schedule 201224.

mpp
ID WBS Task Name Duration Start Finish % Work
Half 2, 2019 Half 1, 2020 Half 2, 2020 Half 1, 2021 Half 2, 2021
Complete S N J M M J S N J M M J S N
0 PLTM CILEUNCA 660,5 days
Mon 23/12/19
Wed 13/10/21
40% 40%
1 1 MILESTONES 659,5 days
Mon 23/12/19 Tue 12/10/210% 0%
2 1.1 Project Start (NTP) 0 days Mon 23/12/19Mon 23/12/19100% 23/12
3 1.2 Generator Onsite 0 days Fri 28/05/21 Fri 28/05/21 0% 28/05
4 1.3 Turbine Onsite 0 days Mon 31/05/21Mon 31/05/210% 31/05
5 1.4 Construction Start 0 days Fri 17/01/20 Fri 17/01/20 100% 17/01
6 1.5 Project Complete 0 days Tue 12/10/21Tue 12/10/210% 12/10
7 2 ENGINEERING 456 daysFri 31/01/20 Fri 30/04/21 70% 70%
8 2.1 General 414 daysFri 13/03/20 Fri 30/04/21 70% 70%
9 2.1.1 Preparation Work / For Information 22 days Fri 10/04/20 Tue 13/04/2174% 74%
10 2.1.2 Technical Data List 45 days Fri 13/03/20 Sat 09/01/21 65% 65%
11 2.1.4 Technical Data Turbine 14,5 daysThu 19/03/20Thu 02/07/20100% 100%
12 2.1.5 Technical Data Generator 23,5 daysThu 19/03/20Thu 02/07/20100% 100%
13 2.1.3 Operation and Maintenance Instruction 15 days Fri 16/04/21 Fri 30/04/21 0% 0%
14 2.2 Civil 379 daysFri 31/01/20 Fri 12/02/21 80% 80%
15 2.2.1 Calculation 30 days Fri 31/01/20 Fri 01/01/21 75% 75%
16 2.2.2 Drawing 379 daysFri 31/01/20 Fri 12/02/21 81% 81%
17 2.2.2.1 Penstock Pipe and Structure 49 days Fri 07/02/20 Thu 26/03/20100% 100%
18 2.2.2.1.1 Penstock Piping 49 days Fri 07/02/20 Thu 26/03/20100% 100%
19 2.2.2.1.2 Saddle 35 days Fri 07/02/20 Thu 12/03/20100% 100%
20 2.2.2.1.3 Anchor Block 35 days Fri 07/02/20 Thu 12/03/20100% 100%
21 2.2.2.2 Penstock Bridge 22 days Fri 31/07/20 Mon 04/01/2151% 51%
22 2.2.2.3 Powerhouse Area 242 daysTue 16/06/20Fri 12/02/21 23% 23%
23 2.2.2.3.1 Powerhouse 50 days Tue 16/06/20Wed 20/01/2146% 46%
24 2.2.2.3.2 Tailrace 50 days Fri 25/12/20 Fri 12/02/21 0% 0%
25 2.2.2.4 Access Road and Bridge 134 daysFri 31/01/20 Fri 12/06/20 100% 100%
26 2.2.2.4.1 Access Road 25,6 daysFri 31/01/20 Fri 12/06/20 100% 100%
27 2.2.2.4.2 Access Bridge 29,34 days
Fri 31/01/20 Fri 12/06/20 100% 100%
28 2.2.2.5 Station Service (Gardu Hubung) 49 days Fri 20/03/20 Thu 07/05/20100% 100%
29 2.2.2.6 Guard Post 35 days Fri 13/03/20 Thu 16/04/20100% 100%
30 2.2.2.7 Temporary Facilities 77 days Fri 21/02/20 Thu 07/05/20100% 100%
31 2.3 Mechanical, Electrical & Instrument 368,2 days
Fri 07/02/20 Tue 09/02/2156% 56%
32 2.3.1 Calculation 91 days Fri 07/02/20 Thu 07/05/20100% 100%
33 2.3.2 Drawing 333,2 days
Fri 13/03/20 Tue 09/02/2143% 43%
34 2.3.2.1 Penstock Area 22 days Fri 13/11/20 Fri 08/01/21 33% 33%
35 2.3.2.2 Powerhouse Area 333,2 days
Fri 13/03/20 Tue 09/02/2144% 44%
36 2.3.2.2.1 Installation Plan 57 days Fri 13/03/20 Wed 20/01/2153% 53%
37 2.3.2.2.2 Turbine Drawing 29,2 daysTue 23/06/20Thu 27/08/20100% 100%

