Download as xls, pdf, or txt
Download as xls, pdf, or txt
You are on page 1of 453

ITEM Unit Rate as per

as TS/HPSR
per
56
DNIT 1 Wiring for light point/ Fan point/ exhaust point/ Call bell point with 1.5 sqmm Nos. 592.00
PVC insulated head resistant flame retardant (HRFR) and low smoke single
core(flexible) copper conductor cable in surface/recessed PVC conduit and
earthing the light point with 1.5sq.mm. HRFRL/PVC insulated single core
copper conductor cable as required Group C
592.00
Add 12% GST 71.04
663.04
Add 1% Labour cess 6.63
Total:- 669.67
Say 670.00
57 2 Wiring for circuit sub main with 2x1.5 Sq.mm PVC insulated heat resistant Rmt 96.00
flame retardant(HRFR) and low smoke single core (flexible) copper
conoductor cable in surface/recessed PVC conduit along with 1 No. 1.5
Sq.mm, HRFRLS/PVC insulated single core copper conductor cable for
earthing as required.
96.00
Add 12% GST 11.52
107.52
Add 1% Labour cess 1.08
Total:- 108.60
Say 109.00
58 3 Wiring for power plug with 2x4sq.mm PVC insulated 9head resistant flame Rmt 148.00
retardant (HRFR) and low smoke single core (flexible) copper conductor cable
in surface/recessed PVC conduit alongwith 1 to 4 Sq.mm HRFRLS/PVC
insulated single core copper conductor cable for earthing as required.

148.00
Add 12% GST 17.76
165.76
Add 1% Labour cess 1.66
Total:- 167.42
Say 167.00
59 4 Wiring for sub main wiring with 2x6sqmm of PVC insulated copper conductor Rmt 199.00
single core cable in surface/ recessed PVC conduit as required.

199.00
Add 12% GST 23.88
222.88
Add 1% Labour cess 2.23
Total:- 225.11
Say 225.00
60 5 Supplying and fixing plain pendant with 16/0.20mm twin twisted flexible PVC Nos. 129.00
in swaled cotton braided copper cable and backlite pendand holder including
connection etc. as required.
129.00
Add 12% GST 15.48
144.48
Add 1% Labour cess 1.44
Total:- 145.92
Say 146.00
61 6 Supplying and fixing metal box of 180 mm x 100mm x60mm deep (nominal Nos. 68.00
size) on surface or in recess with suitable size phenolic laminated sheat cover
in the front including P/F 3 pin 5/6 amps socket outlet and 5/6 amps tumbler
P/T switch connections painting etc. as required (for light plugs).

68.00
Add 12% GST 8.16
76.16
Add 1% Labour cess 0.76
Total:- 76.92
Say 77.00
62 7 Providing and fixing shock proof slim decorative extruded fixture with domestic Nos. 759.00
electronic ballast suitable for 28 Watt FTL (T5) complete with all accessories
(excluding the T-5 tube) connections, testing and commissioning etc. as
required ceiling rosh

759.00
Add 12% GST 91.08
850.08
Add 1% Labour cess 8.50
Total:- 858.58
Say 859.00
63 8 Providing, installation, testing and commissioning of ceiling fan and regulator Nos. 1548.00
including wiring the down rod of standard length (upto 30cm) with 1.5 Sqmm
PVC insulated copper conductor single core cable as required ceiling fan
1200mm sweep (Cat A) within all leads and lifts as per direction by the
Engineer-in-charge

1548.00
Add 12% GST 185.76
1733.76
Add 1% Labour cess 17.34
Total:- 1751.10
Say 1751.00
64 9 S/F 40 Amp rating double pole ( single phase and neutral) 240 Volts (RCCB) No. 1940.00
having a sensivity current upto 300 milliampers in the existing MCB DB
complete with connections testing and commissioning etc. as required.

1940.00
Add 12% GST 232.80
2172.80
Add 1% Labour cess 21.73
Total:- 2194.53
Say 2195.00
65 10 Supplying and erection of 6 Amps. To 32 Amps. Rating 10 KA breaking Nos. 153.00
capacity, 240 volts, C curves, miniature circuit beaker of following poles in the
existing MCB DB complete with connections etc. as required Single pole Cat.
A
153.00
Add 12% GST 18.36
171.36
Add 1% Labour cess 1.71
Total:- 173.07
Say 173.00
66 11 S/F 40 Amp rating double pole 240 Volts. Insulator in the existing MCB DB No. 652.00
complete with connection testing and commissioning etc.
652.00
Add 12% GST 78.24
730.24
Add 1% Labour cess 7.30
Total:- 737.54
Say 738.00
67 12 Providing, installing, testing and commissioning of pre wired flourecent tube Nos. 794.00
fitting complete with ballast, starter and capacitors but excluding florescent
tube rod, suitale to operate on 230 volts, single phase AC supply directly on
surface with copper wiring as required 1x40 watt category "B".

794.00
Add 12% GST 95.28
889.28
Add 1% Labour cess 8.89
Total:- 898.17
Say 898.00
68 13 Supplying and fixing following rating Piano type switch/socket on the existing Nos. 58.00
switch box/cover including connections etc. as required.
58.00
Add 12% GST 6.96
64.96
Add 1% Labour cess 0.65
Total:- 65.61
Say 66.00
69 14 Supplying and erection of bulk head fitting all size and slopes containing one Nos. 385.00
all size and slope containing one GLS lamp holder wire guard and lock
complete in all respedct bulk head fitting Cat"B"
385.00
Add 12% GST 46.20
431.20
Add 1% Labour cess 4.31
Total:- 435.51
Say 436.00
70 15 Suplying and laying 8 SWG copper wire at 0-50 mtr. Below ground level for Rmt 89.00
conductor earth electrode including soldering etc. as required.
89.00
Add 12% GST 10.68
99.68
Add 1% Labour cess 1.00
Total:- 100.68
Say 101.00
Rate of Materials
Name of work :
S.No. Description of items unit Rate
1 Cement Tonne 4500
2 Sand Cum 375
3 M.S. Flate Qtl. 4500
stone Agg.40mm Cum. 440
--- do------- 20 mmm. Cum. 465
-----do------10mm Cum. 475
4 Boulder/ plums Cum. 300
5 Building stones Cum. 350
6 Through and bond stone Each 7
7 Bricks Per 1000 7000
8 Tor Steel Qtl. 4600
9 Welding by electric plant Per cm. 2
10 Barbed wire: Qtl. 2200.00
11 2nd class deodar wood :(Scantling) Cum. 45000
2nd class deodar wood :(Planks) Cum. 49720
13 Kail wood 2nd Class Scantling Cum. 31240
14 Ballies,125mm dia Metre 110
15 Planks (2nd class kail wood) Cum. 29728
16 C.I. Man hole cover & frame Kg. 30
17 Drilling equipment Day 2054.69
18 Special gelatine(80%) Kg. 57
19 Detonators(ordinary) 100 Nos. 350
20 Safety fuse wire(coil 10m length) Coil 18
21 C.I. Rungs Each 90
22 G.I Wire Kg. 36.00
Bitumen Tone 12000.00
23 RCC Pipe
150mm dia Collar Pipe
NP2 Each 36 Rmt 96
P1 Each 0 Rmt 146.4
P2 Each 0 Rmt 169.2
P3 Each 36 Rmt 160
250mm dia
NP2 Each 17 Rmt 128
P1 Each 17 Rmt 195
P2 Each 17 Rmt 310
P3 Each 17 Rmt 354
300mm dia 0
NP2 Each 25 Rmt 170.5
P1 Each 25 Rmt 223
P2 Each 25 Rmt 414
P3 Each 25 Rmt 524
350mm dia 0
NP2 Each 38.5 Rmt 265
P1 Each 38.5 Rmt 285
P2 Each 38.5 Rmt 385
P3 Each 38.5 Rmt 458
400mm dia 0
NP2 Each 49 Rmt 273
P1 Each 49 Rmt 325
P2 Each 49 Rmt 367
P3 Each 49 Rmt 516
Without With P.H.
Rates of Labour. P.Hol.
1 Beldar Each 225 262.5
2 Bhisti Each 225 262.5
3 Mason Ist class Each 267 311.5
4 Mason II nd class Each 267 311.5
5 Mate Each 225 262.5
6 Black Smith Ist class Each 267 311.5
7 Black Smith IIst class Each 267 311.5
8 Carpenter 1 nd class Each 267 311.5
9 Carpenter 2 nd class Each 267 311.5
10 Painter 1st class Each 267 311.5
11 Painter 2nd class Each 240.0 280
12 Plumber (Fitter) Each 267 311.5
13 Plumber (Assistant Fitter) Each 267 311.5
14 Hole Driller Each 225 262.5
15 Blaster Each 225 262.5
16 Stone dresser Each 225 262.5
17 Chisller / Broker Each 225 262.5
18 Bandhani Each 225 262.5

Certified that the rate of material are lowest prevailing


market/issue rates and the rates of labour are approved one.

Executive Engineer,
IPHDivision No.II
Kullu at Bhunter
Analysis of rates
Excavation in foundation and trenches etc.
Detail of cost for 10 cu.m
Sr.
Description of Items Qty. Rate Unit Amount
No
1 Pick Work
Beldar 8.32 Nos. 262.50 each 2184.00
Bhisti 0.28 Nos. 262.50 each 73.50
Total:- 2257.50

Add 1.5% water charges. 33.8625


Total:- 2291.36
Add 10% C.P and 5% over head charges 343.70
except on cement.
Total:- 2635.07

Cost for 10cum.- 2635.07


Cost for 1cum.- 263.51
Say Rs. 263.51

2 Jumper work
Detail of cost for 10 cu.m
Drilling equipment 0.045 P/Day 2054.69 P/Day 92.46
Explosive
Special gelatine 80% 0.63 Kg 57.00 Kg 35.91
Detonators 3.00 Nos. 350.00 100 N. 10.5
Safty fuse coil 0.25 coil 18.00 coil 4.50
Total:- 50.91
Labour
Drillers 0.135 Nos. 262.50 each 35.4375
Blaster 0.09 Nos. 262.50 each 23.63
Beldar 16.00 Nos. 262.50 each 4200
Total:- 4259.06
Total:- 4402.43
Add for 10% C.P. and 5% over head charges. 660.37

Total:- 5062.80

184.45 Cost per cum.= 506.28


151.9 Average rate
336.34 Pick work 80% and jumper work 20% = 336.34

Say Rs. 336.00

Executive Engineer,
IPHDivision No.II
Kullu at Bhunter
Analysis of rates
Cutting in earth work
Detail of cost for 10 cu.m
Sr.
Description of Items Qty. Rate Unit Amount
No
1 Pick Work
Beldar 5 Nos. 262.50 each 1312.50
Total:- 1312.50

Total:- 1312.50
Add 10% C.P and 5% over head charges 196.88
except on cement.
Total:- 1509.38

Cost for 10cum.- 1509.38


Cost for 1cum.- 150.94
Say Rs. 150.94

2 Jumper work
Detail of cost for 10 cu.m
Drilling equipment 0.045 P/Day 2054.69 P/Day 92.46
Explosive
Special gelatine 80% 0.63 Kg 57.00 Kg 35.91
Detonators 3.00 Nos. 350.00 100 10.5
Safty fuse coil 0.25 coil 18.00 coil 4.50
Total:- 50.91
Labour
Drillers 0.135 Nos. 262.50 each 35.4375
Blaster 0.09 Nos. 262.50 each 23.63
Beldar 10.00 Nos. 262.50 each 2625
Total:- 2684.0625
Total:- 2827.43
Add for 10% C.P. and 5% over head charges. 424.12

Total:- 3251.55

Cost per cum.= 325.15


Average rate
Pick work 50% and jumper work 50% = 238.05

Say Rs. 238.00

Executive Engineer,
IPHDivision No.II
Kullu at Bhunter
Analysis of rates
Excavation in Drains and chanel.
Detail of cost for 10 cu.m
Sr.
Description of Items Qty. Rate Unit Amount
No
1 Pick Work
Beldar 6.66 N os. 262.50 each 1748.25
Bhisti 0.22 Nos. 262.50 each 57.75
Total:- 1806.00

Add 1.5% water charges. 27.09


Total:- 1833.09
Add 10% C.P and 5% over head charges 274.96
except on cement.
Total:- 2108.05
Add GST @12% 252.97
2361.02
Add 1% labour cess 21.08
2382.10
Cost for 10cum.- 2382.10
Cost for 1cum.- 238.21
Say Rs. 238.21

2 Jumper work
Detail of cost for 10 cu.m
Drilling equipment 0.045 3600 P/Day 162.00
Explosive
Special gelatine 80% 0.63 Kg 75.00 Kg 47.25
Detonators 3.00 Nos. 300.00 100 9
Safty fuse coil 0.25 coil 30.00 coil 7.50
Total:- 63.75
Labour
Drillers 0.135 Nos. 262.50 each 35.44
Blaster 0.09 Nos. 262.50 each 23.63
Beldar 12.80 Nos. 262.50 each 3360.00
Total:- 3419.06
Total:- 3644.81
Add for 10% C.P. and 5% over head charges. 3419.06 512.86
Total:- 4157.67
Add GST @12%( Except equipment & explosive) 3419.06 410.29
4567.96
Add 1% labour cess 41.58
4609.54
Cost per cum.= 460.95
Average rate
Pick work 50% 119.11
jumper work 50% 230.48

Say Rs. 350.00 only Executive Engineer,


IPHDivision Thunag
Analysis of rates
Dressisng of Beds and prepration of sub-grade for CC lining
Detail of cost for 10 cu.m
Sr.
Description of Items Qty. Rate Unit Amount
No
1 Pick Work
Beldar 1.30 Nos. 262.50 each 341.25
Total:- 341.25

Add 10% C.P and 5% over head charges 51.19


except on cement.
Total:- 392.44

Cost for 10sqmt. 392.44


Cost for 1sqmt. 39.24

Analysis of rates
Dressisng of sides and prepration of sub-grade for CC lining
Detail of cost for 10 cu.m
Sr.
Description of Items Qty. Rate Unit Amount
No
1 Pick Work
Beldar 1.80 Nos. 262.50 each 472.50
Total:- 472.50

Add 10% C.P and 5% over head charges 70.88


except on cement.
Total:- 543.38

Cost for 10sqmt. 543.38


Cost for 1sqmt. 54.34
Say Rs. 54.34
Executive Engineer,
IPHDivision No.II
Kullu at Bhunter
Analysis of rates
Providing and laying of cement concrere 1:4:8
Detail of cost for one cu.m
Sr.
Description of Items Qty. Rate Unit Amount
No
1 Materials
Stone aggregate 40mm 0.65 cum. 440.00 cum. 286.00
Stone aggregate 20mm 0.24 cum. 465.00 cum. 111.60
Sand 0.47 cum. 375.00 cum. 176.25
Cement 0.17 Tone 4500.00 Tone 765.00
Total:- 1338.85

2 Carriage
Stone aggregate 40mm
0.00 Km.by machenical transport 0.65 cum. 0 cum. 0.00
0.5 Km. by head load 0.65 cum. 443.11 cum. 288.02

Sand
7.00 Km by machenical transport 0.47 cum. 277.09 cum. 130.23
0 Km. by head load 0.47 cum. 0.00 cum. 0.00

Stone aggregate below 40mm:-


0.00 Km by machenical transport 0.24 cum. 277.09 cum. 66.50
0.5 Km. by head load 0.24 cum. 0.00 cum. 0.00

Cement
25.00 Km by machenical transport 0.17 Tone 382.17 Tone 64.97
0 Km. by head load 0.17 Tone 0.00 Tone 0.00

Total:- 549.72
3 Labor
Beldar 2.09 Nos. 262.50 each 548.63
Bhisti 0.27 Nos. 262.50 each 70.88
Mason 1st class 0.05 Nos. 311.50 each 15.58
Mason 2nd class 0.05 Nos. 311.50 each 15.58
Mate 0.04 Nos. 262.50 each 10.50
Beldar for extra rammingn 0.25 Nos. 262.50 each 65.63
Sundaries L.S. 15.00
Total:- 741.78

Total:-1+2+3 2630.35

Add 1.5% water charges. 39.46


Total:- 2669.80
Add 10% C.P and 5% over head charges except on
cement. 285.72

2955.53
Say Rs. 2955.53

Executive Engineer,
IPHDivision No.II
Kullu at Bhunter
Analysis of rates
Providing and laying of cement concrere 1:6:12
Detail of cost for one cu.m
Sr.No Description of Items Qty. Rate Unit Amount
1 Materials
Stone aggregate 40mm 0.65 cum. 440.00 cum. 286.00
Stone aggregate 20mm 0.24 cum. 465.00 cum. 111.60
Sand 0.47 cum. 375.00 cum. 176.25
Cement 0.11 Tone 4500.00 Tone 495.00
Total:- 1068.85

2 Carriage
Stone aggregate 40mm
0.00 Km by machenical transport 0.65 cum. 0 cum. 0.00
0.5 Km. by head load 0.65 cum. 443.11 cum. 288.02

Sand
7.00 Km by machenical transport 0.47 cum. 277.09 cum. 130.23
0 Km. by head load 0.47 cum. 0.00 cum. 0.00

Stone aggregate below 40mm:-


7.00 Km by machenical transport 0.24 cum. 277.09 cum. 66.50
0 Km. by head load 0.24 cum. 0.00 cum. 0.00

Cement
25.00 Km by machenical transport 0.11 Tone 382.17 Tone 42.04
0 Km. by head load 0.11 Tone 0.00 Tone 0.00

Total:- 526.79
3 Labour
Beldar 2.09 Nos. 262.50 each 548.63
Bhisti 0.27 Nos. 262.50 each 70.88
Mason 1st class 0.05 Nos. 311.50 each 15.58
Mason 2nd class 0.05 Nos. 311.50 each 15.58
Mate 0.04 Nos. 262.50 each 10.50
Beldar for extra rammingn 0.25 Nos. 262.50 each 65.63
Sundaries L.S. 10.00
Total:- 736.78

Total:-1+2+3 2332.42

Add 1.5% water charges. 34.99


Total:- 2367.41
Add 10% C.P and 5% over head charges except on
cement. 280.86

2648.27
Say Rs. 2648.27

Executive Engineer,
IPHDivision No.II
Kullu at Bhunter
Analysis of rates
Providing and laying of cement concrere 1:5:10
Detail of cost for one cu.m
Sr.
Description of Items Qty. Rate Unit Amount
No
1 Materials
Stone aggregate 40mm 0.65 cum. 440.00 cum. 286.00
Stone aggregate 20mm 0.24 cum. 465.00 cum. 111.60
Sand 0.47 cum. 375.00 cum. 176.25
Cement 0.13 Tone 4500.00 Tone 585.00
Total:- 1158.85

2 Carriage
Stone aggregate 40mm
0.00 Km by machenical transport 0.65 cum. 0 cum. 0.00
0.5 Km. by head load 0.65 cum. 443.11 cum. 288.02

Sand
7.00 Km by machenical transport 0.47 cum. 277.09 cum. 130.23
0 Km. by head load 0.47 cum. 0.00 cum. 0.00

Stone aggregate below 40mm:-


7.00 Km by machenical transport 0.24 cum. 277.09 cum. 66.50
0 Km. by head load 0.24 cum. 0.00 cum. 0.00

Cement
25.00 Km by machenical transport 0.13 Tone 382.17 Tone 49.68
0 Km. by head load 0.13 Tone 0.00 Tone 0.00

Total:- 534.44
3 Labour
Beldar 2.09 Nos. 262.50 each 548.63
Bhisti 0.27 Nos. 262.50 each 70.88
Mason 1st class 0.05 Nos. 311.50 each 15.58
Mason 2nd class 0.05 Nos. 311.50 each 15.58
Mate 0.04 Nos. 262.50 each 10.50
Beldar for extra rammingn 0.25 Nos. 262.50 each 65.63
Sundaries L.S. 15.00
Total:- 741.78

Total:-1+2+3 2435.06

Add 1.5% water charges. 36.53


Total:- 2471.59
Add 10% C.P and 5% over head charges except on
cement. 282.99

2754.58
Say Rs. 2754.58

Executive Engineer,
IPHDivision No.II
Kullu at Bhunter
Analysis of rates
Providing and laying of cement concrere 1:3:6
Detail of cost for one cu.m
Sr.
Description of Items Qty. Rate Unit Amount
No
1 Materials
Stone aggregate 40mm 0.65 cum. 440.00 cum. 286.00
Stone aggregate 20mm 0.24 cum. 465.00 cum. 111.60
Sand 0.47 cum. 375.00 cum. 176.25
Cement 0.22 Tone 4500.00 Tone 990.00
Total:- 1563.85

2 Carriage
Stone aggregate 40mm
0.00 Km by mechanical transport 0.65 cum. 0 cum. 0.00
0.5 km. by head load 0.65 cum. 443.11 cum. 288.02

Sand
7.00 Km by mechanical transport 0.47 cum. 277.09 cum. 130.23
0 Km. by head load 0.47 cum. 0.00 cum. 0.00

Stone aggregate below 40mm:-


7.00 Km by mechanical transport 0.24 cum. 277.09 cum. 66.50
0 Km. by head load 0.24 cum. 0.00 cum. 0.00

Cement
25.00 Km by mechanical transport 0.22 Tone 382.17 Tone 84.08
0 Km. by head load 0.22 Tone 0.00 Tone 0.00

Total:- 568.83
3 Labour
Beldar 2.09 Nos. 262.50 each 548.63
Bhisti 0.27 Nos. 262.50 each 70.88
Mason 1st class 0.05 Nos. 311.50 each 15.58
Mason 2nd class 0.05 Nos. 311.50 each 15.58
Mate 0.04 Nos. 262.50 each 10.50
Beldar for extra rammingn 0.25 Nos. 262.50 each 65.63
Sundaries L.S. 15.00
Total:- 741.78

Total:-1+2+3 2874.46

Add 1.5% water charges. 43.12


Total:- 2917.57
Add 10% C.P and 5% over head charges except on
cement. 289.14

3206.71
Say Rs. 3206.71

Executive Engineer,
IPHDivision No.II
Kullu at Bhunter
Analysis of rates
Providing and laying of cement concrere 1:3:6
Detail of cost for one cu.m
Sr.No Description of Items Qty. Rate Unit Amount
Materials
1
Stone aggregate 20mm 0.70 cum. 465.00 cum. 325.50
Stone aggregate 10mm 0.24 cum. 475.00 cum. 114.00
Sand 0.47 cum. 375.00 cum. 176.25

Cement 0.22 Tone 4500.00 Tone 990.00


Total:- 1605.75

2 Carriage
Sand
7.00 Km by machenical transport 0.47 cum. 277.09 cum. 130.23
0 Km. by head load 0.47 cum. 0.00 cum. 0.00

Stone aggregate below 40mm:-


7.00 Km by machenical transport 0.94 cum. 277.09 cum. 260.46
0 Km. by head load 0.94 cum. 0.00 cum. 0.00

Cement
25.00 Km by machenical transport 0.22 Tone 382.17 Tone 84.08
0 Km. by head load 0.22 Tone 0.00 Tone 0.00

Total:- 474.77
3 Labour
Beldar 2.09 Nos. 262.50 each 548.63
Bhisti 0.27 Nos. 262.50 each 70.88
Mason 1st class 0.05 Nos. 311.50 each 15.58
Mason 2nd class 0.05 Nos. 311.50 each 15.58
Mate 0.04 Nos. 262.50 each 10.50
Beldar for extra ramming 0.25 Nos. 262.50 each 65.63
Sundaries L.S. 10.00
Total:- 736.78

Total:-1+2+3 2817.30

Add 1.5% water charges. 42.26


Total:- 2859.56
Add 10% C.P and 5% over head charges except on
cement.
280.43

3139.99
Say Rs. 3139.99

Executive Engineer,
IPHDivision No.II
Kullu at Bhunter
Analysis of rates
Providing and laying of cement concrere 1:5:10 with 15% plum in R/wall & B/wall
Detail of cost for one cu.m
Sr.
Description of Items Qty. Rate Unit Amount
No
Materials
1
Stone aggregate 40mm 0.6 cum. 440.00 cum. 264.00
Stone aggregate 20mm 0.22 cum. 465.00 cum. 102.30
Sand 0.43 cum. 375.00 cum. 161.25
Selected hard stone (Plum) 0.15 cum. 300.00 cum. 45
Cement 0.1196 Tone 4500.00 Tone 538.20
Total:- 1110.75
2 Carriage
Stone aggregate 40mm
0.00 Km by machenical transport 0.6 cum. 0 cum. 0.00
0.5 Km. by head load 0.6 cum. 443.11 cum. 265.87

Sand
7.00 Km by machenical transport 0.43 cum. 277.09 cum. 119.15
0 Km. by head load 0.43 cum. 0.00 cum. 0.00

Stone aggregate below 40mm:-


7.00 Km by machenical transport 0.22 cum. 277.09 cum. 60.96
0 Km. by head load 0.22 cum. 0.00 cum. 0.00
Solling stone
0.00 Km by machenical transport 0.15 cum. 0 cum. 0.00
0.5 Km. by head load 0.15 cum. 409.84 cum. 61.48
Cement
25.00 Km by machenical transport 0.1196 Tone 382.17 Tone 45.71
0 Km. by head load 0.1196 Tone 0.00 Tone 0.00
Total:- 553.16
3 Labour
Beldar 1.07 Nos. 262.50 each 280.88
Bhisti 0.25 Nos. 262.50 each 65.63
Mason 1st class 0.17 Nos. 311.50 each 52.96
Beldar for extra rammingn 0.98 Nos. 262.50 each 257.25
Sundaries L.S. 20.00
Total:- 676.71

Total:-1+2+3 2340.61
Add 1.5% water charges. 35.11
Total:- 2375.72
Add 10% C.P and 5% over head charges except on
cement. 275.63
2651.35
Say Rs.

