Professional Documents
Culture Documents
CMS-2-10-15-01-2020 Conversion
CMS-2-10-15-01-2020 Conversion
August, 2019
Table of Contents
List of Figures .................................................................................................................................. IV
List of Tables .................................................................................................................................... VI
List of Photos ................................................................................................................................. VII
1. INTRODUCTION ........................................................................................................................ 1
1.1 Preamble ............................................................................................................................ 1
8.4 Visual Aids to Improve the Safety of Road Users and Vehicles ..................... 31
9. REFERENCES................................................................................................................................. 49
LIST OF FIGURES
Figure 1.1: State/ Union Territory wise total number road crashed in the year 2017 ................... 1
Figure 1.2: State/ Union Territory wise Fatal Crashes in the year 2017 .......................................... 2
Figure 6.2: CSIR - CRRI Team with RCD Engineers prior to start of RSA ........................................ 12
Figure 8.3: Typical Examples of Proposed Safety Features at Horizontal Curves on a Two lane
Undivided Carriageway ...................................................................................................................... 34
Figure 8.4: Typical Example of Solar Powered blinkers to caution the road users ....................... 35
Figure 8.7: Yellow and black strips painting on Bridge/CD parapet wall located adjacent to the
carriageway ......................................................................................................................................... 37
Figure 8.8: Typical Example of Hazardous Reach Treatment with Traffic Calming using
Thermoplastic Bar Markings .............................................................................................................. 38
Figure 8.10: Typical Illustration of Provision for stand-alone Pedestrian Crossings ................... 40
Figure 8.11: Typical Design Details of Road Humps to be provided on Minor/Side Roads ......... 41
Figure 8.12: Work Zone Traffic Management Plan to be followed when undertaking widening at
Cross-Drainage Works ........................................................................................................................ 42
Figure 8.13: Stage - 1 of Work Zone Traffic Management Plan while upgrading the road from
Intermediate to Two-Lanes. This is to be adopted while preparing the adjacent surface to
achieve a minimum width of 5.5 m for facilitating two-way movement of traffic. The work will
be taken adjacent to the existing traffic movement. ......................................................................... 43
Figure 8.14: Stage - 2 of Work Zone Traffic Management Plan while upgrading the road from
Intermediate to Two-Lanes. In this stage the traffic will be diverted onto the carriageway and
shoulder prepared during the Stage-1. The Layout of Signs and Markings is suggested to be
strictly followed. .................................................................................................................................. 44
Figure 8.15: Modified Eccentric Loader Terminal (MELT) Arrangement for Approach Side of the
Metal Beam Crash Barrier .................................................................................................................. 45
Figure 8.16: Trailing Terminal (TT) Arrangement for Departure Side of the Metal Beam Crash
Barrier .................................................................................................................................................. 46
Figure 8.17: Typical Illustration of Low Height fencing with raised kerbs in Urban Pockets to
prevent encroachments ...................................................................................................................... 46
LIST OF TABLES
Table 2.1: Road Sections Identified under Gopalganj Division .......................................................... 4
Table 7.2: Spot Speed Survey Results for SH-96(41.3): Afrad Market to Barauli Direction ......... 28
Table 7.3: Spot Speed Survey Results for SH-96(41.3): Barauli to Afrad Market Direction ......... 28
Table 8.1: Spacing of Delineators/ Reflectors based on the Radius of Curve ................................. 31
LIST OF PHOTOS
Photo 6.1: Major junction having poor road geometrics requiring redesign conforming to IRC:
SP-41 (1994) coupled with absence of Traffic Calming Measures on the intersecting roads at Km
0 (Km stone 62.36).Sudden edge drop of pavement at culvert is safety problem and WBM crash
barrier required................................................................................................................................... 22
Photo 6.4: Absence of 'Side Road ahead’ Warning Sign, Direction Sign and Traffic Calming
Measures all approach roads is safety problem at Km 0.4. Absence of reflectors on poles and
trees is safety problem. ....................................................................................................................... 22
Photo 6.5: Encroachments, Parking,, No markings, absence of foot path and absence of edge
markings is safety problem at 0.8 ...................................................................................................... 23
Photo 6.8: Narrow road through busy market area, open drain and parking is safety problem at
Km 1.3 . congested road from 1Km to 1..3km ................................................................................... 23
Photo 6.9: Parking, construction material and absence of markings is safety problem at Km 1.4
