Top Level Tasks as of July 20, 2020

Proyek Rumah Pak Fajar

ID Task Mode Task Name Duration Start Finish % Comp. Cost

0 Auto Scheduled Proyek Rumah Pak Fajar 163 days January 1, 2019 July 24, 2019 0% Rp4,417,709,948
1 Manually Scheduled
PEKERJAAN PERSIAPAN 6 days January 1, 2019 January 7, 2019 0% Rp0
2 Manually Scheduled
Pembersihan Lahan 3 days January 1, 2019 January 3, 2019 0% Rp21,019,200
3 Manually Scheduled
Pekerjaan Pengukuran & Bowplank 3 days January 4, 2019 January 7, 2019 0% Rp30,356,900
5 Manually Scheduled
PEKERJAAN TANAH 8 days January 8, 2019 January 16, 2019 0% Rp0
6 Manually Scheduled
Penggalian 1 m3 tanah biasa sedalam7 1days
m January 8, 2019 January 15, 2019 0% Rp65,038,400
7 Manually Scheduled
Pengurugan kembali 1 m3 galian tanah
2 days January 15, 2019 January 16, 2019 0% Rp14,012,800
9 Manually Scheduled
PEKERJAAN PASANGAN PONDASI 14 days January 17, 2019 February 1, 2019 0% Rp0
10 Manually Scheduled
Pancang Ulin 10/10-400 2 days January 17, 2019 January 18, 2019 0% Rp30,940,000
11 Manually Scheduled
Pengurugan 1 m3 dengan pasir urug 2 days January 18, 2019 January 19, 2019 0% Rp4,967,200
12 Manually Scheduled
Pemasangan 1 m3 batu kosong (aanstamping)
2 days January 21, 2019 January 22, 2019 0% Rp29,328,600
13 Manually Scheduled
Pemasangan 1 m3 Batu belah campuran
8 days
1:4 January 22, 2019 January 30, 2019 0% Rp153,078,764
14 Manually Scheduled
Pengurugan 1 m3 tanah bawah lantai2 days January 31, 2019 February 1, 2019 0% Rp4,975,300
16 Manually Scheduled
PEKERJAAN BETON 41 days February 2, 2019 March 23, 2019 0% Rp0
17 Manually Scheduled
Sloof 15 x 30 10 days February 2, 2019 February 15, 2019 0% Rp229,291,564
18 Manually Scheduled
Kolom 15 x 30 8 days February 16, 2019 February 25, 2019 0% Rp165,321,964
19 Manually Scheduled
Kolom 12 x 20 7 days February 21, 2019 February 28, 2019 0% Rp146,357,164
20 Manually Scheduled
Kolom 12 x 12 7 days February 25, 2019 March 4, 2019 0% Rp145,293,164
21 Manually Scheduled
Balok 15 x 30 8 days March 5, 2019 March 13, 2019 0% Rp165,321,964
22 Manually Scheduled
Balok 12 x 20 5 days March 7, 2019 March 12, 2019 0% Rp104,019,564
23 Manually Scheduled
Balok 20 x 10 5 days March 9, 2019 March 14, 2019 0% Rp109,731,564
24 Manually Scheduled
Ring balok 5 days March 19, 2019 March 23, 2019 0% Rp92,215,564
25 Manually Scheduled
Tangga 6 days March 12, 2019 March 18, 2019 0% Rp110,035,564
26 Manually Scheduled
Pelat dan dak 17 days February 25, 2019 March 15, 2019 0% Rp554,913,164
28 Manually Scheduled
PEKERJAAN DINDING DAN PLESTERAN
32 days March 25, 2019 May 3, 2019 0% Rp0
29 Manually Scheduled
Pemasangan 1m2 dinding bata merah
9 days
tebal ½ batu campuran
March
1SP25,
:4PP
2019 April 4, 2019 0% Rp275,852,864
30 Manually Scheduled
Pemasangan 1m2 dinding bata merah
3 days
tebal ½ batu campuran
April1SP
2, 2019
:2PP April 5, 2019 0% Rp43,273,664
31 Manually Scheduled
Pemasangan 1 m2 plesteran 1SP : 4PP
12tebal
days 15 mm April 6, 2019 April 20, 2019 0% Rp384,139,764
32 Manually Scheduled
Pemasangan 1 m2 plesteran 1SP : 2PP
4 days
tebal 15 mm April 20, 2019 April 24, 2019 0% Rp24,994,164
33 Manually Scheduled
Pemasangan 1 m2 acian 7 days April 25, 2019 May 3, 2019 0% Rp174,317,964
35 Manually Scheduled
PEKERJAAN LANTAI DAN KERAMIK 10 days May 15, 2019 May 25, 2019 0% Rp0
36 Manually Scheduled
Pas. Lantai Keramik 40x40 5 days May 15, 2019 May 20, 2019 0% Rp101,314,364

