Professional Documents
Culture Documents
General Philosophy: 1.0 - Introduction
General Philosophy: 1.0 - Introduction
General Philosophy: 1.0 - Introduction
GENERAL PHILOSOPHY
1.0 - INTRODUCTION
i) Breakdown maintenance
ii) Preventive maintenance
iii) Condition based monitoring
iv) Reliability centered maintenance
i) Breakdown Maintenance
As the name implies the maintenance is carried out when the equipment fails.
This type of maintenance may be appropriate for low value items. However
for costly substation equipments, it is not desirable to wait till the breakdown
of the equipment, as this cost more to the utility as well as the availability
and reliability of power gets affected. The revenue loss due to non-availability
of the system shall be much more than the cost of the failed equipment.
Therefore identifying the defect before failure, is more appropriate to plan
repair / replacement.
1
iv) Reliability Centered Maintenance
Reliability centered maintenance policy is based on the life cycle cost concept
and the decision for replacement of the equipment is taken based on techno-
economic considerations. From the view point of RCM our objective should be
to devise a system, which does not need periodic maintenance and at the
same time predict in advance possible failures/problems of the equipment. To
meet this aim we have to develop equipment which require either no or very
little maintenance and on the other hand the concept of condition based
maintenance should be implemented. Realization of this objective will result
in enhancing availability, reliability and reduction in manpower for
maintenance purposes.
4.1 In the present competitive environment, all utilities are making efforts to
reduce the O&M expenditure. This puts lot of pressure on the utilities to
minimize the outage period due to failure of equipment. This necessitates
adopting of condition based monitoring as the Need of the Hour. This has
necessitated all the power utilities to introduce condition based monitoring
for EHV class equipment so that actual condition of the equipment and its
residual life could determined. Modern techniques are available for condition
based monitoring and the concept of residual life assessment is picking up
world wide.
2
CAUSES OF FAILURES OF MAJOR SUB-STATION
Section -2
EQUIPMENTS AND REMEDIAL MEASURES
1. INTRODUCTION
This section briefly describes about the probable causes of failure of major
sub-station equipment viz. Power Transformers, Reactors, Circuit Breaker,
Instrument Transformers, Surge Arrestors etc. and remedial measures taken
to prevent such failures.
2. POWER TRANSFORMERS
Cause % of cases
Design 36
Manufacturing 28
problem
Material defects 13
Poor maintenance 5
Lightning surges 4
Short circuits 2
Components % of cases
Winding 29
3
Terminal 29
Magnetic Circuit 11
Other accessories 5
However the main causes of failure as pertaining to our country are given
below:
Table
Causes % Failures
Over-fluxing 1.2
Lightning 3.6
Unknown 7.1
4
Weakness in specification, design / manufacturing deficiency
Installation / operation / maintenance deficiency
Adverse operating conditions
Aging
Some of the failures due to defective design are listed in the table given
below.
Failure of yoke bolt Causes local short circuit in the Insulated yoke bands preferred
in insulation lamination resulting in intense local or yoke bolt insulation should
eddy currents be class ‘B’ insulation or higher.
High flux density in Causes large amount of force at time Flux density should not exceed
core of switching and repeated switching 1.9 Tesla at maximum
damage winding insulation operating voltage
Narrow oil duct in Results in improper cooling and Adequate duct from point of
winding damages insulation effective cooling
Improper Results in more loss and more heating Adjust the transpositions so
transpositions that all conductors should have
equal reactance
Clamping ring not May fail during short circuit condition Thickness of clamping ring
properly designed should be designed such as to
withstand short circuit forces
Insufficient bracing May fail during short circuit condition Strong supports are required
of leads for bracing of leads
5
Transformer manufacturing is more a craftsmanship rather than the machine
work. The reliability of the transformer depends on the quality of raw
materials and the workmanship. There are certain steps to be taken at
manufacturing stage so that apparently minus slips-ups at that stage do not
get amplified in major defects later on in service. Some of the failures due to
manufacturing deficiencies are listed in Table given below.
Loose winding and Result in interturn or interdisc Proper sizing for keeping
improper sizing short circuit winding under clamping
condition
Metallic parts left over May cause partial discharge Better house keeping to
during manufacture ensured
All metal components not Partial discharge may start All metal components are to
earthed and oil quality may get be properly earthed and this
affected is to be added in check-list
Improper drying process Winding and insulation are Extensive drying and oil
not fully stabilized due to impregnation process should
moisture leading to failure be strictly followed as per
voltage class
The quality of material used also reflects on the life of the transformers. A
rigid control of quality at all the successive stages of manufacture right from
raw material to finished product will avoid the failure in transformers. Some
of the failures due to defective material is listed in Table given below:
6
Cause Effect Remedial measure
Sharp edges in copper Produce partial discharge The surface finish should be
conductors and damage the conductor smooth
insulation
Poor oil quality Insulation failure Maintain BDV & PPM as per
manufacturer’s
recommendations
Bare copper for connection Formation of oxidation and Provide enamel coating or
sludges paper covering on bare
copper
Defective accessories
Results in transformer These accessories to be
OLTC failure procured from well
established supplier in view
of high service reliability
1. Bushings
2. Buchholz relay
3. Protective equipment
7
Poor/inadequate maintenance in the areas of oil leakage, oil quality, critical
accessories such as tapchangers, bushings, protective instruments etc. will
cause trouble in transformer. In addition to this, there are various trouble-
shooting problems encountered in the field, such as moisture, oxidation, solid
contamination, gas bubbles, overcurrent, overvoltage (transient or dynamic),
over temperatures, short circuit (mechanical forces) etc., for which sufficient
care should be taken to safeguard the transformer. Preventive maintenance is
strongly recommended to improve the reliability of transformer.
Some of the reported failures for transformers have been attributed due to
either of the following causes:
2.7 Failure of HV, LV and Tertiary Winding due to Short Circuit and Surge
Voltages
The tertiary winding provided on the power transformer are not adequately
related to provide insulation to withstand surge voltages as also not rated for
adequate short circuit stresses. Tertiary winding inter-turn insulation failures
have been found to be due to transferred surges also. Based on investigations
of failure of tertiary winding CBIP has already brought out research paper
providing guidelines for protections to be provided on loaded tertiary. As per
CBIP manual on transformers, provision of tertiary winding has now been
deleted upto 100 MVA, 3 phase 3 limbed core type construction. Special
precaution for protection of tertiary is necessary particularly in case of
capcitive/reactive loading. Frequency of switching on/off of
capacitor/reactor, distance of source from the transformer, design and
location of gapless arresters are some of the important factors which have to
be considered before loading of the tertiary. Failure of tertiary windings
generally have been experienced because of:
8
and phase to ground clearance of the leads were found to be less which
resulted into flash over and damage of insulation due to vibration and
displacement under short circuit current. Damage has taken place in some
cases due to failure of insulating components eg., insulating cylinders,
supports, permalli wood etc. The failure of joints have also been reported
while handling short circuit current. A few cases of failure of transformer on
lighting impulse have been reported inspite of protection provided by
lightning arrestors.
There have been failure transformer due to overheating of core and core
burning, failure of core insulation and core assembly getting used, slipping of
stampings and coming in contact with tank bottom. To overcome the above
problems separate provision for core earthing and core fixture earthing
through bushings provided by transformer is being resorted to. This facilitates
monitoring of core leakage current, if any, and in ascertaining that core is not
getting multiple earth and also healthiness of core board insulation.
On –load tap changers are the second largest reason for trouble in power
transformers after short circuit. The defects in OLTC are of the following type:
It appears proper care for selecting current rating of the OLTC is not
exercised by the manufacturer. Factors for efficiency of operation and
over loading capability of transformer have to be accounted for to
arrive at design current rating. The selected current rating normally
should be one step higher than the calculated value. It would be
advisable if purchaser’s technical specifications do not leave this option
to the manufacturer and current/voltage ratings are specifically
stipulated.
Quality and rating of transition resistors have been one of the main
source of problem in OLTC. Repeated incidences of burning of transition
9
resistors is an area which calls for serious attention from OLTC
manufactures.
Condenser type bushings are sent with tip portion sealed and covered by
porcelain rain shade. The bottom condenser portion is sent covered with wax
coated cotton tape. In some of the transformers these transit tapes were
found to have not been removed wqhile hoisting the bushings on the
transformer. Over a period of service, the wax melted on contact with hot oil
inside the tank and the cotton tape opened out and caused discharge inside
the tank. It is better to dispatch bushings from works with bottom portion
sealed in oil filled tanks to be removed at site at the time of erection to avoid
moisture ingress.
By adopting CAD and better shop floor management, more reliable units could
be manufactured to eliminate:
10
By adopting strict pre-commissioning test and checks possible erection
mistakes and omissions could be avoided. This list is enclosed at Annexure 2
and could be based on site experience.
Load management
Overloading
Over fluxing and over voltage
Hot joints and spark over
Frequent feeder tripping due to reflected faults
This could be avoided by periodic testing and using proper duty switch-gear
and battery.
Layout
Provision may be made for the necessary soak pit and drain pit in the
substation layout.
1. interrupting chambers
2. pre-insertion resistor chambers
3. grading capacitors
4. support column including tie/operating rods
Besides the above, the failure of breakers could also be attributed due to
following reasons:
11
Mechanical failure of operating lever
Shearing off of the locking pin of pull rod
Grading capacitor failure
Embedding of PIR fixed contact assembly into the moving contact
housing due to loosening of grub screw.
Dielectric failure inside interrupting chamber due to high moisture in
SF6 gas.
Insulation failure (live to earth) due to accumulation of moisture on tie
rod during storage.
Failure of mechanical coupling between tie rod and operating
mechanism.
Failure of actuating valves in operating mechanism.
Failure due to foreign particles (eye pieces) inside interrupter.
