9th CAD Minutes PDF
9th CAD Minutes PDF
Officers Present:
Sarvasri
2. K.Srinivas
1. K.Jalandhar
Chief Engineer, CDO,
Engineer-in-Chief (Admn.Wing),
CAD Committee Member
CAD Committee, Chairman
V.Sridhar,
3. T.V.N.A.R Kumar 4.
Chief Engineer, GDS, Dowlaiswaram
Chief Engineer, Hydrology
CAD Committee Member
CAD Committee Member
5. U.Annam Naidu,
Executive Engineer, CADA,
CAD Committee, Convenor
*****
finalize the Action plan of O &M works proposed for the year 2020-21.
works under Category ‘A’, Capital head and Revenue head for according
approved the Annual Action plan of O&M works which are detailed as follows:
1
Category-A
9th CAD, 2020-21, Dt: 21-11-2020.
(Rs. in Lakhs)
HOA 2700–80-800-00-14-270/272
Action Plan
Water Action Plan Proposed Action Plan
Project Approved
Sl. HOD Circle Division Tax Approval
Name No.of No.of
Eligible Amount Amount /Remarks
works works
Engineer-in-Chief (I) Vijayawada
Drainage
Division,
reported by ENC(I)
Chirala
SE/IC Vijayawada
Rs.842.20L as
3 43.00 3 43.00 Approved
in the letter
KDS
1 CE Division,
Tenali 54 187.07 54 187.07 Approved
K.W
by CE in the
as reported
Irrigation
Division,
Atmakur
letter
SE/IC Nellore
Rs.84.22L as
CE
reported by
CE in the
Division,
Nellore
Gudur
South
letter
2
4
CE
CE
GDS NTRTGP
Sub-Total
2
4
2
13
37
54
36.34
18.50
18.50
127.16
375.89
539.39
4
2
13
37
54
36.34
18.50
18.50
127.16
375.89
539.39
Approved
Approved
Approved
Approved
3
Amalapuram
Division,
Approved
G.C
1 0.61 1 0.61
puram
SE/IC Dowlaiswaram
Approved
1 1.78 1 1.78
furnished by the
SE/IC Dowlaiswaram
Approved
12 318.01 12 318.01
Kakinada
Drainage
Division,
3 73.16 3 73.16 Approved
Approved
40 445.68 40 445.68
Approved
Dowlaiswaram
1 20.67 1 20.67
GH Division,
Approved
Dowlaiswaram
YI Division,
Approved
15 114.01 15 114.01
4
Capital Head
9th CAD, 2020-21, Dt: 21-11-2020.
(Rs. in Lakhs)
Action Plan
Action Plan Proposed
Sl. Project Budget Approved Remarks
HOD Circle Division
No Name Availability No. of No. of
Amount Amount
works works
HOA 4700-01-137-11-27-530/531
HNSS Phase-II HNSS Phase-II
No-8, Penukonda
HNSS Division
1
Ananthapuramu
HNSS Division
HNSS Phase-II
Division
Approved
HNSS
No.5,
5 87.694 5 87.694
5
4
3
2
HOA
HOA
HOA
Sub-Total
5
2
1
1
7
2.20
9.90
55.47
40.00
95.47
5
2
1
1
7
2.20
9.90
55.47
40.00
95.47
Approved
Approved
Approved
Approved
6
HOA 47010-03-122 GDP-11-27-530/531
Gajuladinne Project
Chief Engineer &
SE/IC, Kurnool
DWRO Kurnool
B.E 2020-21)
(p.no.204 of
Rs.50.00L
TBP
5 Division, 1 9.95 1 9.95 Approved
Adoni
7
General Conditions:
The Action Plan of O&M works once approved by the CAD committee should
not be repeated for the next 3 years except weed removal. The Chief
Engineer/Superintending Engineer should certify that the proposed works
are not repeated and taken up since last 3 years. In case of repetition of the
same works in the succeeding year, the concerned Superintending Engineer
will be personally held responsible.
The Chief Engineer/Superintending Engineer/Executive Engineer should
ensure and certify that the proposed works are not covered under Neeru-
Chettu Programme or any other programme of State/ Central Government
schemes for the past 3 years.
The CAD committee will accord the Action Plan approval after careful
examination of available budgetary/ ploughback funds only. Necessary
administrative approval shall be accorded by the competent authority as per
rules in vogue.
L S provisions towards GST and other provisions may be provided as per the
Rules in vogue while according Technical sanction.
The rates for mechanical items provided in the estimates may be got vetted
by General Superintendent, P.W Workshops.
The Chief Engineer/Superintending Engineer should submit the proposal with
full description of name of O&M work duly mentioning the chainages, specific
locations with Index map showing the name and number of distributory/Sub-
distributory / Minor/Sub-Minor etc.
The proposals of O&M works should be thoroughly verified/ scrutinized at
Chief Engineer/Superintending Engineer level and categorized with available
budget provision/ploughback funds before submission to CADA office.
The works taken up and completed should invariably entered in WTS and
submit proposal for release of LOCs.
Each proposal of O&M works under category-A should invariably accompanied
with the statement showing the availability of WUA/DC/PC wise plough back
amount in the prescribed proforma already communicated. However the
same proforma is shown below.
(Rs. in Lakhs)
Plough back funds Action plan approved Expenditure Balance
Charges
Charges
Charges
Charges
Year
Admin
Admin
Admin
Admin
WUA
WUA
WUA
WUA
DC
DC
DC
DC
PC
PC
PC
PC
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17
2016-17
2017-18
2018-19
2019-20
2020-21
8
List of works under Category-A
Estimate
S.NO Name of Work Amount
(Rs. in Lakhs)
Emergent breach closing Repairs to Scoured and slipped banks
1
on Commamuru Canal from Km.73.000 to Km.73.500 R/B 3.95
9
Embankment Repairs to Scoured and slipped banks on
14 3.85
Commamuru Canal from Km.104.500 to Km.105.200 R/B
Embankment Repairs to Scoured and slipped banks on
15 3.74
Commamuru Canal from Km.106.800 to Km.107.300 R/B
Emergent breach closing of Commamuru canal at Km.107.400
16 4.41
R/B
Emergent breach closing of Commamuru canal at Km.107.470
17 R/B and Repairs to Scoured and slipped banks from 4.01
Km.107.550 to Km.107.700 R/B
Emergent breach closing of Commamuru canal at Km.109.750
18 4.40
R/B
Embankment Repairs to Scoured and slipped banks on R/B of
19 Commamuru canal from Km 109.300 to 109.650 and L/B of 3.92
Commamuru Canal from Km.109.600 to 109.900.
