (6)
For a foundation with two way eccentricity; the soil properties are:
= 18 kN/m3, =35o and c=0. The design criteria are Df =1 m, B=1.5 m, L=2 m,
eB = 0.3 m and eL = 0.364 m. Determine the gross ultimate load that the foundation
could carry.
Solution:
e B 0. 3 1 e 0.364 1
0 .2 , L 0.182 case( I )
B 1 .5 6 L 4 6
3e 3 0.3
B1 B1.5 B 1.51.5 1.35m
B 1.5
3e 3 0.364
L1 L1.5 L 21.5 1.908m
L 2
1 1 A' 1.29
A' B1 L1 1.35 1.908 1.29m 2 B ' ' 0.675m
2 2 L 1.908
1
qu qN q Fqs Fqd B ' N Fs Fd
2
B' 0.675
Fqs 1 '
tan 1 tan 35 1.248
L 1.908'
Fqd 1 2 tan (1 sin ) 2
Df
B
1 2 tan 35(1 sin 35) 2
1
1.5
1.167
B' 0.675
Fs 1 0.4 ' 1 0.4 0.858
L 1.908
Fd 1
1
qu (18 1 33.3 1.248 1.167) 18 0.675 48.03 0.858 1 1123.32kN / m 2
2
Qu qu A 1123.32 1.29 1449.1kN
'
22
PROF. MOHAMMED AWAD
ENG. LUAY QRENAWI ENG. RANA JABER
SOLVED PROBLEMS IN FOUNDATION ENGINEERING
Problem # (7)
A square footing is shown in figure below. Use a F.S of 6 and determine the size of
the footing.
Solution:
M 25,000
e 0.25 ft
Q 100,000
Fqd 1 2 tan (1 sin ) 2
Df
B
1 2 tan 30(1 sin 30) 2
4
B
1
1.15
B
B' B 0.5 0.2
Fs 1 0.4 ' 1 0.4 0. 6
L B B
Fd 1
1 '
qu qN q Fqs Fqd B N Fs Fd
2
0.29 1.15 1 0.2
qu 100 4 18.41.58 1 120 62.4 B 0.5 22.4 0.6
B B 2 B
But qu qall F .S
0.29 1.15 0 .2
107.52 B 0.5 0.6
100,000
qu 6 122.671.58 1
B 0.5B B B B
32
PROF. MOHAMMED AWAD
ENG. LUAY QRENAWI ENG. RANA JABER
SOLVED PROBLEMS IN FOUNDATION ENGINEERING
Problem # (8)
Calculate the base pressure at the points indicated below the mat (raft)
foundation shown. Weight of the mat will not be included.
Total vertical load acting on the foundation is 26000 kN.
Solution:
Y
A 10 15 2 (2 5) 130 m 2
A B
103 5 6 3 5
I yy 2 923.33 m 4
12 12
10 153 2 53
I xx 2 2770.83 m 4
C E F D
12 12
Q M xY M y X
q X X
A Ix Iy 26000 kN
e x 5.75 5 0.75 m K L
G H
e y 0 .0 m
M x Q e y M x 26000 0.0 0.0
M y Q e x M y 26000 0.75 19500 kN .m M N
Then; Y
26000 19500 X
q 200 21.12 X
130 923.33
q ( A,C , K , M ) 200 21.12 5 94.4 kN / m 2
q ( E ,G ) 200 21.12 3 136.64 kN / m 2
q ( F , H ) 200 21.12 3 263.36 kN / m 2
q ( B , D , L , N ) 200 21.12 5 305.6 kN / m 2
F
This figure shows the pressure distribution below A L
E
the mat foundation based on the assumption that the H
N
C
pressure distribution is linear. G
K
42
PROF. MOHAMMED AWAD
ENG. LUAY QRENAWI ENG. RANA JABER
SOLVED PROBLEMS IN FOUNDATION ENGINEERING
Problem # (9)
Consider the weight of footing and determine L and B of a trapezoidal footing for a
uniform soil pressure of 300 kN/m2, thickness of the footing is 1.0 m
Useful formula:
h 2c b
y
3 cb
Solution:
1.5 B
Weight of footing = L 24 12L1.5 B
2
Q 0
1.5 B
3000 2500 4500 12L1.5 B 300 L
2
10000 12L(1.5 B ) 150L1.5 B
52
PROF. MOHAMMED AWAD
ENG. LUAY QRENAWI ENG. RANA JABER