Failure due to high transient recovery voltage (TRV). In case of circuit
breakers switching HVDC filter banks, the normal duty of CB is opening,
the resulting TRV can be severely distorted due to presence of filters
and can severely depart from the 1 – cos wave shape which may cause
high TRV and leading to internal breakdown in grading capacitor or
interrupter.
Dielectric failure in Air Blast CBs.
Others.
The type of failures that have taken place reveals that there is urgent need to
improve manufacturing quality of various components besides, if effective
condition monitoring checks are also carried out, failures could be identified
at the incipient stage and corrective actions can be taken accordingly.
However following areas are suggested for preventive measures.
12
Mechanical endurance test for 10000 operations conducted on 400 kV
CBs.
Dynamic contact resistance measurement and tan delta measurement
of grading capacitor made as part of routine tests.
Tensile test on operating levers made as customer inspection point
Microstructure analysis of operating levers
HV test on operating rod made as 100% customer inspection point
(CIP)
Testing SF6 gas foe dew point measurement before supply
Modification of PIR Pull rod (PTFE) having better tensile strength.
Improvement in machining of contact surface of pilot valves
Nitrogen accumulators
Gaskets: Gaskets can sometime fail to do their job of forming a gas or
liquid seal but care must be exercised against excessive or unevenly
applied greasing of the gasket. Positioning of the gasket is important.
SF6 gas tightness: The possible origins and causes are various for SF 6
gas leakage, for example:
1. Corrosion near a seal can be avoided by controlling moisture
content in SF6 gas.
2. Damage of a seal
3. Impurity under a seal
4. Porosity of metal component (casting, brazing).
Preliminary failure analysis of failed CTs have revealed that most of the CTs
have failed due to pre-mature ageing of primary insulation. Besides, other
probable reasons of failure have been attributed to high system parameters
i.e. voltage and frequency, switching over voltages, lighting over voltages. To
minimize the failure of CTs following tests/checks are suggested for carrying
out at site.
Preliminary failure analysis of failed CVTs have revealed that main reasons of
CVT failures are:
13
High value of tan delta
Secondary voltage abnormal
High value of capacitance
Oil leakage
Humming sound
Besides the above following problems were also observed in one make of CVT:
14
9 Impulse withstand test Yes --- ---
Annexure 2
Checked and found all the component available at site as per Yes/No
drawing (there are no breakages and shortages)
Filtered the oil for 60 KV BD value and recorded in the erection Yes/No
register (with 22.5 mm gap on oil test kit)
Washed with hot oil (in case of other bushing of plain porcelain Yes/No
type)
15
Completed all piping work consrvator explosion vent, equalisr Yes/No
pipes etc. as per the drawing and filled with oil, Buchholz relay
checked (3º -7º incline)
Filled the radiators with 60 KV BDV tested oil. Opened the Yes/No
bottom butterfly valves provided between main tank and the
radiators after opening top air release valve to communicate
with main tank
16
diaphram
Section - 3
1.0 INTRODUCTION
1.1 This section briefly describes about the maintenance schedules, which are normally
adopted by the utilities for the various sub-station equipments. The periodicity for the
various tasks to be performed has also been specified. The test results obtained during
the maintenance activity have to be approved by the appropriate authority, which may
vary from utility to utility.
2.1 Maintenance schedules as generally adopted by the power utilities for the
various sub-station equipments are given in Annex (1-11).
Annex 1
17
g. Measurement of BDV of oil WSD Half Yearly
h. Testing of oil for DGA and other oil WSD Half Yearly
parameters
18
u. Marshalling boxes of ICT/Reactor of: SD Yearly
i) IR valve SD SOS
*Water content, BDV, SP, Resistance, Tand, IFT. Total Acidity, 2-Furfuraldehyde etc.
**First time after one year from commissioning and then once in every three years.
Annex 2
19
b. Checking of oil leaks from Grading SD Monthly
Capacitors
C. MOCBs
20
a. Checking for oil leakage/oil level WSD Monthly
E. MEASUREMENT/TESTING
F. CONTROL CABINET
21
c. Repainting of metallic surfaces (if WSD Yearly
required)
@At time of commissioning then after 6 months and one & half years of commissioning
and thereafter once in every two years.
+First time after one year from commissioning and then once in every three years.
Annex 3
A. I R MEASUREMENT
22
crack in Insulator etc.
MARSHALLING BOX
MARSHALLING BOX
23
c. Clearning of marshalling box and junction SD Yearly
box
*First time after one year from commissioning and then once in every three years.
Annex 5
A. Operating Mechanism
Maintenance of
B. MAIN CONTACTS
b. Alignment SD Yearly
24
C. EARTH SWTICH
D. MARSHALLING BOX
Annex 6
25
c. Cleaning of LA insulator SD Yearly
Annex 7
Annex 8
26
b. IR Value SD Yearly
Annex 9
Annex 10
I. LINE PROTECTION
27
A. DISTANCE PROTECTION
MICROMHO
YTG
RAZFE
LZ 96
28
Reach check for all 4 zones** WSD Yearly
SOTF check
THF Reyrolle
SOTF check
B. UNIT PROTECTION
P 40
29
Modulation threshold WSD Yearly
LBB SD Yearly
DC logic SD Yearly
REACTOR PROTECTIONS
DC logic SD Yearly
30
AUTO TRANSFORMER PROTECTIONS
LBB SD Yearly
PLCC SYSTEM
Note: The tests listed under (A) and (B) above may be carried out with out a Line SD
ensuring :-- i) Proper isolation of the relay under test
ii) The Other Main Protection of the Line is healthy and is in service
31
.MAINTENANCE TECHNIQUES FOR SWITCHYARD EQUIPMENTS
Section - 4 (CB’s, INSTRUMENT TRANSFORMERS, SURGE ARRESTORS
AND ISOLATORS)
1.0 INTRODUCTION
This section briefly covers the maintenance practices / techniques being adopted by
the power utilities for switch gear equipments installed in EHV/HV stations. However,
in the present scenario competitive market utilities are under tremendous pressure to
bring down the maintenance costs. This has led to the adoption of condition based
monitoring rather than conventional based scheduled maintenance. The frequency of
the condition-based maintenance is fixed based on the type of equipment and its
previous history. Test or measurements are carried to determine the condition of the
equipment. It is general experience of practically all the utilities that most of the
equipment don’t show any abnormality during scheduled maintenance and there is no
guarantee that the equipment shall not fail before the next schedule maintenance.
Thus, the scheduled maintenance efforts are in vain as well as costly in view of shut-
down time and manpower costs. Hence modern condition based techniques are being
adopted which are designed to continuously monitor the function parameters and also
assess the components deterioration before a mal-operation occurs.
Field staff should be able to carry out such tests and interpret the test results
Testing procedure to be evolved after detailed discussions with the supplier of
the equipment and testing equipment
Return down procedure to be made available to the operating staff
The equipment should be inspected at the regular interval as per the guidelines given
in Section 3. In addition the manufacturer guidelines should also be followed. The
general checks normally required to be done are:
32
- Silver contact surfaces if required to be cleaned, the same to be done with
soft cloth and solvent (Trichloroethane). Steel brushing or grinding is not
permitted.
- Aluminum contact surfaces should be cleaned with steel brush and emery
cloth. Afterwards, clean it with dry cloth and apply a thin layer of vaseline.
- Silvered: Cleaned if necessary, with soft cloth and solvent (tri-chloro ethane).
No steel brushing.
- Non silvered: Cleaned as silvered surfaces, can be steel brushed. After steel
brushing they shall be thoroughly cleaned from loose particles and dust.
- Lubrication: Lubricant - Grease K is applied in a very thin layer on the
surfaces of the male contact and the puffer cylinder. The superfluous grease is
carefully removed.
Emptying and refilling of SF6 gas – SF6 gas for the circuit breaker is to be
evacuated using the gas treatment equipment. SF 6 gas contained in the
electrical equipments should not be allowed vent into the atmosphere. Before
SF6 gas is removed, the quality of the SF 6 gas has to be checked. The gas after
evacuation has to be stored in a suitable vessel meeting the following criteria
- Oil free
Operational contamination should be absorbed with a suitable filter unit provided in the
gas handling plant. Filter unit should meet the following criteria:
- Desiccative in easily exchangeable cartridges for safe and trouble free disposal
33
- Inputs/outputs should be equipped with self-closing couplings in order to
avoid a saturation of desiccative by ambient air. When SF 6 gas is suctioned from
a gas compartment, the gas is passed automatically through filters which will
dry and purify the gas. Service devices has to be used by the maintenance staff
to fill re-generated SF6 from the storage tanks in SF 6 switch-gear and should
meet the following criteria:
o Oil free
o Easily handling and mobility
o Filling pressure which can be pre-set by pressure reducer. A typical block
diagram of SF6 handling plant is given below:
(Figure 1 )
o Before filling the SF6 gas, the maintenance/over hauled breaker need to
be evacuated by a vacuum pump so that SF 6 gas does not mix with
ambient air and also humidity and dust particles are removed from the
breaker. With the help of vacuum pump a final vacuum should reach
(5m Bar).
Following are some of the important condition based maintenance techniques being
adopted for assessing the condition of circuit breaker:
34
Operating timings of Main / PIR contacts
Monitoring of operating timings is basically done with a aim of finding any problem in
operating mechanism, alignment of main/arcing contacts and also discrepancy in
timing between 2 poles and/or between two breaks of the same pole. Closing timing
(maximum 1ms) and trip timing (maximum 25ms) are the most critical to be
monitored very closely. Each type of circuit breaker has different operating timings.
Initial values obtained at the time of commissioning should be taken as the base value.
Any variation / drift in the timings from the guaranteed value/base value may indicate
some type of problem with the operating mechanism or operating levers.