Embankment Repairs to Scoured and slipped banks on
20 3.71
Commamuru Canal from Km.110.00 to Km.110.900 L/B & R/B
Embankment Repairs to Scoured and slipped banks on
21 3.90
Commamuru Canal from Km.111.00 to Km.112.100 R/B & L/B
Emergent breach closing of damaged lock chamber gates of
22 3.94
pedaganjam lock at Km.112.415 of Commamuru canal
Embankment Repairs to Scoured and slipped banks of R.B
23 4.23
Channel from Km.0.000 to Km.3.500
Embankment Repairs to Scoured and slipped banks of
24 Peddaganjam Channel from Km.0.000 to Km.0.800 and 3.18
Kanaparthy channel from Km. 0.000 to Km 0.750
Embankment Repairs to Scoured and slipped banks of
25 2.68
Santharavur side channel from Km.1.00 to Km 5.000
Embankment Repairs to Scoured and slipped banks of
26 2.70
vetapalem block channel from Km.2.000 to Km.8.000
Embankment repairs to Emileru supply channel from Km.4.00
27 3.00
to Km.4.300
Emergent breach closing of Emileru supply channel from Km.
28 4.09
4.800 to Km.4.900 L/B.
Emergent breach closing of Emileru supply channel from
29 3.92
Km.4.900 to km.5.00 L/B.
Embankment repairs to Emileru supply channel from Km.4.80
30 2.28
to Km.5.00 R/B.
Embankment repairs to Emileru supply channel from Km.5.00
31 1.40
to Km.5.10 R/B.
Emergent breach closing of Emileru supply channel from
32 4.04
Km.6.100 to km.6.200 L/B.
Embankment repairs to Emileru supply channel from Km.6.70
33 4.32
to Km.7.50.
Emergent breach closing of Emileru supply channel from
34 3.66
Km.8.30 to km.8.450.
Embankment repairs to Emileru supply channel from Km.9.20
35 3.00
to km.9.40.
Emergent breach closing of Emileru supply channel from
36 3.66
Km.9.60 to km.9.80.
10
Emergent breach closing of Emileru supply channel from
37 4.49
Km.9.80 to km.10.50
Embankment repairs to Emileru supply channel from
38 3.11
Km.10.700 to km.11.00 L/B.
Emergent breach closing of Emileru supply channel from
39 3.84
Km.11.40 to km.11.600
Emergent breach closing of Emileru supply channel from
40 3.78
Km.12.00 to km.12.300.
Emergent breach closing of Emileru supply channel from
41 3.99
Km.12.30 to km.12.700.
Embankment repairs to Emileru supply channel from
42 3.06
Km.12.700 to km.13.00.
Embankment repairs to IC branch from Km1.00 to Km 2.00 of
43 4.26
Emileru supply channel.
Embankment repairs to Emileru supply channel from Km.16.00
44 3.80
to km.19.00.
Embankment repairs to Emileru supply channel from
45 4.50
Km.21.500 to km.24.00.
Embankment repairs to EAPP leading channel from Km 0.500
46 4.79
to Km.2.000.
Embankment repairs to Emileru supply channel from
47 2.75
Km.10.500 to km.10.700
Embankment repairs to Emileru supply channel from
48 2.50
Km.14.800 to Km.15.400.
Emergent breach closing of Emileru supply channel from
49 4.57
Km.11.700 to km.12.00 L/B.
Embankment repairs to Emileru supply channel from Km.
50 4.37
11.700 to km.12.00 R/B.
Emergent breach closing of Bapatla tank west channel from
51 1.29
Km.4.200 to Km.4.800 R/B.
Emergent breach closing of slipped banks on west bapatla
52 3.42
Channel from Km 9.000 to Km.9.800 L/B & R/B.
Embankment repairs to scoured and slipped banks on west
53 2.77
bapatla Channel from Km0.900 to Km.1.500 R/B.
Embanikment Repairs to scoured and slipped banks on west
54 3.76
bapatla Channel from Km6.700 to Km.7.400 L/B & R/B.
TOTAL 187.07
11
O&M –Weed removal & Desilting of Narasayapalem
side channel, Murukondapadu channel, Nadimi
2 DC-51 Chirala branch channel, Stuartpuram channel and its 5.97
branches, Reconstruction of Retaining wall of
Stuartpuram channel at Km 11.800
O&M - Embankment Repairs to Retaining wall on
WUA- 348, U/S of west Bapatla channel Head sluice and from
3 12.40
Kankatapalem Km 0.100 to 0.150 in west Bapatla channel in
Bapatla Mandal, Guntur District
O&M - Embankment Repairs to Retaining wall on
WUA-353,
4 Narasayapalem side channel at Km 0.000, Nadimi 7.37
Murukondapadu
branch siphon at Km 5.000
O&M Embankment Repairs to Wing wall on
WUA-359, Karamchedu new channel at Km 85.050 of
5 6.34
Karemchedu-II Commamuru canal near Karamchedu(V) in
Karamchedu(M) of Prakasam District.
WUA-349, O&M Embankment Repairs to Adueduct at Km
6 Kankatapalem- 9.185 on west Bapatla channel in Bapatla Mandal, 15.60
II Guntur District
TOTAL 53.58
Estimate
S.NO Name of Work Amount
(Rs. in Lakhs)
Repairs to Masonry & Embankment repairs to pipe culvert across
Veerlagudipadu Channel and Mitta Chenu Kalva near ST Colony
1 5.46
Kottalu of Apparao palem Village in Atmakur Mandal of SPSR Nellore
District.
