WORK ORDER EXECUTION REPORT

Work Order 220000677854 Scheduling Start Date 01.01.2021 - Scheduling Finish Date 01.01.2021, WO Print Date 25.12.2020
First Scheduled Dates Original Planned Start Date 26.12.2020 - Original Planned Finish Date 26.12.2020
Work Description STRAINERS CLEANING - UP TO 6"

Superior Order
Sup. Order Description
Functional Location Z021-7300-LH-002 T STRAINER;4";ON SUCTION PUMP PA-001B
Equipment 2024007902 T STRAINER;4"
Equipment Manufacturer WOOSUNGFLOWTEC
Model Number YC, 4", S80, 150#
Serial Number 107300PA001B
Work Permit
WO Type Work Type Activity Type Status WBS Element
PM02 PM RO Routine APPR 6EIQ02036MA0005

Object List
Equipment Equipment Description Equipment Functional Location Functional Location Description
Tag

Main Discipline MEC Mechanical


PM Plan Z21LH01M41
PM Plan Description STRAINERS CLEANING - UP TO 6"
Planner Group NMS NDGS Mech-Static
Main Work Center CN-MSTAT
Failure Mode
Failure Cause
Failure Consequence
D. Time Hours 0.00
Action Taken

Manhours Required:
W. Centers W.C. Description Num Hrs
Tool Required:
Code Description Q.ty Hrs

Page: 1 of 6
ZFOD-Zubair Field Op.Div.
WORK ORDER EXECUTION REPORT

Work Order 220000677854 Scheduling Start Date 01.01.2021 - Scheduling Finish Date 01.01.2021, WO Print Date 25.12.2020
First Scheduled Dates Original Planned Start Date 26.12.2020 - Original Planned Finish Date 26.12.2020
Work Description STRAINERS CLEANING - UP TO 6"

Superior Order
Sup. Order Description
Functional Location Z021-7300-LH-002 T STRAINER;4";ON SUCTION PUMP PA-001B
Equipment 2024007902 T STRAINER;4"
Equipment Manufacturer WOOSUNGFLOWTEC
Model Number YC, 4", S80, 150#
Serial Number 107300PA001B
Work Permit

Operation List:
Op. Sub. Op. Work Center Description Persons Actual Man Hours

Page: 2 of 6
ZFOD-Zubair Field Op.Div.
WORK ORDER EXECUTION REPORT

Work Order 220000677854 Scheduling Start Date 01.01.2021 - Scheduling Finish Date 01.01.2021, WO Print Date 25.12.2020
First Scheduled Dates Original Planned Start Date 26.12.2020 - Original Planned Finish Date 26.12.2020
Work Description STRAINERS CLEANING - UP TO 6"

Superior Order
Sup. Order Description
Functional Location Z021-7300-LH-002 T STRAINER;4";ON SUCTION PUMP PA-001B
Equipment 2024007902 T STRAINER;4"
Equipment Manufacturer WOOSUNGFLOWTEC
Model Number YC, 4", S80, 150#
Serial Number 107300PA001B
Work Permit

0010 CN-MSTAT STRAINER CLEANING UP TO 6"_6W 2


STRAINER CLEANING UP TO 6"_6W

10,,INFORM CONTROL ROOM OF BEGINNING OF THE WORKS AND OPEN THE WORK
PERMIT
20,,CHECK ITEM SUBJECT TO MAINTENANCE FOR HSE CONDITION
30,,PREPARE AREA TO START THE WORK
40,,CHECK TAG NUMBER ACCORDING TO P<(>&<)>ID
50,,MAKE SURE LINE IS DEPRESSURIZED
60,,ISOLATE THE EQUIPMENT/ LINE ( INSERT BLIND DISCS IF NEEDED )
70,,ASSIST PRODUCTION PERSONAL TO DRAIN ALL FLUID FROM LINE ( IF ANY )
80,,CLEAN THE CONTAMINATED SURFACE ( USE DEGREASING SOLVENT ) AND WASH
IT
90,,DRY THE CLEANED SURFACE BY COMPRESSED AIR ( IF AVAILABLE )
100,,REMOVE COVER AND PULL OUT STRAINER/BASKET SCREEN.
110,,REMOVE DEBRIS FROM SCREEN SURFACE AND FROM STRAINER/BASKET HOUSING.
CHECK THE STRAINER MESH AND REPLACE IF DAMAGED.
120,,CHECK SEALING SURFACES FOR MECHANICAL DAMAGE
130,,CHECK GASKET AND REPLACE IF DAMAGED
140,,REASSEMBLING STRAINER/BASKET FILTER
150,,RESTORE THE PROCESS FLOW (REMOVE BLIND DISCS IF PREVIOUSLY
INSTALLED)
160,,PRESSURIZE THE LINE ( IN ASSISTANCE TO PRODUCTION PERSONNEL )
170,,CHECK FOR ANY LEAKS
180,,CLEAN AREA AND EQUIPMENT AFTER THE WORK
190,,INFORM CONTROL ROOM OF ENDING OF THE WORKS
200,,PREPARE FINAL CHECK REPORT

Page: 3 of 6
ZFOD-Zubair Field Op.Div.
WORK ORDER EXECUTION REPORT

Work Order 220000677854 Scheduling Start Date 01.01.2021 - Scheduling Finish Date 01.01.2021, WO Print Date 25.12.2020
First Scheduled Dates Original Planned Start Date 26.12.2020 - Original Planned Finish Date 26.12.2020
Work Description STRAINERS CLEANING - UP TO 6"

Superior Order
Sup. Order Description
Functional Location Z021-7300-LH-002 T STRAINER;4";ON SUCTION PUMP PA-001B
Equipment 2024007902 T STRAINER;4"
Equipment Manufacturer WOOSUNGFLOWTEC
Model Number YC, 4", S80, 150#
Serial Number 107300PA001B
Work Permit

210,,CLOSE AND CHECK IF THE WORK PERMIT HAS BEEN CORRECTLY SIGNED

Page: 4 of 6
ZFOD-Zubair Field Op.Div.
WORK ORDER EXECUTION REPORT

Work Order 220000677854 Scheduling Start Date 01.01.2021 - Scheduling Finish Date 01.01.2021, WO Print Date 25.12.2020
First Scheduled Dates Original Planned Start Date 26.12.2020 - Original Planned Finish Date 26.12.2020
Work Description STRAINERS CLEANING - UP TO 6"

Superior Order
Sup. Order Description
Functional Location Z021-7300-LH-002 T STRAINER;4";ON SUCTION PUMP PA-001B
Equipment 2024007902 T STRAINER;4"
Equipment Manufacturer WOOSUNGFLOWTEC
Model Number YC, 4", S80, 150#
Serial Number 107300PA001B
Work Permit

Signatures
Work Done

Remarks

Name Date
WO Waiting for Scheduling Salem Ibrahim Mohamed Okasha 07.11.2020
WO Waiting for material by
WO Waiting for Plant
WO Waiting for approval Cristian Zidarescu 07.11.2020
WO Approved by Andrea Cecchi 22.12.2020
WO Approved by Amjad Altaher 22.12.2020