This document contains an assignment asking students to analyze a project schedule using information provided in a table. The table lists 14 project activities with predecessors, duration in days, daily costs, and total costs to be calculated. Students are asked to:
1) Create an AON (Arrow diagramming method of network calculations) diagram to visualize activity flow.
2) Calculate the total time and cost to complete the project if no delays occur.
3) Determine the latest start and finish dates for activities to meet the project completion time.
4) Determine the earliest start and finish dates if no delays occur.
5) Identify critical activities where any delay would delay project completion.
6) Determine how much delay can
This document contains an assignment asking students to analyze a project schedule using information provided in a table. The table lists 14 project activities with predecessors, duration in days, daily costs, and total costs to be calculated. Students are asked to:
1) Create an AON (Arrow diagramming method of network calculations) diagram to visualize activity flow.
2) Calculate the total time and cost to complete the project if no delays occur.
3) Determine the latest start and finish dates for activities to meet the project completion time.
4) Determine the earliest start and finish dates if no delays occur.
5) Identify critical activities where any delay would delay project completion.
6) Determine how much delay can
This document contains an assignment asking students to analyze a project schedule using information provided in a table. The table lists 14 project activities with predecessors, duration in days, daily costs, and total costs to be calculated. Students are asked to:
1) Create an AON (Arrow diagramming method of network calculations) diagram to visualize activity flow.
2) Calculate the total time and cost to complete the project if no delays occur.
3) Determine the latest start and finish dates for activities to meet the project completion time.
4) Determine the earliest start and finish dates if no delays occur.
5) Identify critical activities where any delay would delay project completion.
6) Determine how much delay can
Name ---------------------------------------- Registration # ---------------------------------
Class ---------------------------------------- Section ---------------------------------
ONLINE ASSIGNMENT # 2 Information Technology Project Management
Activity Description Predecessors Days Daily Cost Total Cost
A Excavate ---- 2X Rs. 10,000 ----------? B Lay the foundation A 4X Rs. 8,000 ----------? C Put up the rough wall B 9X Rs. 6,500 ----------? D Put up the roof C 6X Rs. 3,500 ----------? E Install the exterior plumbing C 4X Rs. 2,500 ----------? F Install the interior plumbing E 5X Rs. 12,500 ----------? G Put up the exterior siding D 7X Rs. 11,500 ----------? H Do the exterior painting E,G 9X Rs. 5,500 ----------? I Do the electrical work C 7X Rs. 8,500 ----------? J Put up the wallboard F,I 8X Rs. 10,500 ----------? K Install the flooring J 4X Rs. 15,500 ----------? L Do the interior painting J 5X Rs. 9,500 ----------? M Install the exterior fixtures H 2X Rs. 7,500 ----------? N Install the interior fixtures K,L 6X Rs. 5,500 ----------? Refer the above table and answer the following questions:- Please note that “X” is the extreme right digit of your registration number. ( X=3 for Reg 1263 & X=5 for Reg 1275 etc.) Q. # 1. How can the project be displayed graphically to better visualize the flow of the activities? Please use AON technique only Q. # 2. What is the total time and cost required to complete the project if no delays occur? Q. # 3. When do the individual activities need to start and finish (at the latest) to meet this project completion time? Q. # 4. When can the individual activities start and finish (at the earliest) if no delays occur?) Q. # 5. Which are the critical bottleneck activities where any delays must be avoided to prevent delaying project completion? Q. # 6. For the other activities, how much delay can be tolerated without delaying project completion?