Desilting of Surplus course No.2 of (Zilla Vagu) of Mahimaluru Tank
2 near Mahimaluru Village in Atmakur Mandal of SPSR Nellore District. 13.54
12
Desilting in the bed of Murgalla Tank Feeder Channels in Muragalla
9 6.58
Village limits in Atmakur Mandal of SPSR Nellore District.
Maintenance of Inspection path from Gangamma Gudi to
10 Perapanaidu fields near Vasili Village in Atmakur Mandal of SPSR 18.80
Nellore District.
Maintenance of Inspection path from Zillavagu to Mahimaluru Big
11 Tank of Mahimaluru Village in Atmakur Mandal of SPSR Nellore 26.00
District.
Desilting and Repairs to Masonry to Kotha Kalva, Vattapadu,
12 Mittachenu, Veerlagudipadu, Achangari Kalava near ST Colony of 40.50
Apparaopalem Village in Atmakur Mandal of SPSR Nellore District.
TOTAL 243.75
Project: CE/ Minor & Medium Irrigation, SE/IC Nellore, Nellore South
Division, Gudur
Estimate
S.NO Name of Work Amount
(Rs. in Lakhs)
Desilting of channels and Embankment Repairs to Kadhaluru big tank
1 14.25
& Kadhaluru small tank in Tada mandal, SPSR Nellore District.
Desilting of feeder channel to Ramapuram big tank in Tada mandal,
2 7.62
SPSR Nellore District.
Desilting of Irrigation channels to Konduru big tank & Somayajulu
3 tank in Tada Mandal, SPSR Nellore District. 5.33
13
Project: SE/IC, Nellore, Nellore Central Division, Nellore
Estimate
S.NO Name of Work Amount
(Rs. in Lakhs)
Embankment Repairs to Chalicherla kalava near Kovur Village in
1 9.35
Kovur of SPSR Nellore District.
Embankment repairs to Kalivila Kalava near Ramannapalem Village
2 9.15
of Kodavalur Mandal of SPSR Nellore District.
TOTAL 18.50
14
O&M, Desilting of Yandagandi medium drain from Km 7.000 to Km
7 9.540 in Chilukuru village limits under Drainage Section 9.98
Ganapavaram.
O&M, Desilting of Neelacodu medium drain from Km 0.000 to Km
8 4.400 in Kolamuru village limits under Drainage Section 9.90
Ganapavaram.
O&M, Desilting of Kakinada medium drain from Km 7.000 to Km
9 8.900 in Kolamuru village limits under Drainage Section 8.55
Ganapavaram.
O&M, Desilting of Pora Bodi minor drain of Cherukumilli (V) from Km
10 5.62
0.000 to 2.400 of Akividu Mandal in W.G.Dist.
O&M, Desilting of Elurupadu minor drain of Elurupadu (V) from Km
11 8.50
0.000 to 2.700 of Akividu Mandal in W.G.Dist.
O&M - Formation of Cross Bund across Pali Medium drain at Km 0.05,
Korukollu Minor drain at Km 0.60 & 4.30, Borra Codu Minor drain at
Km 0.30, Kukkala Codu Minor drain at Km 0.10, Ranga raju codu
12 Minor drain at Km 1.00, Adda codu Minor drain at Km 0.00, Ravi 7.80
codu Minor drain at Km 0.00, Santha codu Minor drain at Km 0.00
and Miramiacodu Minor drain at Km 1.500 under Drainage Section
No.1, Bhimavaram.
O&M - Formation of Cross bund across Mogallu Medium drain at Km
1.60, Earla codu Medium drain at Km 3.50 & 4.80, Manchili Medium
13 drain at Km 2.80, Gedala Codu Minor drain at Km 0.900 of Mogallu 8.40
(V), Ura Codu Minor drain at Km 0.300, Gedala codu Minor drain at
Km 0.00 of Korukollu (V) under Drainage Section No.1, Bhimavaram.
15
Formation of cross bund across the Major, Medium and Minor Drains
23 under the jurisdiction of Drainage Section, Narasapuram in W.G. 9.91
Dist.
Formation of cross bunds on Medium and Minor Drains in the
24 jurisdiction of Drainage Section, Gummuluru in W.G.Dist. 12.53
16
Project: CE/GDS, SE/IC, Eluru, Irrigation Division, Eluru
Estimate
S.NO Name of Work Amount
(Rs. in Lakhs)
Desilting from Km 0.650 to 1.050 of East Thammileru River in Limits
1 of Sai Nagar Colony in Eluru City for free flow of flood water 9.75
TOTAL 127.16
1 Repairs to Right Bank at Km. 12.550 of Torrigedda Left Main canal in 0.61
Koti Village Limits of Korukonda (M), in E.G. District
TOTAL 0.61
17
Project: CE/GDS, SE/IC, Dowlaiswaram, Godvari Eastern Division,
Ramachandrapuram
Estimate
S.NO Name of Work Amount
(Rs. in Lakhs)
Embanment Repairs to Nakkala Channel near Dam on Bikkavolu
1 1.78
Drian in Bikkavolu Section.
TOTAL 1.78
18
Project: CE/GDS, SE/IC, Dowlaiswaram, Drainage Division, Kakinada
Estimate
S.NO Name of Work Amount
(Rs. in Lakhs)
Reconstruction of Culvert on Injaram Minor drain near KM 2.60 and 15.46
1 Silt removal in the Vents of UT at KM 3.20 in G.E.Delta
19
Formation of Crossbunds on Anapalamma medium drain at km 2.00,
11 Old Anapalamma Drain at km 0.500 and Rellubadava Minor drain at 7.86
km 2.000 in GE Delta
Formation of Cross bund on major and minor drains in Drainage
12 12.90
Section No.3, Draksharama in G.E. Delta
Formation of Cross bund on medium and minor drains in Drainage
13 Section No.2, Ramachandrapuram in G.E. Delta 8.26
20
Formation of Cross bunds on Vepachettu Medium drain at km 9.00
35 9.99
and 2.00 km in G.C.Delta
Formation of Cross bunds on Rameswaram Medium at km 3.50 and
36 6.00km and Gudimula No.2 Minor drain at km 0.10 in Sakhinetipalli 9.95
Mandal in G.C.Delta
Formation of Cross bunds on Kunavaram Medium drain at km 0.300
37 6.64
and Katrenupadu Minor drain at km 0.100 in G.C.Delta
Formation of Cross bunds on Minor drains in Malikipuram Mandal
38 6.91
in G.C.Delta
Formation of Cross bunds on Medium and Minor drains in Razole
39 Mandal in G.C.Delta 9.05
21
Embankment repairs to the VRB Flood Bank in between Km 76.400
to 76.600 at Buddigavanirevu in Narasapuram Town of Narasapuram
8 Mandal of Narsapuram Constituency in VRB Lower Section 21.80
Narsapuram.
