Who Does What as of July 20, 2020

Proyek Rumah Pak Fajar

ID Indicators Resource Name Work

1 Pekerja 14,272 hrs


ID Task Name Units Work Delay Start Finish
2 Pembersihan Lahan 5 120 hrs 0 days January 1, 2019 January 3, 2019
3 Pekerjaan Pengukuran & Bowplank 3 72 hrs 0 days January 4, 2019 January 7, 2019
6 Penggalian 1 m3 tanah biasa sedalam 1 m 7 392 hrs 0 days January 8, 2019 January 15, 2019
7 Pengurugan kembali 1 m3 galian tanah 5 80 hrs 0 days January 15, 2019 January 16, 2019
10 Pancang Ulin 10/10-400 4 64 hrs 0 days January 17, 2019 January 18, 2019
11 Pengurugan 1 m3 dengan pasir urug 1 16 hrs 0 days January 18, 2019 January 19, 2019
12 Pemasangan 1 m3 batu kosong (aanstamping) 6 96 hrs 0 days January 21, 2019 January 22, 2019
13 Pemasangan 1 m3 Batu belah campuran 1:4 9 576 hrs 0 days January 22, 2019 January 30, 2019
14 Pengurugan 1 m3 tanah bawah lantai 1 16 hrs 0 days January 31, 2019 February 1, 2019
17 Sloof 15 x 30 10 800 hrs 0 days February 2, 2019 February 15, 2019
18 Kolom 15 x 30 8 512 hrs 0 days February 16, 2019 February 25, 2019
19 Kolom 12 x 20 7 392 hrs 0 days February 21, 2019 February 28, 2019
20 Kolom 12 x 12 7 392 hrs 0 days February 25, 2019 March 4, 2019
21 Balok 15 x 30 8 512 hrs 0 days March 5, 2019 March 13, 2019
22 Balok 12 x 20 7 280 hrs 0 days March 7, 2019 March 12, 2019
23 Balok 20 x 10 8 320 hrs 0 days March 9, 2019 March 14, 2019
24 Ring balok 6 240 hrs 0 days March 19, 2019 March 23, 2019
25 Tangga 7 336 hrs 0 days March 12, 2019 March 18, 2019
26 Pelat dan dak 13 1,768 hrs 0 days February 25, 2019 March 15, 2019
29 Pemasangan 1m2 dinding bata merah tebal ½ batu campuran 1SP :4PP 17 1,224 hrs 0 days March 25, 2019 April 4, 2019
30 Pemasangan 1m2 dinding bata merah tebal ½ batu campuran 1SP :2PP 7 168 hrs 0 days April 2, 2019 April 5, 2019
31 Pemasangan 1 m2 plesteran 1SP : 4PP tebal 15 mm 15 1,440 hrs 0 days April 6, 2019 April 20, 2019
32 Pemasangan 1 m2 plesteran 1SP : 2PP tebal 15 mm 2 64 hrs 0 days April 20, 2019 April 24, 2019
33 Pemasangan 1 m2 acian 12 672 hrs 0 days April 25, 2019 May 3, 2019
36 Pas. Lantai Keramik 40x40 10 400 hrs 0 days May 15, 2019 May 20, 2019
37 Pas. Lantai Keramik 20x20 5 80 hrs 0 days May 21, 2019 May 22, 2019
38 Pas. Dinding keramik 20x20 6 144 hrs 0 days May 23, 2019 May 25, 2019
41 Pekerjaan kusen 5 80 hrs 0 days March 26, 2019 March 27, 2019
42 Pekerjaan daun pintu dan jendela (gandeng) 4 64 hrs 0 days March 27, 2019 March 28, 2019
43 Pekerjaan daun pintu 5 160 hrs 0 days March 28, 2019 April 1, 2019
44 Pekerjaan daun jendela 5 120 hrs 0 days April 2, 2019 April 5, 2019
47 Pemasangan rangka langit-langit 6 336 hrs 0 days May 27, 2019 June 11, 2019
48 Pasangan kuda - kuda kayu 6/12 2 80 hrs 0 days June 12, 2019 June 17, 2019
49 Pasangan gording 5 80 hrs 0 days June 15, 2019 June 17, 2019
50 Pasangan nok genteng metal 1 24 hrs 0 days June 18, 2019 June 20, 2019
51 Pasangan rangka atap hollow 2 32 hrs 0 days June 21, 2019 June 22, 2019
52 Pasangan lisplang kayu 2/20 2 48 hrs 0 days June 22, 2019 June 25, 2019
53 Pasangan atap genteng metal 4 128 hrs 0 days June 26, 2019 June 29, 2019
56 Pemasangan langit-langit GRC 3 72 hrs 0 days July 1, 2019 July 3, 2019
57 Pemasangan list langit-langit kayu profil 3 48 hrs 0 days July 3, 2019 July 4, 2019
60 Pengecatan tembok baru interior 3 168 hrs 0 days July 5, 2019 July 12, 2019
61 Pengecatan tembok baru eksterior 3 96 hrs 0 days July 11, 2019 July 15, 2019
62 Pengecatan plafond 2 64 hrs 0 days July 15, 2019 July 18, 2019
63 Pengecatan lisplang 2 32 hrs 0 days July 19, 2019 July 20, 2019
66 Pemasangan kunci tanam biasa 8 128 hrs 0 days March 27, 2019 March 28, 2019
67 Pemasangan kunci tanam Kamar Mandi 2 16 hrs 0 days March 28, 2019 March 28, 2019
68 Pemasangan engsel pintu 5 120 hrs 0 days March 29, 2019 April 1, 2019
69 Pemasangan engsel jendela kupu-kupu 5 120 hrs 0 days April 2, 2019 April 5, 2019