Critical Split Finish-only Baseline Milestone Manual Summary Inactive Task

Critical Split Task Progress Duration-only Milestone Project Summary Inactive Milestone

Critical Progress Manual Task Baseline Summary Progress External Tasks Inactive Summary

Task Start-only Baseline Split Summary External Milestone Deadline

Thu 24/12/20 Page 1 of 6


schedule 201224.mpp
ID WBS Task Name Duration Start Finish % Work
Half 2, 2019 Half 1, 2020 Half 2, 2020 Half 1, 2021 Half 2, 2021
Complete S N J M M J S N J M M J S N
38 2.3.2.2.3 Generator Drawing 47 days Fri 24/07/20 Sat 23/01/21 38% 38%
39 2.3.2.2.4 HPU and Valve Drawing 35 days Thu 16/07/20Thu 31/12/2082% 82%
40 2.3.2.2.5 Electrical Drawing 60 days Fri 13/03/20 Tue 09/02/2123% 23%
41 2.3.2.2.6 Main & Auxiliary Transformers Drawing
45 days Fri 25/12/20 Sun 07/02/210% 0%
42 3 PROCUREMENT 535 daysFri 28/02/20 Sun 15/08/2128% 28%
43 3.1 General 290 daysFri 03/07/20 Sun 18/04/2157% 57%
44 3.1.1 Purchasing Sparepart for Turbine and Accessories
273 days Fri 03/07/20 Sun 18/04/2158% 58%
45 3.1.2 General and Supporting Tools 21 days Wed 16/09/20Wed 06/01/2140% 40%
46 3.2 Civil 372,78 days
Fri 28/02/20 Sat 06/03/2125% 25%
47 3.2.1 Steel Structure 351,78 days
Fri 28/02/20 Sat 06/03/2125% 25%
48 3.2.1.1 Power House 29 days Fri 05/02/21 Sat 06/03/21 0% 0%
49 3.2.1.2 Pipe Bridge 1 (Tunnel) 29 days Mon 04/01/21Tue 02/02/210% 0%
50 3.2.1.3 Pipe Bridge 2 (Talang) 29 days Wed 20/01/21Thu 18/02/210% 0%
51 3.2.1.4 Jembatan Jalan Akses 29 days Fri 28/02/20 Fri 25/12/20 99% 99%
52 3.3 Piping 253,2 days
Fri 05/06/20 Sat 13/02/2113% 13%
53 3.3.1 Penstock Pipe 253,2 days
Fri 05/06/20 Sat 13/02/2115% 15%
54 3.3.1.1 Penstock Pipe Batch 1 (Morning Glory 34
- AB
days
1) Fri 25/12/20 Wed 27/01/210% 0%
55 3.3.1.2 Penstock Pipe Batch 2 (AB 1 - AB 5) 34 days Fri 05/06/20 Sat 13/02/21 20% 20%
56 3.3.1.3 Penstock Pipe Batch 3 (AB 5 - AB 11) 34 days Fri 05/06/20 Thu 21/01/2120% 20%
57 3.3.1.4 Penstock Pipe Batch 4 (AB 11 - AB 15) 34 days Fri 05/06/20 Thu 21/01/2120% 20%
58 3.3.2 Penstock Pipe Elbow 21 days Fri 05/06/20 Sun 10/01/2120% 20%
59 3.3.3 Inlet Pipe and accessories 21 days Fri 25/12/20 Thu 14/01/210% 0%
60 3.3.4 Penstock Pipe section Powerhouse 21 days Fri 05/06/20 Mon 11/01/2115% 15%
61 3.3.5 Penstock accessories 21 days Fri 05/06/20 Thu 28/01/217% 7%
62 3.4 Mechanical 358,2 days
Fri 03/07/20 Sat 26/06/2144% 44%
63 3.4.1 Generator - Fabrication and FAT 270 days Fri 03/07/20 Mon 29/03/2165% 65%
64 3.4.2 Generator - Transportation to site 46 days Tue 13/04/21Fri 28/05/21 0% 0%
65 3.4.3 Turbine - Fabrication and FAT 273 days Fri 03/07/20 Thu 01/04/2164% 64%
66 3.4.4 Turbine - Transportation to site 46 days Fri 16/04/21 Mon 31/05/210% 0%
67 3.4.5 HPU & Valve 214 days Tue 04/08/20Sat 26/06/21 17% 17%
68 3.4.6 Hoist Crane 21 days Fri 25/12/20 Thu 14/01/210% 0%
69 3.5 Electrical 234 daysFri 25/12/20 Sun 15/08/210% 0%
70 3.5.1 Electrical Components - Purchasing 188 days Fri 25/12/20 Wed 30/06/210% 0%
71 3.5.2 Electrical Components - Transportation to46site
days Thu 01/07/21Sun 15/08/210% 0%
72 3.5.3 Main and Auxiliary Transformer - Purchasing
116 days Mon 08/02/21Thu 03/06/210% 0%
73 3.5.4 Main and Auxiliary Transformer - Transportation
3 days toFrisite
04/06/21 Sun 06/06/210% 0%
74 3.5.5 Electrical MV - Purchasing 123 days Tue 09/02/21Sat 12/06/21 0% 0%
75 3.5.6 Electrical MV - Transportation 4 days Sat 12/06/21 Wed 16/06/210% 0%