Embankment repairs between K.M 79.900 to 79.925 at Muskepalem
9 and K.M.90.200 at OFS of East Kokkileru Narsapuram mandal in 4.07
Narsapuram Constituency.
Repairs to Screw gearing shuttets of Kattunga Outfall Sluice at
10 K.M.23.600 of VLB in Rally(V) limits of Atreyapuram Mandal in East 10.80
Godavari District.
Maintenance of inspection path in between K.M.48.400 to 49.400 of
11 Vasista left bank in L Gannavaram Village Limits of P. Gannavaram 20.51
Mandal in East Godavari District.
Maintenance of inspection path in between K.M.62.400 to 63.400 of
12 Vasista left bank in Razole Village Limits of Razole Mandal in East 17.82
Godavari District
Embankment Repairs in between K.M 65.000 to 65.100 of Vasista
13 left bank at Sivakodu Village Limits of Razole Mandal in East 8.65
Godavari Dist.
Maintenanace of inspection path in between K.M.79.200 to 80.550 of
14 Vasista left bank in Sakhinetipalli Village Limits of 25.05
Skhinetipallimandalam in East Godavari District
Maintenance of inspection path in between K.M.90.400 to 90.600 of
15 Vasista left bank in Antharvedi Village Limits of Sakhinetipalli Mandal 11.23
in East Godavari District
Embankment Repairs to the eroded and slipped margin by formation
16 of Pilebox in the D/s of k Munjavaram Outfall sluice in K.M.9.126 of 7.25
VyLB of K Munjavaram (V) limits in P Gananvaram (M) of E.G.Dist.
Repairs to screw gearing shutters of Outlets in Bendamuralanka and
17 Odalarevu (V) limits of VynatheyamLeft Bank 3.34
22
Repairs to the masonry - Outfall Sluice including Head walls at K.M
25 5.791 of P.I.P Flood Bank in Pathainjaram village limits of 14.50
I.Polavaram Mandal in East Godavari District
Desilting of approach channel and leading channel to supply water
26 from River Godavari to Tatapudi pumping scheme to Godavari 13.25
Eastern Delta Bank canal in the rabi period 2020-21.
Maintenance and Operation of pumps at Tatapudi pumping scheme in
27 Rabi season K.M22.700 of G.L.B at Tatapudi[V] limits in Alamuru 6.50
Mandal In East Godavari District.
Embankment repairs to the GRB Flood bank in between Km 35.000
28 to 47.000 in Ainavalli mandal limits in East Godavari District 9.20
23
11 Revetment to retaining wall by Providing platform in between
K.M.19.300 and K.M.19.400 of Akhanda Godavari Left Flood Bank in
23.70
Bobbilanka (V) Limits of Seethanagaram Mandal in East Gadavari
District.
Total 262.91
Estimate
S.NO Name of Work Amount
(Rs. in Lakhs)
Embankment Repairs to eroded ,slipped banks of RRB tank in
1 Mallavaram (V)(near No 7 channel , in between 25.1 km PBC and 7.80
No1 channel of RRB tank) of Mallavaram (V) of Gollaprolu Mandal
Embankment Repairs to RRB No 1 sluice channel @ 3.5km (near
2 penumallu peddireddy fields) and other vulnerable reaches in 6.00
Peddayeru drain in Ramanakkapeta (V),U.Kothapalli (M)
Emergent Breach Closing to Neeladri rama surplus course @0.1 km
3 1.40
,0.3 km in A.V.Nagaram (v) limits in Thondangi Mandal
Embankment Repairs to Uppu tank surplus course @ 0.76km,0.9km
and other vulnerable reaches and strengthening of RRB tank No
4 8,No 9 , No 10 sluice channel of RRB tank in a.v nagram (v) of 6.00
Thondangi mandal.
Embankment Repairs to Uppu tank No 1 sluice channel @0.1 km
5 0.60
,@1.8 km in Kodada (V) in Thondangi Mandal
Embankment Repairs to Left Side Bank of Pithapuram Branch Canal
6 4.37
at Km 0.400 Samalkota (V)&(M)
Emergenrt Breach Closing to Left Side Bank of Pithapuram Branch
7 1.33
Canal at Km 3.200 near 4R Samalkota (V)&(M)
Emergenrt Breach Closing to Right Side Bank of Pithapuram Branch
8 1.30
Canal at Km 6.00, Chandrampalem (V), Samalkota (M)
Emergenrt Breach Closing to to Right Side Bank of Pithapuram
9 2.67
Branch Canal at Km 6.10, Chandrampalem (V), Samalkota (M)
Embankment Repairs to vaalu drain (@ fields of P.Lakshmanadora,
10 Ganeshreddy etc) in seethanagaram (v) and Mallavaram (v) of 4.98
gollaprolu mandal.