SOLVED PROBLEMS IN FOUNDATION ENGINEERING
Let 1.5 B Y
10000 12LY 150LY
10000 138LY
LY 72.5 ………………………………………………………………………(1)
52
PROF. MOHAMMED AWAD
ENG. LUAY QRENAWI ENG. RANA JABER
SOLVED PROBLEMS IN FOUNDATION ENGINEERING
Problem # (10)
Solution:
Arequired
Q
55 45 90 70
15.30m 2
q all ( net ) 16.99
R P1 P2 (55 45) (90 70) 260t
260x (90 70) 4 x 2.46m
72
PROF. MOHAMMED AWAD
ENG. LUAY QRENAWI ENG. RANA JABER
SOLVED PROBLEMS IN FOUNDATION ENGINEERING
Problem # (11)
Solution:
155(5) (155 200) x '
x ' 2.18m
x '' 2.18 0.25 2.43m
Arequired
Q
200 155
17.75m 2
qall ( net ) 20
ab
17.75 5.5
2
a b 6.45……………………………………………………………………… (1)
But:
L 2b a 5.5 2b a
x '' ……………………………………………. (2)
3 ba 3 ba
82
PROF. MOHAMMED AWAD
ENG. LUAY QRENAWI ENG. RANA JABER
SOLVED PROBLEMS IN FOUNDATION ENGINEERING
5.5 6.45 b
2.43
3 6.45
6.45 b
1.325 8.55 6.45 b b 2.1m
6.45
a 6.45 2.1 4.35m
82
PROF. MOHAMMED AWAD
ENG. LUAY QRENAWI ENG. RANA JABER
SOLVED PROBLEMS IN FOUNDATION ENGINEERING
Problem # (12)
Solution:
Assume that the width of the footing is B
Weight of footing & soil = 28 B (1.5 24 1 20) 1568B
e
M
13500
.
Q 11500 1568B
Q 6e
q 1
BL L
Q 6e 11500 1568B 6 13500
q max 1 255 1
BL L 28B 28(11500 1568B )
11500 1568B 81000
255 1
28B 322000 43904B
403000 43904B
7140B (11500 1568B )
322000 43904B
244633088B 2 1162280000B 4634500000 0
03
PROF. MOHAMMED AWAD
ENG. LUAY QRENAWI ENG. RANA JABER
SOLVED PROBLEMS IN FOUNDATION ENGINEERING
B 2 4.751B 18.945 0
4.751 4.7512 4 18.945 2.58m
B
2 7.334 m
Take B = 2.6 m and check qmax < (qall = 255 kN/m2)
11500 1568 2.6 6 13500
q max 1 253.7 255kN / m 2
28 2.6 28(11500 1568 2.6)
11500 1568 2.6 6 13500
q min 1 174kN / m 2 0
28 2.6 28(11500 1568 2.6)
Base pressure due to weight of soil & footing = 1.5x24 + 1x20 = 56 kN/m2
03
PROF. MOHAMMED AWAD
ENG. LUAY QRENAWI ENG. RANA JABER
SOLVED PROBLEMS IN FOUNDATION ENGINEERING
Problem # (13)
Given the cantilever footing shown below with the following data:
Q1 = 1500 kN, Q2 = 2500 kN, qall = 200 kN/m2.
Design the footing for a uniform soil pressure distribution.
The exterior footing is rectangular (B1 × B2) while the interior one is square (B × B).
B1 B
B2
B
L=8m
Q1 = 1500 kN Q2 = 2500 kN
0.6 m
1.0 m a = 4.4 m b=3m
Q1 + Q2 = 4000 kN
Strap Beam
R1 = 1260 kN R2 = 2380 kN
Figure (1)
Solution:
First; locate the point of application of the resultant of the two forces
Q Q1 Q2 1500 2500 4000 kN
1500 8
b 3.0 m
4000
23
PROF. MOHAMMED AWAD
ENG. LUAY QRENAWI ENG. RANA JABER
SOLVED PROBLEMS IN FOUNDATION ENGINEERING
Select B1 = 2.0 m
Then, a = 4.4 m
3 4000
R1 1260 kN
7 .4
R2 4000 1260 2380 kN
1260
Now, B2 4 .0 m
200 2
2380
B 3.45 m
200
By referring to Figure (1), you can draw the shear and moment diagrams.