Critical Split Finish-only Baseline Milestone Manual Summary Inactive Task

Critical Split Task Progress Duration-only Milestone Project Summary Inactive Milestone

Critical Progress Manual Task Baseline Summary Progress External Tasks Inactive Summary

Task Start-only Baseline Split Summary External Milestone Deadline

Thu 24/12/20 Page 2 of 6


schedule 201224.mpp
ID WBS Task Name Duration Start Finish % Work
Half 2, 2019 Half 1, 2020 Half 2, 2020 Half 1, 2021 Half 2, 2021
Complete S N J M M J S N J M M J S N
76 3.5.7 Electrical LV - Purchasing 127 days Tue 09/02/21Wed 16/06/210% 0%
77 3.5.8 Electrical LV - Transportation 4 days Wed 16/06/21Sun 20/06/210% 0%
78 3.5.9 Medium Voltage Cable and Accessories 14 days Fri 25/12/20 Thu 07/01/210% 0%
79 3.5.10 Grounding System 25 days Fri 25/12/20 Mon 18/01/210% 0%
80 3.5.11 Lighting System 25 days Fri 25/12/20 Mon 18/01/210% 0%
81 3.5.12 CCTV and Air Conditioning 25 days Fri 25/12/20 Mon 18/01/210% 0%
82 4 CONSTRUCTION 660,5 daysMon 23/12/19 Wed 13/10/2139% 39%
83 4.1 General Works 470 daysMon 23/12/19 Mon 05/04/2182% 82%
84 4.1.1 Temporary Facilities 470 daysMon 23/12/19 Mon 05/04/2182% 82%
85 4.1.1.1 Direction Keet (Owner) 36 days Fri 10/04/20 Wed 13/01/2147% 47%
86 4.1.1.2 Direction Keet (Contractor) 91 days Fri 17/01/20 Thu 16/04/20100% 100%
87 4.1.1.3 Temporary Warehouse 84 days Fri 17/01/20 Thu 09/04/20100% 100%
88 4.1.1.4 Project Safety Fence 34,55 daysFri 28/02/20 Thu 28/05/20100% 100%
89 4.1.1.5 Temporary Site Access 28 days Fri 17/04/20 Thu 14/05/20100% 100%
90 4.1.1.6 Temporary Warehouse 2 14 days Fri 27/03/20 Thu 09/04/20100% 100%
91 4.1.1.7 Mobilization and demobilization 80 wks Mon 23/12/19Mon 05/04/2175% 75%
92 4.1.2 Access Road Area 63 days Fri 28/02/20 Thu 30/04/20100% 100%
93 4.1.2.1 Site Preparations - Access Road Area 63 days Fri 28/02/20 Thu 30/04/20100% 100%
94 4.1.3 Pipe Penstock Area 77 days Fri 14/02/20 Thu 30/04/20100% 100%
95 4.1.3.1 Site Preparations - Pipe Penstock Area77 days Fri 14/02/20 Thu 30/04/20100% 100%
96 4.1.4 Powerhouse Area 7 days Fri 20/03/20 Thu 26/03/20100% 100%
97 4.1.4.1 Site Preparations - Powerhouse Area 7 days Fri 20/03/20 Thu 26/03/20100% 100%
98 4.1.5 Insurance (EAR, Tenaga Kerja) 30 days Fri 13/03/20 Wed 13/01/2134% 34%
99 4.1.6 Report and Documentation 80 wks Mon 23/12/19Tue 16/03/2180% 80%
100 4.2 Civil Works 390 daysFri 24/04/20 Tue 18/05/219% 9%
101 4.2.1 Access Road Area 390 daysFri 24/04/20 Tue 18/05/2129% 29%
102 4.2.1.1 Base + Sub Base 43 days Fri 24/04/20 Tue 20/04/2155% 55%
103 4.2.1.2 Paving + Drainage 36 days Thu 23/07/20Tue 18/05/2122% 22%
104 4.2.1.3 Access Bridge - Foundation 230,06 days
Thu 16/07/20Wed 03/03/21 21% 21%
105 4.2.1.3.1 Soil Work 23,74 daysThu 16/07/20Sat 09/01/21 35% 35%
106 4.2.1.3.2 Structure 82 days Fri 21/08/20 Wed 03/03/2117% 17%
107 4.2.2 Pipe Penstock Area 304 daysFri 01/05/20 Sun 28/02/2114% 14%
108 4.2.2.1 Pipe Penstock - Saddle Construction 304 daysFri 01/05/20 Sun 28/02/2120% 20%
109 4.2.2.1.1 Penstock Pipe Batch 1 (Morning Glory27 -days
AB 1)Fri 25/12/20 Wed 20/01/210% 0%
110 4.2.2.1.2 Penstock Pipe Batch 2 (AB 1 - AB 5) 27 days Fri 01/05/20 Fri 15/01/21 21% 21%
111 4.2.2.1.3 Penstock Pipe Batch 3 (AB 5 - AB 11)27 days Fri 15/05/20 Wed 20/01/2145% 45%
112 4.2.2.1.4 Penstock Pipe Batch 4 (AB 11 - AB 15)
27 days Fri 01/05/20 Sun 28/02/2114% 14%
113 4.2.2.2 Anchor Blok Construction 269 daysFri 05/06/20 Sun 28/02/2119% 19%

