Critical Tasks As of July 20, 2020 Proyek Rumah Pak Fajar
Critical Tasks As of July 20, 2020 Proyek Rumah Pak Fajar
ID Indicators Task Mode Task Name Duration Baseline Start Baseline Finish
0 Auto Scheduled Proyek Rumah Pak Fajar 163 days January 1, 2019 July 24, 2019
57 Manually Scheduled
Pemasangan list langit-langit kayu profil 2 days July 3, 2019 July 4, 2019
ID Successor Name Type Lag
60 Pengecatan tembok baru interior FS 0 days
60 Manually Scheduled
Pengecatan tembok baru interior 7 days July 5, 2019 July 12, 2019
ID Successor Name Type Lag
61 Pengecatan tembok baru eksterior FS -2 days
61 Manually Scheduled
Pengecatan tembok baru eksterior 4 days July 11, 2019 July 15, 2019
ID Successor Name Type Lag
62 Pengecatan plafond FS -1 day
62 Manually Scheduled
Pengecatan plafond 4 days July 15, 2019 July 18, 2019
ID Successor Name Type Lag
63 Pengecatan lisplang FS 0 days
63 Manually Scheduled
Pengecatan lisplang 2 days July 19, 2019 July 20, 2019
ID Successor Name Type Lag
94 Pek. Septictank Biofil kap. 6,00 m3 uk. 2 X 1,5 X 2 m FS 0 days
93 Manually Scheduled
PEKERJAAN SEPTICTANK DAN RESAPAN 3 days July 22, 2019 July 24, 2019
94 Manually Scheduled
Pek. Septictank Biofil kap. 6,00 m3 uk. 2 X 1,5 X 2 m 3 days July 22, 2019 July 24, 2019
ID Successor Name Type Lag
95 SERAH TERIMA RUMAH FS 0 days
95 Auto Scheduled SERAH TERIMA RUMAH 0 days July 24, 2019 July 24, 2019
Page 1
Critical Tasks as of July 20, 2020
Proyek Rumah Pak Fajar
July 5, 2019 July 12, 2019 57 Pekerja[3],Tukang [2],Kepala Tukang,Mandor,Cat dasar precoat[1 klg],Cat penutup[1 klg]
July 11, 2019 July 15, 2019 60FS-2 days Pekerja[3],Tukang [2],Kepala Tukang,Mandor,Cat Dasar Exterior[1 klg],Cat penutup[1 klg]
July 15, 2019 July 18, 2019 61FS-1 day Pekerja[2],Tukang [2],Kepala Tukang,Mandor,Cat penutup[1 klg]
July 19, 2019 July 20, 2019 62 Pekerja[2],Tukang [2],Kepala Tukang,Mandor,Meni kayu[1 klg],Plamir[1 klg],Cat tembok interior[1 klg],Cat Kayu / Besi[1 klg],Kuas[1