Page 1
Who Does What as of July 20, 2020
Proyek Rumah Pak Fajar

ID Indicators Resource Name Work

"Pekerja" continued
ID Task Name Units Work Delay Start Finish
70 Pemasangan handle pintu 4 64 hrs 0 days April 6, 2019 April 8, 2019
73 Pemasangan bak kontrol 8 128 hrs 0 days May 4, 2019 May 6, 2019
74 Pemasangan bak mandi 7 112 hrs 0 days May 7, 2019 May 8, 2019
75 Pemasangan floordrain 3 24 hrs 0 days May 8, 2019 May 8, 2019
76 Pemasangan closet duduk/monoblock 3 24 hrs 0 days May 9, 2019 May 9, 2019
77 Pemasangan bak cuci piring stainles steel 2 16 hrs 0 days May 10, 2019 May 10, 2019
78 Pemasangan kran Ø ¾” atau ½” 4 96 hrs 0 days May 11, 2019 May 14, 2019
81 Pemasangan pipa PVC tipe AW Ø 3/4” 4 96 hrs 0 days April 2, 2019 April 5, 2019
82 Pemasangan 1 m’ pipa PVC tipe AW diameter 4” 5 80 hrs 0 days April 6, 2019 April 8, 2019
85 Pasang Box Panel Lengkap MCB Standart 2 16 hrs 0 days March 30, 2019 March 30, 2019
86 Pasang Instalasi stop kontak 5 120 hrs 0 days March 30, 2019 April 2, 2019
87 Pasang Stop kontak 4 64 hrs 0 days April 4, 2019 April 5, 2019
88 Pasang Instalasi lampu 7 168 hrs 0 days April 5, 2019 April 8, 2019
89 Pasang saklar engkel 2 32 hrs 0 days April 9, 2019 April 10, 2019
90 Pasang saklar double 1 8 hrs 0 days April 10, 2019 April 10, 2019
91 Pasang Bolham Lampu LED BULB 2 32 hrs 0 days April 11, 2019 April 12, 2019