Critical Split Finish-only Baseline Milestone Manual Summary Inactive Task

Critical Split Task Progress Duration-only Milestone Project Summary Inactive Milestone

Critical Progress Manual Task Baseline Summary Progress External Tasks Inactive Summary

Task Start-only Baseline Split Summary External Milestone Deadline

Thu 24/12/20 Page 3 of 6


schedule 201224.mpp
ID WBS Task Name Duration Start Finish % Work
Half 2, 2019 Half 1, 2020 Half 2, 2020 Half 1, 2021 Half 2, 2021
Complete S N J M M J S N J M M J S N
114 4.2.2.2.1 Penstock Pipe Batch 2 (AB 1 - AB 5) 27 days Fri 05/06/20 Sun 17/01/2114% 14%
115 4.2.2.2.2 Penstock Pipe Batch 3 (AB 5 - AB 11)27 days Fri 05/06/20 Wed 20/01/2130% 30%
116 4.2.2.2.3 Penstock Pipe Batch 4 (AB 11 - AB 15)
27 days Fri 05/06/20 Sun 28/02/2113% 13%
117 4.2.2.3 Tunnel - Pipe Foundation 31 days Mon 05/10/20Wed 04/11/200% 0%
118 4.2.2.4 Penstock Bridge 1 (tunnel outlet) 27 days Fri 25/12/20 Wed 20/01/210% 0%
119 4.2.2.5 Penstock Bridge 2 27 days Fri 05/06/20 Tue 23/02/211% 1%
120 4.2.3 Powerhouse Area 247 daysThu 03/09/20Fri 07/05/21 0% 0%
121 4.2.3.1 Soil Work 28 days Thu 03/09/20Wed 30/09/200% 0%
122 4.2.3.2 Foundation 170,79 days
Thu 03/09/20Sat 20/02/210% 0%
123 4.2.3.2.1 Foundation for Equipment - Turbine28 1 days Thu 03/09/20Wed 30/09/200% 0%
124 4.2.3.2.2 Foundation for Equipment - Turbine31 2 days Wed 20/01/21Sat 20/02/21 0% 0%
125 4.2.3.2.3 Foundation for Powerhouse 27 days Fri 04/09/20 Wed 30/09/200% 0%
126 4.2.3.2.4 Foundation for Guard Post 24 days Mon 07/09/20Wed 30/09/200% 0%
127 4.2.3.3 Building 123 daysMon 05/10/20 Thu 04/02/210% 0%
128 4.2.3.3.1 Powerhouse - Construction 42 days Fri 25/12/20 Thu 04/02/210% 0%
129 4.2.3.3.2 Powerhouse - Architectural and Finishing
42 days Fri 25/12/20 Thu 04/02/210% 0%
130 4.2.3.3.3 Powerhouse - Installation Overhead12 Crane