.............................................................................................................................................................. 23
Photo 6.10: Poor Road, construction material, tree cutting material without reflectors, absence
of edge markings is safety problem at Km 1.7 .................................................................................. 23
Photo 6.11: Poor Road, construction material, tree cutting material without reflectors, absence
of edge markings is safety problem at Km 1.8 .................................................................................. 24
Photo 6.12: Absence of 'Side Road ahead’ Warning Sign, Direction Sign and Traffic Calming
Measures on the Minor Road(s) intersecting with the Project Corridor is safety problem at Km
1.8. Absence of reflectors on tree cut material is problem. They should be removed. .................. 24
Photo 6.13: Absence of OHM and absence of markings is safety problem at Km 1.9 .................... 24
Photo 6.14: Construction materials, Hawkers, Obscured and non standard sign is safety problem
at Km 2.5............................................................................................................................................... 24
Photo 6.15: absence of OHM on Railway barricades, absence of marking on speed hump, Non
standards hump is safety problem at Km 2.6. ................................................................................... 24
Photo 6.16: Absence of reflectors on poles, absence of markings, parking, poor shoulder is safety
problem at Km 2.8. .............................................................................................................................. 24
Photo 6.17: Absence of reflectors on poles, absence of edge marking is safety is problem Km 2.9.
.............................................................................................................................................................. 25
Photo 6.18: Absence of OHM, Broken edge, Absence of edge markings is safety problem at Km
3.4. ........................................................................................................................................................ 25
Photo 6.19: Absence of reflectors on poles and trees and absence of edge marking is safety
problem at Km 3.5 ............................................................................................................................... 25
Photo 6.20: Absence of 'Side Road ahead’ Warning Sign, Direction Sign and Traffic Calming
Measures on the Minor Road(s) intersecting with the Project Corridor is safety problem at Km
3.7 ......................................................................................................................................................... 25
Photo 6.22: Absence of chevron signs, poor shoulder is safety problem at Km 4.5....................... 25
Photo 6.23: General view of the section at Km 5.1. Edge drop, poor shoulder and absence of
markings is safety problem. ............................................................................................................... 25
Photo 6.24: Absence of S curve sign, chevron signs and speed limit sign, protruding tree
branches is safety problem at Km 5.7. ............................................................................................... 25
Photo 6.25: Absence of chevron signs, Compulsory horn sign is safety problem at Km 5.8. ........ 26
Photo 6.26: Absence of OHM, poor shoulder, edge drop, no markings is safety problem at Km 6.5
.............................................................................................................................................................. 26
Photo 6.27: Construction and stacked material, absence of markings is safety problem at Km 7.1
.............................................................................................................................................................. 26
Photo 6.28: Absence of reflectors on poles, absence of traffic calming measures is safety
problem at Km 7.3. .............................................................................................................................. 26
Photo 6.29: Encroachments, absence of markings, absence of reflectors on poles and trees is
safety problem at Km 7.4. ................................................................................................................... 26
Photo 6.30: Broken edges, absence of markings is safety problem at Km 7.7 . .............................. 26
1. INTRODUCTION
1.1 Preamble
The state of Bihar is pegged at the 15th rank in terms of total number of road
crashes numbering 8,855 during the year 2017 constituting a share of 1.9 per cent of
nationwide statistics. Moreover, the state has occupied 11th position numbering 5554 in
terms of number of fatal road crashes considering the pan Indian state level statistics
during the same year which reveals the fact fatal road crashes outnumbers the minor
injury related crashes. The above high number of fatal crash statistics is directly
reflected in the severity of road crashes which is 62.7 i.e. number of persons killed per
100 road crashes during the year 2017 and the above figure is double in terms of
severity of road crashes recorded at national level. Further, the number of persons
killed per lakh population in the road crashes is 5.3 persons killed per 10,000 vehicles
and incidentally Bihar along with state of Uttar Pradesh were the worst performers
recording large increase in the number of road crashes and fatalities in 2017 as
compared to 2016. At the same time, the number of persons killed per 10,000 kilometer
of road length and 10,000 vehicles in the state are 237.4 and 8.9 respectively in the year
2016 which implies that it has registered minor dip as compared to the previous year.
Figure 1.1 shows the state / union territory wise road crashes whereas Figure1. 2 depict
the fatal crashes in each of the sates / union territory.