Precautions
Testing procedure
(Figure 2)
Make connections as per above figure. Ensure that R, Y and B phase marking
cables are connected with proper terminal with the CB (Circuit Breaker)
analyzer and maintained color Coates for all the three poles of CB.
Connection is to be made for measuring the operating timings of auxiliary
contacts
AC/DC supply to be extended to CB analyzer
35
Give closing command to closing coil of CB and note down the PIR and main
contact closing time. Obtain a print from a CB analyzer
Give tripping command to trip coil 1 of CB and note down the main contact
tripping time.
Repeat the same for tripping coil 2
Note the down the timings of various operations of CB viz. CO, OC, OCO by
giving appropriate command.
In the event of PIR opening time is required the same may be isolated from the
main break and treated as a separate contact using different channel of the
analyzer.
The permissible pole discrepancy as per IEC 56 between 2 poles should not be beyond
1/6 of cycle (3.33 ms) and between 2 breaks should not exceed 1/8 th of a cycle (2.5
ms). As per the practice followed by the most power utilities the limit for pole
discrepancy between pole to pole is of the order of 5 ms for breakers under O&M as it
is difficult to make any adjustments at site. If these timings are not within limits it may
lead to over-stressing of one particular interrupting chamber. Switching over voltage
may also be high in case of larger discrepancies in closing timings of the pole because
of presence of trapped charges in the phase of circuit breakers which is going to close
last.
Variation in the operating timing of the order of 3 ms from the base values is generally
considered acceptable. However, if these are not within the limits the same is to be
corrected by:
It is also necessary to measure the timings of auxiliary contacts from the point of view
of variations with respect to main contact. If the difference in timings of the main or
auxiliary contact is maintained within limits this reveals that there is no problem with
the auxiliary contact assembly or with the operating mechanisms or with the operating
levers of the CB.
Testing procedure
Figure 3
36
The ohm meter is employed for measurement of pumping resistance. To measure the
value, connect the leads as per above figure and adjust the varies so that
approximately 100 ampere current flow through the contacts. The value of the contact
resistance is directly displayed on the digital LED display screen. By using the 4
terminal method effects of resistance of test lead is nullified is the input impedance of
the measuring device is very high.
If the value of the contact resistance exceeds the permissible limits given in Section 7.,
this could lead to over heating of contacts. Monitoring contact resistance values is very
good techniques for assessing the condition of main contacts. Resistance values of the
order of the 100-125 micro-ohms per breaker is considered to be alright for the CB in
service.
(Figure 4 )
This another technique for measuring the contact resistance during dynamic conditions
i.e. during operations (close/trip) of CB. A DC current is injected through the CB and
the current and voltage drop are measured and the resistance is calculated. The
graphs of resistance vs. time data provide useful information on the condition of the
main contact of CB and is considered to be a modern diagnostic tool.
The variation in the measure resistance vs. time will be seen as ‘finger print’ for the
breaker contacts and can be used as reference / base value for comparing future
measurement on the same breaker. If the DCRM values matches with the pre-
commissioning /base value then the arcing contact are considered to be O.K. In case of
wide variation and also there is change in arcing contact insertion time this shows
erosion of arcing contacts. Such as situation may lead of transferring of current from
arcing contacts to main contacts and subsequent commutation failure.
37
Contact Travel Measurement
Transducers and fixtures are attached to operating rod or interrupting chamber for
measuring contact travel. When CB closes contact travel is recorded. Contact bouncing
and any other abnormality is also pointed out by contact travel measurement. If
contact travel is recorded with DCRM the length of the arcing contact shall also be
monitored. It is generally observed that after some time due to erosion of arcing
contact the tip length reduces and such condition may lead of commutation failure.
This may lead to shifting to arc to main contacts and results in faster damage of main
contacts. If contact travel, contact speed and contact restoration signature are
compared with the original signature it shall reveal problems related with the operating
mechanism, operating levers, main / arcing contacts, contact alignments etc.
6.4.3 Dew point is the temperature at which moisture content in SF 6 gas/air starts
condensing. Measurement of dew point of SF 6 gas/air is considered to be a adequate
parameter for monitoring of SF6 gas/air.
6.4.4 Measurement of dew point of SF 6 gas in a circuit breaker reveals the change in
the value of dielectric properties of SF6 gas. Dielectric properties of SF6 dew get
changed with time due to mixing of impurities like moisture, decomposition products of
SF6 gas viz. hydroflouride lower valence sulphur fluorides etc. The ingress of moisture
in SF6 gas after filling in CB and during O&M could be due to:
Sulphur oxifulorides, hydrogen fluorides and H 2SO3 formed during these reactions
attack the materials containing silicon-dioxide (SIO 2) viz. glass / porcelain. Primary and
secondary decomposition in the presence of moisture forms corrosive electrolytes
which may cause damage and operation failure.
38
Testing procedure
(Figure 5)
Make the connection to the kit from circuit breaker ensuring that regulating valve is
fully closed at the time of connection of the dew point kit. Regulate the flow rate of SF 6
(0.2-0.5 L/minute) as per IEC 480, the value of the dew point is observed till it
becomes stable.
Note.: If the regulating valve is provided at the outlet of the dew point kit then dew
point value for rated pressure are to be monitored.
The discharge of moisture from the organic insulating material is faster initially and the
rate of release becomes almost negligible after 4 to 5 year of commissioning, and
thereafter moisture entry in the CB is through permeation. Recommended frequency of
dew point measurement is as given below:
Dew point of SF6 gas varies with the pressure due to the fact that saturation vapor
pressure decreases with increase of SF 6 pressure. Dew point of SF 6 at higher pressure
is lower than the dew point at atmospheric pressure. Table given below give the value
of dew point at rated pressure and at atmospheric pressure for various makes of CBs.
Dew point at
Dew point at rated Atmospheric
Sl.No. Make of CB pressure (Min. º Pressure Remarks
C) (limit) (Min º
C)
39
At the time of
-15 - 36
commissioning
1. BHEL
-7 - 29 During O&M
-5 - 27 Critical
At the time of
-- - 39
commissioning
2 M&BG
-- - 32 During O&M
At the time of
- 15 - 35
commissioning
3 CGL
- 10 - 31 During O&M
At the time of
- 15 - 35
commissioning
4 ABB
-5 - 26 During O&M
At the time of
-15 -36
commissioning
5 NGEF
-7 - 29 During O&M
-5 - 27 Critical
The dialectic properties / arc quenching properties of dry air do get change with the
aging of CB and quality of air deterioration if moist air travel to the interrupting
chamber. This will lead to deterioration of internal insulation and resulting in
unsuccessful arc quenching. It is therefore necessary to carryout measurement of dew
point of air in ABCBs. The permissible limits of due point of ABCB is given in Section 7.
40
Figure 6
Testing procedure
Where T0 = 20° C
(if the value is between .05 and 0.3 it considered as questionable conditon.
Value of more than .03 is a sign of alarming condition)
2. Deposit of surface moisture can have significant effect on the surface losses and
consequently on the results. With a view to minimizing the errors the
dissipation measurements may be made when the weather is clear and sunny
and the relative humidity is less than 80%.
3. Surface leakages – Any leakage over the insulation surfaces of the specimen
will get added to the losses in the insulation and make a fake impression about
the condition of specimen. It is recommended that surfaces of insulation should
be cleaned and dry when taking a measurement.
41
4. Electrostatic interference – In the energized switch yard, readings may get
affected by electrostatic interference current resulting from the capacity
coupling between energized line and the bus work to the specimen. To
overcome this all the jumpers connected need to be opened when taking a
measurement. In the modern automatic testing kits the effect of interference
gets nullified due to presence of interference suppression circuits.
Dialectic strength of insulation decreases with the increase in the moisture content. At
high temperature is pushed out of the paper insulation with oil. As insulation cooled
down water starts migrating from oil into paper. The time for temperature drop may be
faster as compared to water returning to cellulose material. Depending upon the
condition the dissipation factor also changes.
An increase in the value of tan delta indicates the deterioration of cellulose insulation
whereas increase in both tan delta and capacitance reveals entry of moisture in the
insulation.
Ambient temperature
At 20 degree C the value of tan delta should not be more than 0.007. In the present
testing kit available the software is available to give the test results at 20 degree C and
also at rated frequency irrespective of the measurement being made at some other
temperature.
Vibration Measurement
Mechanical vibrations experienced during closing and tripping operations are recorded
with the help of accelerometer and data acquisition system. The same fingerprints are
compared with the reference signature, which have been recorded at the time of pre-
commissioning. Any change in the recorded patterns could be attributed due to any
mechanical malfunctions, excessive contact wear, misalignments of contacts, problems
in damping systems. For a measurement of recording of vibration pattern 2 or 3
accelerometer are installed externally in each phase usually one on arching chamber,
one in operating mechanism and one somewhere in-between.
Besides the above mentioned condition based techniques, the other techniques
adopted includes – monitoring of trip / close coil current, coil current measurement,
SF6 gas/air leakage test rate and operating mechanism medium oil/air pressure.
Friction in the plunger movement gap between the plunger and the pin of the coil
assembly are reflected in the recorded current values / wave shapes. Leakage rate of
42
SF6 gas indicates healthiness of the ceiling system, O ring and strength of cementing
joints. SF6 gas leakage upto 1% per annum is considered to be within acceptable
limits.
Operation Lockout Checks for CB Following operation lockout checks are carried
out:
Pump start/stop
CB auto re-close lockout
CB closing lockout
CB operation lockout
a )SF6 gas pressure lockout: All the SF6 gas pressure switches settings should be
checked and corrected with ambient temperature. Settings of SF6 gas pressure
switches should be within + 0.1 bar/Kg/cm2 of the set value (after taking into account
the temperature correction factor).
b) Air pressure lockout: All the air pressure switches settings should be checked and
corrected and should be within + 0.1 bar/Kg/cm2 of the set value.
c) Oil pressure lockout: All the oil pressure switches settings should be checked and
corrected and should be within + 0.1 bar/Kg/cm2 of the set value.
