Statement of Time Elapsed

Construction of one (1) unit Mango Improvement of Casispalan, Vegetable Processing construction of Farm construction of the Canal Construction of farm construction of San Diego
Chips/Juice Processing Facility under Tagkawayan, Quezon Facility under High Machinery Shed in APCO Improvement of Ponon machinery shed in RARES at Dam at Brgy. San Diego, Lian,
High Value Crops Development Value Crops Laguna under rice program Diversion Dam at Brgy. Brgy. Cuyambay, Tanay, Rizal Batangas under SSIP Rice
Program Development Program Ponon, Atimonan, Quezon Program
CY 2019 under small scale irrigation
project of rice banner
program CY 2019

Contractor Juntereal R.M.Adalim Nabong Collantes Nabong Collantes Juntereal Juntereal Industrial Nabong Collantes
and Development Corporation
Corp

Contract Amount 2,805,513.76 1,958,675.00 1,247,773.57 3,175,528.30 1,254,519.07 6,254,628.76


Original Contract Duration 90 CD 90 CD 90 CD 30CD 30 30 150
NTP March 04, 2019 March 12, 2019 May 14, 2019 October 07, 2019 March 15, 2019 May 14, 2019 April 10, 2019
Start March 19, 2019 March 27, 2019 May 14, 2019 October 07, 2019 March 17, 2019 May 14, 2019 April 10, 2019
Expiry (Add 16 days) June 18, 2019 June 17, 2019 August 15, 2019 June 13, 2019 June 15, 2019 April 10, 2019
Request for Suspension (from NTP) March 18, 2019 March 27, 2019 June 11, 2019 October 21, 2019 March 21, 2019 May 20, 2019 July 29, 2019 August 28, 2019
Days Consumed (per NTP) 14 15 28 14 13 6 125
Approved Suspension March 22, 2019 April 15, 2019 July 15, 2019 October 21, 2019 March 28, 2019 May 20, 2019 August 13, 2019
Receipt of Approved Suspension March 26, 2019 April 16, 2019 October 21, 2019 March 28, 2019 May 20, 2019 August 13, 2019
Resume Order May 31, 2019 April 30, 2019 November 20, 2019 June 28, 2019 October 03, 2019 September 02, 2019 September 02, 2019
Receipt of RO May 31, 2019 April 30, 2019 November 20, 2019 June 28, 2019 October 03, 2019 September 02, 2019
Total Shutdown Due to Suspensions (Receipt of RO
from receipt of Approved Suspension) 66 31 30 92 136 21
Contract Time Elapsed (contract end date from NTP) 155 113 64 180.00 166.00 157.00
Effective Time Elapsed (resume order from NTP) 89 82 34 90.00 90.00 136
Contract End Date (should be) August 05, 2019 July 15, 2019 November 06, 2019 September 13, 2019 October 27, 2019 September 28, 2019
Revised Contract Expiry Due to Suspension (per rep.) August 17, 2019 July 18, 2019 December 10, 2019 September 18, 2019 October 27, 2019 September 28, 2019
Should be Contract Expiry after days remaining August 15, 2019 July 14, 2019 December 06, 2019 September 13, 2019 October 27, 2019 September 28, 2019
Difference 12 3 34 5 0 0
Actual Date of Completion August 16, 2019 July 10, 2019 December 05, 2019 September 13, 2019 October 27, 2019 September 13, 2019
No. of Days Delayed per Original date 11 -5 29 0 0 -15
No. of Days Delayed per should be expiry date 1 -4 -1 0 0 -15
Preparer: Abner P. Prudente Redjie M. Adalim Danilo Collantes Danilo Collantes Abner P. Prudente Abner P. Prudente Danilo Collantes
Checker: Jan-jan J. Aguilar Jan-jan J. Aguilar Jan-jan J. Aguilar Jan-jan J. Aguilar Jan-jan J. Aguilar Mark Anthony A. FordJan-jan J. Aguilar
Certified Correct: Engr. Marcos C. Aves, Sr. Engr. Marcos C. Aves, Sr. Engr. Marcos C. Ave Engr. Marcos C. Aves,Engr. Marcos C. Aves, ESngr. Marcos C. Aves, ESngr. Marcos C. Aves, Sr.
Recommending Approval: Dennis R. Arpia Dennis R. Arpia Dennis R. Arpia Dennis R. Arpia Dennis R. Arpia Dennis R. Arpia Dennis R. Arpia
Approval: Engr. Arnel V. De Mesa Engr. Arnel V. De Mesa Engr. Arnel V. De Engr. Arnel V. De MesEngr. Arnel V. De MesEngr. Arnel V. De MesEngr. Arnel V. De Mesa