days Fri 25/12/20 Tue 05/01/210% 0%
131 4.2.3.3.4 Guard Post - Construction 26 days Mon 05/10/20Fri 30/10/20 0% 0%
132 4.2.3.3.5 Guard Post - Arsitektural and Finishing
13 days Fri 25/12/20 Wed 06/01/210% 0%
133 4.2.3.4 Tailrace 84 days Sat 13/02/21Fri 07/05/21 0% 0%
134 4.2.3.4.1 Tailrace Works 84 days Sat 13/02/21 Fri 07/05/21 0% 0%
135 4.2.3.5 Access Road 36 days Sat 13/03/21Sat 17/04/210% 0%
136 4.2.3.5.1 Pavement access road and existing road
36 days
withSat
sirtu
13/03/21 Sat 17/04/21 0% 0%
137 4.2.3.6 Fence and Gate 41 days Fri 05/02/21 Wed 17/03/21 0% 0%
138 4.2.3.6.1 Gate and Fence Installation 36 days Fri 05/02/21 Fri 12/03/21 0% 0%
139 4.2.3.6.2 Drainage 36 days Wed 10/02/21Wed 17/03/210% 0%
140 4.2.4 Station Service (Gardu 7R2) 60 days Fri 25/12/20 Mon 22/02/210% 0%
141 4.3 Piping Works 136 daysThu 28/01/21Sun 13/06/210% 0%
142 4.3.1 Pipe Penstock Area 132 daysThu 28/01/21Wed 09/06/21 0% 0%
143 4.3.1.1 Penstock Pipe batch 1 (Morning Glory 38- AB
days
1) Thu 28/01/21Sun 07/03/210% 0%
144 4.3.1.2 Penstock Pipe Batch 2 (AB 1 - AB 5) 45 days Thu 04/03/21Sun 18/04/210% 0%
145 4.3.1.2.1 Pipe Stringing 24 days Thu 04/03/21Sun 28/03/210% 0%
146 4.3.1.2.2 Pipe Welding and NDT 17 days Thu 18/03/21Sun 04/04/210% 0%
147 4.3.1.2.3 Pipe Coating 21 days Sun 28/03/21Sun 18/04/210% 0%
148 4.3.1.3 Penstock Pipe Batch 3 (AB 5 - AB 11) 41 days Sun 28/03/21Sat 08/05/210% 0%
149 4.3.1.3.1 Pipe Stringing 39 days Sun 28/03/21Thu 06/05/210% 0%
150 4.3.1.3.2 Pipe Welding and NDT 18 days Sun 11/04/21Thu 29/04/210% 0%
151 4.3.1.3.3 Pipe Coating 17 days Wed 21/04/21Sat 08/05/21 0% 0%

Critical Split Finish-only Baseline Milestone Manual Summary Inactive Task

Critical Split Task Progress Duration-only Milestone Project Summary Inactive Milestone

Critical Progress Manual Task Baseline Summary Progress External Tasks Inactive Summary