2 Mandor 2,840 hrs


ID Task Name Units Work Delay Start Finish
2 Pembersihan Lahan 1 24 hrs 0 days January 1, 2019 January 3, 2019
3 Pekerjaan Pengukuran & Bowplank 1 24 hrs 0 days January 4, 2019 January 7, 2019
6 Penggalian 1 m3 tanah biasa sedalam 1 m 1 56 hrs 0 days January 8, 2019 January 15, 2019
7 Pengurugan kembali 1 m3 galian tanah 1 16 hrs 0 days January 15, 2019 January 16, 2019
10 Pancang Ulin 10/10-400 1 16 hrs 0 days January 17, 2019 January 18, 2019
11 Pengurugan 1 m3 dengan pasir urug 1 16 hrs 0 days January 18, 2019 January 19, 2019
12 Pemasangan 1 m3 batu kosong (aanstamping) 1 16 hrs 0 days January 21, 2019 January 22, 2019
13 Pemasangan 1 m3 Batu belah campuran 1:4 1 64 hrs 0 days January 22, 2019 January 30, 2019
14 Pengurugan 1 m3 tanah bawah lantai 1 16 hrs 0 days January 31, 2019 February 1, 2019
17 Sloof 15 x 30 2 160 hrs 0 days February 2, 2019 February 15, 2019
18 Kolom 15 x 30 2 128 hrs 0 days February 16, 2019 February 25, 2019
19 Kolom 12 x 20 2 112 hrs 0 days February 21, 2019 February 28, 2019
20 Kolom 12 x 12 2 112 hrs 0 days February 25, 2019 March 4, 2019
21 Balok 15 x 30 2 128 hrs 0 days March 5, 2019 March 13, 2019
22 Balok 12 x 20 2 80 hrs 0 days March 7, 2019 March 12, 2019
23 Balok 20 x 10 2 80 hrs 0 days March 9, 2019 March 14, 2019
24 Ring balok 2 80 hrs 0 days March 19, 2019 March 23, 2019
25 Tangga 2 96 hrs 0 days March 12, 2019 March 18, 2019
26 Pelat dan dak 3 408 hrs 0 days February 25, 2019 March 15, 2019
29 Pemasangan 1m2 dinding bata merah tebal ½ batu campuran 1SP :4PP 1 72 hrs 0 days March 25, 2019 April 4, 2019
30 Pemasangan 1m2 dinding bata merah tebal ½ batu campuran 1SP :2PP 1 24 hrs 0 days April 2, 2019 April 5, 2019
31 Pemasangan 1 m2 plesteran 1SP : 4PP tebal 15 mm 1 96 hrs 0 days April 6, 2019 April 20, 2019
32 Pemasangan 1 m2 plesteran 1SP : 2PP tebal 15 mm 1 32 hrs 0 days April 20, 2019 April 24, 2019
33 Pemasangan 1 m2 acian 1 56 hrs 0 days April 25, 2019 May 3, 2019
36 Pas. Lantai Keramik 40x40 1 40 hrs 0 days May 15, 2019 May 20, 2019
37 Pas. Lantai Keramik 20x20 1 16 hrs 0 days May 21, 2019 May 22, 2019
38 Pas. Dinding keramik 20x20 1 24 hrs 0 days May 23, 2019 May 25, 2019
41 Pekerjaan kusen 1 16 hrs 0 days March 26, 2019 March 27, 2019