Executive Engineer,
IPHDivision No.II
Kullu at Bhunter
Analysis of rates
Providing and laying of cement concrere 1:1- 1/2:3
Detail of cost for one cu.m
Sr.No Description of Items Qty. Rate Unit Amount
1 Material
20mm stone aggregate 0.57 cum. 465.00 cum. 265.05
10mm stone aggregate 0.28 cum. 475.00 cum. 133.00
Sand 0.425 cum. 375.00 cum. 159.38
Cement 0.40 Tone 4500.00 Tone 1800.00
Total:- 2357.43

2 Carriege
Stone aggregate
7.00 Km by machenical transport 0.85 cum. 277.09 cum. 235.53
0 Km. by head load 0.85 cum. 0.00 cum. 0

Sand
7.00 Km by machenical transport 0.425 cum. 277.09 cum. 117.76
0 Km. by head load 0.425 cum. 0.00 cum. 0.00

Cement
25.00 Km by machenical transport 0.40 Tone 382.17 Tone 152.87
0 Km. by head load 0.40 Tone 0.00 Tone 0.00
Total:- 506.16

3
Labor 2.09 Nos. 262.50 each 548.63
Beldar 0.27 Nos. 262.50 each 70.88
Bhisti 0.05 Nos. 311.50 each 15.58
Mason 1st class 0.05 Nos. 311.50 each 15.58
Mason 2nd class 0.04 Nos. 262.50 each 10.50
Mate 0.25 Nos. 262.50 each 65.63
Beldar for extra rammingn L.S each 15.00
Sundaries Total:- 741.78

Total:-1+2+3 3605.36

Add 1- 1/2% for water charges. 54.08


Total:- 3659.44
Add 10% C.P and 5% over head charges except on
cement. 278.92

3938.35
Say Rs. 3938.35

(1) P/L RCC 1:1 1/2:3 in foundation footing etc. Rate


As per analysis attached
of P.C.C 1:1- 1/2:3 3938.35
(a) Add extra labor for laying CC in RCC due
As per analysis attached
to delay 37.15
Total:- 3975.50

(2) P/l 1:1-1/2:3 in suspended floor roofs etc. Rate of As per analysis attached 3938.35
PCC 1:1-1/2:3
(a) Add extra labor for laying C.C in R.C.C due to delay As per analysis attached 133.26

(b) Add for Extra labor for lifting the material 52.09
Total:- 4123.71
Executive Engineer,
IPHDivision No.II
Kullu at Bhunter
Analysis of rates
Providing and laying of cement concrere 1:1- 1/2:3
Detail of cost for one cu.m
Sr.No Description of Items Qty. Rate Unit Amount
1 Material
20mm stone aggregate 0.57 cum. 465.00 cum. 265.05
10mm stone aggregate 0.28 cum. 475.00 cum. 133.00
Sand 0.425 cum. 375.00 cum. 159.38
Cement 0.40 Tone 4500.00 Tone 1800.00
Total:- 2357.43

2 Carriege
Stone aggregate
7.00 Km by machenical transport 0.85 cum. 277.09 cum. 235.53
0 Km. by head load 0.85 cum. 0.00 cum. 0

Sand
7.00 Km by machenical transport 0.425 cum. 277.09 cum. 117.76
0 Km. by head load 0.425 cum. 0.00 cum. 0.00

Cement
25.00 Km by machenical transport 0.40 Tone 382.17 Tone 152.87
0 Km. by head load 0.40 Tone 0.00 Tone 0.00
Total:- 506.16

3 Labor
Beldar 3.59 Nos. 262.50 each 942.38
Bhisti 0.29 Nos. 262.50 each 76.13
Mason 1st class 0.10 Nos. 311.50 each 31.15
Mason 2nd class 0.10 Nos. 311.50 each 31.15
Mate 0.04 Nos. 262.50 each 10.50
Beldar for extra rammingn 0.25 Nos. 262.50 each 65.63
Sundaries L.S each 15.00
Scaffolding L.S 25.00
Total:- 1196.93

Total:-1+2+3 4060.51

Add 1- 1/2% for water charges. 60.91


Total:- 4121.42
Add 10% C.P and 5% over head charges except on
cement. 348.21

4469.63
Say Rs. 4469.63

(1) P/L RCC 1:1 1/2:3 in column piller post. Rate of As per analysis attached 4469.63
P.C.C 1:1- 1/2:3
(a) Add extra labor for laying C.C in R.C.C due to delay As per analysis attached 133.26

(b) Add for Extra labor for lifting the material 52.09
Total:- 4654.98

Executive Engineer,
IPHDivision No.II
Kullu at Bhunter
Analysis of rates
Providing and laying of cement concrere 1:1- 1/2:3 (in vertical wall)
Detail of cost for one cu.m
Sr.
Description of Items Qty. Rate Unit Amount
No
1 Material
20mm stone aggregate 0.57 cum. 465.00 cum. 265.05
10mm stone aggregate 0.28 cum. 475.00 cum. 133.00
Sand 0.425 cum. 375.00 cum. 159.38
Cement 0.40 Tone 4500.00 Tone 1800.00
Total:- 2357.43

2 Carriege
Stone aggregate
7.00 Km by machenical transport 0.85 cum. 277.09 cum. 235.53
0 Km. by head load 0.85 cum. 0.00 cum. 0

Sand
7.00 Km by machenical transport 0.425 cum. 277.09 cum. 117.76
0 Km. by head load 0.425 cum. 0.00 cum. 0.00

Cement
25.00 Km by machenical transport 0.40 Tone 382.17 Tone 152.87
0 Km. by head load 0.40 Tone 0.00 Tone 0.00
Total:- 506.16
3 Labour
Beldar 2.09 Nos. 262.50 each 548.63
Bhisti 0.28 Nos. 262.50 each 73.50
Mason 1st class 0.06 Nos. 311.50 each 18.69
Mason 2nd class 0.06 Nos. 311.50 each 18.69
Mate 0.04 Nos. 262.50 each 10.50
Beldar for extra rammingn 0.25 Nos. 262.50 each 65.63
Sundaries L.S 15.00
RCC Folding L.S 25.00
Total:- 775.63

Total:-1+2+3 3639.21

Add 1 1/2% for water charges. 54.59


Total:- 3693.80
Add 10% C.P and 5% over head charges except on
cement. 284.07

Total:- 3977.87
RCC Work in vertical wall
P.C.C 1:1 1/2:3 3977.87
Add extra labor for laying c.c in
R.C.C due to delay. As per detail attached 133.26
Total:- 4111.14
Say Rs. 4111.14

Executive Engineer,
IPHDivision No.II
Kullu at Bhunter
Analysis of rates
Providing mild steel / Tor steel reinforcement for RCC work including bending, binding and placing in position
completed.
Sr.
Description of Items Qty. Rate Unit Amount
No
1 Materials:-
Tor Steel 1.05 Qtl. 4600.00 Qtl. 4830.00
Total:- 4830.00
2 Carriege:-
25.00 Km by machenical transport 0.105 Tone 382.17 Tone 40.13
0 Km. by head load 0.105 Tone 0.00 Tone 0.00
Total:- 40.13
3 Labour
Black Smith 1.00 Nos. 311.50 each 311.50
Beldar 1.00 Nos. 262.50 each 262.50
Sundaries and wire L.sd 45.00
Total:- 619.00

Total:-1+2+3 5489.13
Add 1.5% for water charges. 82.34
Total:- 5571.46
Add 10% C.P. profit and 5% over head charges except
on steel. 111.22
Rate per Qtl. 5682.68
Rate per Kg. 56.83
Labor Rate = 8.53 Per Kg.

Executive Engineer,
IPHDivision No.II
Kullu at Bhunter
Analysis of rates
Providing and laying of cement concrere 1:2:4
Detail of cost for one cu.m
Sr.No Description of Items Qty. Rate Unit Amount
1 Materials
Stone aggregate 20mm 0.67 cum. 465.00 cum. 311.55
Stone aggregate 10mm 0.22 cum. 475.00 cum. 104.50
Sand 0.445 cum. 375.00 cum. 166.88
Cement 0.32 Tone 4500.00 Tone 1440.00
Total:- 2022.93
2 Carriage
Stone aggregate
7.00 Km by machenical transport 0.89 cum. 277.09 cum. 246.61
9 Km. by head load 0.89 cum. 0.00 cum. 0.00
Sand
7.00 Km by machenical transport 0.445 cum. 277.09 cum. 123.31
0 Km. by head load 0.445 cum. 0.00 cum. 0.00
Cement
25.00 Km by machenical transport 0.32 Tone 382.17 Tone 122.29
0 Km. by head load 0.32 Tone 0.00 Tone 0.00
Total:- 492.21
3 Labour
Beldar 2.09 Nos. 262.50 each 548.63
Bhisti 0.27 Nos. 262.50 each 70.88
Mason 1st class 0.05 Nos. 311.50 each 15.58
Mason 2nd class 0.05 Nos. 311.50 each 15.58
Mate 0.04 Nos. 262.50 each 10.50
Beldar for extra ramming 0.25 Nos. 262.50 each 65.63
L.S

Total:- 726.78

Total:- 3241.91

Add 1.5% water charges. 48.63


Total:- 3290.54
Add 10% C.P and 5% over head charges except on cement.
277.58
Total:- 3568.12
(1) P/L CC 1:2:4 in Fondation footing and bases
of column.
Rate of PCC in foundation and Plinth etc. 3568.12
Add extra labbour for laying CC in RCC due to 133.26
delay. Total:- 3701.38
(II) P/L CC 1:2:4 in suspended floor roofs etc.
Rate of PCC in foundation and Plinth etc. 3568.12
Add extra labbour for laying CC in RCC due to As per analysis 133.26
delay. attached
Add extra labour for lifting the material. As per analysis 52.09
attached
Total:- 3753.47

Executive Engineer,
IPHDivision No.II
Kullu at Bhunter
Analysis of rates
Providing and laying of cement concreret 1:2:4 IN Arches..
Detail of cost for one cu.m
Sr.
Description of Items Qty. Rate Unit Amount
No

1 C.C. 1:2:4 Detail as cc in foundation & plinth. 26.73 cum 3568.12 cum 95375.82

2 Extra labour for lying CC in RCC slab due to 26.73 cum 133.26 cum 3562.17
delay:-
3 Extra cost involved in lying CC over curved
suface:-

Beldar 4.45 Nos. 262.50 each 1168.13


Bhisti 1.50 Nos. 262.50 each 393.75
Mason 1st class 5 Nos. 311.50 each 1557.5
Mason 2nd class 5 Nos. 311.50 each 1557.50
Total:- 4676.88

Add 1 1/2% for water charges on Rs. 4676.88 70.15


Total:- 4747.03
Add 10% C.P and 5% over head charges on Rs. 4747.03 712.05
5459.08

Cost for 26.73 cum. G. Total 1+2+3 104397.07


Cost for one cum. 3905.61

Executive Engineer,
IPHDivision No.II
Kullu at Bhunter
Analysis of rates
Providing and laying of cement concrere 1:2:4 {Column piller post)
Detail of cost for one cu.m
Sr.No Description of Items Qty. Rate Unit Amount
1 Materials
Stone aggregate 20mm 0.67 cum. 465.00 cum. 311.55
Stone aggregate 10mm 0.22 cum. 475.00 cum. 104.50
Sand 0.445 cum. 375.00 cum. 166.88
Cement 0.32 Tone 4500.00 Tone 1440.00
Total:- 2022.93
2 Carriage
Stone aggregate
7.00 Km by machenical transport 0.89 cum. 277.09 cum. 246.61
0 Km. by head load 0.89 cum. 0.00 cum. 0.00
Sand
7.00 Km by machenical transport 0.445 cum. 277.09 cum. 123.31
0 Km. by head load 0.445 cum. 0.00 cum. 0.00
Cement
25.00 Km by machenical transport 0.32 Tone 382.17 Tone 122.29
0 Km. by head load 0.32 Tone 0.00 Tone 0.00
Total:- 492.21
3 Labour
Beldar 3.59 Nos. 262.50 each 942.38
Bhisti 0.29 Nos. 262.50 each 76.13
Mason 1 class
st
0.10 Nos. 311.50 each 31.15
Mason 2nd class 0.10 Nos. 311.50 each 31.15
Mate 0.04 Nos. 262.50 each 10.50
Beldar for extra ramming 0.25 Nos. 262.50 each 65.63
Sundaries L.S 15.00
Scaffolding L.S 15.00
Total:- 1186.93

Total:- 3702.06

Add 1.5% water charges. 55.53


Total:- 3757.59
Add 10%for C.P and 5% over head charges
except on cement. 347.64
Total:- 4105.23
(1) P/L CC 1:2:4 in Column piller post.
Rate of PCC in foundation and Plinth etc. 4105.23
Add extra labour for laying CC in RCC due to As per analysis 133.26
delay. attached
Add extra labour for lifting the material. As per analysis 52.09
attached
Total:- 4290.58

Executive Engineer,
IPHDivision No.II
Kullu at Bhunter
Analysis of rates
Providing and laying D.P.C 38mm thick with CC 1:2:4
Detail of cost for 10 sqm.
Sr.
Description of Items Qty. Rate Unit Amount
No
1 Materials
CC 1:2:4 10*.038 = 0.38cum. 0.38 cum. 3568.12 cum. 1355.89
Total:- 1355.89

2 Add for extra labor (for delayLabour)


Mason 1stclass 0.50 Nos. 311.50 each 155.75
Mason 2nd class 0.50 Nos. 311.50 each 155.75
Bhisti 0.10 Nos. 262.50 each 26.25
Beldar 1.00 Nos. 262.50 each 262.50
Sundaries form work etc. L.S. 10.00
Total:- 610.25

Total:-1+2 1966.14

Add 1.5% water charges. 9.15


Total:- 1975.29
Add 10% C.P and 5% over head charges.
92.91

Cost for 10 sqm.. 2068.20


Cost per sqm.. 206.82
Say Rs. 206.82

Executive Engineer,
IPHDivision No.II
Kullu at Bhunter
Analysis of rate
Applying a coat of hot bitumen on DPC.
Maxphalt 80/100.
Detail of cost for 10sqmt.
S.No. Description of items Quantity Rate Unit Amount

MATERIAL :

Maxphalt 80/100. 0.017 12000.00 Tone 204.00


Kerocine 1.35 10 Liter 13.50
Fule wood for heating l.s. 15.00
Carriage :(Bitumen)
1.00
Km by mechanical transport. 0.017 163.8 Tone 2.78
0.1 Km by Head load. 0.017 89.25 Tone 1.52
Labour :
Painter 1st class 0.22 311.5 Each 68.53
Beldar 0.18 262.5 Each 47.25
Sundries (Brushes etc. LS. 10.00
362.58

Add 10% for C.P. & 5% for overhead charges : 54.39


Cost of 10 Cum.Sqmt. 416.97
Cost of 1 Sqmt. 41.7

Say Rs. 41.70 /- only.

Executive Engineer,
IPHDivision No.II
Kullu at Bhunter
Analysis of rates
Providing and laying of cement concreret .
Detail of cost for one cu.m
Sr.
Description of Items Qty. Rate Unit Amount
No
Extra labour for lying CC in RCC slab due to
delay:-
Beldar 0.10 Nos. 262.50 each 26.25
Bhisti 0.20 Nos. 262.50 each 52.50
Mason 1st class 0.04 Nos. 311.50 each 12.46
Mason 2nd class 0.04 Nos. 311.50 each 12.46
Mate 0.04 Nos. 262.50 each 10.50
Total:- 114.17

Add 1 1/2% for water charges. 1.71


Total:- 115.88
Add 10% C.P and 5% over head charges except on
cement. 17.38

133.26
Say Rs. 133.26

Extra labour for lifting the material

Beldar 0.17 Nos. 262.5 each 44.63


Total:- 44.63
0.67
Add 1 -1/2% for water charges.
Total:- 45.29
Add 10% C.P. and 5% over head charges. 6.79

Total:- 52.09

Say Rs. 52.09

Executive Engineer,
IPHDivision No.II
Kullu at Bhunter
Analysis of rates
Providing and laying of No Fine cement concrere 1:4
Detail of cost for one cu.m
Sr.No Description of Items Qty. Rate Unit Amount
1 Materials
Stone aggregate 20mm 0.67 cum. 465.00 cum. 311.55
Stone aggregate 10mm 0.22 cum. 475.00 cum. 104.50
Cement 0.32 Tone 4500.00 Tone 1440.00
1856.05
2 Carriage
Stone aggregate
7.00 Km by machenical transport 0.89 cum. 277.09 cum. 246.61
0.0 Km. by head load 0.89 cum. 0.00 cum. 0.00
Cement
25.00 Km by machenical transport 0.32 Tone 382.17 Tone 122.29
0 Km. by head load 0.32 Tone 0.00 Tone 0.00
Total:- 368.90
3 Labour
Beldar 2.09 Nos. 262.50 each 548.63
Bhisti 0.27 Nos. 262.50 each 70.88
Mason 1st class 0.05 Nos. 311.50 each 15.58
Mason 2nd class 0.05 Nos. 311.50 each 15.58
Mate 0.04 Nos. 262.50 each 10.50
Sundaries L.S 15.00
Total:- 676.15

Total:- 2901.10

Add 1.5% water charges. 43.52


Total:- 2944.62
Add 10% C.P and 5% over head charges except on cement.
225.69
Total:- 3170.31

Executive Engineer,
IPHDivision No.II
Kullu at Bhunter
Analysis of rates
S.R. stone masonary in CM 1:6
Detail of cost for one cu.m
Sr.
Description of Items Qty. Rate Unit Amount
No
1 Materials
Cement mortor 0.30 cum. 2382.31 cum. 714.69
Stone at
1.21 cum. 350.00 cum. 423.50
quarry
through stone 7.00 Nos. 7.00 each 49.00
Total:- 1187.19

2 Carriage
0.00 Km by machenical transport 1.37 cum. 0 cum. 0.00
1 Km. by head load 1.37 cum. 831.81 cum. 1139.58
Total:- 1139.58

3 Labour
Stone dresser 2.83 Nos. 262.50 each 742.88
Mason 1st class 1.06 Nos. 311.50 each 330.19
Mason 2nd class 1.06 Nos. 311.50 each 330.19
Beldar 2.65 Nos. 262.50 each 695.63
Sundaries L.S. each 35.00
Total:- 2133.88

Total:-1+2+3 4460.65

Add 1.5% water charges. 56.19


Total:- 4516.84
Add 10% C.P and 5% over head charges.
570.32
5087.16

Executive Engineer,
IPHDivision No.II
Kullu at Bhunter
Analysis of rates
Extra Labour for S/R masonary in super structure above plinth level and up to floor two level.
Detail of cost for one cu.m
Sr.
Description of Items Qty. Rate Unit Amount
No

3 Labour
Mason 2nd class 0.25 Nos. 311.50 each 77.88
Beldar 0.35 Nos. 262.50 each 91.88
Scafolding L.S. Nos. each 25.00
Total:- 194.75

Total:-
194.75
1

Add 1.5% water charges. 2.92


Total:- 197.67
Add 10% C.P and 5% over head charges.
29.65
227.32

Rate for S.R.masonry in super structure.