Embankment Repairs to eroded ,slipped banks of RRB tank under
11 Pithapuram Branch Canalin Mallavaram (V) near no 13 channel and 4.80
(b/w 28.1 km to 29.1 km) of Mallavaram (V) of Gollaprolu Mandal
Embankment Repairs to eroded No1 channel of RRB tank under
12 Pithapuram Branch Canal near SC peta and vulnerable reaches in 3.00
Ramanakkapeta (V),U.Kothapalli (M)
Embankment Repairs to Right Side Bank of Pithapuram Branch Canal
13 1.80
at Km 7.90, Chandrampalem (V), Samalkota (M)
Embankment Repairs to Panduru Tank under Pithapuram Branch
14 0.58
Canal of Panduru (V), Kakianda Rural (M)
Embankment Repairs to Left Side & R/s erroded Banks at 7.725Km
15 6.88
of PBC near Chandrampalem village in Samalkota Mandal
24
Embankment Repairs to Left Side bank of Nakhalakhandi drain @
16 2.5km ( near chaakalivari chenu ) in Gollaprolu (V) limits of 20.00
Gollaprolu Mandal.
Embankment Repairs to Left Side bank of Nakhalakhandi drain @
17 5.1 Km (near Isukapalli Raju farmer fields )Gollaprolu (V) of 6.70
Gollaprolu Mandal
Embankment Repairs to Gandevari calava near 1.55 km (near
18 Ramisetty fields), vulnerable reaches and filling of breaches near 7.80
gandevari calava drain in Gollaprolu (V) in Gollaprolu (M)
Embankment Repairs to Pithapram Branch Main canal @21.3 km
19 ,other vulnerable reaches and paamu calava bank rectification in 6.00
Gollaprolu (V) in Gollaprolu (M)
Embankment Repairs to eroded Ubanda canal and other vulnerable
20 4.00
reaches in Gollaprolu (V) in Gollaprolu (M)
Embankment Repairs to Peddayeru drain @ 1.6 km,1.7 km,1.8 km
21 and other vulnerable reaches in mallavaram (v ) of gollaprolu 8.00
mandal
Revertment Repairs to (OT Collapsed) on Appalaraju calva in
22 3.97
Somarayunipalem (V) of Krilampudi (M)
Revertment Repairs to Takina calava in Turupu Pakala Village of
23 4.57
Peddapuram Mandal
Formation of cross bund across jaganna calva at K.M. 0.000 at
24 4.80
Kandrakota Village limits of Peddapuram Mandal.
Formation of cross bund across jaganna calava at Km. 1.50 at
25 4.95
kandraokota Village limits of Peddapuram mandal.
Embankment Repairs to Gorkiandi Left Side at 0.30 Km in Tadiparthi
26 4.00
Village limits of Peddapuram Mandal
Embankment Repairs to Tupakigedda and yendapalli O.T. Channel
27 4.95
near Gollaprolu (V) & (M)
Embankment Repairs to Pithapuram Branch Canal @ 3.40 and 4.00
28 Km and Navarayeru near Yarla Gedda Channel fields of Samarlakota 3.93
(V) & (M)
Embankment Repairs to Right Side banks of Kotha calva near Dasari
Lakshmi fields Peddamanyam Voddu and Left Side bank of Khandi
29 calva near Bandi Venkateswara Rao fields of Yendapalli (V) of 2.23
U.Kothapalli (M)
Embankment Repairs to Left bank of Erra Calva at Km 4.500 in
30 9.85
Geddanapalli (V) limits in Kilampudi Mandal
Embankment Repairs to Left bank of Erra calva at Km 5.300 in
31 3.25
Ramakrishnapuram (V) limits in Kirlampudi (M)
Embankment Repairs to to Right bank of Gorrikhandi at Km 0.500 to
32 9.80
0.800 in Mukkollu (V) limits in Kirlampudi (M)
Embankment Repairs to Right bank of Gorrikhandia t Km 0.00 to
33 9.55
0.100 in Mukkolu (V) limits in Kirlampudi (M)
Embankment Repairs to Simhandriraju calava at Km 4.00 and 5.500
34 4.99
in Kirlampudi (V) limits in Kirlampudi Mandal
Embankment Repairs to Khandi Calva and Vajracalva in Goneda (V)
35 2.50
limits of Kirlampudi (M)
Embankment Repairs to Left Bank and Right Bank of Khandi Calva
36 between Km 5.50 to Km 7.00 in Katravulapalli (V) limits of 5.00
Jaggampeta (M)
25
Embankment Repairs to Left Bank and Right Bank of Khandi Calva
37 between Km 3.00 to Km 5.00 in Katravulapalli (V) limits of 4.89
Jaggampeta (M)
Embankment Repairs to RBF Yeleru River at Km 6.950 in Irripaka (V)
38 4.90
limits of Jaggampeta (M)
Embankment Repairs to Khandi calva right side bank in
39 1.40
Chandamama Palli (V) of Peddapuram (M)
Embankment Repairs to Gurrakanam sub Channel right side bank in
40 1.30
Vadlamuru (V) of Peddapuram (M)
Embankment Repairs to Peddapuram yeru right side bank at 3.40
41 4.50
K.M/. in G.Ragampeta (V) of Peddapuram (M)
Embankment Repairs to Peddapuram Yeru right side bank at 2.50
42 4.90
Km. in Peddapuram (V) of Peddapuram (M)
Embankment Repairs to Dabba calva left side bank at Km 1.00 in
43 4.95
Kandrakota (V) of Peddapuram (M)
Embankment Repairs to Gorikandi calva right side bank at 0.4 K.M.
44 2.00
in Tadiparthi (V) of Peddapuram (M)
Embankment Repairs to Dabba calva right side bank at Km. 2.50 in
45 4.90
Kattamuru (V) of Peddapuram (M)
Embankment Repairs to Gorrikhandi Right Bank b/w Km.0.000 to
46 3.58
0.500 of Mangiturthi (V) limits in Pithapuram (M)
Embankment Repairs to Pippi Calva Right bank in between
Km.0.000 to 0.500, Pippi Calava Left Bank b/w Km 2.100 to 2.400
47 and Panta Calva b/w 0.800 to 1.000 of Bhogapuram & B.Prathipadi 4.14
(V) limit in Pithapuram (M)
Embankment Repairs to Peddapuram Yeru Left side bank between
48 3.50
2.00 K.M. to 3.00 K.m in Peddapuram (V) of Peddapuram (M)
Embankment Repairs to YI Channel at 1.50 K.M. at both side bank in
49 1.40
Ulimeswaram (V) of Peddapuram (M)
Embankment Repairs to Right Bank of Gorrikhandi at Km 1.00 in
50 4.98
Mukkollu (V) limits in Kirlampudi (M)
Embankment Repairs to Right Bank of Suddagadda at Dontamuru (V)
51 4.99
limits in Pithapuram (M)
Embankment Repairs to Gorrikhandi Right Bank in between Km
52 9.84
9.300 to 9.800 of Veeraraghavapuram (V) limits in Pithapuram (M)
Embankment Repairs to Gorrikhandi Right Bank in between
53 Km.9.300 to 9.400 of Veeraraghavapuram (V) limits in Pithapuram 4.92
(M)
Embankment Repairs to Jaganna calva Right side bank at 1.50 Km.