Instrument transformers are generally the most reliable EHV network equipment.
However, violent failure/blasting due to primary insulation of instrument transformers
may lead to considerable damage to nearby equipments and O&M personals. In order
to avoid violent failures following maintenance techniques have been adopted like
measurement of tan delta and capacitance, insulation measurements, DGA monitoring,
recovery voltage measurement etc.
1. Testing mode for CTs: CTs provided with test steps have to be tested in UST
mode whereas CT with test step are to be tested in GST mode. Before carrying
out the test it may be ensured that jumpers are disconnected and CT/CVT
porcelene housing / insulators are thoroughly cleaned.
2. Testing mode for CVTs: HF panel and neutral terminal of EMU transformer are
to be disconnected and isolated from ground before carrying out the test. The
testing kit which is similar as used for grading capacitors for CB is to be
43
connected between HV/HF points and measurements are done in UST mode. In
the event of test values deviating from the base values, individual capacitor
stacks are to be tested in UST mode.
HV terminal of the tan delta kit should be connected to HV (primary) terminal and LV
terminal should be connected to ten delta test tap.
HV terminal of the tan delta kit to be connected to the HV (primary) terminal and LV
terminal to be connected to the ground/earth.
Figure 7
Connect the megger as shown in the figure. Connect the HV terminal to the primary
terminal of CT by using crocodile clip for firm grip. The measurements may be made as
per the procedure prescribed by the supplier of the kit. A test voltage as specified is
applied as per the above connections and successive readings are taken. Values of IR
should be recorded after 15, 60 and 600 seconds. Ambient temperature and weather
conditions are also to be noted. It is advisable to carry out measurement during sunny
and clear weather.
44
Variation from normal IR value indicate abnormal conditions such as presence of
moisture, dirt, dust, crack in insulation of CT and degradation of insulation.
Analysis of IR values
Conduction current
The steady straight value of the current after a DC voltage is applied to the capacitor is
known as conduction current. Conduction current is directly affected by temperature,
humidity, contaminants and voltage stress. In a solid insulating material which have
absorbed moisture, there will be a non linear larger increase of conduction current for
increase in the voltage stress.
Test is carried out at 5 kV DC voltage. Any variation with respect to base value indicate
problem in CT insulation.
Polarization index (IR60/IR15) and dialectic absorption ratio (IR 600/IR60) are calculated
and these ratios should be more then 1.5 for good quality insulation. However, exact
values depend on the type of insulation and may vary for different type of equipment.
Testing procedure
After ensuring, necessary precautions have been taken, connect leads of O meter
between different terminals of CT secondary course. Select the range of O meter as
per pre-commissioning / factory test results. Following precautions are considered
essential:
Value of secondary winding resistance should be within the acceptable limits. Extreme
low value of resistance indicates turn-to-turn shorting, whereas, if the value is high it
indicates some loose connection which has to be identified and tightened before
repeating the measurement.
45
DGA monitoring
Due large number of failures of CTs, DGA monitoring has been recently introduced for
checking / assessing the health of insulation of CTs. In this monitoring different
dissolved gases like H2, CH4, C2H6 etc. are tested. DGA results are analysed as per
IEC-60599. It is being proposed to do DGA monitoring on three yearly basis. This shall
require special arrangement for oil sampling as well topping of oil when oil levels falls
down.
N2 pressure monitoring
Some of the CTs are provided with N2 cushion at the top of the CT to avoid ingress of
moist air from atmosphere during normal contraction/expansion of oil due to change in
temperature (due to load or ambient variations). N2 pressure is to be maintained at
about 0.30 to 0.50 bar above atmosphere hence monitoring of the same is very
important. In case of leakage of N2 gas, CT will breathe with atmospheric air moisture
may enter in CT oil/paper insulation. This moisture entry will lead to
abnormal/accelerated ageing of the insulation and may even cause pre-mature
insulation failure.
Testing procedure
After making proper connections apply voltage is increased from zero to rated Knee
Point Voltage in steps of 25%, 50% 75% and 100%. Measure the current the drawn by
the CT secondary core at respective applied voltage and record the test results as per
the prescribed formats.
Knee point voltage is normally defined as the voltage at which 10% increase in the
applied voltage causes 30 to 50% increase in secondary current. The magnetization
current at rated Knee Point Voltage should not be more than the specified/designed
value.
A curve can be drawn between applied voltage and magnetizing current. From the
magnetizing curve it can be implied that up to rated KPV (knee point voltage), the VI
curve should be almost a straight line. However, if this line is not linear, this indicates
that the magnetizing characteristics are not desirable. If the slope of the curve starts
increasing it indicates that magnetizing induction becomes low and total primary
46
current is utilized in exciting the core alone. Consequently, output of CT secondary
disappears.
Presently the monitoring of total leakage current (capacitive and resistive currents) is
being used by many utilities. Leakage current monitors are permanently connected
with the surge arrestors, and in case of high leakage current surge arrestors are
removed from surge arrestors. However, it is felt that this method is not the fool proof
method as the total leakage current, which is purely capacitive, does not give precisely
the health of the surge arrestors. There have been the cases when the surge arrestors
have blasted even though total leakage current value was below the limit prescribed by
the manufacturers. Recently, another monitoring method for monitoring the health of
the surge arrestor have been introduced wherein measurement of resistive current is
done which indicates degradation of ZnO / SiC disc. This method has been prescribed
in IEC 60099 (5). Resistive current is current is 15-30% of total current and since
capacitive and resistive currents are at 90 degree face shift even considerable change
of resistive current results in very small increase in the total current. Hence monitoring
total leakage current may not truly indicate the degradation of ZnO disc. Degradation
of long linear ZnO disc generally leads to harmonics in the leakage current when
system voltage of fundamental frequency is applied. Third harmonic resistive current
measurement is based on filtering of third harmonic component from the total leakage
current. Leakage current of the order of about 500 micro amps is generally considered
to be safe.
The resistive part of the leakage current or the power loss can be determined by
several methods given below:
The method relies on using a reference signal representing the voltage across the
arrester. The reference signal can be used for direct reading of the resistive component
of the leakage current at the instant when the voltage is at its peak (dU/dt=0). The
voltage and the resistive current level can be read with an oscilloscope or similar
device. This method is commonly used in the laboratory for accurate determination of
the resistive current since the reference signal is easily accessible through a voltage
divider having a sufficiently small phase-shift.
In practice, the accuracy is limited mainly by the phase-shift of the reference signal
and by the deviations in magnitude and phase of the voltage across the non-linear
metal-oxide resistors at the earthed end of the arrester. The presence of harmonics in
the voltage may further reduce the accuracy of the method.
A restriction on the method during measurement in service is the need for a reference
signal. Temporary connection to the secondary side of a potential transformer or to the
capacitive tap of a bushing is necessary and may be complicated to obtain. The
capacitive currents induced in the earth connection of the arrester by adjacent phases
may reduce the accuracy during measurements in service.
By using a voltage signal to compensate the leakage current for its capacitive
component, the sensitivity in the measurement of the resistive part may be further
increased. The basic principle is a HV bridge where the capacitive-resistive arm is
47
adjusted to balanced the capacitive component of the leakage current so that only the
non-linear resistive part contributes to the output voltage, which can be studies with
the help of an oscilloscope.
The bridge is balanced when the voltage is close to zero and with the capacitive
current being at its peak. Since the differential capacitance of the arrester is voltage
dependent (the capacitance is constant, the remaining current after compensation
comprises not only the resistive component, but also a capacitive part. In this method
also the accuracy may be reduced by phase shifts in voltages and currents due to the
influence of adjacent phases.
This is a compensation method where the need for a voltage signal is eliminated. The
basic principle is that a reference signal of fundamental frequency is created
synthetically by means of information derived from the leakage current. By proper
adjustment of the amplitude and phase angle, which can be done automatically or
using an oscilloscope, the reference signal can be made to compensate the capacitive
component of the leakage current. The method can be implemented with different
degrees of sophistication.
This method can readily be utilized for measurements in service. A potential problem is
the presence of harmonics in the voltage, which cause harmonic capacitive currents
that may interfere with the resistive component.
The method is based on the assumption that the capacitive currents are canceled if the
leakage currents of the arresters in the three phases are summed. The resulting
current is composed of the harmonics of the resistive currents from the three
arresters, since the fundamental components are also canceled as long as they are
equal in magnitude. If there is an increase in the resistive current of any of the
arresters, the capacitive currents remaining constant, the increase will appear in the
summed current. A voltage reference signal is not needed.
For measurements in service, the main disadvantage with the method is that the
capacitive currents of the three phases are not generally equal. Another concern is the
influence of harmonics in the system voltage, which will cause harmonics in the
summed current.
The method is based on the fact that harmonics are created in the leakage current by
the non-linear voltage-current characteristic of the arrester. No voltage reference is
needed since it is assumed that all harmonics arise from the non-linear resistive
current. The harmonic content depends on the magnitude of the resistive current and
on the degree of non-linearity of the voltage-current characteristics.
The third harmonic is the largest harmonic component of the resistive current, and it is
the most commonly used for diagnostic measurements. The conversion from harmonic
to resistive current level, if required, relies on information supplied by the arrester
manufacturer or from measurements in the laboratory.
The method can be readily used for measurements in service. The main problem is the
sensitivity to harmonics in the system voltage. The harmonics in the voltage may
48
create capacitive harmonic current that are comparable in size with the harmonic
currents generated by the non-linear resistance of the arrester. As a result, the error in
the measured harmonic current may be considerable. This is shown in Figure -, where
leakage current is given as function of the third harmonic content in the system
voltage. The figure includes the effects of different voltage-current characteristics and
capacitances, as well as the influence of the phase angle of the third harmonic in the
voltage. It is seen that 1% third harmonic in voltage may give + 100% measuring
error in the current.