Rate of S.R masonary in CM 1:6 in foundation and plinth. 5087.16

Rate for extra labor work in super structure. 227.32


Total:- 5314.49

Executive Engineer,
IPHDivision No.II
Kullu at Bhunter
Analysis of rates
S.R. stone masonary in CM 1:4
Detail of cost for one cu.m
Sr.
Description of Items Qty. Rate Unit Amount
No

1 Materials
Cement mortor 0.30 cum. 3035.39 cum. 910.62
Stone at quarry 1.21 cum. 350.00 cum. 423.50
through stone 7.00 Nos. 7.00 each 49.00
Total:- 1383.12

2 Carriage
0.00 Km by machenical transport 1.37 cum. 0 cum. 0.00
1 Km. by head load 1.37 cum. 831.81 cum. 1139.58
Total:- 1139.58

3 Labour
Stone dresser 2.83 Nos. 262.50 each 742.88
Mason 1st class 1.06 Nos. 311.50 each 330.19
Mason 2nd class 1.06 Nos. 311.50 each 330.19
Beldar 2.65 Nos. 262.50 each 695.63
Sundaries L.S. each 35.00
Total:- 2133.88

Total:-1+2+3 4656.58

Add 1.5% water charges. 63.68


Total:- 4720.26
Add 10% C.P and 5% over head charges.
571.45

5291.70

Executive Engineer,
IPHDivision No.II
Kullu at Bhunter
Analysis of rates
R.R. stone masonary in CM 1:6
Detail of cost for one cu.m
Sr.
Description of Items Qty. Rate Unit Amount
No

1 Materials
Cement mortor 0.33 cum. 2382.31 cum. 786.16
Stone at quarry 1.00 cum. 350.00 cum. 350.00
through stone 7.00 Nos. 7.00 each 49.00
CC 1:6:12 L.S 20.00
Total:- 1205.16

2 Carriage
0.00 Km by machenical transport 1.16 cum. 0 cum. 0.00
1 Km. by head load 1.16 cum. 831.81 cum. 964.90
Total:- 964.90

3 Labour
Mason 2nd class 1.77 Nos. 311.50 each 551.36
Beldar 2.12 Nos. 262.50 each 556.50
Bhisthi 0.09 Nos. 262.50 each 23.63
Sundaries L.S. each 15.00
Total:- 1146.48

Total:-1+2+3 3316.54

Add 1.5% water charges. 37.96


Total:- 3354.50
Add 10% C.P and 5% over head charges.
385.25

3739.75

Executive Engineer,
IPHDivision No.II
Kullu at Bhunter
Analysis of rates
Dry rubble masonary in R/Wall & B/Wall
Detail of cost for one cu.m
Sr.
Description of Items Qty. Rate Unit Amount
No

1 Materials
Stone at quarry 1.00 cum. 350.00 cum. 350.00
through stone 7.00 Nos. 7.00 each 49.00
Total:- 399.00

2 Carriage
0.00 Km by machenical transport 1.16 cum. 0 cum. 0.00
1 Km. by head load 1.16 cum. 831.81 cum. 964.90
Total:- 964.90

3 Labour
Mason 2nd class 0.42 Nos. 311.50 each 130.83
Beldar 0.85 Nos. 262.50 each 223.13
Sundaries L.S. each 20.00
Total:- 373.96

Total:-1+2+3 1737.85

Add 1.5% water charges. 26.07


Total:- 1763.92
Add 10% C.P and 5% over head charges.
264.59

2028.51
Say Rs. 2029

Executive Engineer,
IPHDivision No.II
Kullu at Bhunter
Analysis of rates
Bolder/Stone filling behind R/Wall
Detail of cost for one cu.m
Sr.
Description of Items Qty. Rate Unit Amount
No
1 Materials
Stone at quarry 1.10 cum. 300.00 cum. 330.00
Total:- 330.00

2 Carriage
0.00 Km by machenical transport 1.10 cum. 0 cum. 0.00
0.5 Km. by head load 1.10 cum. 409.84 cum. 450.82
Total:- 450.82

3 Labour
Beldar 0.9 Nos. 262.50 each 236.25
Total:- 236.25

Total:-1+2+3 1017.07

Add 10% C.P and 5% over head charges.


152.56

1169.64
Say Rs. 1170.00 only

Executive Engineer,
IPHDivision No.II
Kullu at Bhunter
Analysis of rates
Precast concrete block masonary with Cc block made of Cc 1:3:6 in cement motor 1:6
Detail of cost for 1.89 cum.
Sr.
Description of Items Qty. Rate Unit Amount
No

1 Materials
Precast conccrete block (solidof size 1.67 cum. 3206.71 cum. 5355.21
39*20*19 cm.=0.01482cum*112.50=1.67cum.
CC 1:3:6

Cement motor 1:6 0.18 cum. 2382.31 cum. 428.82


Total:- 5784.02

2 Labour
Mason 2nd class 2.50 Nos. 311.50 each 778.75
Beldar 3.50 Nos. 262.50 each 918.75
Scafolding L.S 25.00
Sundries L.S 15.00
Total:- 1737.50

Total:-1+2 7521.52
Water charges @1.5% 26.06

7547.59
Add 10% C.P and 5% over head charges.
264.53

Cost for 1.89 cum. 7786


Cost per cum. 4119.61

Executive Engineer,
IPHDivision No.II
Kullu at Bhunter
Analysis of rates
Wire crates of G.I wire filled with bolders with squarecut faces against the wire
. (wire crates to be measured and paid for separately)

Detail of cost for two cum


Sr.
Description of Items Qty. Rate Unit Amount
No

1 Materials
Bolder required for filling the crates. 2.00 cum. 300.00 cum. 600.00
1.25m*1.25m*1.25m=1.95cum.Say=2cum.

Total:- 600.00

2 Carriage
0.00 Km by machenical transport 2.00 cum. 0 cum. 0.00
0.5 Km. by head load 2.00 cum. 409.84 cum. 819.68
Total:- 819.68

3 Labour
Masion 2nd class for filling stone into crates. 0.90 Nos. 311.50 each 280.35
Total:- 280.35

Total:-1+2+3 1700.03

Add 10% C.P and 5% over head charges. 255.00


Cost for 2cum. 1955.03
Cost per cum. 977.52

Executive Engineer,
IPHDivision No.II
Kullu at Bhunter
Analysis of rates
Wire crates of G.I wire filled with bolders with squarecut faces against the wire
. (Bolder filling to be measured and paid for separately)
. G.I wire 5mm thick corresponding to SWG-6.15cm*15cm mesh.
Detail of cost for 9.375(6*1.25m*1.25m) Sqmt.
Sr.
Description of Items Qty. Rate Unit Amount
No

1 Materials
G.I wire 5mm thick (Diagonal dimension)for 31.70
one phase of crate length of wire required
(9+9)*1.25*1.41=

Add for wastage and twisting@10% 3.17

Total:- 34.87
For six side length required 34.87 Rmt.*6=
209.22
Weight of G.I. wire 5mm thick =0.15 Kg per
Rmt.
Therefore total weight =209.22*.15 =
31.38 Kg 2200.00 Kg 69036.00
Add.4% sale tax 2761.44
Total:- 71797.44
2 Carriage of G.I wire L.S. 5.00

3 Labour
Blacksmith 2nd class 1.10 Nos. 311.50 each 342.65

Total:-1+2+3 72145.09

Add 10% C.P and 5% over head charges. 52.15

Cost for 9.375Sqm. 72197.24


Cost per Sqm. 7701.04
Labour Rate:- Say Rs. 7701.0
Carriage 5.00
Labour 342.65
347.65 Executive Engineer,
add 15% 52.15 IPHDivision No.II
Cost for 9.375Sqm. 399.80 Kullu at Bhunter
Cost per Sqm. 42.65
Analysis of rates
Wire crates of G.I wire filled with bolders with squarecut faces against the wire
. (Bolder filling to be measured and paid for separately)
. G.I wire 4mm thick corresponding to SWG-8.25cm*7.5cm mesh.
Detail of cost for 9.375(6*1.25m*1.25m) Sqmt.
Sr.
Description of Items Qty. Rate Unit Amount
No

1 Materials
G.I wire 4mm thick (Diagonal dimension)for 40.54
one phase of crate length of wire required
(17*6)*1.25*1.41=

Add for wastage and twisting@10% 4.05

Total:- 44.59
For six side length required 44.59 Rmt.*6=
267.564
Weight of G.I. wire 4mm thick =0.10 Kg per
Rmt.
Therefore total weight =267.54*.10 =
26.75 Kg 2200.00 Kg 58850.00
Add.4% sale tax 2354.00
Total:- 61204.00
2 Carriage of G.I wire L.S. 3.00

3 Labour
Blacksmith 2nd class 1.63 Nos. 311.50 each 507.75

Total:-1+2+4 61714.75

Add 10% C.P and 5% over head charges. 76.61

Cost for 9.375Sqm. 61791.36


Cost per Sqm. 6591.08

Say Rs. 6591.1

Executive Engineer,
IPHDivision No.II
Kullu at Bhunter
Analysis of rates
Cement mortor 1:4 (1 cement :4 sand)
Detail of cost for one cum.
Sr.
Description of Items Qty. Rate Unit Amount
No
1 Materials
Cement 0.38 Tone 4500 Tone 1710
Sand 1.07 cum. 375 cum. 401.25
Total:- 2111.25

2 Carriage
Cement
25.00 Km by machenical transport 0.38 Tone 382.17 Tone 145.22
0 Km. by head load 0.38 Tone 0 Tone 0.00
Sand
7.00 Km by machenical transport 1.07 cum. 277.09 cum. 296.49
0 km. by head load 1.07 cum. 0.00 cum. 0.00
Total:- 441.71

3 Labour
For measuring carrying disposing and mixing etc.

Beldar 0.90 Nos. 262.50 each 236.25


Bhisti 0.08 Nos. 262.50 each 21.00
Sundaries L.S. 10.00
Total:- 267.25

Total:-
2820.21
1+2+3

Add 1.5% water charges. 42.30


Total:- 2862.51
Add 10% C.P and 5% over head charges except on
cement. 172.88

3035.39

Executive Engineer,
IPHDivision No.II
Kullu at Bhunter
Analysis of rates
Cement mortor 1:3 (1 cement :3 sand)

Detail of cost for one cum.


Sr.
Description of Items Qty. Rate Unit Amount
No
1 Materials
Cement 0.51 Tone 4500 Tone 2295.00
Sand 1.07 cum. 375 cum. 401.25
Total:- 2696.25

2 Carriage
Cement
25.00 Km by machenical transport 0.51 Tone 382.17 Tone 194.91
0 Km. by head load 0.51 Tone 0 Tone 0.00
Sand
7.00 Km by mechanical transport 1.07 cum. 277.09 cum. 296.49
0 Km. by head load 1.07 cum. 0.00 cum. 0.00
Total:- 491.39

3 Labour
For measuring carrying disposing and mixing etc.

Bhisti 0.90 Nos. 262.50 each 236.25


Beldar 0.08 Nos. 262.50 each 21.00
Sundaries L.S. 10.00
Total:- 267.25

Total:-1+2+3 3454.89

Add 1.5% water charges. 51.82


Total:- 3506.72
Add 10% C.P and 5% over head charges except on
cement. 181.76

3688.47

Executive Engineer,
IPHDivision No.II
Kullu at Bhunter
Analysis of rates
Cement mortor 1:6 (1 cement :6 mortor)
Detail of cost for one cum.
Sr.
Description of Items Qty. Rate Unit Amount
No
1 Materials
Cement 0.25 Tone 4500 Tone 1125.00
Sand 1.07 cum. 375 cum. 401.25
Total:- 1526.25

2 Carriage
Cement
25.00 Km by machenical transport 0.25 Tone 382.17 Tone 95.5425
0 Km. by head load 0.25 Tone 0 Tone 0.00
Sand
7.00 Km by mechanical transport 1.07 cum. 277.09 cum. 296.49
0 Km. by head load 1.07 cum. 0.00 cum. 0.00
Total:- 392.03

3 Labour
For measuring carrying disposing and mixing etc.

Bhisti 0.90 Nos. 262.50 each 236.25


Beldar 0.08 Nos. 262.50 each 21.00
Sundaries L.S. 10.00
Total:- 267.25

Total:-1+2+3 2185.53

Add 1.5% water charges. 32.78


Total:- 2218.31
Add 10% C.P and 5% over head charges except on
cement. 164.00

2382.31

Executive Engineer,
IPHDivision No.II
Kullu at Bhunter
Analysis of rates
40mm thick cement concrete flooring 1:2:4
Detail of cost for 10 sqm.
Sr.
Description of Items Qty. Rate Unit Amount
No
1 Materials
Stone ballast 20mm 0.267 cum. 465 cum. 124.16
Stone ballast 10mm 0.089 cum. 475 cum. 42.28
Sand 0.178 cum. 375 cum. 66.75
Cement 0.15 Tone 4500 Tone 675.00
Total:- 908.18

2 Carriage
Sand
7.00 Km by machenical transport 0.178 cum. 277.09 cum. 49.32
0 Km. by head load 0.178 cum. 0.00 cum. 0.00

Stone aggregate below 40mm:-


7.00 Km by machenical transport 0.356 cum. 277.09 cum. 98.64
0 Km. by head load 0.356 cum. 0.00 cum. 0.00

Cement
25.00 Km by machenical transport 0.15 Tone 382.17 Tone 57.33
0 Km. by head load 0.15 Tone 0 Tone 0.00

Total:- 205.29
3 Labour
Mason 2nd class 1.20 Nos. 311.50 each 373.80
Beldar 2.00 Nos. 262.50 each 525.00
Bhisti 0.50 Nos. 262.50 each 131.25
Sundaries L.S. 15.00
Total:- 1045.05

Total:-1+2+3 2158.52

Add 1.5% water charges. 32.38


Total:- 2190.90
Add 10% C.P and 5% over head charges.
227.38

Cost for 10 sqm.= 2418.28

Cost per sqm.= 241.83

Say Rs 241.8 /-only


Executive Engineer,
IPHDivision No.II
Kullu at Bhunter
Analysis of rates
50mm thick cement concrete flooring 1:2:4
Detail of cost for 10 sqm.
Sr.
Description of Items Qty. Rate Unit Amount
No
1 Materials
Stone ballast 20mm 0.334 cum. 465 cum. 155.31
Stone ballast 10mm 0.111 cum. 475 cum. 52.73
Sand 0.222 cum. 375 cum. 83.25
Cement 0.182 Tone 4500 Tone 819.00
Total:- 1110.29

2 Carriage
Sand
7.00 Km by machenical transport 0.222 cum. 277.09 cum. 61.51
0.0 Km. by head load 0.222 cum. 0.00 cum. 0.00

Stone aggregate below 40mm:-


7.00 Km by machenical transport 0.445 cum. 277.09 cum. 123.31
0.0 Km. by head load 0.445 cum. 0.00 cum. 0.00

Cement
25.00 Km by machenical transport 0.182 Tone 382.17 Tone 69.55
0.0 Km. by head load 0.182 Tone 0 Tone 0.00

Total:- 254.37
3 Labour
Mason 2nd class 1.35 Nos. 311.50 each 420.53
Beldar 2.16 Nos. 262.50 each 567.00
Bhisti 0.27 Nos. 262.50 each 70.88
Sundaries L.S. 15.00
Total:- 1073.40

Total:-1+2+3 2438.06

Add 1.5% water charges. 36.57


Total:- 2474.63
Add 10% C.P and 5% over head charges.
248.34

Cost for 10 sqm.= 2722.97

Cost per sqm.= 272.30

Executive Engineer,
IPHDivision No.II
Kullu at Bhunter
Analysis of rates
20mm thick cement plaster in CM 1:6
Detail of cost for 10 sqm.
Sr.
Description of Items Qty. Rate Unit Amount
No
1 Materials
Cement mortor 1:6 0.224 cum. 2382.31 cum. 533.64
Total:- 533.64

2 Labour
Mason 2nd class 1.00 Nos. 311.50 each 311.50
Beldar 1.00 Nos. 262.50 each 262.50
Bhisti 1.06 Nos. 262.50 each 278.25
Sundaries L.S. 10.00
Total:- 862.25

Total:-1+2 1395.89

Add 1.5% water charges. 12.93


Total:- 1408.82
Add 10% C.P and 5% over head charges.
131.28

Cost for 10 sqm.. 1540.10


Cost per sqm.. 154.01
Say Rs. 154.01

Executive Engineer,
IPHDivision No.II
Kullu at Bhunter
Analysis of rates
20mm thick cement plaster in CM 1:3
Detail of cost for 10 sqm.
Sr.
Description of Items Qty. Rate Unit Amount
No
1 Materials
Cement mortor 1:3 0.224 cum. 3688.47 cum. 826.22
Total:- 826.22

2 Labour
Mason 2nd class 1.00 Nos. 311.50 each 311.50
Beldar 1.00 Nos. 262.50 each 262.50
Bhisti 1.06 Nos. 262.50 each 278.25
Sundaries L.S. 10.00
Total:- 862.25

Total:-1+2 1688.47

Add 1.5% water charges. 12.93


Total:- 1701.40
Add 10% C.P and 5% over head charges.
131.28

Cost for 10 sqm.. 1832.68


Cost per sqm.. 183.27
Say Rs. 183.27

Executive Engineer,
IPHDivision No.II
Kullu at Bhunter
Analysis of rates
6mm thick cement plaster in CM 1:3
Detail of cost for 10 sqm.
Sr.
Description of Items Qty. Rate Unit Amount
No
1 Materials
Cement mortor 1:3 0.072 cum. 3688.47 cum. 265.57
Total:- 265.57

2 Labour
Mason 2nd class 0.65 Nos. 311.50 each 202.48
Beldar 0.81 Nos. 262.50 each 212.63
Bhisti 0.27 Nos. 262.50 each 70.88
Sundaries L.S. 10.00
Total:- 495.98

Total:-1+2 761.55

Add 1.5% water charges. 7.44


Total:- 768.98
Add 10% C.P and 5% over head charges.
75.51

Cost for 10 sqm.. 844.50


Cost per sqm.. 84.45
Say Rs. 84.45

Executive Engineer,
IPHDivision No.II
Kullu at Bhunter
Analysis of rates
Flush pointing in CM 1:3
Detail of cost for 10 sqm.
Sr.
Description of Items Qty. Rate Unit Amount
No
1 Materials
Cement mortor 1:3 0.023 cum. 3688.47 cum. 84.83
Total:- 84.83

2 Labour
Mason 2nd class 0.85 Nos. 311.50 each 264.78
Beldar 0.85 Nos. 262.50 each 223.13
Bhisti 0.80 Nos. 262.50 each 210.00
Sundaries L.S. 10.00
Total:- 707.90

Total:-1+2 792.73

Add 1.5% water charges. 10.62


Total:- 803.35
Add 10% C.P and 5% over head charges.
107.78

Cost for 10 sqm.. 911.13


Cost per sqm.. 91.11
Say Rs. 91.11

Executive Engineer,
IPHDivision No.II
Kullu at Bhunter
Analysis of rates
Providing RCC work smooth finishing of the exposed surface with cement mortor 1:3
Detail of cost for 10 sqm.
Sr.
Description of Items Qty. Rate Unit Amount
No
1 Materials
Cement mortor 1:3 0.072 cum. 3688.47 cum. 265.57
Total:- 265.57

2 Labour
Mason 1st class 0.32 Nos. 311.50 each 99.68
Mason 2nd class 0.33 Nos. 311.50 each 102.80
Beldar 0.81 Nos. 262.50 each 212.63
Bhisti 0.27 Nos. 262.50 each 70.88
Sundaries and Scafolding LS 20.00
Extra for removing ,burns,clining out with wire brush and
pack making with plinted tools etc. complete
LS 15.00
Total:- 520.98

Total:-1+2 786.55

Add 1.5% water charges. 7.81


Total:- 794.36
Add 10% C.P and 5% over head charges.
79.32

Cost for 10 sqm.. 873.68


Cost per sqm.. 87.37
Say Rs. 87.37

Executive Engineer,
IPHDivision No.II
Kullu at Bhunter
Analysis of Rate
15 mm cement plaster in single coat on fair side f brick/stone masonry for interior plastering up to
floor two level including arrises, internal rounded angles, chamfers and/or rounded angles not
exceeding 80mm in girth and finished even and smooth .
Detail of cost for 10 Sqm.
Desciption Quantity Rate Unit Amount
In cement mortar 1:3
Material
Cement mortar 1:3
(1cement:3sand) 0.165 Cum. 3688.47 Cum. 608.6
Labour :
Mason II nd class 0.80 Nos. 311.5 Each 249.2
Beldar 0.80 Nos. 262.5 Each 210.00
Bhishti 0.98 Nos. 262.5 Each 257.25
Sundries( Scaffolding etc.) L.S. 10.0
1335.05
Add 1.5% water charges 10.9
1345.95
Add 10% CP & 5% O.H. Charges except cement mortar : 110.6
Cost of 10 Sqm. 1456.55
Cost of 1 Sqm. 145.7

Executive Engineer,
IPHDivision No.II
Kullu at Bhunter
Analysis of rates
Providing and laying R.C.C. Pipe. 150mm dia.NP2
(Detail of cost for 10 Rmt.)
Sr.
Description of Items Qty. Rate Unit Amount
No
1 Materials:-
RCC. Pipe 150mm dia NP2 10 mtr. 96.00 Rmt. 960.00
Collar 5 Nos. 36.00 each 180.00
Total:- 1140.00
Add. 4% sale tax. 45.60
Total:- 1185.60
Cement 0.003 Tone 4500.00 Tone 13.50
Sand 0.004 cum. 375.00 cum. 1.50
Total:- 1200.60
2 Carriege:-
Cement
25.00 Km by machenical transport 0.003 Tone 382.17 Tone 1.15
0.0000 Km. by head load 0.004 Tone 0.00 Tone 0.00
Sand
7.00 Km by machenical transport 0.004 cum. 277.09 cum. 1.11
0.0000 Km. by head load 0.004 cum. 0.00 cum. 0.00
Pipe
0.00 Km by machenical transport 10.00 mtr. 0.00 100mt. 0.00
0.0000 Km. by head load 10.00 mtr. 0.00 100mt. 0.00
Total:- 2.25
3 Labour
Mason 1st. class 0.0235 Nos. 311.50 each 7.32
Mason 2nd. class 0.0235 Nos. 311.50 each 7.32
Beldar 0.94 Nos. 262.50 each 246.75
Bhisti 0.19 Nos. 262.50 each 49.88
Total:- 311.27

Total:-1+2+3 1514.12
Add 1.5% for water charges. 22.71
Total:- 1536.83
Add 10% C.P. profit and 5% over head charges except
on cement & pipe. 50.66
Rate for 10 Rmt. 1587.49
Rate for 1 Rmt. 158.75

Executive Engineer,
IPHDivision No.II
Kullu at Bhunter
Analysis of rates
Providing and laying R.C.C. Pipe. 150mm dia.P1
(Detail of cost for 10 Rmt.)
Sr.
Description of Items Qty. Rate Unit Amount
No
1 Materials:- (RC)
RCC. Pipe 150mm dia P1 10 mtr. 146.40 Rmt. 1464.00
Collar 5 Nos. 0.00 each 0.00
Total:- 1464.00
Add. 4% sale tax. 58.56
Add 10% surcharge = 5.856 Total:- 1528.42
Cement 0.003 Tone 4500.00 Tone 13.50
Sand 0.004 cum. 375.00 Cum. 1.50
Total:- 1543.42
2 Carriege:-
Cement
25.00 Km by machenical transport 0.003 Tone 382.17 Tone 1.15
0.0000 Km. by head load 0.004 Tone 0.00 Tone 0.00
Sand
7.00 Km by machenical transport 0.004 cum. 277.09 cum. 1.11
0.0000 Km. by head load 0.004 cum. 0.00 cum. 0.00
Pipe
0.00 Km by machenical transport 10.00 mtr. 0.00 100mt. 0.00
0.0000 Km. by head load 10.00 mtr. 0.00 100mt. 0.00
Total:- 2.25
3 Labour
Mason 1st. class 0.0235 Nos. 311.50 each 7.32
Mason 2nd. class 0.0235 Nos. 311.50 each 7.32
Beldar 0.94 Nos. 262.50 each 246.75
Bhisti 0.19 Nos. 262.50 each 49.88
Total:- 311.27