54 2.25
in Kandrakota (V) of Peddapuram (M)
Embankment Repairs to Right Side Bank of Navara Yeru at Km
55 2.05
9.40, Timmapuram (V) of Kakinada Rural(M)
Embankment Repairs to Right Side Bank of Navara Yeru at Km 9.60,
56 2.05
Timmapuram (V) of Kakinada Rural(M)
Embankment Repairs to Right Side Bank of Navara Yeru at Km
57 4.20
9.80, Timmapuram (V) of Kakinada Rural(M)
Embankment Repairs to Right Side Bank of Navara Yeru at Km
58 0.50
10.200, Timmapuram (V) of Kakinada Rural(M)
Embankment Repairs to Right Side Bank of Navara Yeru at Km
59 0.54
10.250, Timmapuram (V) of Kakinada Rural(M)
26
Embankment Repairs to Right Side Bank of Navara Yeru at Km
60 2.07
10.300, Timmapuram (V) of Kakinada Rural(M)
Embankment Repairs to Left Side Bank of Navara Yeru at Km 10.52,
61 2.40
Timmapuram (V) of Kakinada Rural(M)
Embankment Repairs to Left Side Bank of Navara Yeru at Km 10.59,
62 1.48
Timmapuram (V) of Kakinada Rural(M)
Embankment Repairs to Left Side Bank of Navara Yeru at Km 10.63,
63 1.65
Timmapuram (V) of Kakinada Rural(M)
Embankment Repairs to Left Side Bank of Navara Yeru at Km 10.68,
64 2.95
Timmapuram (V) of Kakinada Rural(M)
Embankment Repairs to Left Side Bank of Navara Yeru at Km
65 1.85
10.760, Timmapuram (V) of Kakinada Rural(M)
Embankment Repairs to Left Side Bank of Navara Yeru at Km
66 4.57
10.875, Timmapuram (V) of Kakinada Rural(M)
Embankment Repairs to Left Side Bank of Navara Yeru at Km
67 3.35
11.420, Timmapuram (V) of Kakinada Rural(M)
Embankment Repairs to Right Side Bank of Navara Yeru at Km 0.200
68 2.02
Samalkota (V)&(M)
Embankment Repairs to Right Side Bank of Navara Yeru at Km 1.50
69 2.64
of Samalkota (V)&(M)
Embankment Repairs to Right Side Bank of Navara Yeru at Km 1.45
70 2.43
Samalkota (V)&(M)
Embankment Repairs to Navara Yeru R/s Bank at Km 3.00,
71 1.10
Samalkota (V)&(M)
Embankment Repairs to Navara Yeru R/s Bank at Km 3.10,
72 0.96
Samalkota (V)&(M)
Embankment Repairs to Right Side Bank of Navara Yeru at Km 3R
73 4.44
Channel at Km 2.010, Samalkota (V)&(M)
Embankment Repairs to Right Side Bank of Badava Calva at Km
74 1.15
0.600 near Near Ammi Raju Fields of Pavar (V) Samalkota (M)
Embankment Repairs to Right Side Bank of 6R - Channel Km 4.200
75 1.00
Near Ramalayam of Pavar (V) Samalkota (M)
Embankment Repairs to eroded Peddayeru drain near Jammuladodi
76 4.70
and vulnerable reaches in Ramanakkapeta (V),U.Kothapalli (M)
Desilting of Jakkara Cheniu Calva from Aminabad (V) of
77 2.10
U.Kothapalli(M)
78 Desilting of Para Calva from Kothapalli (V) of U.Kothapalli(M) 1.15
79 Weed Removal from Dudekula Calva of Nemam of Kakinada Rural(M) 1.04
Embankment Repairs to Right Side Banks of Paragada Chenu Calva
80 0.48
near Ramana fields of Kothapalli (V) of U.Kothapalli (M)
Embankment Repairs to Right Side banks of Peddayeru Drain @
81 4.70
1.810Km near Dubbulu Chenu of Nagulapalli (V) of U.Kothapalli (M)
Embankment Repairs to Right Side banks of Peddayeru Drain @
82 2.40
1.920Km near Dubbulu Chenu of Nagulapalli (V) of U.Kothapalli (M)
Embankment Repairs to Right Side banks of Peddayeru Drain near
83 3.20
CK Ravulu Fields of Nagulapalli(V) of U.Kothapalli (M)
Embankment Repairs to Right Side banks of Peddayeru Drain @
84 0.98
0.700 Km , Nagulapalli(V) of U.Kothapalli (M)
Embankment Repairs to Right Side banks of Peddayeru Drain @
85 4.99
0.000 Km , Nagulapalli (V) of U.Kothapalli (M)
27
Embankment Repairs to Right Side banks of Peddayeru Drain @
86 4.88
1.010 Km , Nagulapalli(V) of U.Kothapalli (M)
Embankment Repairs to Right Side banks of Peddayeru Drain @
87 4.10
7.020 Km , Ponada(V) of U.Kothapalli (M)
Embankment Repairs to Right Side banks of Peddayeru Drain @
88 3.57
0.300 Km , Nagulapalli (V) of U.Kothapalli (M)
Embankment Repairs to L/s Bank of Juthi Calva at Km 2.900,
89 1.68
Tammavaram(V) of Kakinada Rural(M)
Embankment Repairs to Right Side banks of Badava Calva @ 1.000
90 0.24
Km , Isukapalli (V) of U.Kothapalli (M)
Embankment Repairs to Left Side banks of Badava Calva @
91 0.80
0.00,0.200, 0.250 Km , Isukapalli (V) of U.Kothapalli (M)
Embankment Repairs to Right Side banks of Peddayeru Drain @
92 4.99