Figure (2) outlines the general shape of them, and values are left to student.
Figure (2)
22
PROF. MOHAMMED AWAD
ENG. LUAY QRENAWI ENG. RANA JABER
SOLVED PROBLEMS IN FOUNDATION ENGINEERING
Problem # (14)
Calculate the base pressure at the points indicated below the mat (raft)
foundation shown. Height of the mat is 2.0 m and con = 24 kN/m3
C B
A
F
X X
POINT OF APP. OF Q
D E
Y
Solution:
A 18 12 5 4 196 m 2
18 12 9 4 5 (2.5 13) 1634
X 8.34m
196 196
18 12 6 4 5 (8 2) 1096
Y 5.59m
196 196
183 12 2 53 4
I yy
12 18 (0.66)
20(2.5 4.66) 2 4859 m 4
12 12
18 123 5 43
I xx 12 18 (0.41) 2 4 5 (2 2.41) 2 2212 m 4
12 12
43
PROF. MOHAMMED AWAD
ENG. LUAY QRENAWI ENG. RANA JABER
SOLVED PROBLEMS IN FOUNDATION ENGINEERING
1 4 7
2 5 8 10
3 6 9 11
43
PROF. MOHAMMED AWAD
ENG. LUAY QRENAWI ENG. RANA JABER
SOLVED PROBLEMS IN FOUNDATION ENGINEERING
Q M Y I X M X I XY M I M Y I XY
q X X Y Y
A I X I Y ( I XY ) 2
I I (I ) 2
X Y XY
43
PROF. MOHAMMED AWAD
ENG. LUAY QRENAWI ENG. RANA JABER
SOLVED PROBLEMS IN FOUNDATION ENGINEERING
Retaining Walls
A. Useful Relationships:
K a tan 2 ( 45 Φ/ 2 )
K p tan 2 ( 45 Φ/ 2 )
Where;
Ka is Rankine active earth pressure coefficient
Kp is Rankine passive earth pressure coefficient
is the angle of internal friction of soil
1
Note; K p
Ka
FS (Overturning )
M R
M O
Where;
MO = sum of the moments of forces tending to overturn the wall
MR = sum of the moments of forces tending to resist overturning of the wall
Note; FS against overturning is to be > 2
FS ( Sliding)
F R
F d
Where;
FR = sum of the horizontal resisting forces
Fd = sum of the horizontal driving forces
Notes;
FS against sliding is to be > 1.5
If the factor of safety against sliding < 1.5, dimensions of the wall is to be
changed or a key is needed
73
PROF. MOHAMMED AWAD
ENG. LUAY QRENAWI ENG. RANA JABER
SOLVED PROBLEMS IN FOUNDATION ENGINEERING
For bearing capacity check; the value of q max (q toe) is to be less than the
allowable soil pressure (q all) and no tension is permitted under the base of the wall.
The factor of safety against bearing capacity failure will be:
qult
FS ( Bearing Capacity)
qtoe
Notes;
q ult is determined from the Terzaghi's general bearing capacity equation
1
qu C N c Fci Fcd q N q Fqi Fqd B N F i F d
2
FS against bearing capacity failure is to be > 3
0,3 m 0,3 m
(min) (min)
SLOPE SLOPE
(0.02 H : 1 V) (0.02 H : 1 V)
H
Stem
Stem
0.1 H
D
0.12 to
D
73
PROF. MOHAMMED AWAD
ENG. LUAY QRENAWI ENG. RANA JABER
SOLVED PROBLEMS IN FOUNDATION ENGINEERING
Problem # (15)
This is a nice chance for you – as a student of Civil Engineering – to design a
cantilever retaining wall since it is the first one in retaining structures.
The following points will be taken in consideration:
The passive force of the soil will be neglected in the design since the soil in
front of the wall will be excavated in the future due to water pipe installation.
No water pressure will be considered in the backfill since an adequate
drainage system will be installed.
73
PROF. MOHAMMED AWAD
ENG. LUAY QRENAWI ENG. RANA JABER
SOLVED PROBLEMS IN FOUNDATION ENGINEERING
0,7 m
20 kN/m2
Granular Backfill
= 20 kN/m3
= 35
SLOPE
(1 H : 8 V)
12 m
Stem
2.0 m
2.5 m
B = ??