Total:-1+2+3 1856.94
Add 1.5% for water charges. 27.85
Total:- 1884.79
Add 5% OH on pipe 76.42
Add 10% C.P. profit and 5% over head charges except on cement & pipe. 51.43
Rate for 10 Rmt. 2012.64
Rate for 1 Rmt. 201.26
Say Rs. 201.00 /-only

Executive Engineer,
IPHDivision No.II
Kullu at Bhunter
Analysis of rates
Providing and laying R.C.C. Pipe. 150mm dia.P2 (Detail of
cost for 10 Rmt.)
Sr.
Description of Items Qty. Rate Unit Amount
No
1 Materials:- (RC)
RCC. Pipe 150mm dia P2 10 mtr. 169.20 Rmt. 1692.00
Collar 5 Nos. 0.00 each 0.00
Total:- 1692.00
Add. 4% sale tax. 67.68
Add surcharge 10% = 6.768 Total:- 1766.45
Cement 0.003 Tone 4500.00 Tone 13.50
Sand 0.004 cum. 375.00 Cum. 1.50
Total:- 1781.45
2 Carriege:-
Cement
25.00 Km by machenical transport 0.003 Tone 382.17 Tone 1.15
0.0000 Km. by head load 0.004 Tone 0.00 Tone 0.00
Sand
7.00 Km by machenical transport 0.004 cum. 277.09 cum. 1.11
0.0000 Km. by head load 0.004 cum. 0.00 cum. 0.00
Pipe
0.00 Km by machenical transport 10.00 mtr. 0.00 100mt. 0.00
0.0000 Km. by head load 10.00 mtr. 0.00 100mt. 0.00
Total:- 2.25
3 Labour
Mason 1st. class 0.0235 Nos. 311.50 each 7.32
Mason 2nd. class 0.0235 Nos. 311.50 each 7.32
Beldar 0.94 Nos. 262.50 each 246.75
Bhisti 0.19 Nos. 262.50 each 49.88
Total:- 311.27

Total:-1+2+3 2094.97
Add 1.5% for water charges. 31.42
Total:- 2126.39
Add 5% OH on pipe 88.32
Add 10% C.P. profit and 5% over head charges except on cement & pipe. 51.97
Rate for 10 Rmt. 2266.68
Rate for 1 Rmt. 226.67
Say Rs. 227.00 /-only

Executive Engineer,
IPHDivision No.II
Kullu at Bhunter
Analysis of rates
Providing and laying R.C.C. Pipe. 150mm dia.P3 (Detail of
cost for 10 Rmt.)
Sr.
Description of Items Qty. Rate Unit Amount
No
1 Materials:-
RCC. Pipe 150mm dia P3 10 mtr. 160.00 Rmt. 1600.00
Collar 5 Nos. 36.00 each 180.00
Total:- 1780.00
Add. 4% sale tax. 71.20
Total:- 1851.20
Cement 0.003 Tone 4500.00 Tone 13.50
Sand 0.004 cum. 375.00 Cum. 1.50
Total:- 1866.20
2 Carriege:-
Cement
25.00 Km by machenical transport 0.003 Tone 382.17 Tone 1.15
0.0000 Km. by head load 0.004 Tone 0.00 Tone 0.00
Sand
7.00 Km by machenical transport 0.004 cum. 277.09 cum. 1.11
0.0000 Km. by head load 0.004 cum. 0.00 cum. 0.00
Pipe
0.00 Km by machenical transport 10.00 mtr. 0.00 100mt. 0.00
0.0000 Km. by head load 10.00 mtr. 0.00 100mt. 0.00
Total:- 2.25
3 Labour
Mason 1st. class 0.0235 Nos. 311.50 each 7.32
Mason 2nd. class 0.0235 Nos. 311.50 each 7.32
Beldar 0.94 Nos. 262.50 each 246.75
Bhisti 0.19 Nos. 262.50 each 49.88
Total:- 311.27

Total:-1+2+3 2179.72
Add 1.5% for water charges. 32.70
Total:- 2212.42
Add 5% OH on pipe 92.56
Add 10% C.P. profit and 5% over head charges except on cement & pipe. 52.16
Rate for 10 Rmt. 2357.13
Rate for 1 Rmt. 235.71

Executive Engineer,
IPHDivision No.II
Kullu at Bhunter
Analysis of rates
Providing and laying R.C.C. Pipe. 250mm dia.NP2 (Detail of
cost for 10 Rmt.)
Sr.
Description of Items Qty. Rate Unit Amount
No
1 Materials:-
RCC. Pipe 250mm dia NP2 10 mtr. 128.00 Rmt. 1280.00
Collar 5 Nos. 15.00 each 75.00
Total:- 1355.00
Add. 4% sale tax. 54.20
Total:- 1409.20
Cement 0.0045 Tone 4500.00 Tone 20.25
Sand 0.006 cum. 375.00 Cum. 2.25
Total:- 1431.70
2 Carriege:-
Cement
25.00 Km by machenical transport 0.0045 Tone 382.17 Tone 1.72
0.0000 Km. by head load 0.0045 Tone 0.00 Tone 0.00
Sand
7.00 Km by machenical transport 0.006 cum. 277.09 cum. 1.66
0.0000 Km. by head load 0.006 cum. 0.00 cum. 0.00
Pipe
0.00 Km by machenical transport 10.00 mtr. 0.00 100mt. 0.00
0.0000 Km. by head load 10.00 mtr. 0.00 100mt. 0.00
Total:- 3.38
3 Labour
Mason 1st. class 0.33 Nos. 311.50 each 101.24
Mason 2nd. class 0.33 Nos. 311.50 each 101.24
Beldar 1.26 Nos. 262.50 each 330.75
Bhisti 0.28 Nos. 262.50 each 73.50
Total:- 606.73

Total:-1+2+3 2041.81
Add 1.5% for water charges. 30.63
Total:- 2072.43
Add 5% OH on pipe 70.46
Add 10% C.P. profit and 5% over head charges except on cement & 96.45
pipe. Rate for 10 Rmt. 2239.34
Rate for 1 Rmt. 223.93

Executive Engineer,
IPHDivision No.II
Kullu at Bhunter
Analysis of rates
Providing and laying R.C.C. Pipe. 250mm dia.P1 (Detail of
cost for 10 Rmt.)
Sr.
Description of Items Qty. Rate Unit Amount
No
1 Materials:-
RCC. Pipe 250mm dia P1 10 mtr. 195.00 Rmt. 1950.00
Collar 5 Nos. 17.00 each 85.00
Total:- 2035.00
Add. 4% sale tax. 81.40
Total:- 2116.40
Cement 0.0045 Tone 4500.00 Tone 20.25
Sand 0.006 cum. 375.00 Cum. 2.25
Total:- 2138.90
2 Carriege:-
Cement
25.00 Km by machenical transport 0.0045 Tone 382.17 Tone 1.72
0.0000 Km. by head load 0.0045 Tone 0.00 Tone 0.00
Sand
7.00 Km by machenical transport 0.006 cum. 277.09 cum. 1.66
0.0000 Km. by head load 0.006 cum. 0.00 cum. 0.00
Pipe
0.00 Km by machenical transport 10.00 mtr. 0.00 100mt. 0.00
0.0000 Km. by head load 10.00 mtr. 0.00 100mt. 0.00
Total:- 3.38
3 Labour
Mason 1st. class 0.33 Nos. 311.50 each 101.24
Mason 2nd. class 0.33 Nos. 311.50 each 101.24
Beldar 1.26 Nos. 262.50 each 330.75
Bhisti 0.28 Nos. 262.50 each 73.50
Total:- 606.73

Total:-1+2+3 2749.01
Add 1.5% for water charges. 41.24
Total:- 2790.24
Add 5% OH on pipe 105.82
Add 10% C.P. profit and 5% over head charges except on cement & pipe. 98.04
Rate for 10 Rmt. 2994.10
Rate for 1 Rmt. 299.41

Executive Engineer,
IPHDivision No.II
Kullu at Bhunter
Analysis of rates
Providing and laying R.C.C. Pipe. 250mm dia.P2 (Detail of cost
for 10 Rmt.)
Sr.
Description of Items Qty. Rate Unit Amount
No
1 Materials:-
RCC. Pipe 250mm dia P2 10 mtr. 310.00 Rmt. 3100.00
Collar 5 Nos. 17.00 each 85.00
Total:- 3185.00
Add. 4% sale tax. 127.40
Total:- 3312.40
Cement 0.0045 Tone 4500.00 Tone 20.25
Sand 0.006 cum. 375.00 Cum. 2.25
Total:- 3334.90
2 Carriege:-
Cement
25.00 Km by machenical transport 0.0045 Tone 382.17 Tone 1.72
0.0000 Km. by head load 0.0045 Tone 0.00 Tone 0.00
Sand
7.00 Km by machenical transport 0.006 cum. 277.09 cum. 1.66
0.0000 Km. by head load 0.006 cum. 0.00 cum. 0.00
Pipe
0.00 Km by machenical transport 10.00 mtr. 0.00 100mt. 0.00
0.0000 Km. by head load 10.00 mtr. 0.00 100mt. 0.00
Total:- 3.38
3 Labour
Mason 1st. class 0.33 Nos. 311.50 each 101.24
Mason 2nd. class 0.33 Nos. 311.50 each 101.24
Beldar 1.26 Nos. 262.50 each 330.75
Bhisti 0.28 Nos. 262.50 each 73.50
Total:- 606.73

Total:-1+2+3 3945.01
Add 1.5% for water charges. 59.18
Total:- 4004.18
Add 5% OH on pipe 165.62
Add 10% C.P. profit and 5% over head charges except on cement & 100.73
pipe. Rate for 10 Rmt. 4270.53
Rate for 1 Rmt. 427.05

Executive Engineer,
IPHDivision No.II
Kullu at Bhunter
Analysis of rates
Providing and laying R.C.C. Pipe. 250mm dia.P3 (Detail
of cost for 10 Rmt.)
Sr.
Description of Items Qty. Rate Unit Amount
No
1 Materials:-
RCC. Pipe 250mm dia P3 10 mtr. 354.00 Rmt. 3540.00
Collar 5 Nos. 17.00 each 85.00
Total:- 3625.00
Add. 4% sale tax. 145.00
Total:- 3770.00
Cement 0.0045 Tone 4500.00 Tone 20.25
Sand 0.006 cum. 375.00 Cum. 2.25
Total:- 3792.50
2 Carriege:-
Cement
25.00 Km by machenical transport 0.0045 Tone 382.17 Tone 1.72
0.0000 Km. by head load 0.0045 Tone 0.00 Tone 0.00
Sand
7.00 Km by machenical transport 0.006 cum. 277.09 cum. 1.66
0.0000 Km. by head load 0.006 cum. 0.00 cum. 0.00
Pipe
0.00 Km by machenical transport 10.00 mtr. 0.00 100mt. 0.00
0.0000 Km. by head load 10.00 mtr. 0.00 100mt. 0.00
Total:- 3.38
3 Labour
Mason 1st. class 0.33 Nos. 311.50 each 101.24
Mason 2nd. class 0.33 Nos. 311.50 each 101.24
Beldar 1.26 Nos. 262.50 each 330.75
Bhisti 0.28 Nos. 262.50 each 73.50
Total:- 606.73

Total:-1+2+3 4402.61
Add 1.5% for water charges. 66.04
Total:- 4468.65
Add 10% C.P. profit and 5% over head charges except
on cement & pipe. 101.76
Rate for 10 Rmt. 4570.41
Rate for 1 Rmt. 457.04

Executive Engineer,
IPHDivision No.II
Kullu at Bhunter
Analysis of rates
Providing and laying R.C.C. Pipe. 300mm dia.NP2 (Detail
of cost for 10 Rmt.)
Sr.
Description of Items Qty. Rate Unit Amount
No
1 Materials:-
RCC. Pipe 300mm dia NP2 10 mtr. 170.50 Rmt. 1705.00
Collar 4 Nos. 0.00 each 0.00
Total:- 1705.00
Add. 4% sale tax. 68.20
Total:- 1773.20
Cement 0.005 Tone 4500.00 Tone 22.50
Sand 0.0075 cum. 375.00 Cum. 2.81
Total:- 1798.51
2 Carriege:-
Cement
25.00 Km by machenical transport 0.005 Tone 382.17 Tone 1.91
0.0000 Km. by head load 0.005 Tone 0.00 Tone 0.00
Sand
7.00 Km by machenical transport 0.0075 cum. 277.09 cum. 2.08
0.0000 Km. by head load 0.0075 cum. 0.00 cum. 0.00
Pipe
0.00 Km by machenical transport 10.00 mtr. 0.00 100mt. 0.00
0.0000 Km. by head load 10.00 mtr. 0.00 100mt. 0.00
Total:- 3.99
3 Labour
Mason 1st. class 0.355 Nos. 311.50 each 110.58
Mason 2nd. class 0.355 Nos. 311.50 each 110.58
Beldar 1.30 Nos. 262.50 each 341.25
Bhisti 0.28 Nos. 262.50 each 73.50
Total:- 635.92

Total:-1+2+3 2438.42
Add 1.5% for water charges. 36.58
Total:- 2474.99
Add 10% C.P. profit and 5% over head charges except
on cement & pipe. 101.89
Rate for 10 Rmt. 2576.89
Rate for 1 Rmt. 257.69

Executive Engineer,
IPHDivision No.II
Kullu at Bhunter
Analysis of rates
Providing and laying R.C.C. Pipe. 300mm dia.P1 (Detail
of cost for 10 Rmt.)
Sr.
Description of Items Qty. Rate Unit Amount
No
1 Materials:-
RCC. Pipe 300mm dia P1 10 mtr. 223.00 Rmt. 2230.00
Collar 4 Nos. 25.00 each 100.00
Total:- 2330.00
Add. 4% sale tax. 93.20
Total:- 2423.20
Cement 0.005 Tone 4500.00 Tone 22.50
Sand 0.0075 cum. 375.00 Cum. 2.81
Total:- 2448.51
2 Carriege:-
Cement
25.00 Km by machenical transport 0.005 Tone 382.17 Tone 1.91
0.0000 Km. by head load 0.005 Tone 0.00 Tone 0.00
Sand
7.00 Km by machenical transport 0.0075 cum. 277.09 cum. 2.08
0.0000 Km. by head load 0.0075 cum. 0.00 cum. 0.00
Pipe
0.00 Km by machenical transport 10.00 mtr. 0.00 100mt. 0.00
0.0000 Km. by head load 10.00 mtr. 0.00 100mt. 0.00
Total:- 3.99
3 Labour
Mason 1st. class 0.355 Nos. 311.50 each 110.58
Mason 2nd. class 0.355 Nos. 311.50 each 110.58
Beldar 1.30 Nos. 262.50 each 341.25
Bhisti 0.28 Nos. 262.50 each 73.50
Total:- 635.92

Total:-1+2+3 3088.42
Add 1.5% for water charges. 46.33
Total:- 3134.74
Add 10% C.P. profit and 5% over head charges except
on cement & pipe. 103.36
Rate for 10 Rmt. 3238.10
Rate for 1 Rmt. 323.81

Executive Engineer,
IPHDivision No.II
Kullu at Bhunter
Analysis of rates
Providing and laying R.C.C. Pipe. 300mm dia.P2 (Detail
of cost for 10 Rmt.)
Sr.
Description of Items Qty. Rate Unit Amount
No
1 Materials:-
RCC. Pipe 300mm dia P2 10 mtr. 414.00 Rmt. 4140.00
Collar 4 Nos. 25.00 each 100.00
Total:- 4240.00
Add. 4% sale tax. 169.60
Total:- 4409.60
Cement 0.005 Tone 4500.00 Tone 22.50
Sand 0.0075 cum. 375.00 Cum. 2.81
Total:- 4434.91
2 Carriege:-
Cement
25.00 Km by machenical transport 0.005 Tone 382.17 Tone 1.91
0.0000 Km. by head load 0.005 Tone 0.00 Tone 0.00
Sand
7.00 Km by machenical transport 0.0075 cum. 277.09 cum. 2.08
0.0000 Km. by head load 0.0075 cum. 0.00 cum. 0.00
Pipe
0.00 Km by machenical transport 10.00 mtr. 0.00 100mt. 0.00
0.0000 Km. by head load 10.00 mtr. 0.00 100mt. 0.00
Total:- 3.99
3 Labour
Mason 1st. class 0.355 Nos. 311.50 each 110.58
Mason 2nd. class 0.355 Nos. 311.50 each 110.58
Beldar 1.30 Nos. 262.50 each 341.25
Bhisti 0.28 Nos. 262.50 each 73.50
Total:- 635.92

Total:-1+2+3 5074.82
Add 1.5% for water charges. 76.12
Total:- 5150.94
Add 10% C.P. profit and 5% over head charges except
on cement & pipe. 107.83
Rate for 10 Rmt. 5258.76
Rate for 1 Rmt. 525.88

Executive Engineer,
IPHDivision No.II
Kullu at Bhunter
Analysis of rates
Providing and laying R.C.C. Pipe. 300mm dia.P3 (Detail of
cost for 10 Rmt.)
Sr.
Description of Items Qty. Rate Unit Amount
No
1 Materials:-
RCC. Pipe 300mm dia P3 10 mtr. 524.00 Rmt. 5240.00
Collar 4 Nos. 25.00 each 100.00
Total:- 5340.00
Add. 4% sale tax. 213.60
Total:- 5553.60
Cement 0.005 Tone 4500.00 Tone 22.50
Sand 0.0075 cum. 375.00 Cum. 2.81
Total:- 5578.91
2 Carriege:-
Cement
25.00 Km by machenical transport 0.005 Tone 382.17 Tone 1.91
0.0000 Km. by head load 0.005 Tone 0.00 Tone 0.00
Sand
7.00 Km by machenical transport 0.0075 cum. 277.09 cum. 2.08
0.0000 Km. by head load 0.0075 cum. 0.00 cum. 0.00
Pipe
0.00 Km by machenical transport 10.00 mtr. 0.00 100mt. 0.00
0.0000 Km. by head load 10.00 mtr. 0.00 100mt. 0.00
Total:- 3.99
3 Labour
Mason 1st. class 0.355 Nos. 311.50 each 110.58
Mason 2nd. class 0.355 Nos. 311.50 each 110.58
Beldar 1.30 Nos. 262.50 each 341.25
Bhisti 0.28 Nos. 262.50 each 73.50
Total:- 635.92

Total:-1+2+3 6218.82
Add 1.5% for water charges. 93.28
Total:- 6312.10
Add 10% C.P. profit and 5% over head charges except
on cement & pipe. 110.40
Rate for 10 Rmt. 6422.50
Rate for 1 Rmt. 642.25

Executive Engineer,
IPHDivision No.II
Kullu at Bhunter
Analysis of rates
Providing and laying R.C.C. Pipe. 350mm dia.NP2 (Detail
of cost for 10 Rmt.)
Sr.
Description of Items Qty. Rate Unit Amount
No
1 Materials:-
RCC. Pipe 350mm dia NP2 10 mtr. 265.00 Rmt. 2650.00
Collar 4 Nos. 38.50 each 154.00
Total:- 2804.00
Add. 4% sale tax. 112.16
Total:- 2916.16
Cement 0.006 Tone 4500.00 Tone 27.00
Sand 0.009 cum. 375.00 cum. 3.38
Total:- 2946.54
2 Carriege:-
Cement
25.00 Km by machenical transport 0.006 Tone 382.17 Tone 2.29
0.0000 Km. by head load 0.006 Tone 0.00 Tone 0.00
Sand
7.00 Km by machenical transport 0.009 cum. 277.09 cum. 2.49
0.0000 Km. by head load 0.009 cum. 0.00 cum. 0.00
Pipe
0.00 Km by machenical transport 10.00 mtr. 0.00 100mt. 0.00
0.0000 Km. by head load 10.00 mtr. 0.00 100mt. 0.00
Total:- 4.79
3 Labour
Mason 1st. class 0.355 Nos. 311.50 each 110.58
Mason 2nd. class 0.355 Nos. 311.50 each 110.58
Beldar 1.30 Nos. 262.50 each 341.25
Bhisti 0.28 Nos. 262.50 each 73.50
Total:- 635.92

Total:-1+2+3 3587.24
Add 1.5% for water charges. 53.81
Total:- 3641.05
Add 10% C.P. profit and 5% over head charges except
on cement & pipe. 104.68
Rate for 10 Rmt. 3745.73
Rate for 1 Rmt. 374.57

Executive Engineer,
IPHDivision No.II
Kullu at Bhunter
Analysis of rates
Providing and laying R.C.C. Pipe. 350mm dia.P 1 (Detail
of cost for 10 Rmt.)
Sr.
Description of Items Qty. Rate Unit Amount
No
1 Materials:-
RCC. Pipe 350mm dia NP2 10 mtr. 285.00 Rmt. 2850.00
Collar 4 Nos. 38.50 each 154.00
Total:- 3004.00
Add. 4% sale tax. 120.16
Total:- 3124.16
Cement 0.006 Tone 4500.00 Tone 27.00
Sand 0.009 cum. 375.00 cum. 3.38
Total:- 3154.54
2 Carriege:-
Cement
25.00 Km by machenical transport 0.006 Tone 382.17 Tone 2.29
0.0000 Km. by head load 0.006 Tone 0.00 Tone 0.00
Sand
7.00 Km by machenical transport 0.009 cum. 277.09 cum. 2.49
0.0000 Km. by head load 0.009 cum. 0.00 cum. 0.00
Pipe
0.00 Km by machenical transport 10.00 mtr. 0.00 100mt. 0.00
0.0000 Km. by head load 10.00 mtr. 0.00 100mt. 0.00
Total:- 4.79
3 Labour
Mason 1st. class 0.355 Nos. 311.50 each 110.58
Mason 2nd. class 0.355 Nos. 311.50 each 110.58
Beldar 1.30 Nos. 262.50 each 341.25
Bhisti 0.28 Nos. 262.50 each 73.50
Total:- 635.92

Total:-1+2+3 3795.24
Add 1.5% for water charges. 56.93
Total:- 3852.17
Add 10% C.P. profit and 5% over head charges except
on cement & pipe. 105.15
Rate for 10 Rmt. 3957.32
Rate for 1 Rmt. 395.73

Executive Engineer,
IPHDivision No.II
Kullu at Bhunter
Analysis of rates
Providing and laying R.C.C. Pipe. 350mm dia.P2
(Detail of cost for 10 Rmt.)
Sr.
Description of Items Qty. Rate Unit Amount
No
1 Materials:-
RCC. Pipe 350mm dia NP2 10 mtr. 385.00 Rmt. 3850.00
Collar 4 Nos. 38.50 each 154.00
Total:- 4004.00
Add. 4% sale tax. 160.16
Total:- 4164.16
Cement 0.006 Tone 4500.00 Tone 27.00
Sand 0.009 cum. 375.00 cum. 3.38
Total:- 4194.54
2 Carriege:-
Cement
25.00 Km by machenical transport 0.006 Tone 382.17 Tone 2.29
0.0000 Km. by head load 0.006 Tone 0.00 Tone 0.00
Sand
7.00 Km by machenical transport 0.009 cum. 277.09 cum. 2.49
0.0000 Km. by head load 0.009 cum. 0.00 cum. 0.00
Pipe
0.00 Km by machenical transport 10.00 mtr. 0.00 100mt. 0.00
0.0000 Km. by head load 10.00 mtr. 0.00 100mt. 0.00
Total:- 4.79
3 Labour
Mason 1st. class 0.355 Nos. 311.50 each 110.58
Mason 2nd. class 0.355 Nos. 311.50 each 110.58
Beldar 1.30 Nos. 262.50 each 341.25
Bhisti 0.28 Nos. 262.50 each 73.50
Total:- 635.92