1.50Km near Nagulapalli (V) of U.Kothapalli (M)
Embankment Repairs to Right Side banks of Peddayeru Drain @
93 2.90
1.425Km near Nagulapalli (V) of U.Kothapalli (M)
Embankment Repairs to Right Bank of Pampa Main Canal at
94 1.18
Km./2.900 in Gopalapatnam (V) limits in Thondangi (M)
Embankment Repairs to Left Bank and R/B of Pampa Main Canal at
95 1.32
Km 3.100 in Gopalapatnam (V) limits in Thondangi (M)
Embankment Repairs to Left Bank of Pampa Mediun Irrigation
96 Project Thondangi Channel (PAtha Calva) at Km.3.200 in A.Kothapalli 6.78
(V) limits in Thondangi (M)`
Embankment Repairs to Left Bank of Pampa Mediun Irrigation Project
97 Thondangi Channel at Km 4.300 in P.Agraharam (V) Limits in 7.56
thondangi (M)
Embankment Repairs to Left Bank & Right Bank of Pampa Mediun
98 Irrigation Project (Paatha Calva) at Km.9.800 in Thondangi (V) Limits 7.62
in Thondangi (M)
Embankment Repairs to Left Bank & Right Bank of Pampa Mediun
99 Irrigation Project MD3 Channel b/w Km1.800 to 2.200 in Thondangi 1.48
(V) limits in Thondangi (M)
Embankment Repairs to Nukanna Tank in Thondangi (V) limits in
100 2.42
Thondangi (M) underMedium Irrigation Project.
Embankment Repairs to L/B of Pampa Medium Irrigation Project
101 Thondangi Channel at Km.5.600 in Srungavriksham (V) limits in 4.88
Thoandangi (M)
Embankment Repairs to L/B of Pampa Medium Irrigation Project MD1
102 Channel b/w Km.0.800 to 1.00 in A.Kothapalli (V) limits im 4.48
Thondangi (M)
Embankment Repairs to L/B & R/B of Pampa Medium Irrigation
103 Project. Reavilanka Channel B/W Km.1.200 to 1.400 in A.Kotghapalli 1.26
(V) limits in Thondangi (M)
Embankment Repairs to L/B of Gabu Voora Tank in Krishnapuram (V)
104 6.72
limits in Thondangi (M) Pampa under Medium Irrigation Project.
Embankment Repairs to D2 Channel Km.0.000 to 0.300 and MD2
105 Channel Km.0.200 and 0.500 Pampa underMedium Irrigation Project 0.94
in A.Kothapalli (V) limits, Thondangi (M)
28
Embankment Repairs to D4 Channel Km.0.300 to 1.400, Md6 Km
0.400 to 1.200, MD7 Km.0.600 to 1.300, MD8 Km1.100 to 1.500 and
106 kamayyagedda at Km 1.450 in Srungavriksham (V) limits, Thondangi 4.3
(M) under Pampa Medium Irrigation Project.
Embankment Repairs to Bezawada Cheruvu in A.Annavaram (V)
107 4.4
sankhavaram (M) under Pampa Medium Irrigation Project.
Embankment Repairs to Canal of Voora Tank of Subbareddy Sagar
108 Project at Km 0.35, 0.50, 0.52 0.54 & 0.55 near P.Jagannadhapuram 2.5
(V) Limits in Prathipadu (M), E.G.Dt.
Embankment Repairs to Gokavaram yeti Calava of Subba Reddy
109 Sagar Project at Km 7.20 near P.Jagannadhapuram (V) Limits in 0.45
Prathipadu (M), E.G.Dt.
Embankment Repairs to L/B and R/B in between KM 4.300 and
110 4.600 of Veerappa Kaalva in Thondangi (V) in Thondangi (M)Under 4.88
Pampa Medium Irrigation Project.
Embankment Repairs to Gokavaram yeti Calava of Subba Reddy
111 Sagar Project at Km 3.49 near Uttrakanchi (V) Limits in Prathipadu 0.40
(M), E.G.Dt.
Embankment Repairs to Gokavaram yeti Calava of Subba Reddy
112 Sagar Project at Km 0.85 near E.Gokavaram (V) Limits of Prathipadu 1.00
(M), E.G.Dt.
Embankment Repairs to Gokavaram yeti Calava of Subba Reddy
113 Sagar Project at Km 1.50 near Uttarakanchi (V) Limits in Prathipadu 0.40
(M), E.G.Dt.
Embankment Repairs to Yerra Calava of Subba Reddy Sagar Project
114 0.85
at Km 1.20 near Lampakalova (V) Limits in Prathipadu (M), E.G.Dt.
TOTAL 417.81
Estimate
S.NO Name of Work Amount
(Rs. in Lakhs)
1 Formation of Cross Bund Across Thammabvaram Tailed kalingala
2.45
cross bund on Navarayeru near Thammavaram (V)
2 Formation of Cross Bund Across West Yelaru drain @ 2/0 regulator
5.45
and on 4R Channel near Samalkota (V)
3 Formation of Cross Bund Across Nagulapalli Regulator on
1.8
Nakkalakhandi
4 Formation of Cross Bund on Ponnada kalingala Ponnada Calv a near
0.27
Nagulapalli (V) of U.Kothapalli (M)
5 Formation of Cross Bund across Ponnada Bridge of Ponnada (V) of
2.51
U.Kothapalli (M)
6 Repairs to Pithapuram Branch Canal Right Bank @ Km 17.010 near
Yendapalli OT near Madhapuram (V) limits 1.75
29
8 Repairs to R/s Banks of Peddayeru Drain @ 7.350 Km, Ponnada (V)
7.1
of U.Kothapalli (M)