4.0 m
04
PROF. MOHAMMED AWAD
ENG. LUAY QRENAWI ENG. RANA JABER
SOLVED PROBLEMS IN FOUNDATION ENGINEERING
Solution:
0,7 m
V4
V1 V5
H1
12 m
H2
V2
2.0 m
2.5 m
V3
1.6 m
B = 8.0 m
4.0 m
04
PROF. MOHAMMED AWAD
ENG. LUAY QRENAWI ENG. RANA JABER
SOLVED PROBLEMS IN FOUNDATION ENGINEERING
K a tan 2 ( 45 Φ/ 2 )
Φ 35
K a 0.27
Assume B 8.0 m
Pr essure due to surch arg e :
P q K a 20 0.27 5.4 kN / m 2
At Z 0.0 the pressureis 0.0
i.e. Pa 0.0
At Z 12.0 the pressureis :
Pa H K a 20 12 0.27 64.8 kN / m 2
Overturning:
FS (Overturning )
M R
M O
7621.8
FS 3.92 2 O.K .
1944
04
PROF. MOHAMMED AWAD
ENG. LUAY QRENAWI ENG. RANA JABER
SOLVED PROBLEMS IN FOUNDATION ENGINEERING
Sliding:
FS ( Sliding)
F R
V
F d H
1
1611.3 ( )
FS 2 1.78 1.5 O.K .
453.6
Bearing capacity:
B M
e
2 V
8 7621.9 1944
e 0.48m
2 1611.3
q max
V (1 6e )
min A B
A 8 m2 (Note; A 8 1 ).
1611.3 6 0.48
q max 1
min 8 8
q max 273.4 kN / m 2
q min 129.5 kN / m 2
Both q max and q min are less than the allowable soil pressureand no tension
belowthe base of the footing
That is O.K .
07
PROF. MOHAMMED AWAD
ENG. LUAY QRENAWI ENG. RANA JABER
SOLVED PROBLEMS IN FOUNDATION ENGINEERING
V5
H3
H4
A A
V10 B C V11
V7 V9
V8
V6 129
202
238
274
SECTION A-A
Force Value (kN/m) Arm (m) Moment (kN.m/m)
H3 H 3 0.27 20 10.4 56.2 5.20 292.2
1
H4 H 4 0.27 20 (10.4) 2 292.0 3.47 1012.3
2
Shear 348.2(LEFT)
Moment 1304.5 (CCW)
00
PROF. MOHAMMED AWAD
ENG. LUAY QRENAWI ENG. RANA JABER
SOLVED PROBLEMS IN FOUNDATION ENGINEERING
SECTION A-B
Force Value (kN/m) Arm (m) Moment (kN.m/m)
V10 V10 1.6 24 2.0 76.8 1.00 - 76.8
1 2
V6 V6 2 274 274 2 365.3
2 3
1 2
V7 V7 238 2 238 158.6
2 3
Shear 435.2 (Up)
Moment 447.2 (CW)
SECTION A-C
Force Value (kN/m) Arm (m) Moment (kN.m/m)
V5 V5 832 2.00 - 1664
1 4
V8 V8 4 202 404 538.7
2 3
1 2
V9 V9 4 129 258 4 688
2 3
V11 V11 4 24 1.6 135.6 2.00 - 307.2
Shear 323.6 (Down)
Moment 744.5 (CW)
04
PROF. MOHAMMED AWAD
ENG. LUAY QRENAWI ENG. RANA JABER
SOLVED PROBLEMS IN FOUNDATION ENGINEERING
Qs qsAs CuAs
1
Where:
0.9
qs (or fs) = unit skin friction (or adhesion in this case)
between pile and clay (kN/m2). 0.8
α
Cu = un-drained shear strength. 0.6
0.4
If there are n different layers;
n 0.3
i 1 2
Cu, (KN/m )
Where;
As = p L Figure (1)
P is the perimeter of the pile, then;
n
Qs p i Cui Li
i 1
The general expression used to estimate the end bearing capacity of the pile is:
Qp ApcNc 12 BN DfNq
Where;
Nc, Nγ, Nq bearing capacity factors for deep foundations
Qp qpAp Nc Cu Ap
Nc = 9 is commonly used, then;
Qp 9 C u A p
64
PROF. MOHAMMED AWAD
ENG. LUAY QRENAWI ENG. RANA JEBER
SOLVED PROBLEMS IN FOUNDATION ENGINEERING
Where;
Cu is the un-drained shear strength at pile point level.