Road Crashes 0 10000 20000 30000 40000 50000 60000
Tamil Nadu
Madhya Pradesh
Karnataka
Uttara Pardesh
Kerala
Maharashtra
Andhra Pradesh
Telangana
Rajasthan
Gujarat
Chhattisgarh
West Bengal
Haryana
Odisha
Bihar
Assam
Delhi 15th Rank
Punjab
Jammu & Kahmir
Jharkhand
Goa
Himachal Pradesh
Puducherry
Uttarakhand
Meghalaya
Manipur
Nagaland
Tripura
Chandigarh
Arunachal Pradesh
Sikkim
Andaman & Nicobar Islands
Daman & Diu
Mizoram
Dadra & Nagar Haveli
Lakshadweep
Figure 1.1: State/ Union Territory wise total number road crashed in the year 2017
Figure 1.2: State/ Union Territory wise Fatal Crashes in the year 2017
On the other hand, the state of Bihar has registered consistent increase in terms
of number of persons killed per 100 road crashes from 51.4 in the year 2014 to 62.7 in
the year 2017. This is despite the fact that the road length in the state of Bihar and the
number of registered vehicles in the state is not very high as compared to the other top
ranked states in terms of reported road crashes in the country. Further, the number of
reported road crashes on the national highways and state highways in the state of Bihar
has recorded steady trend during the last three years without any substantial reduction.
This aspect is found to be a major cause of concern for the stakeholders like the Road
Construction Department (RCD) of Bihar and general road users alike which need to be
accorded due attention.
damaged guardrails, dilapidated road markings and more importantly, the provision of
safety measures commensurate with the traffic growth which are essential to create a
safe road network. The above aspects can be effectively addressed through the conduct
of RSA on the existing roads which are faced with increasing road crash records.
Out of the above listed parameters, the methodology and parameters applicable
for the conduct of RSA on the Bihar road network conforming to IRC: SP-88 (2010) and
other international standards (wherever applicable) would be adopted by the CSIR –
CRRI study team. This would help to arrive at effective improvement and up gradation
strategies for implementation by the Bihar Road Construction Deportment (RCD) after
the closure meeting. The methodology deployed for the Existing Stage RSA of the study
sections is described in the succeeding sections.
iii) Based on the assessment of road crash prone locations during the RSA visit,
action plans have been conceived in this report. Some examples are pedestrians,
roadside developments, sociological aspects that need special attention and
development of appropriate facilities.
iv) Help of checklists [IRC: SP-88 (2010), IRC: 35 (2015), IRC:67 (2012), IRC: SP-55
(2014) and IRC:119 (2015), IRC:SP-73 (2017)] for road signs, markings, crash
protection measures and conceptual junction design have been suitably utilized
to ensure that problems and situations that can affect the road safety at the
desired stage of RSA have been taken into consideration. The checklists broadly
covered the following aspects:
a) Alignment
b) Cross-sections
c) Shoulders, footpaths
d) Side slopes, drainage facilities
e) Road markings
f) Road signs
g) Road lighting
h) Junction layout
i) Bridges / CD works
j) Roadside furniture
k) Roadside hazards etc.
l) Facilities for Non-Motorized Traffic
ii) Appropriate recommendations / remedial measures for the identified safety
deficiencies have been provided along with the action plan for implementation.
Further depending upon the type of facility, the items mentioned above have
been appropriately grouped while conducting RSA and the priority for their
implementation have been provided as part of the RSA report submitted for each
of the -wise issues identified in each candidate road section. By correlating the
above data with the road crash data from the FIR data which is supplied by RCD,
Bihar the necessary safety features have been recommended for each candidate
road section aimed at enhancing the safety of all types of road users.
Data Collection:
Field Studies investigations
Traffic Studies and Road Crash
proposed by RCD in line with the aim of enhancing road safety as well as socio-
economic conditions of the people residing in the vicinity.
Following the methodology listed in the previous section, Road Safety Audit of
the study corridor namely, Manjhi - Barauli Road (SH-96), was carried out by an
experienced team of Road Safety Auditors representing CSIR - CRRI comprising of Sh.