Total:-1+2+3 4835.24
Add 1.5% for water charges. 72.53
Total:- 4907.77
Add 10% C.P. profit and 5% over head charges except
on cement & pipe. 107.49
Rate for 10 Rmt. 5015.26
Rate for 1 Rmt. 501.53

Executive Engineer,
IPHDivision No.II
Kullu at Bhunter
Analysis of rates
Providing and laying R.C.C. Pipe. 350mm dia P3 (Detail
of cost for 10 Rmt.)
Sr.
Description of Items Qty. Rate Unit Amount
No
1 Materials:-
RCC. Pipe 350mm dia NP2 10 mtr. 458.00 Rmt. 4580.00
Collar 4 Nos. 38.50 each 154.00
Total:- 4734.00
Add. 4% sale tax. 189.36
Total:- 4923.36
Cement 0.006 Tone 4500.00 Tone 27.00
Sand 0.009 cum. 375.00 cum. 3.38
Total:- 4953.74
2 Carriege:-
Cement
25.00 Km by machenical transport 0.006 Tone 382.17 Tone 2.29
0.0000 Km. by head load 0.006 Tone 0.00 Tone 0.00
Sand
7.00 Km by machenical transport 0.009 cum. 277.09 cum. 2.49
0.0000 Km. by head load 0.009 cum. 0.00 cum. 0.00
Pipe
0.00 Km by machenical transport 10.00 mtr. 0.00 100mt. 0.00
0.0000 Km. by head load 10.00 mtr. 0.00 100mt. 0.00
Total:- 4.79
3 Labour
Mason 1st. class 0.355 Nos. 311.50 each 110.58
Mason 2nd. class 0.355 Nos. 311.50 each 110.58
Beldar 1.30 Nos. 262.50 each 341.25
Bhisti 0.28 Nos. 262.50 each 73.50
Total:- 635.92

Total:-1+2+3 5594.44
Add 1.5% for water charges. 83.92
Total:- 5678.35
Add 10% C.P. profit and 5% over head charges except
on cement & pipe. 109.20
Rate for 10 Rmt. 5787.55
Rate for 1 Rmt. 578.76

Executive Engineer,
IPHDivision No.II
Kullu at Bhunter
Analysis of rates
Providing and laying R.C.C. Pipe. 400mm dia.NP2 (Detail
of cost for 10 Rmt.)
Sr.
Description of Items Qty. Rate Unit Amount
No
1 Materials:-
RCC. Pipe 350mm dia NP2 10 mtr. 273.00 Rmt. 2730.00
Collar 4 Nos. 49.00 each 196.00
Total:- 2926.00
Add. 4% sale tax. 117.04
Total:- 3043.04
Cement 0.012 Tone 4500.00 Tone 54.00
Sand 0.0165 cum. 375.00 cum. 6.19
Total:- 3103.23
2 Carriege:-
Cement
25.00 Km by machenical transport 0.012 Tone 382.17 Tone 4.59
0.0000 Km. by head load 0.012 Tone 0.00 Tone 0.00
Sand
7.00 Km by machenical transport 0.0165 cum. 277.09 cum. 4.57
0.0000 Km. by head load 0.0165 cum. 0.00 cum. 0.00
Pipe
0.00 Km by machenical transport 10.00 mtr. 0.00 100mt. 0.00
0.0000 Km. by head load 10.00 mtr. 0.00 100mt. 0.00
Total:- 9.16
3 Labour
Mason 1st. class 0.45 Nos. 311.50 each 140.18
Mason 2nd. class 0.45 Nos. 311.50 each 140.18
Beldar 1.80 Nos. 262.50 each 472.50
Bhisti 0.40 Nos. 262.50 each 105.00
Total:- 857.85

Total:-1+2+3 3970.24
Add 1.5% for water charges. 59.55
Total:- 4029.79
Add 10% C.P. profit and 5% over head charges except
on cement & pipe. 139.91
Rate for 10 Rmt. 4169.70
Rate for 1 Rmt. 416.97

Executive Engineer,
IPHDivision No.II
Kullu at Bhunter
Analysis of rates
Providing and laying R.C.C. Pipe. 400mm dia.P1 (Detail
of cost for 10 Rmt.)
Sr.
Description of Items Qty. Rate Unit Amount
No
1 Materials:-
RCC. Pipe 350mm dia NP2 10 mtr. 325.00 Rmt. 3250.00
Collar 4 Nos. 49.00 each 196.00
Total:- 3446.00
Add. 4% sale tax. 137.84
Total:- 3583.84
Cement 0.012 Tone 4500.00 Tone 54.00
Sand 0.0165 cum. 375.00 cum. 6.19
Total:- 3644.03
2 Carriege:-
Cement
25.00 Km by machenical transport 0.012 Tone 382.17 Tone 4.59
0.0000 Km. by head load 0.012 Tone 0.00 Tone 0.00
Sand
7.00 Km by machenical transport 0.0165 cum. 277.09 cum. 4.57
0.0000 Km. by head load 0.0165 cum. 0.00 cum. 0.00
Pipe
0.00 Km by machenical transport 10.00 mtr. 0.00 100mt. 0.00
0.0000 Km. by head load 10.00 mtr. 0.00 100mt. 0.00
Total:- 9.16
3 Labour
Mason 1st. class 0.45 Nos. 311.50 each 140.18
Mason 2nd. class 0.45 Nos. 311.50 each 140.18
Beldar 1.80 Nos. 262.50 each 472.50
Bhisti 0.40 Nos. 262.50 each 105.00
Total:- 857.85

Total:-1+2+3 4511.04
Add 1.5% for water charges. 67.67
Total:- 4578.70
Add 10% C.P. profit and 5% over head charges except
on cement & pipe. 141.13
Rate for 10 Rmt. 4719.83
Rate for 1 Rmt. 471.98

Executive Engineer,
IPHDivision No.II
Kullu at Bhunter
Analysis of rates
Providing CC Lining 15 cm. thick or less in c.c.1:3:6.
Detail of cost for 10 sqm.
Sr.
Description of Items Qty. Rate Unit Amount
No
A. (A) IN BED
1 Materials
CC 1:3:6 1 cum. 3139.99 cum. 3139.99
Total:- 3139.99

2 Labour for making slab up to 15cm thick or less


Mason 1stclass 0.17 Nos. 311.50 each 52.96
Beldar 0.17 Nos. 262.50 each 44.63
Total:- 97.58

Total:-1+2 3237.57

Total:- 3237.57
Add 10% C.P and 5% over head charges.
14.64

Cost for 1 cum.. 3252.21


Say Rs. 3252.21

{ B }.C.C. Linning in side slope


Material
C.C. 1:3:6 1 cum 3252.21 cum 3252.21
Add. Additional labour i/c 10% C.P. & 5%O.H charges for carriage
of material and difficalty of adjestment of side slope laying &
finishing upper surfaces.. L. S. 20.00

Total 3272.21
Say Rs. 3272.21

Executive Engineer,
IPHDivision No.II
Kullu at Bhunter
Analysis of rates
Extra allounce for formwork in C.C Lining.
Detail of cost for 9.30Sqm. or 1.40.
Sr.
Description of Items Qty. Rate Unit Amount
No
1 2 3 4 5 6
(A) IN BED
1 Material:
2nd class kail wood planks.
(Quantity as per
Analysis of 24.39 HPSR.1979 0.055 cum. 29728 cum. 1635.04
2 Carriage of Kail wood:
3.00 Km by machenical transport 0.055 cum. 193.71 cum. 10.65
0.0000 Km. by head load 0.055 cum. 0 cum. 0.00
Total:- 1645.69

Add 10% C.P and 5% over head charges. 246.85


1892.55
Assuming that Timber will become
unreversable after being used 20 times Cost using one 94.63
Sundaries. L.S. 5.00
(A) 99.63
3 Labour:
Detail of cost for 8.50cum.
Carpenter 2nd class 1 Nos. 311.50 each 311.5
Beldar 1 Nos. 262.50 each 262.50
Total:- 574.00
Add 10% C.P and 5% over head charges. 86.10
Total:- 660.10
Labor per block i.e 1.40cum.= (B) 108.72
Labor
Total A+B = 208.35
Cost of 1.40cum. 208.35
Cost per cum. 148.82

(B) ON SIDE SLOPS:


1 Material same as in bed (A) 99.63
2 (ii)Labour:
Detail of cost for 7.08mm.
Carpenter 2nd class 1 Nos. 311.50 each 311.5
Beldar 1 Nos. 262.50 each 262.50
Total:- 574.00
Add 10% C.P and 5% over head charges. 86.1
Labour for 7.08cum. 660.10
Labour for block i.e. 1.40 cum. (B) 130.53
Cost for 1.40cum. A+B 230.16
Cost for 1cum. 164.40
Say Rs. 164.00

Executive Engineer,
IPHDivision No.II
Kullu at Bhunter
Providing Filter Media
Detail of cost for one cum..
Sr.
Description of Items Qty. Rate Unit Amount
No

1 Top layer
(a) Material
Fine sand screened; clean, washed and 1.00 cum. 375.00 cum. 375.00
graded effective size 0-2 to 0.4mmwith
uniformity cofficient 2.0 to 3 from
approved souce.
Rate increased by 20% for screening & 75.00
washing.
Total:- 450.00
(b) Caringe
Sand
7.00 Km by machenical transport 1 cum. 277.09 cum. 277.09
0.000 Km. by head load 1 cum. 0.00 cum. 0.00
Total:- 277.09
© Labour for placing filter media
Rate as per HPSR 1987 6.9
Add. 441.67% above on HPSR 30.48
1987. =
Total = 37.38 37.38
Total:- 764.47

Add 10% C.P and 5% over head charges . 114.67


Total:- 879.14
Say Rs. 879.14

Executive Engineer,
IPHDivision No.II
Kullu at Bhunter
Providing Filter Media
Detail of cost for one cum..
Sr.
Description of Items Qty. Rate Unit Amount
No

2 2nd. Layer
(a) Material
Cource sand screened; clean, washed and 1.00 cum. 375.00 cum. 375.00
graded from 3mm to 6mm from approved
souce.

Rate increased by 20% for screening & 75.00


washing.
Total:- 450.00
(b) Caringe
Sand
7.00 Km by machenical transport 1 cum. 277.09 cum. 277.09
0.0000 Km. by head load 1 cum. 0.00 cum. 0.00
Total:- 277.09
© Labour for placing filter media
Rate as per HPSR 1987 6.9
Add. 441.67% above on HPSR 30.48
1987. =
Total = 37.38 37.38
Total:- 764.47

Add 10% C.P and 5% over head charges . 114.67


Total:- 879.14
Say Rs. 879.14

Executive Engineer,
IPHDivision No.II
Kullu at Bhunter
Providing Filter Media
Detail of cost for one cum..
Sr.
Description of Items Qty. Rate Unit Amount
No

3 3rd.Layer
(a) Material
Bajari screened; clean, washed and graded 1.00 cum. 465.00 cum. 465.00
from 6mm to 20mm from approved souce.

Rate increased by 20% for screening & 93.00


washing.
Total:- 558.00
(b) Caringe
Stone aggregate
7.00 Km by machenical transport 1 cum. 277.09 cum. 277.09
0.0000 Km. by head load 1 cum. 0.00 cum. 0.00
Total:- 277.09
( C ) Labour for placing filter media
Rate as per HPSR 1987 9.2
Add. 441.67% above on HPSR 40.64
1987. =
Total = 49.84 49.84
Total:- 884.93

Add 10% C.P and 5% over head charges . 132.74


Total:- 1017.67
Say Rs. 1017.67

Executive Engineer,
IPHDivision No.II
Kullu at Bhunter
Providing Filter Media
Detail of cost for one cum..
Sr.
Description of Items Qty. Rate Unit Amount
No

4 4th.Layer
(a) Material
Bajari screened; clean, washed and graded 1.00 cum. 465.00 cum. 465.00
from 20mm to 25mm from approved souce.

Rate increased by 20% for screening & 93.00


washing.
Total:- 558.00
(b) Caringe
Stone aggregate
7.00 Km by machenical transport 1 cum. 277.09 cum. 277.09
0.0000 Km. by head load 1 cum. 0.00 cum. 0.00
Total:- 277.09
( C ) Labour for placing filter media
Rate as per HPSR 1987 9.2
Add. 441.67% above on HPSR 40.64
1987. =
Total = 49.84 49.84
Total:- 884.93

Add 10% C.P and 5% over head charges . 132.74


Total:- 1017.67
Say Rs. 1017.67

Executive Engineer,
IPHDivision No.II
Kullu at Bhunter
Providing Filter Media
Detail of cost for one cum..
Sr.
Description of Items Qty. Rate Unit Amount
No

5 Bottom layer
(a) Material
Broken stone screened; clean, washed and 1.00 cum. 440.00 cum. 440.00
graded from 50mm to 75mm from
approved souce.

Rate increased by 20% for screening & 88.00


washing.
Total:- 528.00
(b) Caringe
Stone aggregate
0.00 Km by machenical transport 1 cum. 0 cum. 0.00
0.5000 Km. by head load 1 cum. 443.11 cum. 443.11
Total:- 443.11
(c) Labour for placing filter media
Rate as per HPSR 1987 9.2
Add. 441.67% above on HPSR 40.64
1987. =
Total = 49.84 49.84
Total:- 1020.95

Add 10% C.P and 5% over head charges . 153.14


Total:- 1174.09
Say Rs. 1174.09

Executive Engineer,
IPHDivision No.II
Kullu at Bhunter
Providing Filter Media
Detail of cost for one cum..
Sr.
Description of Items Qty. Rate Unit Amount
No

6 Dry bricks laid over drain


(a) Material
Bricks 502.00 Nos. 7000.00 1000 3514.00
Total:- 3514.00
(b) Caringe
Bricks.
3.00 Km by machenical transport 502 Nos.484.28 1000 243.11
0.0 Km. by head load 502 Nos. 0 1000 0.00
Total:- 243.11
( c) Labour for placing Bricks (Rate same as per L.R. of broken stone)
Rate as per HPSR 1987 9.2
Add. 441.67% above on HPSR 40.64
1987. =
Total = 49.84 49.84
Total:- 3806.95

Add 10% C.P and 5% over head charges . 571.04


Cost for 502 Nos. Total:- 4377.99
Cost for 1000 Nos.
8721

Executive Engineer,
IPHDivision No.II
Kullu at Bhunter
Analysis of rates
Providing plinth protection with CC 1:3:6 (50mm thick)
Detail of cost for 10 sqmt.
Sr.
Description of Items Qty. Rate Unit Amount
No
1 Materials
Cement Concrete 1:3:6 10*0.050 = 0.50 cum. 0.50 cum. 3139.99 cum. 1570.00

Cost for 10 Sqmt. = Total:- 1570.00


Cost per Sqmt. = 157.00

Providing under layer plinth protection 75mm thick


Detail of cost for 10 sqmt.
1 Material
Stone aggregate 40mm. 0.75 cum. 440.00 cum. 330.00
Sand 0.06 cum. 375.00 cum. 22.50
Total:- 352.50
2 Caringe
Stone aggregate
0.00 Km by machenical transport 0.75 cum. 0 cum. 0.00
0.5000 Km. by head load 0.75 cum. 443.11 cum. 332.33
Sand
7.00 Km by machenical transport 0.06 cum. 277.09 cum. 16.63
0.0000 Km. by head load 0.06 cum. 0.00 cum. 0.00
Total:- 348.96
3 Labour for laying ramming and consolidating

Beldar 3.25 Nos. 262.50 each 853.13


Total:- 853.13

Total:- 1554.58

Add 1.5% water charges. 23.32


Total:- 1577.90
Add 10% C.P and 5% over head charges .
236.69
Cost for 10 sqm. Total:- 1814.59
Cost per sqm. 181.46

Say Rs. 181.46

Executive Engineer,
IPHDivision No.II
Kullu at Bhunter
Analysis of rate
Applying priming coat over new steel and other metel
with ready mixed priming paint brushing wood primer pink.
Detail of cost for 10sqmt.
S.No. Description of items Quantity Rate Unit Amount

MATERIAL :

Ready mixed Red lead pante 0.54 140 1 Ltrs. 75.60

Carriage : LS. 2.00

Labour :
Painter 2nd class 0.30 280 Each 84.00
Beldar 0.30 262.5 Each 78.75
Sundries (Brushes etc. LS. 10.00
250.35

Add 10% for C.P. & 5% for overhead charges : 37.55


Cost of 10 Cum.Sqmt. 287.90
Cost of 1 Sqmt. 28.79

Say Rs. 28.79 /- only.

Executive Engineer,
IPHDivision No.II
Kullu at Bhunter
Analysis of rate
Painting two coat over new steel and other metal suface.
Enamel paint other than white.
Detail of cost for 10sqmt.
S.No. Description of items Quantity Rate Unit Amount

MATERIAL :

Enamel paint other than white. 1.00 150 1 Ltrs. 150.00

Carriage : LS. 1.00

Labour :
Painter 2nd class 0.54 280 Each 151.2
Beldar 0.54 262.5 Each 141.75
Sundries (Brushes etc. LS. 20.00
463.95

Add 10% for C.P. & 5% for overhead charges : 69.59


Cost of 10 Cum.Sqmt. 533.54
Cost of 1 Sqmt. 53.35

Say Rs. 53.4 /- only.

Executive Engineer,
IPHDivision No.II
Kullu at Bhunter
Analysis of rate
Applying priming coat over new wood and wood based surface.
with ready mixed paint brushing wood primer pink.
Detail of cost for 10sqmt.
S.No. Description of items Quantity Rate Unit Amount

MATERIAL :

Ready mixed Red lead pante 0.75 150 1 Ltrs. 112.50

Carriage : LS. 1.00

Labour :
Painter 2nd class 0.30 280 Each 84.00
Beldar 0.30 262.5 Each 78.75
Sundries (Brushes etc. LS. 10.00
286.25

Add 10% for C.P. & 5% for overhead charges : 42.94


Cost of 10 . Sqmt. 329.19
Cost of 1 Sqmt. 32.92

Say Rs. 32.9 /- only.

Executive Engineer,
IPHDivision No.II
Kullu at Bhunter
Analysis of rate
Applying two coat of wood preservative over new wood and wood based surface.
Wood preservative (oil type)
Detail of cost for 10sqmt.

S.No. Description of items Quantity Rate Unit Amount

MATERIAL :

Ready mixed Red lead pante 1 110 1 Ltrs. 110.00

Carriage : LS. 2.00

Labour :
Painter 2nd class 0.15 280 Each 42
Beldar 0.15 262.5 Each 39.38

Sundries (Brushes etc. LS. 10


203.38

Add 10% for C.P. & 5% for overhead charges : 30.51


Cost of 10 . Sqmt. 233.89
Cost of 1 Sqmt. 23.39

Say Rs. 23 /- only.

Executive Engineer,
IPHDivision No.II
Kullu at Bhunter
Analysis of rate
Painting two coat Excluding priming coat on new wood and wood based.
with ready mixed paint other than white.
Detail of cost for 10sqmt.
S.No. Description of items Quantity Rate Unit Amount

MATERIAL :

with ready mixed paint other than white. 1.25 140 1 Ltrs. 175.00

Carriage : LS. 2.00

Labour :
Painter 2nd class 0.54 280 Each 151.2
Beldar 0.54 262.5 Each 141.75
Sundries (Brushes etc. LS. 20
489.95

Add 10% for C.P. & 5% for overhead charges : 73.49


Cost of 10 . Sqmt. 563.44
Cost of 1 Sqmt. 56.34

Say Rs. 56.3 /- only.

Executive Engineer,
IPH Divn. Nohradhar.
Distt. Sirmour, HP.
Analysis of rate
White washing with lime on undecorated wallsurfaces two coat:

Detail of cost for 10sqmt.


S.No. Description of items Quantity Rate Unit Amount

MATERIAL :

Lime 0.02 800.00 Qtl. 16.00


Indigo Gum LS. 5.00
Carriage : LS. 1.00
Labour :
White Washer 0.13 262.5 Each 34.13
Beldar 0.07 262.5 Each 18.38
Sundries (Brushes etc. LS. 10
84.51
Add. 1.5% Water chages 1.26765
85.78
Add 10% for C.P. & 5% for overhead charges : 12.87
Cost of 10 . Sqmt. 98.65
Cost of 1 Sqmt. 9.86

Say Rs. 9.9 /- only.

Executive Engineer,
IPHDivision No.II
Kullu at Bhunter
Analysis of rates
1.80mtr.high fencing with 2.50mtr.Angle Posts 2.50mtr.centre to centre with 9 horizontal lines and 2 diagonals of
galvanised steel bar bed wire(I.S:278-1962 Type1)weighing 9.38Kg.per 100mtr.(minimum)strained and fixed to post
.Cost of post,struts and straining bolts shall be paid seperately.

Sr.
Description of Items Qty. Rate Unit Amount
No

1 Materials
G.I bar bed wire 9*30mtr. = 270.00 mtr.
2*13*2.97mtr. = 71.28 mtr.
Total:- 341.28
Weight @ 9.38Kgper100mtr. = 32.01 Kg.
0.3201 Qtl. 2200.00 Qtl. 704.22
Add.4% sale tax 28.17
Total:- 732.39
2 Carriage of G.I wire
25.00 Km by machenical transport 0.032 Tone 382.17 Tone 12.23
0.0000 Km. by head load 0.032 Tone 0.00 Tone 0.00
Total:- 12.23
3 Labour
For fixing and stretching barbed wire:
Blacksmith 2nd class 1.15 Nos. 311.50 each 358.23
Beldar 1.15 Nos. 262.5 each 301.88
Sundries LS. 10.00
Total: 670.10
Total:-1+2+3 1414.72

Add 10% C.P and 5% over head charges. 102.35

Cost for 30mtr. 1517.07


Cost per mtr. 50.57
Say Rs. 50.57

Executive Engineer,
IPHDivision No.II
Kullu at Bhunter
Analysis of rates
1.20mtr.high fencing with 1.80mtr.steel posts 300mm girth (minimum) 2.5 mtr c/c with 6 horizontal horizontal lines and 2
diagonals of galvanised steel bar bed wire(I.S:278-1962 Type1)weighing 9.38Kg.per 100mtr.(minimum)strained and fixed
to post with GI staples including coal tarring or ballies complete (cost posts struts and straining bolts shall be paid for
seperately).