Nc is the bearing capacity factor for cohesion for deep foundations.
Ap is the base (point) area of pile.
Where;
qs or qf is the unit skin friction (kPa), qs h' tan
Ks is the coefficient of earth pressure depending on relative, volume, displacement of pile,
material and shape of pile (See Table 1)
δ is angle of friction between pile and soil
Note;
The recommended value for for concrete piles is 20o
Since As p L
n
Qs p tan Ksivo ' Li
i 1
Note that:
' vo is average for each layer considered (i.e. taken as mid height)
Ks is usually constant, but if Dr's of the layers are significantly different, use Table 1
Driven Pile
Small Displacement Pile Bored Pile
(Displacement Pile)
Low Dr High Dr Low Dr High Dr
0.5
1.0 2.0 0.5 1.0
64
PROF. MOHAMMED AWAD
ENG. LUAY QRENAWI ENG. RANA JEBER
SOLVED PROBLEMS IN FOUNDATION ENGINEERING
(Note that the term with Nγ in the general equation is comparatively small, so it is cancelled)
Note;
The vertical effective stress is considered to be constant after 20D or 20B which is called the
critical depth
64
PROF. MOHAMMED AWAD
ENG. LUAY QRENAWI ENG. RANA JEBER
SOLVED PROBLEMS IN FOUNDATION ENGINEERING
Problem # (16)
A rectangular footing is acted by a vertical load of 8060 kN and two horizontal forces of
1500 kN in both the long and the short directions with a distance of 0.6 m from the ground surface.
Determine:
1. The base pressure at the four corners if the footing was on soil.
2. Pile loads at the four corners if the footing was on piles whose pattern as shown.
Solution:
soil 20 kN / m 3
8060 KN
0.5 m
2*2 m pedestal
conc 24 kN / m 3 Hp = 1500 KN
1.4 m 1 m
7m
0.5 m
B A
1m 1m 1m 1m
Hp = 1500 KN
5m
0.5 m D 1m 1m 1m 1m 1m 1m C 0.5 m
0.5 m
Hs = 1500 KN
64
PROF. MOHAMMED AWAD
ENG. LUAY QRENAWI ENG. RANA JEBER
SOLVED PROBLEMS IN FOUNDATION ENGINEERING
q max
Q 6e L
6eB
min A L B
1500 3
eL eB 0.45m
10,000
10,000 6 0.45 6 0.45
q max 1
min 5 7 7 5
Qmax 285.7 111 .4 154.3
min
Q
Q M x M y
y x
n Iy Ix
eL eB 0.45m
e Q M L M B 4500KN / m
IB = (12 + 32) ×3×2 + 22×2×2 = 76 pile.m2
IL = 22 ×4×2 + 12×2×3 = 38 pile.m2
05
PROF. MOHAMMED AWAD
ENG. LUAY QRENAWI ENG. RANA JEBER
SOLVED PROBLEMS IN FOUNDATION ENGINEERING
Problem # (17)
For the group of friction piles shown; determine the settlement of the clay layers.
Total Q= 3600 KN
4.0 m
1.2
Friction piles
Incomressible
2.8 m
2/3 Df = 8.0 m
1.2
0.4
mv=0.0001 KN 1.2 1.2 1.2
12 piles group
17 m SOFT CLAY
Q1=3600/(4*2.8)=321.4KN/m2
1/3Df = 4.0 m
Q2=138.5KN/m2 A1
1.5
30
1.5
Q3=77.0KN/m2 Incompressible A2
Incomressible
Q3=33.9KN/m2
5.0 m
A4
3.0
Q3=19.0KN/m2
Solution:
S P H mv AL mv
A = Pressure area
S is the settlement of the clay layer
A1 = 0.5× (321.4 + 138.5) × 1.5 = 345 kN/m.
A2 = 0.5× (138.5 + 77.0) × 1.5 = 162 kN/m.
A3 = 0.5× (77.0 + 33.9) × 3.0 = 166 kN/m.
A4 = 0.5× (33.9 + 19) × 3.0 = 79 kN/m.
S1 = 345×0.0001 = 0.0345 m
S2 = 162×0.0001 = 0.0162 m
S3 = 166×0.0001 = 0.0166 m
S4 = 79×0.0001 = 0.0079 m
Total Settlement = 0.0752 m = 75.2 mm
Note that almost the half of the settlement of the pile group is due to compression of the upper 1.50
thick layer.