Subhash Chand [Senior Principal Scientist and HoD(TES)] and Dr. J. Nataraju [Principal
Scientist and Project Leader]. RCD officials who accompanied the CSIR - CRRI team
during the RSA included Sh. Vijay Shankar Prasad, AE. The geographical location of the
Project Corridor is shown in Figure 6.1. A glimpse of the CSIR - CRRI study team
performing RSA and Speed studies on the study section is presented in Figure 6.2.
Figure 6.2: CSIR - CRRI Team with RCD Engineers prior to start of RSA
The findings emerging from the RSA of the above road are discussed in detail in
the succeeding sections. It may be noted RSA findings are applicable for both directions
of travel i.e. Left Hand Side (LHS) and Right Hand Side (RHS) of the carriageways
especially in the case of recommendation in respect of Visual Aids in the form of Traffic
Control Devices as well as Crash Protection measures.
Photo 6.5: Encroachments, Parking,, No Photo 6.6: Flag pole shall be removed at Km 0.9
markings, absence of foot path and absence of
edge markings is safety problem at 0.8
Photo 6.11: Poor Road, construction material, tree Photo 6.12: Absence of 'Side Road ahead’ Warning
cutting material without reflectors, absence of Sign, Direction Sign and Traffic Calming Measures
edge markings is safety problem at Km 1.8 on the Minor Road(s) intersecting with the
Project Corridor is safety problem at Km 1.8.
Absence of reflectors on tree cut material is
problem. They should be removed.
Photo 6.15: absence of OHM on Railway Photo 6.16: Absence of reflectors on poles,
barricades, absence of marking on speed hump, absence of markings, parking, poor shoulder is
Non standards hump is safety problem at Km 2.6. safety problem at Km 2.8.
Photo 6.17: Absence of reflectors on poles, Photo 6.18: Absence of OHM, Broken edge,
absence of edge marking is safety is problem Km Absence of edge markings is safety problem at
2.9. Km 3.4.
Photo 6.19: Absence of reflectors on poles and Photo 6.20: Absence of 'Side Road ahead’ Warning
trees and absence of edge marking is safety Sign, Direction Sign and Traffic Calming Measures
problem at Km 3.5 on the Minor Road(s) intersecting with the
Project Corridor is safety problem at Km 3.7
Photo 6.21: Absence of OHM, absence of markings Photo 6.22: Absence of chevron signs, poor
is safety problem at Km 4.3 shoulder is safety problem at Km 4.5.
Photo 6.23: General view of the section at Km 5.1. Photo 6.24: Absence of S curve sign, chevron signs
Edge drop, poor shoulder and absence of and speed limit sign, protruding tree branches is
markings is safety problem. safety problem at Km 5.7.
Photo 6.25: Absence of chevron signs, Photo 6.26: Absence of OHM, poor shoulder, edge
Compulsory horn sign is safety problem at Km drop, no markings is safety problem at Km 6.5
5.8.
Photo 6.27: Construction and stacked material, Photo 6.28: Absence of reflectors on poles,
absence of markings is safety problem at Km 7.1 absence of traffic calming measures is safety
problem at Km 7.3.
S. Time of Survey
Location Chainage Description
No
9:30 AM
1 Location Km 41/300 Straight
15/03/2019
The survey location is selected in a way that it should be representative of the
prevailing speed characteristics at the selected location. The location should be as
influenced due to any form of roadside friction. The results of the survey at this location
in both the directions of travel are given in Tables 7:2 and Table 7:3.
It is evident from the results that the 85th Percentile speeds of all the
vehicles in both the directions of travel is about 55 Kmph. Since the road section
passes through heavily built-up areas including some curved sections and is single lane
section, it is prudent. Therefore, traffic calming is essentially required in both the
directions of travel as proposed in Section 6..
