Professional Documents
Culture Documents
Chapter-Four: Time Control and Monitoring
Chapter-Four: Time Control and Monitoring
Chapter-Four: Time Control and Monitoring
Introduction
2
CHAPTER-FOUR
of the activities and computation of resources required at
different stages in time.
Every construction projects are time bounded.
Due to the above nature, based on the contract time, delays
Time control and monitoring
results to penalties while early completion might earn rewards
There may be many reasons both foreseeable and
unforeseeable, for non-completion of a project on the
intended completion time.
3 …Cont’d 4
…Cont’d
The absence of a project time plan almost makes certain that Planning requires an intimate knowledge of construction
a project cannot be completed on schedule without incurring methods combined with the ability to visualize distinct work
extra costs.
A plan prepared well before the commencement of elements and to establish their mutual interdependencies.
construction project can be instrumental in: Construction planning is a fundamental and challenging
Formulating directions, activity in the management and execution of construction
Coordinating functions,
projects.
Setting targets,
Forecasting resources. A good construction plan is the basis for developing the
Budgeting costs, budget and the schedule for works.
Optimum utilization and orderly arrangements of resources,
Control of cost and progress of executed work,
Controlling performance and motivating people
1
5/14/2013
Construction planning consists of the following basic The approved Master schedule, called the schedule
steps baseline, is a component of the overall project plan.
Choice of technology and method of construction, It provides the basis for measuring and reporting
Definition of work tasks, schedule performance.
Creating logical relationship among individual tasks
In PPA, the general conditions of contract Clause 29-
Estimation of the required resources and durations for
32 has clear stipulation on project schedule(program),
individual tasks, and
2
5/14/2013
…Cont’d …Cont’d
9 10
…Cont’d …Cont’d
11 12
Clause 32, (Early Warning)
Clause 30, (Delays ordered by the Engineer) Clause 32.1
Clause 30.1 The Contractor shall warn the Engineer at the earliest
The Engineer may instruct the Contractor to delay the start or opportunity of specific likely future events or circumstances that
progress of any activity within the Works. may adversely affect the quality of the work, increase the
Clause 31, ( Management Meetings) Contract Price or delay the execution of the Works.
The Engineer may require the Contractor to provide an
Clause 31.1
estimate of the expected effect of the future event or
Either the Engineer or the Contractor may require the other to circumstance on the Contract Price and Completion Date
attend a Management meeting,
Clause 32.2
Clause 31.2
The Contractor shall cooperate with the Engineer in making and
The Engineer shall record the business of management meetings considering proposals for how the effect of such an event or
and provide copies of the record to those attending the circumstance can be avoided or reduced by anyone involved in
meeting and to the Employer the work.
3
5/14/2013
Construction work plan and review Construction work plan and review
4
5/14/2013
Change requests
Performance reports
Status reporting_ describing where the project now stands Change requisites may occur in many forms-oral or
Progress reporting- describing what the project team has accomplished
written, direct or indirect, externally or internally
Forecasting- predicting future project status and progress.
initiated, and legally mandated or optional.
Performance reporting should generally provide information on scope,
schedule, cost, and quality. Changes may require extending the schedule or
may allow accelerating it.
5
5/14/2013
6
5/14/2013
Reports …Formats
26
Date
Time, duration Site Diary
Weather conditions
Persons present
Progress report
Percentage of work completed by trade
Schedule
Work progress compared to schedule
Work now being accomplished, work scheduled before next visit
Questions raised by the contractor or owner
Determinations made by the engineer
Any questions or actions which remain pending for appropriate later
attention.