Page 1
Top Level Tasks as of July 20, 2020
Proyek Rumah Pak Fajar

ID Task Mode Task Name Duration Start Finish % Comp. Cost

37 Manually Scheduled
Pas. Lantai Keramik 20x20 2 days May 21, 2019 May 22, 2019 0% Rp22,077,164
38 Manually Scheduled
Pas. Dinding keramik 20x20 3 days May 23, 2019 May 25, 2019 0% Rp39,973,164
40 Manually Scheduled
PEKERJAAN KUSEN, PINTU, DAN JENDELA
9 days March 26, 2019 April 5, 2019 0% Rp0
41 Manually Scheduled
Pekerjaan kusen 2 days March 26, 2019 March 27, 2019 0% Rp31,306,600
42 Manually Scheduled
Pekerjaan daun pintu dan jendela (gandeng)
2 days March 27, 2019 March 28, 2019 0% Rp26,680,800
43 Manually Scheduled
Pekerjaan daun pintu 4 days March 28, 2019 April 1, 2019 0% Rp55,339,900
44 Manually Scheduled
Pekerjaan daun jendela 3 days April 2, 2019 April 5, 2019 0% Rp46,963,100
46 Manually Scheduled
PEKERJAAN RANGKA ATAP DAN PENUTUP
23 days
ATAP May 27, 2019 June 29, 2019 0% Rp0
47 Manually Scheduled
Pemasangan rangka langit-langit 7 days May 27, 2019 June 11, 2019 0% Rp137,877,500
48 Manually Scheduled
Pasangan kuda - kuda kayu 6/12 5 days June 12, 2019 June 17, 2019 0% Rp68,515,500
49 Manually Scheduled
Pasangan gording 2 days June 15, 2019 June 17, 2019 0% Rp28,842,700
50 Manually Scheduled
Pasangan nok genteng metal 3 days June 18, 2019 June 20, 2019 0% Rp15,147,500
51 Manually Scheduled
Pasangan rangka atap hollow 2 days June 21, 2019 June 22, 2019 0% Rp14,785,500
52 Manually Scheduled
Pasangan lisplang kayu 2/20 3 days June 22, 2019 June 25, 2019 0% Rp28,134,900
53 Manually Scheduled
Pasangan atap genteng metal 4 days June 26, 2019 June 29, 2019 0% Rp38,783,700
55 Manually Scheduled
PEKERJAAN PLAFON 4 days July 1, 2019 July 4, 2019 0% Rp0
56 Manually Scheduled
Pemasangan langit-langit GRC 3 days July 1, 2019 July 3, 2019 0% Rp35,833,100
57 Manually Scheduled
Pemasangan list langit-langit kayu profil
2 days July 3, 2019 July 4, 2019 0% Rp19,569,200
59 Manually Scheduled
PEKERJAAN PENGECATAN 14 days July 4, 2019 July 19, 2019 0% Rp0
60 Manually Scheduled
Pengecatan tembok baru interior 7 days July 5, 2019 July 12, 2019 0% Rp60,174,700
61 Manually Scheduled
Pengecatan tembok baru eksterior 4 days July 11, 2019 July 15, 2019 0% Rp34,582,000
62 Manually Scheduled
Pengecatan plafond 4 days July 15, 2019 July 18, 2019 0% Rp29,861,300
63 Manually Scheduled
Pengecatan lisplang 2 days July 19, 2019 July 20, 2019 0% Rp15,184,700
65 Manually Scheduled
PEKERJAAN KUNCI & KACA 10 days March 27, 2019 April 8, 2019 0% Rp0
66 Manually Scheduled
Pemasangan kunci tanam biasa 2 days March 27, 2019 March 28, 2019 0% Rp35,849,500
67 Manually Scheduled
Pemasangan kunci tanam Kamar Mandi
1 day March 28, 2019 March 28, 2019 0% Rp7,488,100
68 Manually Scheduled
Pemasangan engsel pintu 3 days March 29, 2019 April 1, 2019 0% Rp39,812,600
69 Manually Scheduled
Pemasangan engsel jendela kupu-kupu
3 days April 2, 2019 April 5, 2019 0% Rp41,143,700
70 Manually Scheduled
Pemasangan handle pintu 2 days April 6, 2019 April 8, 2019 0% Rp22,025,300
72 Manually Scheduled
PEKERJAAN SANITAIR 9 days May 4, 2019 May 14, 2019 0% Rp0
73 Manually Scheduled
Pemasangan bak kontrol 2 days May 4, 2019 May 6, 2019 0% Rp37,028,464
74 Manually Scheduled
Pemasangan bak mandi 2 days May 7, 2019 May 8, 2019 0% Rp33,961,364