Page 2
Who Does What as of July 20, 2020
Proyek Rumah Pak Fajar

ID Indicators Resource Name Work

"Mandor" continued
ID Task Name Units Work Delay Start Finish
42 Pekerjaan daun pintu dan jendela (gandeng) 1 16 hrs 0 days March 27, 2019 March 28, 2019
43 Pekerjaan daun pintu 1 32 hrs 0 days March 28, 2019 April 1, 2019
44 Pekerjaan daun jendela 1 24 hrs 0 days April 2, 2019 April 5, 2019
47 Pemasangan rangka langit-langit 2 112 hrs 0 days May 27, 2019 June 11, 2019
48 Pasangan kuda - kuda kayu 6/12 1 40 hrs 0 days June 12, 2019 June 17, 2019
49 Pasangan gording 1 16 hrs 0 days June 15, 2019 June 17, 2019
50 Pasangan nok genteng metal 1 24 hrs 0 days June 18, 2019 June 20, 2019
51 Pasangan rangka atap hollow 1 16 hrs 0 days June 21, 2019 June 22, 2019
52 Pasangan lisplang kayu 2/20 1 24 hrs 0 days June 22, 2019 June 25, 2019
53 Pasangan atap genteng metal 1 32 hrs 0 days June 26, 2019 June 29, 2019
56 Pemasangan langit-langit GRC 1 24 hrs 0 days July 1, 2019 July 3, 2019
57 Pemasangan list langit-langit kayu profil 1 16 hrs 0 days July 3, 2019 July 4, 2019
60 Pengecatan tembok baru interior 1 56 hrs 0 days July 5, 2019 July 12, 2019
61 Pengecatan tembok baru eksterior 1 32 hrs 0 days July 11, 2019 July 15, 2019
62 Pengecatan plafond 1 32 hrs 0 days July 15, 2019 July 18, 2019
63 Pengecatan lisplang 1 16 hrs 0 days July 19, 2019 July 20, 2019
66 Pemasangan kunci tanam biasa 1 16 hrs 0 days March 27, 2019 March 28, 2019
67 Pemasangan kunci tanam Kamar Mandi 1 8 hrs 0 days March 28, 2019 March 28, 2019
68 Pemasangan engsel pintu 1 24 hrs 0 days March 29, 2019 April 1, 2019
69 Pemasangan engsel jendela kupu-kupu 1 24 hrs 0 days April 2, 2019 April 5, 2019
70 Pemasangan handle pintu 1 16 hrs 0 days April 6, 2019 April 8, 2019
73 Pemasangan bak kontrol 1 16 hrs 0 days May 4, 2019 May 6, 2019
74 Pemasangan bak mandi 1 16 hrs 0 days May 7, 2019 May 8, 2019
75 Pemasangan floordrain 1 8 hrs 0 days May 8, 2019 May 8, 2019
76 Pemasangan closet duduk/monoblock 1 8 hrs 0 days May 9, 2019 May 9, 2019
77 Pemasangan bak cuci piring stainles steel 1 8 hrs 0 days May 10, 2019 May 10, 2019
78 Pemasangan kran Ø ¾” atau ½” 1 24 hrs 0 days May 11, 2019 May 14, 2019
81 Pemasangan pipa PVC tipe AW Ø 3/4” 1 24 hrs 0 days April 2, 2019 April 5, 2019
82 Pemasangan 1 m’ pipa PVC tipe AW diameter 4” 1 16 hrs 0 days April 6, 2019 April 8, 2019
85 Pasang Box Panel Lengkap MCB Standart 1 8 hrs 0 days March 30, 2019 March 30, 2019
86 Pasang Instalasi stop kontak 1 24 hrs 0 days March 30, 2019 April 2, 2019
87 Pasang Stop kontak 1 16 hrs 0 days April 4, 2019 April 5, 2019
88 Pasang Instalasi lampu 1 24 hrs 0 days April 5, 2019 April 8, 2019
89 Pasang saklar engkel 1 16 hrs 0 days April 9, 2019 April 10, 2019
90 Pasang saklar double 1 8 hrs 0 days April 10, 2019 April 10, 2019
91 Pasang Bolham Lampu LED BULB 1 16 hrs 0 days April 11, 2019 April 12, 2019

3 Kepala Tukang 2,800 hrs


ID Task Name Units Work Delay Start Finish
3 Pekerjaan Pengukuran & Bowplank 1 24 hrs 0 days January 4, 2019 January 7, 2019
10 Pancang Ulin 10/10-400 2 32 hrs 0 days January 17, 2019 January 18, 2019
12 Pemasangan 1 m3 batu kosong (aanstamping) 1 16 hrs 0 days January 21, 2019 January 22, 2019
13 Pemasangan 1 m3 Batu belah campuran 1:4 1 64 hrs 0 days January 22, 2019 January 30, 2019
17 Sloof 15 x 30 2 160 hrs 0 days February 2, 2019 February 15, 2019
18 Kolom 15 x 30 2 128 hrs 0 days February 16, 2019 February 25, 2019
19 Kolom 12 x 20 3 168 hrs 0 days February 21, 2019 February 28, 2019
20 Kolom 12 x 12 2 112 hrs 0 days February 25, 2019 March 4, 2019