Table 7.2: Spot Speed Survey Results for SH-96(41.3): Afrad Market to Barauli Direction
Parameters All Car 2W Auto Tr Bus Cycle LCV 2T MT
Sample Size 110 10 65 8 4 1 18 1 2 3
Min. Speed (Kmph) 8 31 23 20 17 36 8 39 27 28
Max. Speed (Kmph) 74 58 74 39 28 36 14 39 35 31
Mean Speed (Kmph) 40 47 47 30 24 14 33 32
Average Speed (Kmph) 38 45 45 29 22 11 31 29
15th percentile speed (Kmph) 8 30 28 16 14 24
50th percentile speed (Kmph) 34 43 41 28 18 26
85th percentile speed (Kmph) 52 54 56 32 25 30
95th percentile speed (Kmph) 62 56 67 36 27 32
Table 7.3: Spot Speed Survey Results for SH-96(41.3): Barauli to Afrad Market Direction
Parameters All Car 2W Auto Tr Bus Cycle LCV 2T MT
Sample Size 103 16 67 10 1 2 7
Min. Speed (Kmph) 10 36 27 27 21 30 10
Max. Speed (Kmph) 72 72 72 48 21 38 14
Mean Speed (Kmph) 45 53 49 37 35 14
Average Speed (Kmph) 43 51 47 36 34 12
15th percentile speed (Kmph) 27 37 31 25 14
50th percentile speed (Kmph) 41 49 43 31 14
85th percentile speed (Kmph) 55 57 56 40 14
95th percentile speed (Kmph) 65 69 66 45 14
limit of 60 Kmph in straight sections in open areas in the undivided portions of the
highway. However, on the vulnerable sections, the Speed Limit shall be reduced to
25 - 30 Kmph. However, ‘Restriction End’ Regulatory Sign must be provided after
the vulnerable reach has ended followed by the posting of Speed Limit sign of 50
Kmph within a distance of 50 m. More importantly, the adherence to the enforced
speed limit shall be strictly monitored by the PWD by seeking the help of Police.
All the vulnerable reaches, such as Pedestrian Crossings, Market Places and
Schools nearby the road shall be accorded the Vulnerable Reach Treatment as
demonstrated in Section 8.
Thermoplastic Bar Markings (TBM) shall be installed on the project road near all
the major and minor intersections. The thickness of the markings shall be
increased to 8 to 10 mm from the specified thickness of 5 mm as per IRC: 35
(2015). This is because the greater rumbling effect would facilitate in higher
reduction of speeds at the vulnerable locations. Also, on all the intersecting roads,
Speed Humps shall necessarily be provided so that the vehicles do not merge with
the traffic on the main road at high speeds.
8. ACTION PLAN
To reduce the road crash proneness on Manjhi - Barauli Road section of SH-96
and thus enhancing safety, the following action plans are recommended.
8.4 Visual Aids to Improve the Safety of Road Users and Vehicles
It is recommended to install new visual aids in the form of various types of road
appropriate signs (suiting to the site conditions detailed in Section 6.4 for various s) in
the form of flashing signals, retro-reflective markers, delineators, chevron markings,
chevron signs at curves and road markings such as lane marking, pavement marking,
object marking, zebra crossings etc. as typically presented in the report (refer Figure
8.3). These would provide positive guidance to the road users and thus help to enhance
safety for all types of road users both during day and night. Further at all the Minor
Roads intersecting with the Project Corridor, consider providing Solar Powered
Blinkers on the main carriageway as shown in Figure 8.4 which would prompt the road
users to exercise caution while negotiating the minor intersections as well as help in
sensitization of all types of road users. Moreover, at such locations as well as on
horizontal curves, consider providing appropriate signs (as given in Section 6.4) coupled
with road studs [spaced at 9 m centre to centre conforming to IRC: 35 (2015)] and
Transverse Bar Marking (TBM) as shown in Figure 8.5. Further in the case of minor
intersecting roads located on sharp horizontal curves of 100 m and below, consider
providing Convex Lens on the farther side of the road as shown in Figure 8.6 which
would enable the drivers to keep a track of the traffic emerging from the Project
Corridor with ease.
Page |33
Road Safety Audit Report of Manjhi - Barauli Road (SH-96)
Figure 8.3: Typical Examples of Proposed Safety Features at Horizontal Curves on a Two lane Undivided
Carriageway
Figure 8.4: Typical Example of Solar Powered blinkers to caution the road users
Wherever objects are located adjacent to the carriageway, i.e. up to 2.4 m from
the paved shoulders portion, it is recommended to apply 6 stripes of alternate black
and white road marking downward at an angle of 45 degrees towards traffic.
At the Causeway locations wherein valley curve is observed, use the steel fencing
for both approaches coupled with erection of valley curve sign along with road
studs, Transverse Bar Marking (TBM) and the solar amber blinkers shall be
provided as explained in the succeeding section.
Figure 8.7: Yellow and black strips painting on Bridge/CD parapet wall located
adjacent to the carriageway
8.6 Treatment for Safety of Vulnerable Road Users
As mentioned in the report, there are several vulnerable spots on the project
corridor that require special treatment on the part of the engineers and road users
alike.
