PLTM Cileunca 660,5 Days Mon 23/12/19 Wed 13/10/21 40%
PLTM Cileunca 660,5 Days Mon 23/12/19 Wed 13/10/21 40%
mpp
ID WBS Task Name Duration Start Finish % Work
Half 2, 2019 Half 1, 2020 Half 2, 2020 Half 1, 2021 Half 2, 2021
Complete S N J M M J S N J M M J S N
0 PLTM CILEUNCA 660,5 days
Mon 23/12/19
Wed 13/10/21
40% 40%
1 1 MILESTONES 659,5 days
Mon 23/12/19 Tue 12/10/210% 0%
2 1.1 Project Start (NTP) 0 days Mon 23/12/19Mon 23/12/19100% 23/12
3 1.2 Generator Onsite 0 days Fri 28/05/21 Fri 28/05/21 0% 28/05
4 1.3 Turbine Onsite 0 days Mon 31/05/21Mon 31/05/210% 31/05
5 1.4 Construction Start 0 days Fri 17/01/20 Fri 17/01/20 100% 17/01
6 1.5 Project Complete 0 days Tue 12/10/21Tue 12/10/210% 12/10
7 2 ENGINEERING 456 daysFri 31/01/20 Fri 30/04/21 70% 70%
8 2.1 General 414 daysFri 13/03/20 Fri 30/04/21 70% 70%
9 2.1.1 Preparation Work / For Information 22 days Fri 10/04/20 Tue 13/04/2174% 74%
10 2.1.2 Technical Data List 45 days Fri 13/03/20 Sat 09/01/21 65% 65%
11 2.1.4 Technical Data Turbine 14,5 daysThu 19/03/20Thu 02/07/20100% 100%
12 2.1.5 Technical Data Generator 23,5 daysThu 19/03/20Thu 02/07/20100% 100%
13 2.1.3 Operation and Maintenance Instruction 15 days Fri 16/04/21 Fri 30/04/21 0% 0%
14 2.2 Civil 379 daysFri 31/01/20 Fri 12/02/21 80% 80%
15 2.2.1 Calculation 30 days Fri 31/01/20 Fri 01/01/21 75% 75%
16 2.2.2 Drawing 379 daysFri 31/01/20 Fri 12/02/21 81% 81%
17 2.2.2.1 Penstock Pipe and Structure 49 days Fri 07/02/20 Thu 26/03/20100% 100%
18 2.2.2.1.1 Penstock Piping 49 days Fri 07/02/20 Thu 26/03/20100% 100%
19 2.2.2.1.2 Saddle 35 days Fri 07/02/20 Thu 12/03/20100% 100%
20 2.2.2.1.3 Anchor Block 35 days Fri 07/02/20 Thu 12/03/20100% 100%
21 2.2.2.2 Penstock Bridge 22 days Fri 31/07/20 Mon 04/01/2151% 51%
22 2.2.2.3 Powerhouse Area 242 daysTue 16/06/20Fri 12/02/21 23% 23%
23 2.2.2.3.1 Powerhouse 50 days Tue 16/06/20Wed 20/01/2146% 46%
24 2.2.2.3.2 Tailrace 50 days Fri 25/12/20 Fri 12/02/21 0% 0%
25 2.2.2.4 Access Road and Bridge 134 daysFri 31/01/20 Fri 12/06/20 100% 100%
26 2.2.2.4.1 Access Road 25,6 daysFri 31/01/20 Fri 12/06/20 100% 100%
27 2.2.2.4.2 Access Bridge 29,34 days
Fri 31/01/20 Fri 12/06/20 100% 100%
28 2.2.2.5 Station Service (Gardu Hubung) 49 days Fri 20/03/20 Thu 07/05/20100% 100%
29 2.2.2.6 Guard Post 35 days Fri 13/03/20 Thu 16/04/20100% 100%
30 2.2.2.7 Temporary Facilities 77 days Fri 21/02/20 Thu 07/05/20100% 100%
31 2.3 Mechanical, Electrical & Instrument 368,2 days
Fri 07/02/20 Tue 09/02/2156% 56%
32 2.3.1 Calculation 91 days Fri 07/02/20 Thu 07/05/20100% 100%
33 2.3.2 Drawing 333,2 days
Fri 13/03/20 Tue 09/02/2143% 43%
34 2.3.2.1 Penstock Area 22 days Fri 13/11/20 Fri 08/01/21 33% 33%
35 2.3.2.2 Powerhouse Area 333,2 days
Fri 13/03/20 Tue 09/02/2144% 44%
36 2.3.2.2.1 Installation Plan 57 days Fri 13/03/20 Wed 20/01/2153% 53%
37 2.3.2.2.2 Turbine Drawing 29,2 daysTue 23/06/20Thu 27/08/20100% 100%
Critical Split Task Progress Duration-only Milestone Project Summary Inactive Milestone
Critical Progress Manual Task Baseline Summary Progress External Tasks Inactive Summary
Critical Split Task Progress Duration-only Milestone Project Summary Inactive Milestone
Critical Progress Manual Task Baseline Summary Progress External Tasks Inactive Summary
Critical Split Task Progress Duration-only Milestone Project Summary Inactive Milestone
Critical Progress Manual Task Baseline Summary Progress External Tasks Inactive Summary
Critical Split Task Progress Duration-only Milestone Project Summary Inactive Milestone
Critical Progress Manual Task Baseline Summary Progress External Tasks Inactive Summary
Critical Split Task Progress Duration-only Milestone Project Summary Inactive Milestone
Critical Progress Manual Task Baseline Summary Progress External Tasks Inactive Summary
Critical Split Task Progress Duration-only Milestone Project Summary Inactive Milestone
Critical Progress Manual Task Baseline Summary Progress External Tasks Inactive Summary