ONLINE ASSIGNMENT # 2
Information Technology Project Management

Activity Description Predecessors Days Daily Cost Total Cost


A Excavate ---- 2X Rs. 10,000 ----------?
B Lay the foundation A 4X Rs. 8,000 ----------?
C Put up the rough wall B 9X Rs. 6,500 ----------?
D Put up the roof C 6X Rs. 3,500 ----------?
E Install the exterior plumbing C 4X Rs. 2,500 ----------?
F Install the interior plumbing E 5X Rs. 12,500 ----------?
G Put up the exterior siding D 7X Rs. 11,500 ----------?
H Do the exterior painting E,G 9X Rs. 5,500 ----------?
I Do the electrical work C 7X Rs. 8,500 ----------?
J Put up the wallboard F,I 8X Rs. 10,500 ----------?
K Install the flooring J 4X Rs. 15,500 ----------?
L Do the interior painting J 5X Rs. 9,500 ----------?
M Install the exterior fixtures H 2X Rs. 7,500 ----------?
N Install the interior fixtures K,L 6X Rs. 5,500 ----------?
Refer the above table and answer the following questions:-
Please note that “X” is the extreme right digit of your registration number.
( X=3 for Reg 1263 & X=5 for Reg 1275 etc.)
Q. # 1. How can the project be displayed graphically to better visualize the flow of the activities?
Please use AON technique only
Q. # 2. What is the total time and cost required to complete the project if no delays occur?
Q. # 3. When do the individual activities need to start and finish (at the latest) to meet this
project completion time?
Q. # 4. When can the individual activities start and finish (at the earliest) if no delays occur?)
Q. # 5. Which are the critical bottleneck activities where any delays must be avoided to prevent
delaying project completion?
Q. # 6. For the other activities, how much delay can be tolerated without delaying project
completion?