9 Repairs to RRB tank sluice channels No1,2,3, No 7 muruku Kalava,
Pathayeti Calava, Vaalu calava in Mallavaram (V) limits, 9.7
Ramanakkapeta (V) of Gollaprolu & U.Kothapalli Mandal
10 Cost of Diesel Oil for lifting of Water from Dabba Calva to
Supplement the Standing Crop of Rabi 2020-21 under the Ayacut of
9.9
Turupumuta Calva in Kandrakota Village limits in Peddapuram
Mandal
11 Cost of Diesel Oil for lifting of Water from Dabba Calva to
Supplement the Standing Crop of Rabi 2020-21 under the Ayacut of 9.99
Kannalanka Calva in Kandrakota Village limits in Peddapuram Mandal
12 Supply of E.C. Bags and Casurina Ballies of Jurisdiction of Y.I.
6.7
Division, Peddapuram
13 Repairs to Shutters on Kotha Calva & Panta Calva, Desilting of
Kelangi vari Calva offtake of Panta Calva, Pakkapotu Calva offtake of 7.06
Hanumanthu Calva in Pithapuram Mandal
14 Repairs to Sluices on Yerrakayya Systemfed Tank of Yeleru Irrigation
30.2
System in Somavaram Village Limits in Pithapuram Mandal
15 Repairs to RCC Slab Culvert on Ramavaram Calva in Somarayunipeta
12.33
and Palem Village limits of Kirlampudi Mandal
Total 114.01
30
Project: CE(P), Ananthapuramu, SE/HNSS Circle No.2, Ananthapuramu,
HNSS Division No.8, Penukonda
Estimate
S.NO Name of Work Amount
(Rs. in Lakhs)
Estimate for closing of Breaches at Km 40.500, 49.500Km, 67.400
Km, 71.045 Km, and 72.390 Km on Punganuru Branch Canal
1 (Package No.26) in Nallacheruvu Mandal and Tanakallu Mandal of 6.43
Ananthapuramu District.
TOTAL 6.43
31
Project: CE (Projects)/Ananthapuram, SE/HNSS Circle No-2, Ananthapuram,
HNSS Division No.5, Guntakal
Estimate
S.NO Name of Work Amount
(Rs. in Lakhs)
Closing & Opening of Outlets and maintenance of main canal towards
Hiring of JCB and Man Mazdoors for Water Regulation period during
1 17.00
the season 2020-21, (i.e., from 01-10-2020 to 31-03-2021) from Km
134.000 to Km 155.00/155.575 and Km 210.00 to Km 216.300.
Closing & Opening of Outlets and maintenance of main canal towards
Hiring of JCB and Man Mazdoors for Water Regulation period during
2 the season 2020-21, (i.e., from 01-10-2020 to 31-03-2021) from Km 19.40
155.00 to Km 176.00.
Closing & Opening of Outlets and maintenance of main canal towards
Hiring of JCB and Man Mazdoors for Water Regulation period during
3 the season 2020-21, (i.e., from 01-10-2020 to 31-03-2021) from Km 19.544
176.00 to Km 192.000.
Closing & Opening of Outlets and maintenance of main canal towards
Hiring of JCB and Man Mazdoors for Water Regulation period during
4 the season 2020-21, (i.e., from 01-10-2020 to 31-03-2021) from Km 15.65
192.000 to Km 210.000.
Closing & Opening of Outlets and maintenance of main canal towards
Hiring of JCB and Man Mazdoors for Water Regulation period during
5 the season 2020-21, (i.e., from 01-10-2020 to 31-03-2021) to feed 16.10
an Ayacut of 65,600 Acres under Package No.36A.
TOTAL 87.694
32
Project: CE & DWRO/Kurnool, SE/SRBC Circle No.1, Nandyal,
SRBC Division No.3 Nandyal
Estimate
S.NO Name of Work Amount
(Rs. in Lakhs)
Improvements to the existing SRBC Approach Road leading to
1 Gorukallu Balancing Reservoir (GBR) from Km 0/550 to Km 1/450 20.00
(From Bridge to permises of Indu Royal Homes).
Improvements to the existing SRBC Approach Road leading to
2 Gorukallu Balancing Reservoir (GBR) from Km 1/500 to Km 2/100 20.00
(From Indu Royal Homes to SRBC Colony Gate).
TOTAL 40.00
33
Abstract
Rs. in Lakhs
Date of Revenue Deposited
Category-A Category-B Capital Head
CAD Head funds
Committee Am
No. of No. of No. of No. of No. of Amo
meeting Amount oun Amount Amount
works works works works works unt
t
1st CAD,
23 435.47 --- --- --- --- --- ---
9-4-2020
2nd CAD,
27-4-2020 273 3725.82 --- --- --- --- --- ---
3rd CAD
492 5650.29 --- --- 76 1276.86 --- ---
20-5-2020
4th CAD
326 4932.49 --- --- 552 7364.04 28 334.59
22-6-2020
5th CAD
55 772.56 --- --- 53 454.345 --- ---
4-8-2020
6th CAD
489 5316.751 --- --- 60 752.60 3 78.00
9-9-2020
7th CAD 4 16.36
13-10-2020 75 723.205 --- --- 54 556.66 --- ---
8th CAD
7 146.06 --- --- 2 16.70 --- --- --- ---
3-11-2020
9th CAD
369 3228.26 --- --- 25 342.624 --- --- --- ---
21-11-2020
TOTAL 2109 24930.906 --- --- 822 10763.829 31 412.59 4 16.36
Sd/-
Sd/- Sd/-
U.Annam Naidu, V.Sridhar
Executive Engineer, CADA & Chief Engineer, GDS, Dowlaiswaram
CAD Committee Convenor CAD Committee Member
Sd/- Sd/-
T.V.N.A.R Kumar K.Srinivas
Chief Engineer, Hydrology Chief Engineer, CDO
CAD Committee Member CAD Committee Member
Sd/-Sd/
Sd/-
K.Jalandhar
Engineer-in-Chief (A.W),
CAD Committee Chairman
34