05
PROF. MOHAMMED AWAD
ENG. LUAY QRENAWI ENG. RANA JEBER
SOLVED PROBLEMS IN FOUNDATION ENGINEERING
Problem # (18)
Determine the settlement of the group of point bearing piles shown.
Total Q= 3600 KN
4.0 m
0.4 m
mv=0.0001 KN
1.2
2.8 m
1.2
1.2 1.2 1.2
0
12 piles group
3.0
30 Q1=77.0 kN/m2
3.0
Q2=33.9 kN/m2
6.0
CLAY
3.0
Q3=19.0KN/m2
Solution:
S P H mv AL mv
A = Pressure area
S is the settlement of the clay layer
Note; Q is used instead of P in the following equations
3600
Q1 77.0 kN / m 2
(4 2 3 tan 30) (2.8 2 3 tan 30)
3600
Q2 33.9 kN / m 2
(4 2 6 tan 30) (2.8 2 6 tan 30)
3600
Q3 19 kN / m 2
(4 2 9 tan 30) (2.8 2 9 tan 30)
1
S1 (77.0 33.9) 3.0 0.0001 0.0166 m
2
1
S 2 (33.9 19.0) 3.0 0.0001 0.0079 m
2
Total Settlement S = 0.0166 + 0.0079 = 0.0245 m = 24.5 mm
05
PROF. MOHAMMED AWAD
ENG. LUAY QRENAWI ENG. RANA JEBER
SOLVED PROBLEMS IN FOUNDATION ENGINEERING
Problem # (19)
A reinforced concrete circular pile is driven to the soil as shown below. Calculate the
negative skin friction force acting on the pile.
17KN / m 3
4.0 m
New sand fill (1)
35o
18KN / m 3
4.0 m
Rock
0.5 m
Solution:
Ko 1 sin 0.43
Resultant of lateral
23 tan 0.467
4.0 m
F 1 PoD
F1 58.48 0.467 0.5 43KN
F 2 Dh Cu
F2 0.5 4 15 94.3KN
05
PROF. MOHAMMED AWAD
ENG. LUAY QRENAWI ENG. RANA JEBER
SOLVED PROBLEMS IN FOUNDATION ENGINEERING
Problem # (20)
A pile supported foundation is given below. A vertical force of 1200 kN (including all the
loads on foundation) is acting downward at point K.
Determine the loads carried by piles A, B and C.
Axis of Symmetry
B
3.464 m
2.07 m
K
X X
c.g
0.69 m
1.5 m
A
C
Ө Ө
2.4 m
0.46 m
4.0 m
Pile Cap
Solution:
3.464
tan 60 o
2
x
tan tan 30 0 x 0.46m.
2 0. 8
Eccentricity :
e 1.5 (0.69 0.46) 0.35m
Moment :
M 1200 0.35 420KN .m
06
PROF. MOHAMMED AWAD
ENG. LUAY QRENAWI ENG. RANA JEBER
SOLVED PROBLEMS IN FOUNDATION ENGINEERING
Problem # (21)
One of the exterior columns of a steel frame structure is acted by a vertical force of 10,000
kN, a horizontal force of 2000 kN and a moment of 5000 kN.m. Due to a poor foundation soil; it was
decided to support that column by a pile foundation consisting of a twelve pile group. Piles are
concrete filled steel pipe piles. Allowable axial compressive load on each pile is 2000 kN. It is also
predicted that each pile can also resist a horizontal force of 60 kN. Passive resistance of soil will not
be considered.
Is the selected pile group satisfactory?
5000 KN.m
2000 KN 10000 KN
1.5*1.5m pedestal
5.5*7.5 m Pile cap
0.75
2
5.5 m
2
0.75
0.75 2 2 2 0.75
7.5 m
Solution:
Column load = 10,000 kN
Weight of pedestal = 1.5 ×1.5 ×2 ×24 = 108 kN
Weight of pile cap = 5.5 ×7.5 ×2 ×24 = 1,980 kN
Weight of soil = (5.5 ×7.5 – 1.5 ×1.5) ×2 ×20 = 1,560 kN
00
PROF. MOHAMMED AWAD
ENG. LUAY QRENAWI ENG. RANA JEBER
SOLVED PROBLEMS IN FOUNDATION ENGINEERING
I 1 1 2 3 (12 32 ) 60 pile.m 2
Qn
Q M X n 1
n I1 1
13648 13000
Qn Xn 1137 217 Xn A B C D
12 60
Then;
QA = 1137 -217×3 = 486 kN/pile
QB = 1137 -217×1 = 920 kN/pile
QC = 1137 +217×1 = 1354 kN/ple
QD = 1137 +217×3 = 1788 kN/pile
2m 1m 1m 2m
Total load = 4548×3 = 13644 ≈ 13648
1
486 1788
Unbalanced horizontal force = 2000 3 3 698KN
3 3
698
Now; 58kN / pile 60 O.K .