Sr.No Description of Items Qty. Rate Unit Amount

1 Materials
G.I bar bed wire 9*30mtr. = 270 mtr.
10*6.32mtr. = 63.20 mtr.
Total:- 333
Weight @ 9.38Kgper100mtr. = 31.24 Kg.
0.3124 Qtl. 3500.00 Qtl. 1093.40
Add.4% sale tax 43.74
G.I staple for binding wire LS. 10
Total:- 1147.14
2 Carriage of G.I wire
25 Km by machenical transport 0.03124 Tone 382.17 Tone 11.94
0 Km. by head load 0.03124 Tone 0 Tone 0.000
Total:- 11.939
3 Labour
For fixing and stretching barbed wire:
Blacksmith 1st class 0.60 Nos. 311.5 each 186.9
Blacksmith 2nd class 0.12 Nos. 311.5 each 37.38
Beldar 1.20 Nos. 262.5 each 315
Sundries LS. 10
Total: 549.28
Total:-1+2+3 1708.35

Add 10% C.P and 5% over head charges. 84.18

Cost for 30mtr. 1792.54


Cost per mtr. 59.75
Say Rs. 60.00

Executive Engineer,
IPHDivision No.II
Kullu at Bhunter
Analysis of rates
Stone soling properly hand packed filling interstices with

Detail of Cost for One Cum


Sr.
Description of Items Qty. Rate Unit Amount
No
1 Materials
Stone at quarry 1.00 cum. 300.00 cum. 300.00
Total:- 300.00

2 Carriage
0.00 Km by machenical transport 1.00 cum. 0.00 cum. 0.00
0.5 Km. by head load 1.00 cum. 409.84 cum. 409.84
Total:- 409.84

3 Labour
Beldar 0.8 Nos. 262.50 each 210.00
\ Total:- 210.00

Total:-1+2+3 919.84

Add 10% C.P and 5% over head charges.


137.98

1057.82

Executive Engineer,
IPHDivision No.II
Kullu at Bhunter
Analysis of rate
Writing letters or fig. on any surface with black japan paint(stops,comas,hyphens and the like
Block letters/figures
Detail of cost for i00 letters/figures of 15 cm height
S.No. Description of items Quantity Rate Unit Amount

MATERIAL :

Black japan paint 0.56 150 1 Ltrs. 84.00

Carriage : LS. 1.50

Labour :
Painter 1st class 6.00 280 Each 1680
Beldar 2.00 262.5 Each 525.00
Sundries (Brushes etc. LS. 20.00
2310.50

Add 10% for C.P. & 5% for overhead charges : 346.58


Cost for 100 letter/fig of 15 cm height 2657.08
Costper letter/figure per cm. height 0.65

Say Rs. 0.65 /- only.

Executive Engineer,
IPHDivision No.II
Kullu at Bhunter
Removing dry or oil bound distemper by washing and scraping and sand papering the wall surface smooth
including necessary

repair to scratches complete.


Detail of cost for 10 Sqm
Carriage LS 5

LABOUR
Beldar 0.16 81.67 Each 13.07
Painter 2nd class 0.05 89.83 Each 4.49
Sundries /Scaffolding etc. LS 7
Total 29.56
Add for water charges 1.5 0.44
Total 30
Add 10%CP&5%OH 0.15 4.5
Total 34.5
Cost per Sqm. 10 3.45
Say Rs. 3.50

Executive Engineer,
IPHDivision No.II
Kullu at Bhunter
Distempering (two coats) with oil bound washable distemper of approved brand and manufacture of and of required
shade of undecorated wall surfaces to give an even shade over and including a priming coat with Alkali resistance
primer of approved brand and manufacture after thoroughly brushing the surface free from mortar dropping and
other foreign matter

Detail of cost for 10 Sqm.


Material Qty, Rate Unit Amount

Priming coat with distemper primer.


Distemper primer 0.81 Liter 120 P.Liter 97.2
For top coats. 1.5 kg 40 P.Kg 60
Distemper 1.5 kg 35 P.Kg 52.5
Putty for filling holes etc. LS 5
Carriage 2
LABOUR
Painter 1st class 0.27 Each 311.5 84.11
Beldar 0.27 Each 262.5 70.88
Painter 1st 0.67 Each 311.5 208.71
class
Beldar 0.34 Each 262.5 89.25
Sundries (scaffolding LS 5
674.65
Add W.C @ 1.5% 1.5 10.12
684.77
Add 10%CP&5%OH 0.15 102.72
787.49
Cost Per Sqm 10 78.75
Executive Engineer,
IPHDivision No.II
Kullu at Bhunter
Removing old paint or polish from wood and wood based surfaces with paint remover of approved brands and
manufacture and making the surface even withDetail
Paint of
remover
cost forof10
approved
Sqm brand and manufacture.
Material
Paint remover 0.70 lit 100 P.Lit. 70.00
Puty etc, LS 6.00

Carriage LS 1.00
LABOUR
Painter 2nd class 0.54 Each 89.83 48.51
Beldar 0.54 Each 81.67 44.10
Sundries (scaffolding LS 15.00
184.61
Add105CP &5%OH 0.15 27.69
212.30
Cost per Sqm 10 21.23

Removing white wash or colour wash by steel wire brushing and /or scrapping sand papering and preparing the wall
surface smooth including necessary repairs OF
DEATAIL to scratches
COST FOR complete.
10 Sqm.
LABOUR
White Washer 0.01 each 81.67 0.82
Beldar 0.13 each 81.67 10.62

Bhishti 0.04 each 81.67 3.27


Sundries L.S 4
Total 18.71
Add 1.5% W. C. 1.5 0.28
18.99
Add 10% C.P & 5% O.H Charges 0.15 2.85
21.84
Cost Per Sqm. 10 2.18
Finishing wall with water proofing cement paint of approved brand and manufacture and of required shade on
undecorated wall surfaces (two coats) to give an even shade after thoroughly brushing the surface to remove all dirt
and remains of loose powderd materials.

Detail of cost for 10 Sqm.

Material
Paint. 3 kg 75 225

Brushes & sand paper etc. L.S 10

Carriage of materials L.S 2


Labour
Painter 1st class 0.4 Nos 89.83 Each 35.93

Beldar 0.4 Nos 140 Each 56


Bhishti 0.4 Nos 140 Each 56
Sundries L.S 2

386.93

Add 1.5% W.C 1.5 5.8

392.73
Add 10 % CP & 5 % O.H Charges. 0.15 58.91
451.64
Cost Per Sqmt. 10 45.16
Stone work ashlar punched (ordinary work ) in superstructure upto floor two level in cement mortar 1:6 (1cement: 6
sand) including pointing with cement mortar 1:2 (1 cement 2 sand)

Detail of cost for 10 CU.dm


Material
Finished work 10 cu.dm
Wastage 33.3% = 3.33 cu.dm

Total 13.33 cu.dm.


Cost of stone 13.33 cu.dm 50 10 66.65
Mortar for laying/pointing L.S 2.5
Carriage
0.00 KM By Mech. Transport 0.031 Tonne 0.00 0
1.0 Mt. by head load 0.031 Tonne 831.81 25.79
Labour
Mason 1st class 0.059 Nos 0
Black smith 1st class 0.006 Nos 0
Beldar 0.066 Nos 0
Bandhani 0.044 Nos 0
Laying charges of stone work
including
LABOUR pointing
Mason 1st class 0.044 Nos. 130.67 5.75
Bandhani 0.022 Nos. 81.67 1.8
Beldar 0.044 Nos. 81.67
3.59
Black smith 1st class 0.006 Nos. 130.67 0.78
Bhishti 0.022 Nos. 81.67 1.8
Scaffolding 2.5
Mortar for laying/pointing 2.5
113.66
Add 1.5 % W.C 1.5 1.7
115.36
Add 10% CP & 5% OH 0.15 17.3
132.66
Cost for per cum 10 cu.dm 13266

Executive Engineer,
IPHDivision No.II
Kullu at Bhunter
Analysis of rates
Providing stone kharanja drain 45cm wide i/c 25 cm side stone laid in cm 1;6
Detail of cost for 10 Rmt.
Sr.
Description of Items Qty. Rate Unit Amount
No
1 Materials
Cement mortor 0.09 cum. 2382.31 cum. 221.55
Stone at quarry 1.43 cum. 220.00 cum. 314.60

Total:- 536.15

2 Carriage
0.00 Km by machenical transport 1.43 cum. 0 cum. 0.00
1 Km. by head load 1.43 cum. 831.81 cum. 1189.49
Total:- 1189.49

3 Labour

Mason 1st class 0.25 Nos. 311.50 each 77.88

Beldar 0.41 Nos. 262.50 each 107.63


Sundaries L.S. each 6.00
Total:- 191.50

Total:-1+2+3 1917.14

Add 1.5% water charges. 28.83


Total:- 1945.97
Add 10% C.P and 5% over head charges.
258.66
2204.63
Cost Per Mt. 220.46

Executive Executive Engineer,


IPH Divn. IPHDivision No.II
Distt. Sir Kullu at Bhunter
Wall painting (Two Coats) with plastic emulsion paint of approved brand and manufacture on undecorated wall surface to
give an even shade including thoroughly brushing the surface free from mortar droppings and other foreign matter and
sand papered smooth including applying of putty a required for making the surface.
Sr.
Description of Items Qty. Rate Unit Amount
No
DETAIL OF COST FOR 10 SQM
Material
Paint 1.21 Lit. 175 P.Lit. 211.75
Materials for filling holes etc. L.S 5
Carriage of materials LS 3
LABOUR
Painter 1st Class 0.54 Nos 103.83 Each 56.07
Beldar 0.54 Nos 81.67 Each 44.1
Sundries(Scaffolding etc.) 15
Total 334.92
Add 1.5 % Water Charges 1.5 5.02
339.94
Add 10 % C.P & 5% O.H Charges 0.15 50.99
COST FOR 10 SQM 390.93
COST PER SQM 10 39.09

Extra for painting with plastic emulsion paint of approved brand and manufacture on ceilling and / or sloping roofs.
DETAIL OF COST FOR 10 SQM
LABOUR
Painter 1st Class 0.05 Nos 103.83 Each 5.19
Beldar 0.05 Nos 81.67 Each 4.08

Sundries(Scaffolding etc.) 5
Total 14.27
Add 1.5 % water Charges 1.5 0.21
14.48
Add 10 % C.P & 5 % O.H Charges 0.15 2.17
16.65
COST PER SQM 10 1.665
Providing & welding of flanges with GI Pipes 100 mm F.T -5

Cost of one Pair


Material
100 mm dia G.I Pipe
ii Flanges Nuts and Bolts
Supplying and fixing glass panes with putty and nails including removal of brocken glass panes wherever necessary
(Plain Glass 4mm thick)
Detail of cost for 10 glasses area each .1 Sqm
Material
Plain glasspans 1.00 Sqm
Add for wastage @10 %=.10 Sqm
Total 1.10 Sqm
1.1 Sqm 170 P.Sqm 187
Putty 0.68 Kg. 20 P.Kg 13.6
Mythelated spirit & nails 10
Carriage of materials 2
LABOUR
Glazier 0.23 Nos 311.5 Each 71.65
Beldar 0.23 Nos 262.5 Each 60.38
Sundries 5
Total 349.63
Add 10 % C.P & 5% O.H Charges 0.15 52.44
402.07
COST PER SQM Rs. 402.07
Providing wood work in frames of false celling partitions etc. sawn and put up in positions 2nd class Deodar Wood

Details of cost for celling for rooms 3 x 3 m.

Materials
2nd class Deodar wood. 0.166 Cum 50000 8300

Carriage of Timber 0

1 KM By Mech Transport. 0.166 Cum 193.71 32.16

0.1 Mt. by Head Load 0.166 Cum 0.00 0

LABOUR 0

Carpenter 2nd class 1.01 Nos 311.5 314.62

Beldar 1.01 Nos 262.5 265.13

Sundries 20
Total 8931.91
Add 10% CP & 5 % OH Charges 0.15 1339.79
Cost for .158 cum 10271.7
Cost per CUM 0.158 65010.76

Say Rs. 65011


Manufacturing supplying and fixing of cup board made with ply board and teak ply
DETAIL OF COST FOR CUP BOARD 4.83 SQMT.
Description Qty Rate Unit Amount
1 Kit ply 6 mm thick.
Back side cup board 1*2.10*2.30=4.83
Back side cup board 1*.45*1.20=.54
Total 5.37
Add 10 % Wastage = 0.54
Total 5.91 5.91 Sqm 165 Sqm 975.15
2 19mm thick ply board 0
Vertical Side 4*0.55*2.10=4.62 0
Horizantal 4*0.55*2.30=5.06 0
Shutter for box 1*0.35*0.60=0.21 0
Side of mirror 2* 1.55*.08=0.25 0
Top and bottom of mirror 2*0.60*0.20=0.24 0
Total:- 10.38 0
Add 10 % Wastage = 1.04 0
Total 11.42 11.42 Sqm 412 Sqm 4705.04
3 25 mm thick ply for main shutter 0
1*1.55*0.87=1.35 0
Add 10 % Wastage = 0.14 0
Total 1.49 1.49 Sqm 500 Sqm 745
4 4mm thick Teak ply board 0
On shutter1*1.55*0.87= 1.35 0
Add 10 % Wastage = 0.14 0
Total 1.49 1.49 Sqm 306 Sqm 455.94
5 Moulding (Teak Wood) 5mmthick 0
Vertical= 4*1.55 = 6.20 0
Horizental 4*0.44 = 1.76 0
7.96 0
Add 10 % Wastage = 0.80 0
Total 8.76 8.76 Sqm 40 Sqm 350.4
6 Mirror 5 mm thick (Modi Guard 45*120 L.S 450
7 Curtain Rod 0.9 60 54
8 Handle 100 mm (Brass) 2 90 180
9 Tower bolt 100 mm 3 50 150
10 Lock mortage 1 450 450
11 Piano hinges 3.1 40 124
12 Nails 0.5 50 25
13 Fevi coal 2 125 250
14 Screw 1 70 70
15 Carriage L.S 150
16 Labour 0
Carpenter Ist Class 4.5 130.67 588.02
Carpenter 2nd Class 2.9 103.83 301.11
Beldar 1 81.67 81.67
Sundries 25
10130.33
Add 12.5 % Vat on item 1 to 5i.e Rs. 7231.53 12.5 903.94
11034.27
Add 10 % C.P & 5 % O.H Charges 0.15 1655.14
Cost for 4.83 Sqmt. 12689.41
Cost Per Sqmt. 4.83 2627.21
Executive Engineer,
IPHDivision No.II
Kullu at Bhunter
Providing and fixing commercial ply wood celing of approved quality with butt jointing and nails (frame work and
cover fillets to be paid for separately) 6 mm Detail
thick of cost for 10 Sqm
Materials
Commercial ply wood of 6 mm 10.5 Sqm 250 2625
Nails 20

Carriage
Carriage of ply 12
LABOUR
Carpenter 1st class 0.54 Nos 130.67 70.56
Beldar 0.13 Nos 81.67 10.62
Scaffolding 15
Sundries 7
Total 2760.18
Add 10% CP & 5% OH Charges 0.15 414.03
Cost for 10 Sqm 3174.21
Cost per Sqm 10 317.42
Say 317
Providing and laying spartic ceremic tiles 5.5 mm thick in flooring (300x300mm size) treads of steps
laid on a bed of 12 mm thick cement mortarDetail
1:3 (1ofcement
cost for3one
sand) finished with flush pointing in
Sqm.
white cement.
Material
Spartic tiles 300x300x5.5 mm = 11 Nos 30 330
12 mm thick CM 1:3 0.015 Cum 3688.47 55.33

White cement for slurry 0.0035 Tonne 12000 42


Mortar for pointing 20
Carriage of brick tiles
3.00 KM By Mech. Transport 11 1000 484.28 5.33
0 Mtrs by Head Load 11 1000 0.00 0
LABOUR
Mason 1st class 0.7 Nos 130.67 91.47
Beldar 0.7 Nos 81.67 57.17
Sundries L.S 15
Total 616.3
Add 1.5 % water Charges 1.5 9.24
625.54
Add 10% CP & 5% OH Charges 0.15 93.83
719.37
Say 719
2 mm thick PVC/rubber tiles flooring plain,coloured.corbed or mosaic or mattled finish, laid with
approved adhesive on sub floor damp proofing treetment
Detail (to 10
of cost for be Sqm
measured separately) for payment.
Material
1 mm thick pvc tiles 10.5 Sqm 400 4200
Adhesine (as recommended by the 3 Lit. 250 750
manufacturer)

Carriage of materials 20
LABOUR
Mason 2nd class 1.5 Nos 103.83 Each 155.75
Beldar 1.5 Nos 81.67 Each 122.51

Sundries 10
5258.26
Add 10%CP & 5% OH Charges 0.15 788.74
Cost for 10 Sqm 6047
Cost for Per Sqm 10 604.7
Say 605
Distempring with Dry Distemper of approved brand and manufacture(Two Coats)and of required
shade on undecorated wall surface to given an even shade over and including primer coat of
whiting after thoroughly brushing the surface free from mortar droppings and other foreign matter
including preparing the surface even and sand papered smooth

Details of cost for 10 Sqm


Materials
Distempers kg 1 40 40
Chalk Whiting kg 1 12 12

Putty,glue,brushes,sand paper LS 5
CARRIAGE
Carriage of materials 1
LABOUR
Painter 1st Class Each 0.8 178.5 142.8
Beldar Each 0.4 140 56
Sundries(Scaffolding) 25
281.8
Add for water charges @ 1.5 % 1.5 4.23
286.03
Add 10%CP & 5 % OH Charges 0.15 42.9
Cost for 10 Sqmt. 328.93
Cost per Sqmt. 10 32.89
3 mm thick pvc/rubber tile flooring plain coloured morbed or mosaic or mottled finish laid with
approved adhesine on such floor completeDetails
sub floor including
of cost for 10damp
Sqm.proofing treatment to be
Material measured separately for payment.
3mm thick pvc tile= 10 sqm
Add for wastage @ 5%=.50 Sqm

Total = 10.50 Sqm Sqm 10.5 475 P.Sqm 4987.5


Adhesive Litter 3 175 P.Litre 525
CARRIAGE
Carriage of materials 20
LABOUR
Mason 2nd class 1.5 Nos 103.83 Each 155.75
Beldar 1.5 Nos 81.67 Each 122.51
Sundries L.S 20
5830.76
Add 10 % CP & 5% OH Charges 0.15 874.61
Cost for 10 Sqmt. 6705.37
Cost per Sqm 10 670.54

Executive Engineer,
IPH Divn. Nohradhar.
Distt. Sirmour, HP.
Providing and fixing pressed steel doors frames manufactured from commercial mild steel sheet of
1.25 mm thickness including hinges jump lock jamb beed and if required angle threshold of mild
steel angle of section 50x25 mm or base ties of 1.25 mm pressed mild steel welded or regidly fixed
together by mechanical means adjustable lugs with split and tails to each jamb including steel butt
hinges 2.5 mm thick with guards lock strike plate and shock as specified and applying a coat of
approved steel primer after pretreetment of the surface as directed by Engineer in charge.
( PROFILE- A)

Detail of cost for 5 metres


Material
Pressed steel frame 1 KG 13 60 780
CARRIAGE
Carriage Charges 10
LABOUR
Fitter 0.15 Nos 311.5 46.73
Beldar 0.2 Nos 81.67 16.33
Sundries 15
868.06
Add 10% CP & 5% OH Charges 0.15 130.21
Cost for 5 mt. 998.27
Cost per mt. 5 199.65
Providing and fixing pressed steel doors frames manufactured from commercial mild steel sheet of
1.25 mm thickness including hinges jump lock jamb beed and if required angle threshold of mild
steel angle of section 50x25 mm or base ties of 1.25 mm pressed mild steel welded or regidly fixed
together by mechanical means adjustable lugs with split and tails to each jamb including steel butt
hinges 2.5 mm thick with guards lock strike plate and shock as specified and applying a coat of
approved steel primer after pretreetment of the surface as directed by Engineer in charge.
( PROFILE- B)

Detail of cost for 5 metres

Material
Pressed steel frame 1 KG 14 60 840
CARRIAGE
Carriage Charges 15
LABOUR
Fitter 0.15 Nos 311.5 46.73
Beldar 0.2 Nos 81.67 16.33
Sundries 15
933.06
Add 10% CP & 5% OH 0.15 139.96
Charges
Cost for 5 mt. 1073.02
Cost per mt. 5 214.6
Providing and fixing pressed steel doors frames manufactured from commercial mild steel sheet of
1.25 mm thickness including hinges jump lock jamb beed and if required angle threshold of mild
steel angle of section 50x25 mm or base ties of 1.25 mm pressed mild steel welded or regidly fixed
together by mechanical means adjustable lugs with split and tails to each jamb including steel butt
hinges 2.5 mm thick with guards lock strike plate and shock as specified and applying a coat of
approved steel primer after pretreetment of the surface as directed by Engineer in charge.
( PROFILE- C)

Detail of cost for 5 metres


Material
Pressed steel frame 1 KG 15 60 900
CARRIAGE
Carriage Charges 10
LABOUR
Fitter 0.15 Nos 311.5 46.73
Beldar 0.2 Nos 81.67 16.33
Sundries 15
988.06
Add 10% CP & 5% OH Charges 0.15 148.21
Cost for 5 mt. 1136.27
Cost per mt. 5 227.25
ANALYSIS OF RATE
Providing & Laying Plaster Of Paris (Gypsum) Cornish & wall with ceiling as per drawing
Cost for 10 RMT
Materials
Plaster of paries (Gypsum)
10 RPM @ 16 / for R/M
160 kg @ 4/-Per KG 640
LABOUR
Lowest Market rate for kornish
45/- P R/M 450
Nails 10
Sundries,scaffolding etc. 50
1150
Add 1.5 % W.Charges 1.5 17.25
1167.25
Add 10%CP & 5% OH Charges 0.15 175.09
1342.34
Cost per Rmt. 10 134.23
Say Rs.
Providing & Laying Plaster of paris (Gypsum)plaster on walls & ceiling to make the surface
smooth 7 even
Cost for 1 Sqm
Plaster of Paries(Gypsum)
10.76 m2 @ 2 kg p m2 i/c whiting
21.52 kg @ 4/- P.KG 86
LABOUR
Lowest Market Labour rate for
Plaster
& paris @ 3.50 P m2 x 10.76 x 3.50 37.66
Sundries/Scaffolding etc. 20
143.66
Add 1.5 % water charges 1.5 2.15
145.81
Add 10% CP & 5% OH Charges 0.15 21.87
167.68
CARRIAGE
By Mech.Tran. By Head Load
Km. Rate Km. Rate
Issue rate 25.00 382.17 0.0 0.00
Rate at quarry 7.00 277.09 0.0 0.00
M.Rate. 1) 41.32.
Rate at crusher 0.00 0.00 0.5 443.11 (2) 47.38
Rate at crusher 7.00 277.09 0.0 0.00 (3) 53.37
Rate at crusher 7.00 277.09 0.0 0.00 4) 59.10.
At Quarry 0.00 0.00 0.5 409.84
At Quarry 0.00 0.00 1.0 831.81
At Quarry 0.00 0.00 1.0 831.81
At Kilan 3.00 484.28 0.0 0.00
Issue rate 25.00 382.17 0.0 0.00
M.Rate.
M.Rate. 25.00 382.17 0.0 0.00
M.Rate 3.00 193.71 0.0 0.00
M.Rate 3.00 193.71 0.0 0.00
M.Rate. 3.00 193.71 0.0 0.00
M.Rate. 3.00 193.71 0.0 0.00
M.Rate. 3.00 193.71 0.0 0.00
M.Rate. 25.00 382.17 0.0 0.00
HPSR-99
HPSR-99
HPSR-99
HPSR-99
M.rate
R.C 25.00 382.17 0.0 0.00
HPSR-99 1.00 163.80 0.1 89.25