Page 3
Who Does What as of July 20, 2020
Proyek Rumah Pak Fajar

ID Indicators Resource Name Work

"Kepala Tukang" continued


ID Task Name Units Work Delay Start Finish
21 Balok 15 x 30 2 128 hrs 0 days March 5, 2019 March 13, 2019
22 Balok 12 x 20 2 80 hrs 0 days March 7, 2019 March 12, 2019
23 Balok 20 x 10 2 80 hrs 0 days March 9, 2019 March 14, 2019
24 Ring balok 2 80 hrs 0 days March 19, 2019 March 23, 2019
25 Tangga 2 96 hrs 0 days March 12, 2019 March 18, 2019
26 Pelat dan dak 3 408 hrs 0 days February 25, 2019 March 15, 2019
29 Pemasangan 1m2 dinding bata merah tebal ½ batu campuran 1SP :4PP 1 72 hrs 0 days March 25, 2019 April 4, 2019
30 Pemasangan 1m2 dinding bata merah tebal ½ batu campuran 1SP :2PP 1 24 hrs 0 days April 2, 2019 April 5, 2019
31 Pemasangan 1 m2 plesteran 1SP : 4PP tebal 15 mm 1 96 hrs 0 days April 6, 2019 April 20, 2019
32 Pemasangan 1 m2 plesteran 1SP : 2PP tebal 15 mm 1 32 hrs 0 days April 20, 2019 April 24, 2019
33 Pemasangan 1 m2 acian 1 56 hrs 0 days April 25, 2019 May 3, 2019
36 Pas. Lantai Keramik 40x40 1 40 hrs 0 days May 15, 2019 May 20, 2019
37 Pas. Lantai Keramik 20x20 1 16 hrs 0 days May 21, 2019 May 22, 2019
38 Pas. Dinding keramik 20x20 1 24 hrs 0 days May 23, 2019 May 25, 2019
41 Pekerjaan kusen 1 16 hrs 0 days March 26, 2019 March 27, 2019
42 Pekerjaan daun pintu dan jendela (gandeng) 1 16 hrs 0 days March 27, 2019 March 28, 2019
43 Pekerjaan daun pintu 1 32 hrs 0 days March 28, 2019 April 1, 2019
44 Pekerjaan daun jendela 1 24 hrs 0 days April 2, 2019 April 5, 2019
47 Pemasangan rangka langit-langit 1 56 hrs 0 days May 27, 2019 June 11, 2019
48 Pasangan kuda - kuda kayu 6/12 1 40 hrs 0 days June 12, 2019 June 17, 2019
49 Pasangan gording 1 16 hrs 0 days June 15, 2019 June 17, 2019
50 Pasangan nok genteng metal 1 24 hrs 0 days June 18, 2019 June 20, 2019
51 Pasangan rangka atap hollow 1 16 hrs 0 days June 21, 2019 June 22, 2019
52 Pasangan lisplang kayu 2/20 1 24 hrs 0 days June 22, 2019 June 25, 2019
53 Pasangan atap genteng metal 1 32 hrs 0 days June 26, 2019 June 29, 2019
56 Pemasangan langit-langit GRC 1 24 hrs 0 days July 1, 2019 July 3, 2019
57 Pemasangan list langit-langit kayu profil 1 16 hrs 0 days July 3, 2019 July 4, 2019
60 Pengecatan tembok baru interior 1 56 hrs 0 days July 5, 2019 July 12, 2019
61 Pengecatan tembok baru eksterior 1 32 hrs 0 days July 11, 2019 July 15, 2019
62 Pengecatan plafond 1 32 hrs 0 days July 15, 2019 July 18, 2019
63 Pengecatan lisplang 1 16 hrs 0 days July 19, 2019 July 20, 2019
66 Pemasangan kunci tanam biasa 1 16 hrs 0 days March 27, 2019 March 28, 2019
67 Pemasangan kunci tanam Kamar Mandi 1 8 hrs 0 days March 28, 2019 March 28, 2019
68 Pemasangan engsel pintu 1 24 hrs 0 days March 29, 2019 April 1, 2019
69 Pemasangan engsel jendela kupu-kupu 4 96 hrs 0 days April 2, 2019 April 5, 2019
70 Pemasangan handle pintu 1 16 hrs 0 days April 6, 2019 April 8, 2019
73 Pemasangan bak kontrol 1 16 hrs 0 days May 4, 2019 May 6, 2019
74 Pemasangan bak mandi 1 16 hrs 0 days May 7, 2019 May 8, 2019
75 Pemasangan floordrain 1 8 hrs 0 days May 8, 2019 May 8, 2019
76 Pemasangan closet duduk/monoblock 1 8 hrs 0 days May 9, 2019 May 9, 2019
77 Pemasangan bak cuci piring stainles steel 1 8 hrs 0 days May 10, 2019 May 10, 2019
78 Pemasangan kran Ø ¾” atau ½” 1 24 hrs 0 days May 11, 2019 May 14, 2019
81 Pemasangan pipa PVC tipe AW Ø 3/4” 1 24 hrs 0 days April 2, 2019 April 5, 2019
82 Pemasangan 1 m’ pipa PVC tipe AW diameter 4” 1 16 hrs 0 days April 6, 2019 April 8, 2019
85 Pasang Box Panel Lengkap MCB Standart 1 8 hrs 0 days March 30, 2019 March 30, 2019
86 Pasang Instalasi stop kontak 1 24 hrs 0 days March 30, 2019 April 2, 2019
87 Pasang Stop kontak 1 16 hrs 0 days April 4, 2019 April 5, 2019
88 Pasang Instalasi lampu 1 24 hrs 0 days April 5, 2019 April 8, 2019