Page 2
Top Level Tasks as of July 20, 2020
Proyek Rumah Pak Fajar

ID Task Mode Task Name Duration Start Finish % Comp. Cost

75 Manually Scheduled
Pemasangan floordrain 1 day May 8, 2019 May 8, 2019 0% Rp8,959,500
76 Manually Scheduled
Pemasangan closet duduk/monoblock
1 day May 9, 2019 May 9, 2019 0% Rp13,529,800
77 Manually Scheduled
Pemasangan bak cuci piring stainles steel
1 day May 10, 2019 May 10, 2019 0% Rp9,159,100
78 Manually Scheduled
Pemasangan kran Ø ¾” atau ½” 3 days May 11, 2019 May 14, 2019 0% Rp32,993,800
80 Manually Scheduled
PEKERJAAN INSTALASI AIR 5 days April 3, 2019 April 8, 2019 0% Rp0
81 Manually Scheduled
Pemasangan pipa PVC tipe AW Ø 3/4”
3 days April 2, 2019 April 5, 2019 0% Rp35,177,875
82 Manually Scheduled
Pemasangan 1 m’ pipa PVC tipe AW 2
diameter
days 4” April 6, 2019 April 8, 2019 0% Rp26,633,200
84 Manually Scheduled
PEKERJAAN INSTALASI LISTRIK 11 days March 30, 2019 April 12, 2019 0% Rp0
85 Manually Scheduled
Pasang Box Panel Lengkap MCB Standart
1 day March 30, 2019 March 30, 2019 0% Rp8,133,800
86 Manually Scheduled
Pasang Instalasi stop kontak 3 days March 30, 2019 April 2, 2019 0% Rp36,181,900
87 Manually Scheduled
Pasang Stop kontak 2 days April 4, 2019 April 5, 2019 0% Rp21,849,700
88 Manually Scheduled
Pasang Instalasi lampu 3 days April 5, 2019 April 8, 2019 0% Rp46,691,500
89 Manually Scheduled
Pasang saklar engkel 2 days April 9, 2019 April 10, 2019 0% Rp12,387,000
90 Manually Scheduled
Pasang saklar double 1 day April 10, 2019 April 10, 2019 0% Rp5,076,600
91 Manually Scheduled
Pasang Bolham Lampu LED BULB 2 days April 11, 2019 April 12, 2019 0% Rp12,386,500
93 Manually Scheduled
PEKERJAAN SEPTICTANK DAN RESAPAN
3 days July 22, 2019 July 24, 2019 0% Rp0
94 Manually Scheduled
Pek. Septictank Biofil kap. 6,00 m3 uk.
3 days
2 X 1,5 X 2 m July 22, 2019 July 24, 2019 0% Rp1,496,429
95 Auto Scheduled SERAH TERIMA RUMAH 0 days July 24, 2019 July 24, 2019 0% Rp0

Page 3
Top Level Tasks as of July 20, 2020
Proyek Rumah Pak Fajar

Work

28,728 hrs
0 hrs
144 hrs
168 hrs
0 hrs
448 hrs
96 hrs
0 hrs
160 hrs
32 hrs
192 hrs
1,024 hrs
32 hrs
0 hrs
1,520 hrs
1,088 hrs
952 hrs
952 hrs
1,088 hrs
680 hrs
720 hrs
600 hrs
720 hrs
3,672 hrs
0 hrs
1,872 hrs
288 hrs
2,592 hrs
160 hrs
1,176 hrs
0 hrs
680 hrs

Page 4
Top Level Tasks as of July 20, 2020
Proyek Rumah Pak Fajar

Work

144 hrs
264 hrs
0 hrs
160 hrs
128 hrs
320 hrs
264 hrs
0 hrs
896 hrs
400 hrs
144 hrs
96 hrs
96 hrs
168 hrs
256 hrs
0 hrs
192 hrs
128 hrs
0 hrs
392 hrs
224 hrs
192 hrs
96 hrs
0 hrs
240 hrs
48 hrs
264 hrs
264 hrs
144 hrs
0 hrs
240 hrs
224 hrs

Page 5
Top Level Tasks as of July 20, 2020
Proyek Rumah Pak Fajar

Work

56 hrs
56 hrs
48 hrs
216 hrs
0 hrs
216 hrs
160 hrs
0 hrs
48 hrs
240 hrs
144 hrs
312 hrs
80 hrs
32 hrs
80 hrs
0 hrs
0 hrs
0 hrs

Page 6