12
3QA 1548
Q 2000
04
PROF. MOHAMMED AWAD
ENG. LUAY QRENAWI ENG. RANA JEBER
SOLVED PROBLEMS IN FOUNDATION ENGINEERING
Deep Foundations
1. Equations:
Qu
Qu = Ultimate Pile Capacity.
QP = Load-Capacity of pile point.
Qs = Skin friction resistance.
L = Pile length. Pile
D
D
Pile cross-section
q'
Qp
Figure 1, Parameters' definition
QP = AP q’ Nq*
Or, QP = AP q1
Whichever is smaller.
Where;
q1 (kPa) = 50 Nq* tan Φ
Nq* = Bearing capacity factor for deep foundations.
57
PROF. MOHAMMED AWAD
ENG. LUAY QRENAWI ENG. RANA JABER
SOLVED PROBLEMS IN FOUNDATION ENGINEERING
O f
L' = 15D
Qs (1)
L'
Qs (2)
Qs (1) = P L’ f av
Qs (2) = p (L – L’) f
Qs = Qs (1) + Qs (2)
Where;
f = K ơv’ tan ơ (skin friction)
σ v’ = overburden pressure
K = lateral earth pressure = 0.5 + 0.008Dr (Dr = Relative Density in Percent)
δ = friction angle between soil and pile (usually 0.6 Φ)
P = perimeter of the pile
fav = average skin friction (From 0 to L it is f / 2)
58
PROF. MOHAMMED AWAD
ENG. LUAY QRENAWI ENG. RANA JABER
SOLVED PROBLEMS IN FOUNDATION ENGINEERING
2n1 n 2 2 d 4 D
Efficiency,
pn1n 2
Where the parameters are as defined in Figure 3.
L
Allowable load capacity of pile group:
Qa (g) = Qu (g) / SF
n piles
d d d
d
m piles
d
d
d
59
PROF. MOHAMMED AWAD
ENG. LUAY QRENAWI ENG. RANA JABER
SOLVED PROBLEMS IN FOUNDATION ENGINEERING
Problem # (22)
Consider a precast concrete pile 12 – m long in a homogenous sandy soil layer. The pile
cross section is 305 mm × 305 mm, the dry unit weight of sand is, γd = 16.8 kN / m3, and the soil
friction angle Ф = 35o.
Calculate the ultimate point load that the pile can carry.
305 mm
305 mm
X X
12 m
Section X-X
Solution:
OR
60
PROF. MOHAMMED AWAD
ENG. LUAY QRENAWI ENG. RANA JABER
SOLVED PROBLEMS IN FOUNDATION ENGINEERING
Problem # (23):
Consider a pre-cast concrete pile in Problem # (21):
Assume that for the given dry unit weight the relative density of the sand Dr = 100 %
76.86
O
Qs (2)
12 m
Z
Solution:
61
PROF. MOHAMMED AWAD
ENG. LUAY QRENAWI ENG. RANA JABER
SOLVED PROBLEMS IN FOUNDATION ENGINEERING
Problem # (24):
Estimate the total load that the pile group shown below can carry. Note that; every single
pile is identical to that in problems # (21) and # (22).
Pile Cap
Soil surface
12 m
4 piles
d = 1.5 m
1.5 m
5 piles
Solution:
Total load that the single pile can carry Q = 844.73 kN (Problem # (21) and # (22))
m=5
n=4
so, m × n = 20 piles
QT = 844.73 × 20 = 16894.6 kN
The efficiency of the group:
2m n 2 d 4 D
pmn
Therefore; the total load that can be carried by the pile group is;
QTG = 16894.6 × 0.91 = 15374.09 kN.