Task Start-only Baseline Split Summary External Milestone Deadline

Thu 24/12/20 Page 4 of 6


schedule 201224.mpp
ID WBS Task Name Duration Start Finish % Work
Half 2, 2019 Half 1, 2020 Half 2, 2020 Half 1, 2021 Half 2, 2021
Complete S N J M M J S N J M M J S N
152 4.3.1.4 Penstock Pipe Batch 4 (AB 11 - AB 15)42 days Wed 28/04/21 Wed 09/06/210% 0%
153 4.3.1.4.1 Pipe Stringing 22 days Wed 28/04/21Thu 20/05/210% 0%
154 4.3.1.4.2 Pipe Welding and NDT 28 days Wed 05/05/21Wed 02/06/210% 0%
155 4.3.1.4.3 Pipe Coating 21 days Wed 19/05/21Wed 09/06/210% 0%
156 4.3.2 Powerhouse Area 22 days Mon 01/03/21 Mon 22/03/210% 0%
157 4.3.2.1 Pipe Installation 22 days Mon 01/03/21Mon 22/03/210% 0%
158 4.3.3 Hydrostatic Test 4 days Wed 09/06/21Sun 13/06/210% 0%
159 4.4 Mechanical Works 90,73 days
Sun 13/06/21Sat 11/09/210% 0%
160 4.4.1 Powerhouse Area 90,73 days
Sun 13/06/21Sat 11/09/210% 0%
161 4.4.1.1 Turbine Installation 47 days Sun 13/06/21Fri 30/07/21 0% 0%
162 4.4.1.1.1 Spiral Housing & Draftube (Unit 1 &92)days Sun 13/06/21Tue 22/06/210% 0%
163 4.4.1.1.5 Concrete Pouring 10 days Tue 22/06/21Fri 02/07/21 0% 0%
164 4.4.1.1.6 Concrete Drying 28 days Fri 02/07/21 Fri 30/07/21 0% 0%
165 4.4.1.1.2 Turbine Accessories 7 days Tue 22/06/21Tue 29/06/210% 0%
166 4.4.1.1.3 Power Cable & Control 19 days Tue 29/06/21Sun 18/07/210% 0%
167 4.4.1.1.4 Final Installation Turbine Accessories
9 days Sun 18/07/21Tue 27/07/210% 0%
168 4.4.1.2 Generator Installation 77,8 daysSat 26/06/21Sat 11/09/210% 0%
169 4.4.1.2.1 Generator & HPU 5 days Sat 26/06/21 Thu 01/07/210% 0%
170 4.4.1.2.5 Concrete Pouring 5 days Thu 01/07/21Tue 06/07/210% 0%
171 4.4.1.2.6 Concrete Drying 28 days Tue 06/07/21Tue 03/08/210% 0%
172 4.4.1.2.2 Generator Accessories 5 days Thu 01/07/21Tue 06/07/210% 0%
173 4.4.1.2.3 Electric & Instrument 24 days Mon 16/08/21Wed 08/09/210% 0%
174 4.4.1.2.4 Final Installation Generator & Electrical
4 days Wed 08/09/21Sat 11/09/21 0% 0%
175 4.5 Electrical, Instrument and Control Works 215,5 days Fri 05/02/21 Wed 08/09/210% 0%
176 4.5.1 Powerhouse Area 215,5 days
Fri 05/02/21 Wed 08/09/210% 0%
177 4.5.1.1 Cable Pulling 31,5 daysSun 30/05/21Wed 30/06/210% 0%
178 4.5.1.2 Switchgear Installation 10,5 daysThu 01/07/21Sun 11/07/210% 0%
179 4.5.1.3 Main Transformer Installation 10,5 daysTue 13/07/21Fri 23/07/21 0% 0%
180 4.5.1.4 Station Service Trafo Installation 10,5 daysTue 13/07/21Fri 23/07/21 0% 0%
181 4.5.1.5 SKTM Works 30 days Sat 10/07/21 Mon 09/08/210% 0%
182 4.5.1.6 Gardu Tembok Works 30 days Mon 09/08/21Wed 08/09/210% 0%
183 4.5.1.7 Grounding System 10 days Fri 05/02/21 Sun 14/02/210% 0%
184 4.5.1.8 Lighting System 10 days Fri 12/02/21 Sun 21/02/210% 0%
185 4.5.1.9 CCTV 10 days Fri 19/02/21 Sun 28/02/210% 0%
186 4.5.1.10 Air Conditioning 10 days Fri 26/02/21 Sun 07/03/210% 0%
187 4.6 COMMISSIONING and COMPLETION 35,5 daysWed 08/09/21 Wed 13/10/210% 0%
188 4.6.1 General 5 days Wed 08/09/21 Sun 12/09/210% 0%
189 4.6.1.1 Training (Class & Site) 5 days Wed 08/09/21Sun 12/09/210% 0%