Figure---------
Third order harmonic analysis with compensation for harmonics in the voltage
The method is based on the same principle as mentioned above, but the sensitivity to
harmonics in the voltage is greatly reduced by the introduction of a compensating
current signal for the capacitive third harmonic current in the arrester. The
compensating current signal is derived from a "field probe"L positioned at the base of
the arrester. After proper scaling, the harmonic current induced in the probe by the
electric field in subtracted from the total harmonic current. The result is the harmonic
current generated by the non-linear resistive current of the arrester. The conversion
from third harmonic to resistive current if wanted requires additional information from
the arrester manufacturer. The method is suitable for measurements in service and is
described in more detail below.
The power loss is the integral of the product of the instantaneous values of the voltage
and leakage current divided by time. The power loss may be expressed in terms of the
product of the r.m.s. value of the resistive component of leakage current and the
r.m.s. value of the voltage across the arrester. The influence of the harmonics in the
voltage is greatly reduced by the multiplication and integration procedure. The main
disadvantage is the need for a voltage signal. The accuracy during measurements in
the service may be limited by phase shifts in voltages and currents, caused by the
adjacent phases.
The use of modern diagnostic techniques means generally increased service reliability
and cost savings for the electric power industry. It is therefore desirable to check the
condition of surge arresters at regular time intervals, by measuring the resistive
component of the continuous leakage current in service without deenergising the
arrester. Reliable measurements are achieved by introduction of a field probe as
illustrated in Figure -, which allows a compensation for the harmonic currents
generated by the harmonics in the voltage.
The leakage current monitor system is used for gap less metal oxide surge arresters
and is connected to the arrester as illustrated in Figure-. It consists of three main
parts:
49
A current probe attached to the connector of either a clip-on current
transformer or a toroid-transformer in case of permanent installation.
A field probe positioned near the base of the arrester to pick up the capacitive
current component, is connected to the current probe via coax cable and an
adaptor. A telescope rod of insulating material is used to locate the field probe
at the correct position
A leakage current instrument, using harmonic analysis of current and field
probe signals to determination of the resistive component of the leakage
current.
Testing procedure
1. ZnO surge arrester continuously conducts a small leakage current Figure-. The
resistive component of this leakage current may increase with time due to
different stresses causing ageing and finally cause arrester failure.
2. The value of third harmonic resistive current shall depend on type and make of
surge arrester. A value of 500 micro-ampere is considered to be safe limit for
third harmonic resistive currents based on technical papers/reports (IEEE etc.).
3. While monitoring third harmonic resistive current, temperature and voltage
correction factors are to be applied because leakage resistive current also
depends on these factors apart from ageing of the arrester discs. These factors
shall be circulated to sites after receipt from suppliers. For the time being as far
as possible, measurements should be carried at temperature from 30 to 30
degree centigrade.
4. Effect of Harmonics in the system voltage: If harmonics are present in the
system voltage, it shall effect the value of the measured third harmonic current
since it shall introduce capacitive third harmonic current in the total current. By
using suitable compensating device, the effect of harmonics in the system
voltage can be nullified.
50
Following test may be carried out for determining the health of battery/battery
charger.
a) Battery
b) Battery charger
51
Firing card factory/replace with new card
4. Output voltage - problem in control - Check amplifier card for reference level
shooting high card and comparator output as per description
in auto mode given below.
2. Firing card
3. Amplifier card
4. Current limit indication card
5. Pulse card
6. Over current/over voltage card
Various maintenance test required to be carried out are normally done as per suppliers
guidelines. However various equipments required for conducting the test are covered
in Section 8.
F. Protective Relays
Testing requirements
52
2. Portable test equipment for testing distance relays comprising supply
unit, control unit and fault impedance unit. Suitable for AC voltage from
380-440 V, three phase, 3 wire system 20 Ampere (short time rated)
with built in safety devices.
Automatic test kits
2. It shall include all the accessories required for making the complete test
set up.
3. It shall have three phase current output range 0-30 amps. (rms) and
three phase voltage range 0-110 voltage (PH-G).
4. It shall work on single phase 240 V, 50 Hz + 10% SUPPLY
5. Shall include necessary software and hardware
i)1 % for voltage and current output and resolution of time measurement of 1 ms or
better
INTRODUCTION
53
The acceptable / permissible limits for values obtained during maintenance test results
as discussed in the earlier section in respect of sub-station equipment which are
considered safe is given in Annexure 1, 2, and 3.
Annexure 1
1. Transformer/Reactor
a) BDV
- At the time of first charging 600 kV (Gap – 2.5 mm) – Minimum IS – 1866
b) Moisture content
60 Microns (Average)
54
C
2. Circuit Breakers
D) PIR time
55
F) Pir and main contacts overlap 5 MS (Min.) – at rated pressure
time [BHEL, M&G, ABB
(imported) make CBs]
K) IR value:
3. Current Transformers
A) IR value
56
3. Control cables 50 M-Ohm (Min.) by 0.5 kV Megger
D) IR Value
57
F) CVT voltage ratio errors + 5% protection cores IEEE/C93.1.1990
5. Isolators
C) IR value
6. Surge Arrester
7. Miscellaneous
B) Thermovision scanning
58
D) IR values
8. Batteries
*Temperature correction factor for measured values of Tan Delta to be applied which given
in Annexure&ldots;&ldots;&ldots;&ldots;.
1 10 0.8
2 15 0.9
3 20 1.0
4 25 1.12
5 30 1.25
6 35 1.40
7 40 1.55
8 45 1.75
59
9 50 1.95
10 55 2.18
11 60 2.42
12 65 2.70
13 70 3.00
If Tan Delta of bushing/winding/CVT/CT is measured at oil temperature T Deg. C. Then Tan Delta at 20 Deg.
C shall be as given below:
Annexure 2
At the time of
1. BHEL -15 -36
commissioning
-5 -27 Critical
At the time of
2. M&G -- -39
commissioning
At the time of
3. CGL -15 -35
commissioning
60
At the time of
4. ABB -15 -35
commissioning
At the time of
5. NGEF -15 -36
commissioning
-5 -27 Critical
Note: Dew point of SF6 gas varies with pressure at which measurement is carried
out. So it is to be ensured that if measurement is done at pressure other than
atmospheric pressure, it needs to be converted to the atmospheric pressure as given
below.
1.0 INTRODUCTION
The testing and maintenance equipment covered in this section are generally meant
for carrying testing and maintenance at site and shall be complete with all material and
accessories. These shall be robust in design, so that they give accurate results even in
adverse site conditions.
All equipments shall be of reputed make, type tested, and shall be subjected to
acceptance and routine test in accordance with the requirements stipulated under the
respective equipment specification.
61
2.0 NEED FOR SELECTION OF TESTING EQUIPMENT
Most of the testing equipment don’t give satisfactory performance under induced
voltage conditions. Tan delta/capacitance measurement and winding resistance
measurement kits etc. very often don’t give stable readings. In case of tan delta
measurement it is very difficult to carry out these measurements specially in GST,
GSTg modes or if capacitance value is low say 100 pF.
It is generally seen that testing equipments, which are required to be transported from
one sub-station to another sub-station, don’t work as desired.
Out put of testing equipments is not consistent and when measurements are repeated,
same test results are not achieved.
After sales-service
Supplier of testing equipment generally have tendency to "Supply and Forget It’ and
don’t provide adequate after sales service. In case of imported kits, Indian agents are
frequently changed and there is always a problem of after sales service.
Lead length
For out-door testing it is generally found that supply lead length is not adequate and it
becomes difficult to carry out measurements.
Some of the main testing equipments required for switchyard maintenance are given
below:
62
CT secondary injection kit
Earth tester
Insulation tester
LA leakage current analyzer
Clamp – on meters
BDV-on meters
BDV kit for oil
Other test kits like single/three phase varic etc.
Electrostatic interference
Technical requirements
It is very essential to specify technical requirements, which are actually needed for site
testing. It is generally observed that utilities do not specify such requirements and it
results in procuring instruments which may not be useful at the site. In the technical
specifications we should specify both functional and general requirements. Under
functional requirement we have to specify range, accuracy and resolution and sampling
frequency. For general requirements the following parameters may be specified.
CB operation analyzer
Accuracy and resolution of operating timings and contract travel are to be specified
correctly for achieving this CB analyzer should have a resolution of ± 0.1 ms in respect
of operating timings and a resolution of ± 1mm for contract travel. For both this a
sampling rate of 10 Kz is required.
As per IEC the following are the 2 techniques for measurement of dew point of SF 6 gas.
63
1. Direct method using dry ice and acetonel/methyated sprit: This gives a direct
reading but availability of dry ice at remote site is a problem. Besides,
measurement accuracy varies with the operator as it requires human skill for
correct measurement. Hence, this method is not preferred.
2. Indirect method based on capacitance/impedance measurement: The
principle involved in this method is change in capacitance or impedance of
the sensor changing with moisture content of SF6 gas. Connecting pipe
should be made of PTFE or having stainless steel. Flow rate as per IEC has
to be maintained.
The kit to be procured should be suitable for working under induced voltage conditions.
The kit should be field test before deciding about the procurement. It may be ensured that
HV led is double shielded and LV led single shielded.
3rd harmonic leakage current analyzer for surge arrestors: Two methods available are:
Lead length:
Proper selection of cable, proper size for carrying current and adequate length is very much
essential.
64
mechanical stress or other environmental conditions and certain combination of these
conditions and
b) Ability to withstand storage and transport. Some of the requirements are given
below:
Parameter Number
Vibration 5-95 Hz
- Range
- Accuracy
- Resolution / sampling frequency
The equipment offered shall be suitable for on line dissolved gas monitoring required
for detection of incipient fault in oil filled electrical equipment i.e. transformers and
rectors. The equipment shall at least respond to dissolved gases such as H2, CO,
C2H2, & C2H4 in transformer oil.