62
PROF. MOHAMMED AWAD
ENG. LUAY QRENAWI ENG. RANA JABER
SOLVED PROBLEMS IN FOUNDATION ENGINEERING
Problem # (25)
Determine the depth of penetration and the maximum bending moment of a cantilever sheet
pile wall constructed in a three layered soil system as shown below. What should be the required
section modulus of a steel sheet pile if the allowable stress of steel is 150 MPa?
q = 20 kN/m2
Clay, qu = 40 kN/m2
= 20 kN/m3
Sand, = 30
= 18 kN/m3
Dredge Line
Solution:
a (q v ' ) K a 2 C K a
p (q v ' ) K a 2 C K a
For the clay layer; = 0.0o, that means Ka = Kp = 1.0
1
For the sand layer; = 30.0o, that means K a and Kp = 3.0
3
From soil mechanics, q = 2C
Pressure Diagram:
At depth (Z) = 0.0 m
a (20 0.0) 1 2 20 1 20 kN/m 2
63
PROF. MOHAMMED AWAD
ENG. LUAY QRENAWI ENG. RANA JABER
SOLVED PROBLEMS IN FOUNDATION ENGINEERING
1 1
a (20 2 20) 2 0.0 20 kN/m 2
3 3
64
PROF. MOHAMMED AWAD
ENG. LUAY QRENAWI ENG. RANA JABER
SOLVED PROBLEMS IN FOUNDATION ENGINEERING
q = 20 kN/m2
-20
H1
20
H3
H2
Dredge Line 38
H4
86 H6
34
H6
Now; taking the sum of the moment about the base of the wall (point P) will lead to:
M Base 0.0
43 X 2 100 X 311.6 0.0
X 4 .1 m
Depth of penetration of the sheet pile will be;
Do = 1.5 + 4.1 = 5.6 m
D = 1.2 × 5.6 = 6.7 m
65
PROF. MOHAMMED AWAD
ENG. LUAY QRENAWI ENG. RANA JABER
SOLVED PROBLEMS IN FOUNDATION ENGINEERING
Problem # (26)
66
PROF. MOHAMMED AWAD
ENG. LUAY QRENAWI ENG. RANA JABER
SOLVED PROBLEMS IN FOUNDATION ENGINEERING
Solution:
F x 0
36 1082 18.375 24 1.712 P 0
P 92.2kN Per meter width of the wall
66
PROF. MOHAMMED AWAD
ENG. LUAY QRENAWI ENG. RANA JABER
SOLVED PROBLEMS IN FOUNDATION ENGINEERING
Solution :
MA 0
5.875 P 36 3.875 108 2.875 18.375 0.583 0
P = 78.42 kN per meter width of the wall
66
PROF. MOHAMMED AWAD
ENG. LUAY QRENAWI ENG. RANA JABER
SOLVED PROBLEMS IN FOUNDATION ENGINEERING
F x 0
78.42 36 108 18.375 R A 0
R A 84.375kN
MO 0
x3
84.375x 24 0 x 3.25m
3
D = 3.25 + 0.875 = 4.12 m
Penetration depth = 1.2D = 4.95 m
Fx 0
1
6Z 6 Z Z 78.42 0
2
3Z 2 6 Z 78.42 0 Z 4.21m
4.212 1 4.212
M max 78.42 (4.21 1) 6 6 4.21 123.94kN.m
2 2 3
66
PROF. MOHAMMED AWAD
ENG. LUAY QRENAWI ENG. RANA JABER
SOLVED PROBLEMS IN FOUNDATION ENGINEERING
Problem # (27)
Refer to problem 25, what would be the depth of penetration, maximum bending
moment and anchored pull if the soil below dredge line was a clay deposit with a unit
weight of 18 kN/m3 and unconfined compressive strength of 75 kN/m2 (Use free
earth support method)
Solution:
Fx 0
36 108 24 2.62 P 0
67
PROF. MOHAMMED AWAD
ENG. LUAY QRENAWI ENG. RANA JABER
SOLVED PROBLEMS IN FOUNDATION ENGINEERING
Fx 0
1
6Z 6 Z Z 81.12 0
2
3Z2 6 Z 81.12 0 Z 4.29m
4.292 1 4.292
M max 81.12 (4.29 1) 6 6 4.29 132.72kN.m
2 2 3
67
PROF. MOHAMMED AWAD
ENG. LUAY QRENAWI ENG. RANA JABER