R.C 0.00 0.00 0.0 0.00


R.C 0.00 0.00 0.0 0.00
R.C 0.00 0.00 0.0 0.00
R.C 0.00 0.00 0.0 0.00

R.C 0.00 0.00 0.0 0.00


R.C 0.00 0.00 0.0 0.00
R.C 0.00 0.00 0.0 0.00
R.C 0.00 0.00 0.0 0.00

R.C 0.00 0.00 0.0 0.00


R.C 0.00 0.00 0.0 0.00
R.C 0.00 0.00 0.0 0.00
R.C 0.00 0.00 0.0 0.00

R.C 0.00 0.00 0.0 0.00


R.C 0.00 0.00 0.0 0.00
R.C 0.00 0.00 0.0 0.00
R.C 0.00 0.00 0.0 0.00

R.C 0.00 0.00 0.0 0.00


R.C 0.00 0.00 0.0 0.00
R.C 0.00 0.00 0.0 0.00
R.C 0.00 0.00 0.0 0.00
Approved rate.
Analysis of rates
Excavation in Earth Work and disposal of all excavated earth
Detail of cost for 10 cu.m

Sr.No Description of Items Qty. Rate Unit Amount


1 Pick Work
Beldar 5.83 Nos. 262.50 each 1530.38

Total:- 1530.38

Add 1.5% water charges. 22.95563


Total:- 1553.33
Add 10% C.P and 5% over head charges 233.00
except on cement.
Total:- 1786.33

Cost for 10cum.- 1786.33


Cost for 1cum.- 178.63
Say Rs. 178.63

2 Jumper work
Detail of cost for 10 cu.m
Drilling equipment 0.045 P/Day 2054.69 P/Day 92.46
Explosive
Special gelatine 80% 0.63 Kg 57.00 Kg 35.91
Detonators 3.00 Nos. 350.00 100 N. 10.5
Safty fuse coil 0.25 coil 18.00 coil 4.50
Total:- 50.91
Labour
Drillers 0.135 Nos. 262.50 each 35.4375
Blaster 0.09 Nos. 262.50 each 23.63
Beldar 12.00 Nos. 262.50 each 3150
Total:- 3209.06
Total:- 3352.43
Add for 10% C.P. and 5% over head 502.87
charges.
Total:- 3855.30

Cost per cum.= 385.53


Average rate
Pick work 50% and jumper work 50% = 282.08

Say Rs. 282.08

Executive Engineer,
IPHDivision No.II
Kullu at Bhunter
Analysis of rate
Excavation in earth work and filling in 15 cm layers in foundation & plinth
Detail of cost for 10 cu.m

Description of Items Qty. Rate Unit Amount


Pick Work
Beldar 6.11 Nos 262.50 Each 1603.88
Bhishti 0.29 Nos 262.50 Each 76.13

1680.01
Add 1.5% water charges 25.2
1705.21

Add 10 % CP & 5 % O.H Charges 255.78


1960.99

Cost per CUM 196.099

Executive Engineer,
IPHDivision No.II
Kullu at Bhunter
Analysis of rates
Excavation inearth work and banking in 20 cm layers
Detail of cost for 10 cu.m

Sr.No Description of Items Qty. Rate Unit Amount


1 Pick Work
Beldar 6.37 N os. 262.50 each 1672.13

Total:- 1672.13

Add 1.5% water charges. 25.08188


Total:- 1697.21
Add 10% C.P and 5% over head charges 254.58
except on cement.
Total:- 1951.79

Carriage of Earth 100 mt 35.32

Cost for 10cum.- 1987.11


Cost for 1cum.- 198.71
Say Rs. 198.7
3974.22

Executive Engineer,
IPHDivision No.II
Kullu at Bhunter
Analysis of rates
Providing and laying of cement concrere 1:3:6 for Walls
Detail of cost for one cu.m
Sr.No Description of Items Qty. Rate Unit Amount
Materials
1
Stone aggregate 20mm 0.70 cum. 465.00 cum. 325.50
Stone aggregate 10mm 0.24 cum. 475.00 cum. 114.00
Sand 0.47 cum. 375.00 cum. 176.25

Cement 0.22 Tone 4500.00 Tone 990.00


Total:- 1605.75

2 Carriage
Sand
7.00 Km by machenical transport 0.47 cum. 277.09 cum. 130.23
0.0 Km. by head load 0.47 cum. 0.00 cum. 0.00

Stone aggregate below 40mm:-


7.00 Km by machenical transport 0.94 cum. 277.09 cum. 260.46
0.0 Km. by head load 0.94 cum. 0.00 cum. 0.00

Cement
25.00 Km by machenical transport 0.22 Tone 382.17 Tone 84.08
0.0 Km. by head load 0.22 Tone 0.00 Tone 0.00

Total:- 474.77
3 Labour
Beldar 2.09 Nos. 262.50 each 548.63
Bhisti 0.28 Nos. 262.50 each 73.50
Mason 1st class 0.06 Nos. 311.50 each 18.69
Mason 2nd class 0.06 Nos. 311.50 each 18.69
Mate 0.04 Nos. 262.50 each 10.50
Beldar for extra ramming 0.25 Nos. 262.50 each 65.63
Sundaries/Scaffolding L.S. 40.00
Total:- 775.63

Total:-1+2+3 2856.15

Add 1.5% water charges. 42.84


Total:- 2899.00
Add 10% C.P and 5% over head charges except on cement.

1 286.35

3185.35
Say Rs. 3185.35

Executive Engineer,
IPHDivision No.II
Kullu at Bhunter
Analysis of rates
Providing and laying of cement concrere 1:3:6 with 15% plum in R/wall & B/wall
Detail of cost for one cu.m
Description
Sr.No Qty. Rate Unit Amount
of Items
Materials
1
Stone aggregate 20mm 0.64 cum. 465.00 cum. 297.60
Stone aggregate 10mm 0.22 cum. 475.00 cum. 104.50
Sand 0.43 cum. 375.00 cum. 161.25
Selected hard stone (Plum) 0.15 cum. 170.00 cum. 25.5
Cement 0.2 Tone 4500.00 Tone 900.00
Total:- 1488.85
2 Carriage
Stone aggregate 20mm
7.00 Km by machenical transport 0.64 cum. 277.09 cum. 177.34
0.0 Km. by head load 0.64 cum. 0.00 cum. 0.00

Sand
7.00 Km by machenical transport 0.43 cum. 277.09 cum. 119.15
0.0 Km. by head load 0.43 cum. 0.00 cum. 0.00

Stone aggregate below 10mm:-


7.00 Km by machenical transport 0.22 cum. 277.09 cum. 61.00
0.0 Km. by head load 0.22 cum. 0.00 cum. 0.00
Solling stone
0.00 Km by machenical transport 0.15 cum. 0.00 cum. 0.00
0.5 Km. by head load 0.15 cum. 409.84 cum. 61.48
Cement
25.00 Km by machenical transport 0.2 Tone 382.17 Tone 76.43
0.0 Km. by head load 0.2 Tone 0.00 Tone 0.00
Total:- 495.40
3 Labour
Beldar 1.07 Nos. 262.50 each 280.88
Bhisti 0.25 Nos. 262.50 each 65.63
Mason 1st class 0.17 Nos. 311.50 each 52.96
Beldar for extra rammingn 0.98 Nos. 262.50 each 257.25
Sundaries L.S. 20.00
Total:- 676.71

Total:-1+2+3 2660.95
Add 1.5% water charges. 39.91
Total:- 2700.87
Add 10% C.P and 5% over head charges except on cement.
270.13
2971.00
Say Rs.

Executive Engineer,
IPHDivision No.II
Kullu at Bhunter
Analysis of Rate.

Providing and laying CC 1:2:4 (Wall any thickness)

Detail of cost for one cu.m


Sr.No Description of Items Qty. Rate Unit Amount
1 Materials
Stone aggregate 20mm 0.67 cum. 465.00 cum. 311.55
Stone aggregate 10mm 0.22 cum. 475.00 cum. 104.50
Sand 0.445 cum. 375.00 cum. 166.88
Cement 0.32 Tone 4500.00 Tone 1440.00
Total:- 2022.93
2 Carriage
Stone aggregate
7.00 Km by machenical transport 0.89 cum. 277.09 cum. 246.61
0.0 Km. by head load 0.89 cum. 0.00 cum. 0.00
Sand
7.00 Km by machenical transport 0.445 cum. 277.09 cum. 123.31
0.0 Km. by head load 0.445 cum. 0.00 cum. 0.00
Cement
25.00 Km by machenical transport 0.32 Tone 382.17 Tone 122.29
0.0 Km. by head load 0.32 Tone 0.00 Tone 0.00
Total:- 492.21
3 Labour
Beldar 2.09 Nos. 262.50 each 548.63
Bhisti 0.27 Nos. 262.50 each 70.88
Mason 1st class 0.05 Nos. 311.50 each 15.58
Mason 2nd class 0.05 Nos. 311.50 each 15.58
Mate 0.04 Nos. 262.50 each 10.50
Beldar for extra ramming 0.25 Nos. 262.50 each 65.63
Sundaries L.S 15.00
Scaffolding LS 35.00
Total:- 776.78
G.Total 3291.91

Add 1.5 % water charges 49.38


3341.29
Add 10%CP&5%OHCharges except on cement 285.1934
3626.48
P/L Wall any thickness

Rate as per 9.18 cum 3626.48 33291.11


Add extra Labour 133.26
Cost for 9.18 33424.38
9.18 3641.00
Say Rs. 2238.10/ - only.

Executive Engineer,
IPHDivision No.II
Kullu at Bhunter
Analysis of rates
Stair cases(except spiral stair cases) excluding landing
Detail of cost for a flight of 3.40 m clear span including I mt. landing (cost of landing excluded)

Sr.No Description of Items Qty. Rate Unit Amount

1 C.C. 1:2:4 Detail as cc in foundation & plinth. 0.79 cum 3568.12 cum 2818.81

2 Extra labour for lying CC in RCC slab due 0.79 cum 133.26 cum 105.28
to delay:-
3 Extra cost involved in lying CC over
curved suface:-
Mason 1st class 0.5 Nos. 311.50 each 155.75
Mason 2nd class 0.5 Nos. 311.50 each 155.75
Extra labour for lifting material
Beldar 0.17 Each 81.67 each 13.88

Total:- 3249.47

Add 1 1/2% for water charges on Rs. 3249.47 48.74


Total:- 3298.22
Add 10% C.P and 5% over head charges on Rs. 479.40 71.91
Cost for 0.79 3370.13
Cost per cum 4265.98

Executive Engineer,
IPHDivision No.II
Kullu at Bhunter
Analysis of rate
P/L CC 1:2:4 mix (1cement 2 sand 4 graded stone aggregate 20 mm nominal size for reinforced concrete chajjas
not exceeding
Detail of cost for 30 mt. long 60 cm wide and 8 cm thick.
Sr.No Description of Items Qty. Rate Unit Amount
C.C. 1:2:4 1.44 cum 3568.12 5138.09
Form work 22.9 sqm 514.276 11776.93
Additional Labour 1.44 Cum 133.26 191.9
Labour for extra lifting 0
Beldar 0.33 Nos 81.67 26.95
17133.87
Add for water charges @ 1.5 % 1.5 257.01
17390.88
Add 10% CP & 5% O.H Charges on Rs. 475.86 71.38
17462.26
Cost for 1.44
Cost Per Cum 12126.57

Executive Engineer,
IPHDivision No.II
Kullu at Bhunter
Analysis of rates
S.R. stone masonary in CM 1:3
Detail of cost for one cu.m

Sr.No Description of Items Qty. Rate Unit Amount

1 Materials
Cement mortor 0.30 cum. 3688.47 cum. 1106.54
Stone at quarry 1.21 cum. 350.00 cum. 423.50
through stone 7.00 Nos. 7.00 each 49.00
Total:- 1579.04

2 Carriage
0.00 Km by machenical transport 1.37 cum. 0 cum. 0.00
1 Km. by head load 1.37 cum. 831.81 cum. 1139.58
Total:- 1139.58

3 Labour
Stone dresser 2.83 Nos. 262.50 each 742.88
Mason 1st class 1.06 Nos. 311.50 each 330.19
Mason 2nd class 1.06 Nos. 311.50 each 330.19
Beldar 2.65 Nos. 262.50 each 695.63
Sundaries L.S. each 35.00
Total:- 2133.88

Total:-1+2+3 4852.50

Add 1.5% water charges. 63.68


Total:- 4916.18
Add 10% C.P and 5% over head charges.
571.45

5487.63

Executive Engineer,
IPHDivision No.II
Kullu at Bhunter
Analysis of rates
Wire crates made of interlink chain of G.I wire filled with bolders with squarecut faces against the wire (Bolder
filling to be measured and paid for separately) G.I wire 4mm thick corresponding to SWG-8.25cm*7.5cm mesh.

Detail of cost for 9.375(6*1.25m*1.25m) Sqmt.


Sr.No Description of Items Qty. Rate Unit Amount

1 Materials
G.I wire 4mm thick (Diagonal 40.54
dimension)for one phase of crate length
of wire required (17*6)*1.25*1.41=

Add for wastage and twisting@10% 4.05

Total:- 44.59
For six side length required 44.59
Rmt.*6= 267.564
Weight of G.I. wire 4mm thick =0.10 Kg
per Rmt.
Therefore total weight =267.54*.10 =
26.75 Kg 2200.00 Kg 58850.00
Add.4% sale tax 2354.00
Total:- 61204.00
2 Carriage of Interlink chain/G.I wire
25.00 KM by machanical transport 0.031 Tonne 382.17 Tonne 11.85
0 KM by Head load 0.031 Tonne 0.00 Tonne 0.00
Total:- 11.85
3 Labour
Blacksmith 2nd class 0.15 Each 311.50 Each 46.73

Total:-1+2+4 61262.57

Add 10% C.P and 5% over head charges. 2.93

Cost for 9.375Sqm. 61265.50


Cost per Sqm. 6534.99

Say Rs. 6534.99


Analysis of rates
Cement plaster skirting (upto 30 cm height) with cement mortar 1:3 (1cement 3 sand) finished with a floating coat of neat
cement
Detail of cost for 10 sqm

Sr.No Description of Items Qty. Rate Unit Amount


Materials
Cement mortar 1:3 0.202 cum 3688.47 P.Cum 745.07
0.00
Cement for finishing coat 0.01 Tonne 4500 P.Tonne 45.00

Cement
25.00 Km by machenical transport 0.01 Tone 382.17 Tone 3.82
0 Km. by head load 0.01 Tone 0.00 Tone 0.00

LABOUR
Mason 2nd class 1.00 Nos 311.5 Each 311.50
Beldar 1.00 Nos 262.5 Each 262.50
Bhishti 0.55 Nos 262.5 Each 144.38
Sundries 25.00
1537.27
Add for water charges @ 1.5 % 1.5 23.06
1560.33
Add 10 % CP & 5 % OH Charges on Rs. 815.26 0.15 122.29
Cost for 10 sqm 1682.62
Cost per sqm 10 168.26

Executive Engineer,
IPHDivision No.II
Kullu at Bhunter
Analysis of rates
Cement mortor 1:5 (1 cement :5mortor)
Detail of cost for one cum.
Sr.No Description of Items Qty. Rate Unit Amount
1 Materials
Cement 0.31 Tone 4500 Tone 1395.00
Sand 1.07 cum. 375 cum. 401.25
Total:- 1796.25

2 Carriage
Cement
25.00 Km by machenical transport 0.31 Tone 382.17 Tone 118.4727
0.0 Km. by head load 0.31 Tone 0.00 Tone 0.00
Sand
7.00 Km by mechanical transport 1.07 cum. 277.09 cum. 296.49
0.0 Km. by head load 1.07 cum. 0.00 cum. 0.00
Total:- 414.96

3 Labour
For measuring carrying disposing
and mixing etc.
Bhisti 0.90 Nos. 262.50 each 236.25
Beldar 0.08 Nos. 262.50 each 21.00
Sundaries L.S. 10.00
Total:- 267.25

Total:-1+2+3 2478.46

Add 1.5% water charges. 37.18


Total:- 2515.64
Add 10% C.P and 5% over head charges except on
cement. 168.10

2683.73
Cement plaster skirting in CM 1:3

Sr.No Description of Items Qty. Rate Unit Amount


Detail of cost for 10 SQM.

Material:-
cement mortar 1:3 0.172 cum
add for rounding corners 0.03
0.202 cum 0.202 cum 3688.47 cum 745.07
Cement for finishing coat 0.01 tonne 4500 45
Carriage:-
Cement
25.00 km by Mech. Transport 1 tonne 382.17 tonne 382.17
0.0 km by head load 1 tonne 0.00 tonne 0

Labour:-
Mason 2nd class 1 No. 311.5 Each 311.5
Beldar 1 No. 262.5 Each 262.5
Bhishti 0.55 No. 262.5 Each 144.38

Sundries LS 12

1902.62
Add 1.5% for water charges 28.54

1931.16
Add 15% for CP& OH charges 289.67

Cost for 10 Sqm Rs. 2220.83

Cost for One Sqm Rs. 222.08

Say Rs. 222.08 only

Executive Engineer,
IPHDivision No.II
Kullu at Bhunter
Analysis of rates
P/F 10mm thick anti skit water proof atain and ompact resistant heavy duty vertified tiles
Nitco or equivalent 600x600x10mm manufactured of approved shade and colour in flooring
treads of steps and landings laid over 12mm thick cement mortar 1;3 ( 1cement;3sand)
jointed with cement slurry mixed with pigment to match the shade of tiles as required .
Detail of cost for 1 SQM.
Sr.No Description of Items Qty. Rate Unit Amount
Materials:-
10mm thick vertified tiles= 1.00 sqm
add 5% for wastage 0.05 sqm
Total:- 1.05 sqm
1.05 sqm 1021 sqm 1072.05
Add 13.75% for VAT 147.41
Total:- 1219.46
12mm thick cement mortar 0.015 cum 3688.47 cum 55.33
Cement for slurry 0.003 Tonne 4500 Tonne. 13.50
Pigment medium shade 0.45 Kg 90 Kg 40.50
Carriage:- Total:- 109.33
3 Carriage of tiles.
0 Km by mechnical transport 3.00 Nos. 484.28 1000Nos. 1.45
Km by head load 3.00 Nos. 0.00 1000Nos. 0.00

Carriage of cement/ pigment 5.00


Labour:- Total:- 6.45
Mason for tarrazo works 0.70 Nos. 311.5 Each 218.05
Beldar 0.70 Nos. 262.5 Each 183.75
Sundries 20.00
Total:- 421.80

Total:- 1757.04
Add 1.5% for water charges except on CM on Rs. 1540.80 23.11
Total:- 1780.15
Add 15% CP & OH charges on RS 1563.91 234.59
Cost for One qsm> Rs:- 2014.74

Say Rs:- Rs:- 2015.00

Executive Engineer,
IPHDivision No.II
Kullu at Bhunter
Analysis of rates
Flush pointing in CM 1:4
Detail of cost for 10 sqm.
Sr.No Description of Items Qty. Rate Unit Amount
1 Materials
Cement mortor 1:4 0.023 cum. 3035.39 cum. 69.81
Total:- 69.81

2 Labour
Mason 2nd class 0.85 Nos. 311.50 each 264.78
Beldar 0.85 Nos. 262.50 each 223.13
Bhisti 0.80 Nos. 262.50 each 210.00
Sundaries L.S. 10.00
Total:- 707.90

Total:-1+2 777.71

Add 1.5% water charges. 10.62


Total:- 788.33
Add 10% C.P and 5% over head charges.
107.78

Cost for 10 sqm.. 896.11


Cost per sqm.. 89.61
Say Rs. 89.61
Painting two coat (excluding priming coat) on previously painted steel & other metel surfaces
with enamel paint other than white brushing to even shade including cleaning
the surface of all dirt dust and other foreign matter
with enamel paint other than

Detail of cost for 10sqmt.


S.No. Description of items Quantity Rate Unit Amount
0
MATERIAL :

Readymixed paint other than white. 1.00 130 1 Ltrs. 130.00

Carriage : LS. 2.00

Labour :
Painter 2nd class 0.36 280 Each 100.8
Beldar 0.36 262.5 Each 94.50
Sundries (Brushes etc. LS. 20.00
347.30

Add 10% for C.P. & 5% for overhead charges : 52.1


Cost of 10 Cum. Sqmt. 399.40
Cost of 1 Sqmt. 39.94

Say Rs. 40.00 /- only.


Executive Engineer,
IPHDivision No.II
Kullu at Bhunter
Painting one coat (excluding priming coat) on previously painted steel & other metel surfaces
with ready mixed paint brushing finishing oil gloss to give an even shade including cleaning
the surface of all dirt dust and other foreign matter
With ready mixed paint other than white.

Detail of cost for 10sqmt.


S.No. Description of items Quantity Rate Unit Amount

MATERIAL :

Readymixed paint other than white. 1.00 145 1 Ltrs. 145.00

Carriage : LS. 1.50

Labour :
Painter 2nd class 0.36 280 Each 100.8
Beldar 0.36 262.5 Each 94.50
Sundries (Brushes etc. LS. 20.00
361.80

Add 10% for C.P. & 5% for overhead charges : 54.27


Cost of 10 Cum. Sqmt. 416.07
Cost of 1 Sqmt. 41.61

Say Rs. 41.6 /- only. Executive Engineer,


IPHDivision No.II
Kullu at Bhunter
Analysis of rate
Painting one coat(excluding priming coat)on previously painted wood and wood based surfaces
withready mixed paint brushing to give an even shade including cleaning of all dirt,dust and other
foreign matter sand papering and stopping with ready mixed paint(white)
Detail of cost for 10sqmt.
S.No. Description of items Quantity Rate Unit Amount

MATERIAL :

Ready mixed paint white 0.75 150 1 Ltrs. 112.50


Putty LS. 10
Carriage : LS. 2.00

Labour :
Painter 2nd class 0.36 280 Each 100.80
Beldar 0.36 262.5 Each 94.50
Sundries (Brushes etc. LS. 20.00
339.80

Add 10% for C.P. & 5% for overhead charges : 50.97


Cost of 10 . Sqmt. 390.77
Cost of 1 Sqmt. 39.08

Say Rs. 39.08 /- only. Executive Engineer,


IPHDivision No.II
Kullu at Bhunter
Analysis of rate

Paintingonecoat(excluding priming coat) on previously painted wood and wood based surfaces with enamel
paint to given and even shade including cleaning of all dirt,dust and other foreign matter sand papering and
stopping With white enamel paint
Details of cost for 10 Sqm
Material
With white enamel paint Litter 0.61 150 91.5
Putty L.S 6
Carriage

Carriage of materials 2
LABOUR

Painter 1st Class 0.36 Nos 89.83 Each 32.34


Beldar 0.36 Nos 81.67 Each 29.4
Sundries 10

171.24
Add 10% CP & 5% OH Charges 0.15 25.69
Cost for 10 Sqm 196.93
Cost for one sqm 10 19.69
Say Rs.

Executive Engineer,
IPHDivision No.II
Kullu at Bhunter
Analysis of rate
Polishing two coats with french polish on new wood and wood based surfaces to give an even surface
i/c cleaning the surface of all dirt,dust and sand papered smooth and i/c a coat of wood filler.
Detail of cost for 10sqmt.
S.No. Description of items Quantity Rate Unit Amount
MATERIAL :
Spirit 1.60 70.00 1 Ltrs. 112.00
Shallac 0.245 91.00 1 Kg 22.30
Pigment(Colour) L-S 5.00
Sand paper cotton etc. L-S 9.00
White woolen cloth,Putty. L-S 10.50
Linseed oil L-S 1.50
Carriage : LS. 1.75

Labour :
Painter 2nd class 3.50 280 Each 980

Sundries (Brushes etc. LS. 5.00


Total: 1147.05

Add 10% for C.P. & 5% for overhead charges : 172.06


Cost of 10 . Sqmt. 1319.11
Cost of 1 Sqmt. 131.91

Say Rs. 131.91 /- only.