The equipment shall have suitable sensing device to accurately detect and measure the
hydrogen equivalent of H2, CO, C2H2, & C2H4 in oil filled electrical equipment. The
sensor assembly shall be robust in design shall be suitable for operation in tropical site
condition and complete in all respects. The sensor assembly shall be suitable for
connection to any transformer and reactor in service and bidder shall provide
necessary adapter/fittings required for this purpose along with the sensor assembly.
The sensor assembly shall be rated for oil temperature range from 10 Deg. C to 100
Deg. C and give accurate detection of dissolved gases. Supplier shall provide
recommended location of fixing sensor assembly in the transformer and reactor.
The equipment shall be provided with a digital display unit to indicate the dissolved gas
concentration level in ppm. The digital display shall be provided in such a way that it is
suitable for reading from ground in day light and should be used in a dust and weather
65
proof enclosure as per IP55 in accordance with IS: 2147. Connection from sensor unit
shall be provided to display unit by weatherproof-shielded cable. Suitable provision
shall be made at the display unit to give alarm and trip signal at the Owner’s control
panel housed in control room. Any special cables (other than normal shielded PVC
control cable) if required for connection between control panel and display unit shall be
supplied by the supplier. Supplier shall also furnish sufficient literature along with their
recommended gas level for setting of alarm and trip contacts.
The equipment shall also have RS-232 port for down loading data to purchaser’s PC.
The suitable software in Windows environment shall be supplied.
Detection & measurement H2, CO, C2H2, C2H4 with sensitivity of 100%
of gas of H2.
Accuracy + 10%
The supplier shall also supply a suitable calibration equipment for calibrating the on
line dissolved gas monitoring system.
The equipment offered shall be of reputed make such as Syprotec, Canada (Hydran
20IR), Morgan Schaffeur, mocromonitors or equivalent.
As per ISO – 9001, calibration certificate of each instrument shall be supplied along
with the test kit at the time of supply.
General
66
The equipment offered shall be suitable for dissolved gas analyzer of a small quantity
of insulating mineral oil of oil filled electrical equipment such as transformers, reactor,
instrument transformers, bushings etc. The equipment shall be robust in design and of
portable type so that the same can be used at site conditions. The equipment shall at
least be able to analyse H 2 and CO in oil. The equipment offered shall consist of oil
sampling device, oil collecting bottles, sensing device, display unit etc. and shall be
complete in all respect to carry out on the spot dissolved gas analysis at site.
The sensing device of the equipment shall be suitable for accurate detection and
measurement of hydrogen equivalent of H2 and CO. The sensor assembly shall be
rated for oil temperature range from 10° C to 50° C and give accurate detection of
dissolved gases.
The display unit shall be of digital type and shall indicate the dissolved gas
concentration level in ppm.
A suitable device such as syringe required for collecting oil from the electrical
equipment and the oil storage bottles (at least 5 No.) shall be made of unbreakable
material. These devices shall be suitable for handling oil in temperature range from
10°C to 100°C.
Accuracy ± 10%
Repeatability ± 2%
67
Micro-processor based Gas Chromatograph
General
Power supply
Compatibility
ASTM - D3612 - 77
Mainframe
Complete with injection part, columns, oven, detector gas flow regulation and
measurement system, related electronic and battery back up for a minimum of half an
hour power interruption. Suitable accessories such as sampling syringe, drier, oven
etc. shall be provided.
Columns
The standard system should have 3 columns and appropriate automatic valve
switching to provide rapid determination of the following components:
H2 (Hydrogen) Benzene
O2 (Oxygen) Toluene
C3H6 (Proplyene)
C3H8 (Propane)
68
Recorders
A suitable chart recorder with full range of 10 mv or less. A maximum full scale
balance time of 2 sec. And minimum chart speed of ½ inch/min. (time programmable).
Detectors
Note: Any other detector suitable for the above application may also be quoted.
Integrator
A suitable integrator to integrate all the component peaks precisely matching the
detectors sensitivity. Display or results shall be directly in ppm on PC screen
compatable H/w with RS – 232 interface shall be provided.
The instrument shall be equipped with suitable facilities to provide a flow of carrier gas
through columns at a flow that is constant to 1% throughout even during temperature
programming.
Reference gas shall be supplied in four standards (in ppm) for calibration as given
below:
69
H2 50 150 500 2000
These shall be supplied in pressure cylinders in sufficient quantity for atleast to last 2
years or 1000 samples/instrument. Reference gases for benzene, toluene,
ethybenzene, xylene etc. shall be provided for 3 years or 1000 samples/instrument.
Accessories
Gas extraction apparatus as per IEC 567 ASTM method D2995-71 (ASTM standards,
Vol. 40). Guide for sampling of gases of oil from oil filled electrical equipment and for
the analysis of free and dissolved gases. Any other accessories required for
independent operation of the equipment.
Spares
Operational manual
6 copies
Service manual
6 copies
Other requirements
General
The instruments shall be used for testing of EHV transformers/reactors in the charged
switchyard (upto 400 kV AC and 500 kV DC) and facility to store data ana analyse the
data on PC.
Functional requirements
70
Excitation current/power
Insulation resistance
Winding resistance
Transformer turns ratio
General requirements
1. The instruments shall contain all standard accessories including testing lead of
20 meters with wuitable clamps/connectors and carrying case.
2. The instrument should have been proved for repeatability of test results in
charged switchyard conditions. Documentary evidence for this should be
furnished along with the bid in the form of certificate.
3. The kit should be capable of operating and storing data at temperature from 0-
50 ° C and humidity 10 to 100%.
4. Functional requirements for parameters as mentioned above, shall be achieved
with the help of one or more instruments. Software suitable for operating on
windows 95 for data storage and comparison of past data for operating on
purchasers PC shall be supplied.
5. Input supply of the kit shall be AC 230 Volts, 50 Hz, variations ± 15% and 5%
in voltage and frequency respectively.
6. The kit shall be compatible for electromagnetic and electrostatic environment
arising out of equipments charged at 400 kV/800 kV.
7. For tan delta, capacitance and winding resistance measurement /turns ratio
readings shall be displayed automatically. It shall use 4 wire method and shall
withstand induction kicks for transformer/reactor windings. Kit shall have
transformer winding/core discharge facility.
8. The testing kit shall be suitable for measuring capacitance and tan delta of bus
and line CVTs, grading capacitors of CBs, CTs, transformer and reactor windings
and bushings successfully in charged upto 420 kV swithyard.
9. As per ISO- 9001 calibration certificate shall be supplied with each instrument
at the time of supply.
71
The unit shall have motorized drive to increase voltage linearly as per the rate
specified in IS:6792. Provision should also be available for manual increase of
voltage. The unit shall be complete with test cell, stirrer and "GO" and "NO GO"
gauge for adjusting the gap.
The equipment shall be suitable for operation at 240 volts 50 Hz. Single-phase
AC supply.
Accuracy ± 0.1%
Following test will be conducted in addition to all
Acceptance test routine tests as per relevant standards.
Dielectric test
I.R. measurement
Functional test
Verification of calibration
72
Make The equipment offered shall be of reputed make
preferably Tettex (2791) or equivalent
This portable equipment is required for measurement of vibration and noise level of
transformers, reactors and other machinery at shops and sites in line with IEC, ISO or
other international standards. Equipment shall have provision for fixing of vibration
probes for vibration readings and will meet the following requirement.
Range
Sensitivity
73
Environmental condition Temperature – 15 ° C to 50 ° C
Standard accessories
Technical requirements
Ambient temperature 0 to 50 ° C
74
Leather carrying case The instrument shall be supplied with 2 meter long
mains lead and leather carrying case.
Test requirement
Type of test certificate for all ten tests as per C1.11.1 of IS:2992
General
This instrument shall be used for testing of EHV circuit breakers (up to 800 kV) in the
charged switchyard (800 kV AC and 520 kV DC). Data shall be stored and analysed on
PC with software to be supplied by the manufactuer/supplier.
Functional requirements
1. Main contacts timings: the kit shall measure operating timings of CBs from 0 to
1500 msec in multiple ranges with an accuracy of ± 1 msec, resolution of ± 1
msec and minimum sampling rate at 10 KHz.
2. Contact travel: The kit shall record the contact travel from 0 to 500 mm with an
accuracy of ± 0.1 mm.
3. Contact speed: The kit shall record the contact speed ranging from 0 to 10
m/sec with an accuracy of ± 1%.
4. Dynamic contact resistance: The kit shall record dynamic contact resistance of
main/arcing contacts ranging from 0 to 2000 micro-ohm with an accuracy of ±
2% of the measured value.
5. Static contact resistance: The kit shall be used to measure contact resistance of
main contacts ranging from 0 to 1000 micro-ohm with an accuracy of ± 1%.
75
6. Trip/closing coil currents: The kit shall be able to record trip/close coil currents
ranging from 0 to 25 amp with an accuracy of 2%.
General requirements
1. The instruments shall contain all standard accessories including testing lead of
20 meters with suitable clamps/connectors and carrying case.
2. The instrument should have been proven for repeatability of test results in
charged switchyard conditions. Documentary evidence for this should be
furnished along with the bid.
3. The kit should be capable of operating and storing data at temperature from 10
° C to 50 ° C and humidity 10 to 99%.
4. The notebook PC Pentium 166 MHz – or above with Windows – 95 software
(latest version), 16 MB RAM, 2 GB hard disc storage, 1.44 MB floppy drive, CD
ROM drive, inkjet printer, FAX/Modem shall be supplied along with test kit. The
software supplied along with the kit should have facility to display and generate
reports in graphical and numerical formats and compare results obtained at
different times.