At all locations like sharp horizontal curves wherein soft Traffic Calming
measures are required, Thermoplastic Bar Markings (TBM) shall be provided
(Figure 8.8) conforming to IRC:35 (2015). However, the thickness of the TBM may
be kept at 8 mm for achieving effective speed reduction.
Figure 8.8: Typical Example of Hazardous Reach Treatment with Traffic Calming using
Thermoplastic Bar Markings
At places, especially near Market areas, Schools, Colleges and Hospitals which
witnesses large pedestrian activity, there is a need to forewarn the users and also to
implement appropriate traffic calming measures in the form of Speed Breakers
conforming to IRC:35 (2015). Moreover, such locations shall be accorded the following
‘Vulnerable Reach Treatment’ in the form of zigzag marking as presented in Figure 8.9
need to be provided on the ground conforming to IRC:35 (2015).
Figure 8.11: Typical Design Details of Road Humps to be provided on Minor/Side Roads
Figure 8.13: Stage - 1 of Work Zone Traffic Management Plan while upgrading the road from Intermediate to
Two-Lanes. This is to be adopted while preparing the adjacent surface to achieve a minimum width of 5.5 m for
facilitating two-way movement of traffic. The work will be taken adjacent to the existing traffic movement.
Page |43
CSIR-Central Road Research Institute, New Delhi
Road Safety Audit Report of Manjhi - Barauli Road (SH-96)
Figure 8.14: Stage - 2 of Work Zone Traffic Management Plan while upgrading the road from Intermediate to Two-Lanes.
In this stage the traffic will be diverted onto the carriageway and shoulder prepared during the Stage-1. The Layout of
Signs and Markings is suggested to be strictly followed.
Page |44
Road Safety Audit Report of Manjhi - Barauli Road (SH-96)
Figure 8.16: Trailing Terminal (TT) Arrangement for Departure Side of the
Metal Beam Crash Barrier
8.10 Control of Encroachments at Urban Areas
Wherever the Project Corridor is passing through the urban developed areas and to
mitigate road encroachment by footpath vendors / shop keepers /parking etc., low height
fencing as given in Figure 8.17 shall be erected. These activities spread across the road and
create potential road crash spots. To control the above unauthorized encroachments, it is
strongly recommended for strict monitoring by PWD and subsequent evacuation of any such
encroachments at the early stages with the help of Bihar Police.
Figure 8.17: Typical Illustration of Low Height fencing with raised kerbs in
Urban Pockets to prevent encroachments
All the kilometer stones are to be painted in Green Color conforming to IRC 8:
1980 namely, “Type Designs for Highway Kilometer Stones” i.e. Green Color
Paint should be used for SHs.
Last but not the least, soft shoulders shall be maintained properly by providing
gravel / brick on edge shoulders after removing the grass coupled with removing
the undulations of the shoulder which would facilitate its effective use by all
types of road users. However, in the long run, depending on the quantum of Non
Motorized Traffic (NMT) using the corridor, the RCD, Bihar shall think of
providing segregated paved shoulders which would facilitate the safe movement
of cyclists and pedestrians. This measure is only applicable on specific pockets of
the road stretch spanning between two adjacent villages wherein increased
movement of school children or other commuters by cycle / foot are witnessed.
9. REFERENCES
1. IRC: SP-88 (2010) “Manual on Road Safety Audit”, IRC, New Delhi
3. TRB (2009) "Manual on Uniform Traffic Control Devices for Streets and Highways”,
Transportation Research Board, USA.
4. IRC:67 (2012) “Code of Practice for Road Signs (Third Revision)”, IRC, New Delhi
5. IRC:35 (2015) “Code of Practice for Road Markings (First Revision)”, IRC, New Delhi
6. IRC: SP-55 (2014) “Guidelines for Traffic Management in Work Zones”, IRC, New
Delhi.
7. IRC: 119 (2015) “Guidelines for Traffic Safety Barriers”, IRC, New Delhi.
8. IRC: SP-73 (2015) “Manual of Specifications and Standards for Two Laning of
Highways with Paved Shoulders (First Revision)” IRC, New Delhi.
9. IRC: 99 (2018) “Guidelines for Traffic Calming Measures in Urban and Rural Area
(First Revision)”, IRC, New Delhi.