Critical Split Finish-only Baseline Milestone Manual Summary Inactive Task

Critical Split Task Progress Duration-only Milestone Project Summary Inactive Milestone

Critical Progress Manual Task Baseline Summary Progress External Tasks Inactive Summary

Task Start-only Baseline Split Summary External Milestone Deadline

Thu 24/12/20 Page 5 of 6


schedule 201224.mpp
ID WBS Task Name Duration Start Finish % Work
Half 2, 2019 Half 1, 2020 Half 2, 2020 Half 1, 2021 Half 2, 2021
Complete S N J M M J S N J M M J S N
190 4.6.1.2 Brosure, Catalog, Spare Parts 5 days Wed 08/09/21Sun 12/09/210% 0%
191 4.6.1.3 SOP & Maintenance Procedure 5 days Wed 08/09/21Sun 12/09/210% 0%
192 4.6.1.4 As Build Drawing & MDR 5 days Wed 08/09/21Sun 12/09/210% 0%
193 4.6.1.5 As Build Drawing & MDR (lokal) 5 days Wed 08/09/21Sun 12/09/210% 0%
194 4.6.2 Electrical 7 days Wed 08/09/21 Wed 15/09/21 0% 0%
195 4.6.2.1 Gardu Tembok Test 7 days Wed 08/09/21Wed 15/09/210% 0%
196 4.6.3 Commissioning 27 days Wed 15/09/21 Tue 12/10/210% 0%
197 4.6.3.1 Commissioning & Running Testing 7 days Wed 15/09/21 Wed 22/09/21 0% 0%
198 4.6.3.1.1 Preparation Test 1 day Wed 15/09/21Thu 16/09/210% 0%
199 4.6.3.1.2 No Load Test 1 day Thu 16/09/21Fri 17/09/21 0% 0%
200 4.6.3.1.3 Load Performance Test 40%, 60%, 80%
1 day
and 100%
Thu 16/09/21Fri 17/09/21 0% 0%
201 4.6.3.1.4 Emergency Overload Test 1 day Thu 16/09/21Fri 17/09/21 0% 0%
202 4.6.3.1.5 Stop Rejection Test 1 day Fri 17/09/21 Sat 18/09/21 0% 0%
203 4.6.3.1.6 Over Speed Test For Relay Over Speed
1 day Fri 17/09/21 Sat 18/09/21 0% 0%
204 4.6.3.1.7 Temperature Measurement On Load 1 Test
day Fri 17/09/21 Sat 18/09/21 0% 0%
205 4.6.3.1.8 Start and Automatic Stop Test 1 day Fri 17/09/21 Sat 18/09/21 0% 0%
206 4.6.3.1.9 Vibration And Noise Test 1 day Sat 18/09/21 Sun 19/09/210% 0%
207 4.6.3.1.10 Guide Vane And Generator Output Test
1 day Sat 18/09/21 Sun 19/09/210% 0%
208 4.6.3.1.11 Index Polarity Test 1 day Sat 18/09/21 Sun 19/09/210% 0%
209 4.6.3.1.12 Report 3 days Sun 19/09/21Wed 22/09/210% 0%
210 4.6.3.2 Test Run 21 days Tue 21/09/21Tue 12/10/210% 0%
211 4.6.3.2.1 Performance Test (Non-Stop) 21 days Tue 21/09/21Tue 12/10/210% 0%
212 4.6.4 Final Report & Handover 12 days Fri 01/10/21 Wed 13/10/21 0% 0%
213 4.6.4.1 Closed Out Report 11 days Fri 01/10/21 Tue 12/10/210% 0%
214 4.6.4.2 Hand Over Unit 1 & Unit 2 1 day Tue 12/10/21Wed 13/10/210% 0%

Critical Split Finish-only Baseline Milestone Manual Summary Inactive Task

Critical Split Task Progress Duration-only Milestone Project Summary Inactive Milestone

Critical Progress Manual Task Baseline Summary Progress External Tasks Inactive Summary

Task Start-only Baseline Split Summary External Milestone Deadline

Thu 24/12/20 Page 6 of 6