5. The kit should have facility to get hard copy through plain paper printer by
directly connecting printer to Test Kit.
6. Travel adapter and transducers along with the various clamps to suit all
400/220/132 kV CB models/types available in (BHEL, M&G, CGL, NGEF, HBB,
ABB, COGLEX make) shall be supplied with each test kit.
7. The functional requirements as mentioned above can either be achieved with
one or more kits. In case of more than one kit, facility shall be there to co-
relate various parameters. Necessary interface cards shall be supplied along
with the kit.
8. Input supply of the kit shall be AC 230 Volts, 50 Hz, variations ± 15% and 5%
in voltage and frequency.
9. The kit shall be compatible for EMI/EMC environment.
General
The equipment should be microprocessor based for measuring the resistance of circuit
breaker and bus-bar joints. The system should incorporate built-in software to carry
out different tests and store the results. There should be provision for connecting a PC
to the equipment so that test results could be analyzed further. The design of the
equipment should enable quick demagnetization of CT after testing breaker. An AC
output should be available in this regard.
Technical requirements
No load voltage 9 V DC
76
Measurement range 0-200 micro ohm.
Operating temperature 0 to 50 ° C.
Protection via miniature circuit breaker, thermal fuse should be available. Manufacturer
should supply a robust transport case and operational manual along with the
equipment.
The meter shall be capable of measuring the dew point of SF 6 gas of the circuit
breaker, nitrogen gas, air etc. in transformer tank. It may be a moisture
measuring device to know the dew point temperature of SF 6 gas, Nitrogen gas,
air, etc. It should be portable and adequately protected for out door use. The
meter shall be provided with dew point hygrometer with digital/analog
indication unit to display the dew point temperature, corresponding to pressure
at which the dew point is being measured.
The calibration and measurement of the instrument must be simple, direct
without the use of any other material/chemical like dryice/acetone etc. it should
be battery operated with rechargeable batteries.
The SF6 gas leak detector shall meet the following requirements.
The detector shall be free from induced voltage effects.
The sensing probe shall be such that it can reach all the points on the breaker
where leakage is to be sensed.
77
The capacity of this plant shall be such that it shall not take appreciable time for
filling or evacuating the breaker. The required vacuum for complete evacuation
shall be attained with the help of this plant
This shall include all the necessary devices for measurement of purity, moisture
content, decomposition products etc., of SF6 gas. Mixing with air/oil/moisture
during the above process should be proved to be Nil during testing. The storage
capacity of the reservoir should be sufficient for storing complete SF6 gas for at
least one 420 kV vircuit breaker (3 poles) or 105 kg whichever is higher.
The plant shall be complete with accessories and fittings so that SF6 gas from
the breaker can be directly filled in the plant storage reservoir.
In case purging of the equipment before filling with SF6 gas is desirable, then
the required equipment for dry gases etc. shall be furnished as a part of the
plant.
For heavy items within the plant lifting hooks shall be provided for lifting and
moving with the overhead cranes.
a) the plant shall be complete with all the necessary pipes, couplings, flexible tubes
and valves for coupling to the equipment for the filling or evacuating SF6 gas to be
used with all necessary instructions for storage and handling of the plant.
b) The design and construction of the plant, valves, coupling, connections shall be such
that leakage of SF6 gas shall be minimum. Similarly valves, couplings and pipe work
shall be so arranged that accidental loss of gas to the atmosphere shall be minimum.
c) Facilities shall be provided to reduce SF6 gas pressure within the circuit breaker to a
value not less than 8 millibars.
General
The analyzer shall measure total leakage current, capacitive current, resistive current
and third harmonic resistive current components of leakage current of surge arrester
(upto 800 kV AC).
Functional requirements
Accuracy ± 1% of measured
78
value
Range 0 to 1 mA
Accuracy ± 1% of measured
value
General requirements
1. The equipment should be light weight (Not exceeding 1.5 kg), portable and
suitable for predictive maintenance of power transformers.
2. It should detect partial discharge, corona, and other ultrasonic activities
happening inside the equipment. The equipment should be able to detect
transformer defects viz. loose parts, defective tap changers, restricted /
turbulent flow in oil cooling pumps and thus provide a predictive maintenance
schedule to periodically inspect transformers to prevent failures and maintain
safe operating conditions.
3. Frequency range: The equipment should band pass the following frequencies:
(100 Hz to 11KHz, 3 KHz to 11 KHz and 20 KHz to 250 KHz).
4. The equipment should incorporate a piezoelectric sensor to detect defects by
making a contact with the transformer shell. The instrument must also comprise
of a highly sensitive air probe for detection of corona discharge with centre
frequency 40 KHz ± 10%.
5. The instrument should be supplied with a noise attenuating head set (with
volume control) to hear the ultrasonic noise. It should have noise reduction
rating of 24 db or better. Supplier should also supply a cordless headset
operable on rechargeable NiCd battery.
6. The equipment should be battery operated (lead acid battery). A single battery
should ensure at least 08 (eight) hours of operation. Indication of battery status
should be available.
79
7. Display: Ultrasonic activities in selected frequency range should be displayed
digitally (LED display with 0 1999 counts).
8. All necessary leads, cables etc. required for measurement are to be supplied
with the instrument. Operating and instruction manual and carrying case are to
be supplied.
Thermovision Camera
General
Functional requirements
The thermovision camera shall have the facility to measure the following
temperatures:
1. Temperature measurement: The camera shall be able to measure the hot spot
temperatures ranging from 0 to 500 Deg. C with accuracy of + 1 Deg. C. Focal
range shall be from 0.4m to infinity.
General requirements
The instrument shall be handy, light weight so that operator can easily scan the
switchyard equipment for hot spots.
The instrument shall have storage capacity up to 200 thermal images.
The instrument should have been proven for repeatability of test results in
charged switchyard conditions.
The kit should be capable of operating and storing data at temperature from –
10 Deg. C to 50 Deg. C and humidity of 10 to 90%.
The notebook PC of Pentium 166 MHz – or above with Windows – 95 software
(latest version), 16 MB RAM, 2 GB hard disc storage, 1.44 MB floppy drive, CD
ROM drive, inkjet printer shall be supplied along with the test kit. The software
supplied along with the kit should have facility to display and generate reports
in Graphical and Numerical formats and compare results obtained at different
times.
The kit shall be compatible for EMI/EMC environment
The hot spot focusing shall be motorized.
The accessories shall also include FOV wide angle lens of 32 Deg. Or better, 8
Deg. GOV telephoto lens for detailed scanning.
Battery and Battery charger: a) Battery shall be re-chargeable Ni-cd battery, b)
Battery charger should be suitable for 230 V AC, 50 Hz, variations + 15% and
+ 5% in voltage and frequency.
Infrared detectors shall use micro coolers and scanning techniques shall be
based on focal plane array.
80
Software for retrieval of data to maintain database and preparation of reports
shall be supplied along with the kit.
Instrument shall be capable of measuring hot temperature from 1m to 1000
meter distance.
Video recording for thermal image with a facility to replay through display unit
shall be provided.
General
Technical specifications
1. Portable over current relays testing equipment. The input rating shall be
between 200-250 V. 50 Hz, AC supply and the current output range shall be
0.05-200 amps. With negligible harmonic distortion of less than 1%. A time
interval meter shall be fitted to read and display 0-10 seconds with an accuracy
of ± 10 miliseconds.
2. Portable test equipment for testing distance relays comprising supply unit,
control unit and fault impedance unit. Suitable for AC voltage from 380-440 V,
three phase, 3 wire system 20 Ampere (short time rated) with built in safety
devices.
The equipment offered shall be trolley mounted and shall consist of double wound
transformer having primary rated for 230 V and four secondary windings each rated for
750 A, 5 V. By connecting secondary windings in series, parallel and in series parallel –
the following ranges shall be obtainable
81
3. All the secondaries in Parallel – 5V, 3000A
All the secondary windings shall be brought out which shall be selectable by means of
links for the above arrangement. Oil cooled type continuous rated Auto Transformer for
obtaining stepless variation on output shall be provided.
Ratings
0-5 V, 3000 A
Capacity 15 kVA
Accuracy ± 1%
Unit shall be supplied with first filling of oil plus 10% extra oil and output connecting
cable suitable for 3000 Amps and of 20 mtr. Length. The cable should have two cores
and should have two cores and should be provided with suitable clamps at both the
end of the cable for testing of any outdoor EHV equipment.
AC input terminal
AC input fuses
Pilot lamp to indicate main ON
Single phase dimerstat continuously variable voltage transformer
Single phase, double would loading transformer with graded secondary
Multi ratio current transformer (750/1500/3000/5A) for measuring current
output
144x144 mm square type moving iron ammeter of 0.5 amps range.
3 Pin plug socket with on/off switch to provide 230 V to external timer etc.
The set should have operating instructions printed on the set for convenience of
operator. As per ISO-9001, calibration certificate of each instrument shall be supplied
along with the test kit at the time of supply.
Technical specifications
The equipment offered shall be compact, enclosed in a single carrying case and
suitable for routine testing and timing of protective relays and equipment
including directional relays, differential relays, automatic-reclosing devices etc.
The testing kit shall measure and display voltage, current, impedance, power,
power factor, phase angle and time via an easy to read liquid crystal display.
The equipment should be supplied with an additional current source for testing
of differential relays.
82
The unit shall be operatable both with a P.C. (as RS 232 interface should be
available) and without a P.C. Any software if required for data transfer to a PC
should also be supplied.
A hold function shall be provided which will allow voltage and current readings
to be taken for duration of half a cycle or less. The timer start-stop input shall
respond to change of voltage or contact opening and closing.
Indication shall be provided to show status of timer start – stop inputs and
normally open (N.O.) and normally closed (N.C.) contacts. The testing kit must
incorporate a provision for continues phase shifting and fine adjustment of
voltage and current.