Page 4
Who Does What as of July 20, 2020
Proyek Rumah Pak Fajar

ID Indicators Resource Name Work

"Kepala Tukang" continued


ID Task Name Units Work Delay Start Finish
89 Pasang saklar engkel 1 16 hrs 0 days April 9, 2019 April 10, 2019
90 Pasang saklar double 1 8 hrs 0 days April 10, 2019 April 10, 2019
91 Pasang Bolham Lampu LED BULB 1 16 hrs 0 days April 11, 2019 April 12, 2019

4 Tukang 8,816 hrs


ID Task Name Units Work Delay Start Finish
3 Pekerjaan Pengukuran & Bowplank 2 48 hrs 0 days January 4, 2019 January 7, 2019
10 Pancang Ulin 10/10-400 3 48 hrs 0 days January 17, 2019 January 18, 2019
12 Pemasangan 1 m3 batu kosong (aanstamping) 4 64 hrs 0 days January 21, 2019 January 22, 2019
13 Pemasangan 1 m3 Batu belah campuran 1:4 5 320 hrs 0 days January 22, 2019 January 30, 2019
17 Sloof 15 x 30 5 400 hrs 0 days February 2, 2019 February 15, 2019
18 Kolom 15 x 30 5 320 hrs 0 days February 16, 2019 February 25, 2019
19 Kolom 12 x 20 5 280 hrs 0 days February 21, 2019 February 28, 2019
20 Kolom 12 x 12 6 336 hrs 0 days February 25, 2019 March 4, 2019
21 Balok 15 x 30 5 320 hrs 0 days March 5, 2019 March 13, 2019
22 Balok 12 x 20 6 240 hrs 0 days March 7, 2019 March 12, 2019
23 Balok 20 x 10 6 240 hrs 0 days March 9, 2019 March 14, 2019
24 Ring balok 5 200 hrs 0 days March 19, 2019 March 23, 2019
25 Tangga 4 192 hrs 0 days March 12, 2019 March 18, 2019
26 Pelat dan dak 8 1,088 hrs 0 days February 25, 2019 March 15, 2019
29 Pemasangan 1m2 dinding bata merah tebal ½ batu campuran 1SP :4PP 7 504 hrs 0 days March 25, 2019 April 4, 2019
30 Pemasangan 1m2 dinding bata merah tebal ½ batu campuran 1SP :2PP 3 72 hrs 0 days April 2, 2019 April 5, 2019
31 Pemasangan 1 m2 plesteran 1SP : 4PP tebal 15 mm 10 960 hrs 0 days April 6, 2019 April 20, 2019
32 Pemasangan 1 m2 plesteran 1SP : 2PP tebal 15 mm 1 32 hrs 0 days April 20, 2019 April 24, 2019
33 Pemasangan 1 m2 acian 7 392 hrs 0 days April 25, 2019 May 3, 2019
36 Pas. Lantai Keramik 40x40 5 200 hrs 0 days May 15, 2019 May 20, 2019
37 Pas. Lantai Keramik 20x20 2 32 hrs 0 days May 21, 2019 May 22, 2019
38 Pas. Dinding keramik 20x20 3 72 hrs 0 days May 23, 2019 May 25, 2019
41 Pekerjaan kusen 3 48 hrs 0 days March 26, 2019 March 27, 2019
42 Pekerjaan daun pintu dan jendela (gandeng) 2 32 hrs 0 days March 27, 2019 March 28, 2019
43 Pekerjaan daun pintu 3 96 hrs 0 days March 28, 2019 April 1, 2019
44 Pekerjaan daun jendela 4 96 hrs 0 days April 2, 2019 April 5, 2019
47 Pemasangan rangka langit-langit 7 392 hrs 0 days May 27, 2019 June 11, 2019
48 Pasangan kuda - kuda kayu 6/12 6 240 hrs 0 days June 12, 2019 June 17, 2019
49 Pasangan gording 2 32 hrs 0 days June 15, 2019 June 17, 2019
50 Pasangan nok genteng metal 1 24 hrs 0 days June 18, 2019 June 20, 2019
51 Pasangan rangka atap hollow 2 32 hrs 0 days June 21, 2019 June 22, 2019
52 Pasangan lisplang kayu 2/20 3 72 hrs 0 days June 22, 2019 June 25, 2019
53 Pasangan atap genteng metal 2 64 hrs 0 days June 26, 2019 June 29, 2019
56 Pemasangan langit-langit GRC 3 72 hrs 0 days July 1, 2019 July 3, 2019
57 Pemasangan list langit-langit kayu profil 3 48 hrs 0 days July 3, 2019 July 4, 2019
60 Pengecatan tembok baru interior 2 112 hrs 0 days July 5, 2019 July 12, 2019
61 Pengecatan tembok baru eksterior 2 64 hrs 0 days July 11, 2019 July 15, 2019
62 Pengecatan plafond 2 64 hrs 0 days July 15, 2019 July 18, 2019
63 Pengecatan lisplang 2 32 hrs 0 days July 19, 2019 July 20, 2019
66 Pemasangan kunci tanam biasa 5 80 hrs 0 days March 27, 2019 March 28, 2019
67 Pemasangan kunci tanam Kamar Mandi 2 16 hrs 0 days March 28, 2019 March 28, 2019

