Professional Documents
Culture Documents
Running Head: Project Management 1
Running Head: Project Management 1
Running Head: Project Management 1
Name
Course
Tutor
Date
PROJECT MNAGEMENT 2
Question 1
Fast-tracking in project management defines the act of simultaneously running two activities
of schedules in activity implementation and, as such, has no additional cost to the process. On
the other hand, crashing entails frantic efforts by a project manager to rush through the
completion of a project’s activities. Usually, crashing involves the use of additional financial
costs since the changes made are not necessarily limited to rescheduling. To reduce project
duration, crash in an effective way of minimizing time, and there are various processes that, if
For instance, a project manager ought to establish the most cost-effective crash sequence to
achieve optimum results. In so doing, other processes involved include defining project logic,
adding a duration for each activity, and calculating the crash cost for each activity. Reducing
the number of project activities by focusing on the critical project path ensures minimized
durational resources while maintaining the project integrity regarding its efficacy. When the
window for durational rescheduling becomes shorter, a more radical approach is required.
The only realistic option lies in crashing the network to its crash limit, which requires the
Question 2
like slack or float are quite important. During PM, two types of slacks manifest; total slack
and free slack. The former describes a situation whence an activity can be delayed without
impact on the finish durations for the whole project. On the other hand, free black defines the
allowance by which a project activity can be delayed without affecting the subsequent
PROJECT MNAGEMENT 3
activity. For the project manager, planning is an essential component of the job.
Consequently, time management is an essential factor, slacking, therefore, free and total are
consequential to the completion of a project and the financial implications that come with it.
Budgeting, resource allocation, and personnel identification are crucial aspects of project
("Total Slack and Free Slack for Project Decisions - Advisicon", 2020).
PROJECT MNAGEMENT 4
References
https://www.pmi.org/learning/library/performing-crash-analysis-alternative-cost-
schedule-6750
Mabutas, Y. (2020). PMP® Exam Tip: Crashing & Fast Tracking explained. Retrieved 16
exam/tips/318-pmp-exam-tip-crashing-fast-tracking-explained.
Total Slack and Free Slack for Project Decisions - Advisicon. (2020). Retrieved 16
decisions/