The equipment shall be complete with memory storage for a minimum of ten
test results and instrument settings.
The offered kit must meet the following minimum specifications:
83
The instrument shall be suitable for testing all types of three phase relays (both static
and electromagnetic type). Shall be portable and handy for each transportation to be
carried by one Person. It should be able to test all protection relays based on
impedance, voltage, current, frequency, harmonics, synchronization. The equipment
must be capable of efficiently testing all types of electronic and electro-mechanical
relays with a high degree of accuracy. The testing systdem shall be able to simulate all
the waveforms and transients as recorded on the disturbance recorder. The system
should be operable manually, semi-automatic and automatic and should meet the
following specifications:
Technical specifications
The testing system must generate at least four independent voltages and three
independent currents with the facility to control their amplitudes and phase angles
independently. The kit should have df/dt facility (i.e. frequency variation with respect
to time).
Frequency 50 Hz ± 5%
Timer section
Resolution 1 ms
To ensure extra protection of relay, the relay testing kit must incorporate auxiliary DC
voltage with range (25 V l- 210 V) and output power minimum 70 W.
84
Generator frequency range
Weight of the instrument should not be more than 25. the relay testing kit offered mus
be computer compatible. It should be capable of being operated with a computer and
also without a computer. A knob on the front panel of the equipment should be
provided for the manual operation for variation of all parameters. An on-board digital
display should also be provided on the system for visual display of parameters. (This is
essential for use of system without laptop). A laptop computer pre-loaded with the
easy to use relay testing software should be provided for fully automatic operation of
the relay testing set.
Software
The software should be easy to use without the requirement of extensive computer
literacy and should be possible to use in manual, semi-automatic and fully automatic
mode. It should be possible to automatically create the IEC and IEEE standard waves
and/or creates other characteristics using the standard circular lens and linear
elements. The software should also contain an automatic test plan editor to create
automatic test plans for new/unknown relays easily and without programming
knowledge. The kit should have the capability to accept transient fault data recorded
by disturbance recorder from 3.5" floppy and relay these on the relay under test. It
should be able to perform both static and dynamic testing such as fault and prefault
generation, simultaneous ramping of quantities and editing waveforms etc. The kit
offered must have provision for generating COMTRADE and EMTP files (EMTP PC
programmes also) as well as editing the wave forms.
Calibration
Apart from self-calibration (software), the system should also be provided with an
independent calibration box as an independent external means of verifying the
relevant parameters. It should be possible to calibrate the calibration box and
therefore the kit to relevant International traceable standards.
Analog inputs
The kit shall also have anlog inputs for measurement of AC/DC current and voltages
(both low and high) as per the following specifications.
85
Accuracy 0.03%
Accuracy 0.03%
The equipment should be designed to operate under the adverse conditions of external
influence like electrostatic discharge, magnetic field, electromagnetic field induction, RF
Interference, input waveform distortion and harmonics, input voltage and frequency
variation.
The phase shifting kit should be ideal for testing relays in situations where current,
voltage and phase angle must be varied independently. It should perform satisfactorily
in high voltage environments and should conform to relevant IEC/VDE standards. The
instrument must incorporate in-built over current and over-voltage protection and
should meet the following minimum specifications but not limited to:
Phase angle
86
Accuracy ±1º or better
With provision of displaying the phase angle in digital manner in the equipment.
Party should supply a sturdy and shock-proof transport case so that the equipment
could be properly housed in to avoid any damage when used at site. Operating and
instruction manual is also to be supplied along with the equipment. Party must have
supplied atleast one number of similar equipment to any power utility.
Technical specifications
The equipment should be able to precisely detect any earth fault occurring in DC
systems (24 V upto 360 V) to ensure operational safety and availability of electrical
systems. It should ensure fast location of the insulation fault and no disconnection of
the electrical system should be required so that insulation fault could be located during
operation of the system itself.
The equipment should comprise of a test device and an evaluator unit. A clamp – on
probe is to be supplied for embracing the conductors under test. The evaluator unit
should be immediately ready for operation without any need for balancing. The
equipment should be light weight, portable and rechargeable battery operated. Party
should supply one battery charger along with the equipment.
Display: There should be provision for a liquid crystal display to indicate test currents
of respective conductors. Indication of battery status should be available on the LC
display. It should also indicate whether the connection to the clamp on probe is
interrupted. All necessary cables, leads required for measurement are to be supplied
with the equipment. Party should also supply operating and instruction manual.
Technical specifications
It should include impedance & return loss measuring attachment compatible with level
generator
87
With balanced input –60 to +20 db/dbm
Sensitively in steps of 10 db
With unbalanced input –70 to +10 db/dbm
0 scale division
Resolution 5 Hz.
Power supply One internal rechargeable batter of 230 V AC. 50 Hz. for
AC operation and for charging battery. Battery charger is
included in the scope.
The equipment shall also have the provision for impedance measurement and return
loss measurement. The technical parameters for these measurements are given below.
Impedance measurement
88
i) Frequency range 300 Hz – 600 KHz
iv) accuracy ± 1 db
Technical specifications
89
Spurious signal At 0 db – 60 db below fundamental
frequency
As per ISO – 9001, calibration certificate of each instrument shall be supplied along with
the test kit at the time of supply.
The dual trace oscilloscope offered shall include suitable printer/plotter. The
oscilloscope shall have the following features:
Vacuum Tester
The vacuum tester should permit to select among six test voltage from 10 to 60 kV DC
and should have following minimum specifications
Ripple : Max. 3%
90
Maximum permissible transient current through : 12mA
external load
The unit should weigh about 6 Kg. (approx) and easy to use. It should be supplied with
permanently mounted cables set of 5m length, ground cable and transport case.
The battery management system should be portable, light weight and hand held type.
It should be able to measure and store cell voltage. There should also be provision for
measurement and storage ;of temperature, density, ripple voltage and voltage drip
across connections. The equipment must have data logging as well as data storage
facility. Audible as well as usual indication should be available when a value is stored.
An alarm should also be generated if a value exceeds the limit value. It should
incorporate a serial interface as well as a parallel interface so that test data can be
printed immediately after a test in tabular form or can be transferred to a PC for
further analysis. Suitable Windows Based Software shall also be supplied which should
be cable of providing results in the form of curves or bar charts. The software should
also incorporate a convenient cut and paste function for transferring values to other
programs. The equipment should meet the vollowing minimum technical specifications.
DC voltage range : 245mV, 2.45V, 245V, 600V with resolution 0.01 mV, 0.1mV,
1.0mV, 10mV and 100 mV respectively.
AC voltage : 2-160mV
Input Impedance : 1 MW
91
Storage capacity : Minimum 25,000 measurement values
Accessories : Test cables, printer cable, datacom cable for computer, batter
charger, software, transport case, instruction manual etc.
The unit is intended to test sub-station batteries. The load unit should be able to
discharge the batteries at constant current, constant output, constant resistance or as
per a pre-selected load profile. It should also have current voltage time measurement
capability. The detailed specifications are as under:
Resolution : 0.02 V
The equipment offered shall be suitable to measure, in the field or laboratory, the total
amount of water contained in mineral dielectric oil. The result in PPM shall directly
correlate with the Karl Fischer Colorimetric Titration method. It shall be useful for
onsite routine testing of transformer mineral oil, on site acceptance tests of reclaimed
and reconditioned mineral dielectric oil and onsite tests of oil before re-energizing oil-
filled electrical equipment. The equipment should be portable, rugged and user friendly
and should meet the following specifications:
92
Range of measurement : 0-50 ppm (by weight)
Time required
Battery low indication : There should be battery status indication to enable the
user to know the charging time in advance.
Waste Oil Reservoir : The equipment should also incorporate a waste oil
reservoir of capacity minimum 50 ml.
The offered equipment should be CE marked and shall meet low voltage and EMC
directives. Party should supply a oil injection syringe, a reinforced carrying case and
operational manual alongwith the equipment.
The equipment should be able to precisely detect any earth fault occurring in
DC systems (24 V upto 360 V) to ensure operational safety and availability of
electrical systems.
It should ensure fast location of the insulation fault and no disconnection of the
electrical system should be required so that insulation fault could be located
during operation of the system itself.
Maximum test current: 25mA and 10mA selectable in two ranges
93
The equipment should comprise of a test device and an evaluator unit. A clamp-
on probe is to be supplied for embracing the conductors under test. The
evaluator unit should be immediately ready for operation without any need of
balancing.
The equipment should be light weight, portable and rechargeable battery
operated. Party should supply one battery charger along with the equipment.
Display: There should be provision for a liquid crystal display to indicate test
currents of respective conductors. Indication of battery status should be
available on the LC display. It should also indicate whether the connection to
the clamp on probe is interrupted.
All necessary cables, leads required for measurement are to be supplied with
the equipment. Part should also supply operating and instruction manual.
Calibration Equipment
Functional requirements
The Kit shall be suitable for periodic calibration of meters mentioned at clause 12.0
against the following parameters:
DC Voltage
DC Current
Range: + 10 Amp
Accuracy: + 0.05%
AC Voltage
AC Current
Resistance
94
Range: 0 to 5000 ;Mohm
Accuracy: + 0.01%
Capacitance
Frequency
Range: 10 Hz to 20 MHz
Accuracy: + 0.01%
General requirements
95
Section -7 EQUIPMENT FAILURE REPORT
INTRODUCTION
Though there have been reported failure of equipment in all the power utilities,
however the details and causes of the failures are not being compiled in a systematic
manner. In the absence of this data it is difficult to set indices for the reliability of the
various sub-station equipment. A need has been felt for some time for standardization
of reporting of failure equipment, which should be uniformly followed by all the power
utilities. Equipment failure report is just like a FIR (First Information Report).
The above documents should be signed by the maintenance engineer and counter
signed by the DIVISONAL incharge.
96