Page 5
Who Does What as of July 20, 2020
Proyek Rumah Pak Fajar

ID Indicators Resource Name Work

"Tukang " continued


ID Task Name Units Work Delay Start Finish
68 Pemasangan engsel pintu 4 96 hrs 0 days March 29, 2019 April 1, 2019
69 Pemasangan engsel jendela kupu-kupu 1 24 hrs 0 days April 2, 2019 April 5, 2019
70 Pemasangan handle pintu 3 48 hrs 0 days April 6, 2019 April 8, 2019
73 Pemasangan bak kontrol 5 80 hrs 0 days May 4, 2019 May 6, 2019
74 Pemasangan bak mandi 5 80 hrs 0 days May 7, 2019 May 8, 2019
75 Pemasangan floordrain 2 16 hrs 0 days May 8, 2019 May 8, 2019
76 Pemasangan closet duduk/monoblock 2 16 hrs 0 days May 9, 2019 May 9, 2019
77 Pemasangan bak cuci piring stainles steel 2 16 hrs 0 days May 10, 2019 May 10, 2019
78 Pemasangan kran Ø ¾” atau ½” 3 72 hrs 0 days May 11, 2019 May 14, 2019
81 Pemasangan pipa PVC tipe AW Ø 3/4” 3 72 hrs 0 days April 2, 2019 April 5, 2019
82 Pemasangan 1 m’ pipa PVC tipe AW diameter 4” 3 48 hrs 0 days April 6, 2019 April 8, 2019
85 Pasang Box Panel Lengkap MCB Standart 2 16 hrs 0 days March 30, 2019 March 30, 2019
86 Pasang Instalasi stop kontak 3 72 hrs 0 days March 30, 2019 April 2, 2019
87 Pasang Stop kontak 3 48 hrs 0 days April 4, 2019 April 5, 2019
88 Pasang Instalasi lampu 4 96 hrs 0 days April 5, 2019 April 8, 2019
89 Pasang saklar engkel 1 16 hrs 0 days April 9, 2019 April 10, 2019
90 Pasang saklar double 1 8 hrs 0 days April 10, 2019 April 10, 2019
91 Pasang Bolham Lampu LED BULB 1 16 hrs 0 days April 11, 2019 April 12, 2019