Executive Engineer,
IPHDivision No.II
Kullu at Bhunter
Analysis of rate
White washing with lime on decorated wallsurfaces (one coat)

Detail of cost for 10sqmt.


S.No. Description of items Quantity Rate Unit Amount

MATERIAL :

Lime 0.01 800.00 Qtl. 8.00


Indigo Gum LS. 5.00
Carriage : LS. 1.00
Labour :
White Washer 0.06 262.5 Each 15.75
Beldar 0.03 262.5 Each 7.88
Sundries (Brushes etc. LS. 10
47.63
Add. 1.5% Water chages 0.71445
48.34
Add 10% for C.P. & 5% for overhead charges : 7.25
Cost of 10 . Sqmt. 55.59
Cost of 1 Sqmt. 5.56
Extra for every subsequent
coat of white washing Say Rs. 5.6 /- only.
Cost for one coat Rs. 5.6
Labour. Rs. 3.4
say Rs. 8.9
Executive Engineer,
IPHDivision No.II
Kullu at Bhunter
Analysis of rates
Steel work in single section including cutting hoisting fixing in position and applying a priming coat of red lead paint:-
R.S.joists, channel, Angles Tees.

Detail of cost for 2.65 Quintals.

Sr.No Description of Items Qty. Rate Unit Amount

Material;-
R S Joists. 2.78 Qtl 3200 Qtl 8896.00

Applying priming coat 7 Sqm 15 Sqm 105.00

Carriage:- 9001.00
Steel
25.00 KM by mech Transport 0.278 Tonne 382.17 Tonne 106.24
0.0 KM by head load 0.278 Tonne 0.00 Tonne 0.00
106.24
Labour;-

Black smith 2nd class 0.6 No. 311.5 Each 186.90


Bandhani 1.2 No. 262.5 Each 315.00
Beldar 3.3 Nos. 262.5 Each 866.25
Fitter 0.6 Nos. 311.5 Each 186.90
Sundries LS 15.00
1570.05
Total:- 10677.29
Add 1.5% water charges 158.58
10835.87
Add 15% CP&OH charges 1609.63
Cost for 2.65 quintal:- Rs. 12445.51
Cost for one quintal;- Rs. 4696.42

Say Rs. 4696.00

Executive Engineer,
IPHDivision No.II
Kullu at Bhunter
Analysis of rates
Demolition above GL up to floor two level including disposal of unserviceable materials with in 20mtrs lead
and including the necessary reinforcement and separating out from RCC/RB works.

RCC Work:-
Detail of cost for one cum

Labour
Mate Each 0.72 No. 262.5 189.00
Beldar Each 4.46 No. 262.5 1170.75
Black smith 2nd class Each 6.00 No. 311.5 1869.00
Beldar Each 6.00 No. 262.5 1575.00
Scaffolding LS 65.00
Sundries LS 65.00
Total: 4933.75
Add 15% for CP & OH Charges. 740.06
Cost for 1 cum. Total:- 5673.81

Say Rs. = 5674.00 /-only.

Executive Engineer,
IPHDivision No.II
Kullu at Bhunter
Analysis of rates
Stone soling properly hand packed filling interstices with spalls and consolidating with power road
roller to thr reqd. gradient including spreading,watering and rolling of binding materials moorum or
earth etc.
Detail of cost for one cum.
Sr.No Description of Items Unit Qty. Rate Amount

Materials:-
Ordinary quarried stone cum 1 300 300
Moorum/earth L.S 30
Carriage :
Soling stone
0.0 KM by mech. Transport cum 1 0.00 0
0.5 by head load cum 1 409.84 409.84

LABOUR :
Mate each 0.08 262.5 21.00
Beldar each 0.08 262.5 21.00
Bhishti each 0.21 262.5 55.13
Sundries. L.S 20
Total 856.97
Add for water charges @ 1.5% 12.85
Total 869.82
Add 15 % C.P & O.H Charges 130.47
Total 1000.29

Executive Engineer,
IPHDivision No.II
Kullu at Bhunter
Distempering (One coat) with oil bound washable distemper of approved brand and manufacture of and of
required shade of decorated wall surfaces to give an even shade over and including a priming coat with
Alkali resistance primer of approved brand and manufacture after thoroughly brushing the surface free
from mortar dropping and other foreign matter

Detail of cost for 10 Sqm.


Material Qty, Rate Unit Amount

Distemper 1.00 40.00 Kg 40.00

Brushes,sand paper putty etc LS 3.00

Carriage
Carriage of material LS 1.00

Labour.
Painter 1st class 0.40 311.5 Each 124.60
Beldar 0.20 262.5 Each 52.50
Sundried sacffolding etc. LS 2.00

223.10
Add 1.5% for water charges 3.35
226.45
Add 15% for CP & OH charges except carriage. 225.45 33.82
Cost for 10sqmRs. 260.26

Cost for onr sqm 26.03


Extra over for every subsequent of distemper 19.46
Total 45.49
Rs.
Say 45.5
Rs.

Executive Engineer,
IPHDivision No.II
Kullu at Bhunter
Extra for distempring with oil bound distemper on ceiling and /or sloping roofs.
Detail of cost for 10 Sqm.

LABOUR
Painter 1st 0.09 Each 89.83 8.08
class
Beldar 0.06 Each 81.67 4.9
Sundries (scaffolding LS 2.5
Total 15.48
Add W.C 1.5 0.23
@ 1.5%
15.71
Add 0.15 2.3565
10%CP&5% 18.0665
OH
10 1.81

Executive Engineer,
IPHDivision No.II
Kullu at Bhunter
Removing old paint or polish from steel andother metal surfaces with paint remover of approved brands
and manufacture and making the surface even with hand scraping
Detail of cost for 10 Sqm
Material

LABOUR
Painter 2nd class 0.81 Each 89.83 72.76
Beldar 0.81 Each 81.67 66.15
Sundries (scaffolding LS 10.00
148.91
Add105CP &5%OH 0.15 22.34
171.25
Cost per Sqm 10 17.13

Executive Engineer,
IPHDivision No.II
Kullu at Bhunter
Painting wall with water proofing cement paint of approved brand(APEX) and manufacture and of required
shade on undecorated wall surfaces (two coats) to give an even shade after thoroughly brushing the
surface to remove all dirt and remains of loose powderd materials.

Detail of cost for 10 Sqm.

Material
Water 1.21 Litre 230.00 Per Litre 278.30
proofing
paint(APEX)
Material for L.S 3.00
filling holes
etc.
Carriage of L.S 2.00
materials
Labour
Painter 1st 0.54 Nos 103.83 Each 56.07
class
Beldar 0.54 Nos 81.67 Each 44.10

Sundries (Scaffoldin L.S 7.00


g etc.)
390.47

Add 1.5% 1.5 5.86


W.C
396.33
Add 10 % CP & 5 % O.H Charges. 0.15 59.45
455.78
Cost Per 10 45.58
Sqmt.
Analysis of rates
Providing stone kharanja drain 60cm wide i/c 25 cm side stone laid in cm 1;6
Detail of cost for 10 Rmt.

Sr.No Description of Items Qty. Rate Unit Amount


1 Materials
Cement mortor 0.14 cum. 2382.31 cum. 333.52
Stone at quarry 1.65 cum. 220.00 cum. 363.00

Total:- 696.52

2 Carriage
0.00 Km by machenical transport 1.65 cum. 0 cum. 0.00
1 Km. by head load 1.65 cum. 831.81 cum. 1372.49
Total:- 1372.49

3 Labour

Mason 1st class 0.41 Nos. 311.50 each 127.72


Bhisti 0.16 Nos. 262.50 each 42.00
Beldar 0.66 Nos. 262.50 each 173.25
Sundaries L.S. each 10.00
Total:- 352.97

Total:-1+2+3 2421.97

Add 1.5% water charges. 35.50


Total:- 2457.48
Add 10% C.P and 5% over head charges.
318.59
2776.07
Cost Per Mt. 277.61

Executive E Executive Engineer,


IPH Divn. N IPHDivision No.II
Distt. Sirmo Kullu at Bhunter
Providing and fixing 75 mm x 60 mm rounded hand rails in straight length complete in 1st class Deodar wood

Details of cost for 3.05 mt run

Materials
1st class Deodar wood. 0.015 Cum 45000 675

Carriage of Timber 0

1 KM By Mech Transport. 0.015 Cum 193.71 2.91

0.1 Mt. by Head Load 0.015 Cum 0.00 0

LABOUR 0

Carpenter 1st class 0.75 Nos 311.5 233.63

Beldar 0.19 Nos 262.5 49.88

Sundries 20
Total 981.42
Add 10% CP 0.15 147.21
& 5 for
Cost % OH3.05 1128.63
Charges
cum
Cost per CUM 3.05 370.04

Say Rs. 370


q
CARRIAGE OF MATERIALS
Providing
A CEMENT & STEEL: Unit : Per Tonne.
LEAD : By Mech. 0 Km.
By Head : 0.1 Km.
1 By Mech. Rate/ Km.
0.00
5 Km. 0 64.64 0.00
5- 10 Km. 0 5.04 0.00
10-20 Km 0 4.16 0.00
Beyond 2 0 3.47 0.00
TOTAL : 0.00

2 By Head load
1st. 1 Km 0 120.89 0.00
1st. 100 0 19.21 0.00
Beyond 1 0 60.45 0.00
Beyond 10 0 5.65 0.00
Total : 0.00

G.Total: 1+2= 0.00 Per Tonne.


Analysis of rates
Removal of slips.
Detail of cost for 2.20 cu.m

Sr.No Description of Items Qty. Rate Unit Amount

1 Labour:- Beldar 1 No 262.5 each 262.5

Add 25% extra 65.63

Total:- 328.125
Add 15& CP & OH charges. 49.22
Cost for 2.20 cum Rs:- 377.34

Cost for One cum Rs. 171.52

Executive Engineer,
IPHDivision No.II
Kullu at Bhunter
Analysis of rate
Hirmachi colour wash on undecorated wall surface (Two coats)

Detail of cost for 10sqmt.


S.No. Description of items Quantity Rate Unit Amount

MATERIAL :
Lime unslaked 0.02 800.00 Qtl. 16.00
Hirmachi 0.25 35 Kg 8.75
Indigo Gum LS. 5.00
Carriage : LS. 2.00
Labour :
White Washer 0.13 262.5 Each 34.13
Beldar 0.03 262.5 Each 7.88
Sundries (Brushes etc. LS. 15
Total:- 88.76
Add. 1.5% Water chages 1.33
Total:- 90.09
Add 10% C.P. & 5% for overhead charges : 13.51
Cost of 10 . Sqmt. 103.60
Cost of 1 Sqmt. 10.36

Executive Engineer,
IPHDivision No.II
Kullu at Bhunter
Analysis of rates
Supplying and fixing galvanised steel barbed wire (IS: 278-1962 Type-I) weighing 9.38 kg per 100 mtrs
(minumem) straining and fixing to any type of standard rails,straining bolts i/c securing with and
provision of galvanised mild steel wire , staples or steel pinsetc., as directed ( Posts and struts of wood
concrete steel etc and straining bolts shall be paid separately)
Detail of cost per 100 mtrs (Each line of wire)

Sr.No Description of Items Qty. Rate Unit Amount

Material;-
Galvanised steel barbed wire (IS:278-1962 type-I)
9.38 kg per 100 mtrs (min) =9.38 kg or 0.0938 qtl
or 0.0094 tonne 0.0938 qtl 3000 qtl 281.40
GI staples steel pins etc. LS 2.00
283.40
Carriage
25.00 Km by mech. Tpt. 0.009 Tonne 382.17 Tonne 3.43953
0.0 km by head load 0.009 Tonne 0.00 Tonne 0
3.43953
Labour
Labour for fixing and stretching wire.
Black smith 1st class 0.18 Nos 311.5 Each 56.07
Black smith 2nd class 0.18 Nos 311.5 Each 56.07
Beldar 0.36 Nos 262.5 Each 94.50
Sundries LS 5.00
211.64
G Total 498.48
Add 1.5% for water charges 7.48
505.96
Add 15% for CP & OH charges. 75.89
Cost for 100 mtr each line of wire. Rs. 581.85

Cost for 1 Mtr each line of wire. Rs. 5.82


Say Rs. 6.00 only

Executive Engineer,
IPHDivision No.II
Kullu at Bhunter
Analysis of rates
Dismentalling roofing including ridges hips valley gutters etc., stacking the serviceable materials and
disposal of unserviceable materials .

Sr.No Description of Items Qty. Rate Unit Amount

GI Sheet roofing.
Detail of cost for 10 sqm.

Labour

Carpenter 2nd class 0.60 No. 311.5 Each 186.90


Beldar. 1.50 Nos. 262.5 Each 393.75
Sundries LS 8.00

Total:- 588.65
Add 1.5% for water charges. 8.83
597.48
Add 15% CP &OH charges. 89.62
Cost for 10 sqm 687.10

Cost for one sqm Rs. 68.71

Say Rs. 68.7

Executive Engineer,
IPH Divn. Nohradhar.
Executive Engineer,
IPHDivision No.II
Kullu at Bhunter
Analysis of rates
Dismentalling doors windows and clerestory windows vantilators etc., (wood or steel0 shutters i?c
chowkhats architraves hold fast and other attachements etc. complete and stacking tem.

Sr.No Description of Items Qty. Rate Unit Amount

Not exceeding 3 sqm in area.

Detail of cost for Each


Labour

Mason 2nd class 0.12 311.5 Each 37.38


Beldar 0.24 262.5 Each 63.00
Blacksmith 2nd class. 0.06 311.5 Each 18.69
Sundries. LS 2.00
Total:- 121.07
Add 1.5% for water charges. 1.82
122.89
Add 15% CP &OH charges. 18.43
Cost for Each 141.32

Say Rs. 141.3

Executive Engineer,
IPHDivision No.II
Kullu at Bhunter
Analysis of rates
Dismentalling cement asbestos celotax/ hard board in ceiling or partitions walls i/c stacking of the
serviceable materials and disposal of unserviceable materials.(Frame work such as joists beams to be
measured and paid for separately)

Sr.No Description of Items Qty. Rate Unit Amount

Detail of cost for 10 sqm.


Labour

Carpenter 2nd class 0.22 311.5 Each 68.53


Beldar 0.86 262.5 Each 225.75
Sundries. LS Each 5.00

Total:- 299.28
Add 1.5% for water charges. 4.49
303.77
Add 15% CP &OH charges. 45.57
Cost for 10 sqm 349.33

Cost for one sqm Rs. 34.93

Say Rs. 34.9

Executive Engineer,
IPHDivision No.II
Kullu at Bhunter
Extra for every subsequent coat of distempering with oil bound washable distemper of approved
brand and manufacture.

Detail of cost for 10 Sqm.


Material Qty, Rate Unit Amount

Distemper 1.00 40.00 Kg 40.00

Brushes,sand paper putty etc LS 3.00

Carriage
Carriage of material LS 1.00

Labour.
Painter 1st class 0.27 311.5 Each 84.11
Beldar 0.14 262.5 Each 36.75
Sundried sacffolding LS 2.00
etc.
166.86
Add 1.5% for water charges 2.50
169.36
Add 15% for CP & OH charges except 168.36 25.25
carriage. Cost for 10sqmRs. 194.61

Cost for onr sqm 19.46

Executive Engineer,
IPHDivision No.II
Kullu at Bhunter
Analysis of rates
Dismentalling wood work wrought framed and fixed in frames other frames and trusses of span up to 10
mtrs., and height between ridge and floor level up to 5 mtrs. i/c stacking the serviceable material and
disposal of unserviceable material.
Sectional area average 40 sqm or over.
Detail of cost for 1 cum
Sr.No Description of Items Qty. Rate Unit Amount

Labour

Carpenter 2nd class 1.4 311.5 Each 436.10


Beldar 2.56 262.5 Each 672.00
Sundries. LS Each 15.00

Total:- 1123.10
Add 1.5% for water charges. 16.85
1139.95
Add 15% CP &OH charges. 170.99
Cost for 1cum 1310.94

Say Rs. 1310.9


Laying in trenches G.M.S tubes and tube fittings (Earth work in trenches to be measured and paid
seperataly).
Unit : 10 Rmtr.
S.No. Desciption Unit Quantity Rate Amount
1 15 mm (L)
Labour :
Plumber( Fitter) Each 0.10 311.50 31.15
Beldar Each 0.19 262.5 49.88
Total : 81.03

Carriage
25.00 Km.By mechanical transport Ton 0.01 382.17 3.82
0 Km.By head load Ton 0.01 0.00 0.00
Total 3.82

84.85

Add 10% C.P.& 5%O.H.charges : 12.73


Cost of 10 Rmtr. = Total : 97.57
Cost of 1 Rmtr. = 9.76
Say Rs. 9.8

20 mm nominal
Labour :
Plumber( Fitter) Each 0.10 311.50 31.15
Beldar Each 0.19 262.5 49.88
Carriage Total : 81.03
25.00 Km.By mechanical transport Ton 0.02 382.17 7.64
0.00 Km.By head load Ton 0.02 0.00 0.00
7.64
88.67

Add 10% C.P.& 5%O.H.charges : 13.30


Cost of 10 Rmtr. = Total : 101.97
Cost of 1 Rmtr. = 10.20
Say Rs. 10.2

2 25 mm nominal
Labour :
Plumber( Fitter) Each 0.14 311.50 43.61
Beldar Each 0.3 262.5 78.75
Total : 122.36
Carriage
25.00 Km.By mechanical transport Ton 0.0217 382.17 8.29
0.00 Km.By head load Ton 0.0217 0.00 0.00
8.29

130.65
Add 10% C.P.& 5%O.H.charges : 19.60
Cost of 10 Rmtr. = Total : 150.25
Cost of 1 Rmtr. = 15.03
Say Rs. 15.0

Executive Engineer,
IPHDivision No.II
Kullu at Bhunter
32 mm nominal
Labour :
Plumber( Fitter) Each 0.14 311.50 43.61
Beldar Each 0.3 262.5 78.75
Total : 122.36
Carriage
25.00 Km.By mechanical transport Ton 0.03 382.17 11.47
0.00 Km.By head load Ton 0.03 0.00 0.00
11.47

133.83
Add 10% C.P.& 5%O.H.charges : 20.07
Cost of 10 Rmtr. = Total : 153.90
Cost of 1 Rmtr. = 15.39
Say Rs. 15.4

3 40 mm nominal
Labour :
Plumber( Fitter) Each 0.19 311.50 59.19
Beldar Each 0.4 262.5 105.00
Total 164.19
Carriage
25.00 Km.By mechanical transport Ton 0.04 382.17 15.29
0.00 Km.By head load Ton 0.04 0.00 0.00
15.29

Total : 179.47
Add 10% C.P.& 5%O.H.charges : 26.92
Cost of 10 Rmtr. = Total : 206.39
Cost of 1 Rmtr. = 20.64
Say Rs. 20.6

50 mm nominal
Labour :
Plumber( Fitter) Each 0.19 311.50 59.19
Beldar Each 0.4 262.50 105.00
Total : 164.19
Carriage
25.00 Km.By mechanical transport Ton 0.0447 382.17 17.08
0.00 Km.By head load Ton 0.0447 0.00 0.00
17.08

181.27
Add 10% C.P.& 5%O.H.charges : 27.19
Cost of 10 Rmtr. = Total : 208.46
Cost of 1 Rmtr. = 20.85
Say Rs. 20.8
Executive Engineer,
IPHDivision No.II
Kullu at Bhunter
4 65 mm nominal
Labour :
Plumber( Fitter) Each 0.30 311.50 93.45
Beldar Each 0.79 262.5 207.38
Total : 300.83
Carriage
25.00 Km.By mechanical transport Ton 0.06 382.17 22.93
0.00 Km.By head load Ton 0.06 0.00 0.00
22.93

323.76
Add 10% C.P.& 5%O.H.charges : 48.56
Cost of 10 Rmtr. = Total : 372.32
Cost of 1 Rmtr. = 37.23
Say Rs. 37.2
Cost of GI Pipe Mtr 0.0

80 mm nominal
Labour :
Plumber( Fitter) Each 0.30 311.50 93.45
Beldar Each 0.79 262.5 207.38
Total : 300.83
Carriage
25.00 Km.By mechanical transport Ton 0.07 382.17 26.75
0.00 Km.By head load Ton 0.07 0.00 0.00
26.75

327.58
Add 10% C.P.& 5%O.H.charges : 49.14
Cost of 10 Rmtr. = Total : 376.71
Cost of 1 Rmtr. = 37.67
Say Rs. 37.7

5 100mm
Labour :
Plumber( Fitter) Each 0.40 311.50 124.60
Beldar Each 1.19 262.5 312.38
Total : 436.98
Carriage
25.00 Km.By mechanical transport Ton 0.102 382.17 38.98
0.00 Km.By head load Ton 0.102 0.00 0.00
38.98

475.96
Add 10% C.P.& 5%O.H.charges : 71.39
Cost of 10 Rmtr. = Total : 547.35
Cost of 1 Rmtr. = 54.73
Say Rs. 54.7

Executive Engineer,
IPHDivision No.II
Kullu at Bhunter
A Heavy material and pipe
below 100mm. Unit : Per Tonne.
LEAD : By Mech. 25 Km.
By Head : 0 Km.
1 By Mech. Nos. Rate/ Km.
1 Km. 0 98.28 0.00
2 Km. 0 113.79 0.00
3 Km. 0 129.14 0.00
4 Km. 0 144.07 0.00
5 Km. 1 158.32 158.32
5- 10 Km. 5 13.21 66.05
10-20 Km. 10 11.09 110.90
Beyond 20 Km. 5 9.38 46.90
TOTAL : 382.17
2 By Head load
1st. 1 Km. 0 561.75 0.00
1st. 100 Mtr 0 89.25 0.00
Bey:1 Km.Per 1/2Km. 0 280.88 0.00
Bey:100 Mtr Per 50 Mtr 0 26.25 0.00
Total : 0.00
1+2= 382.17 Per Tonne.

Executive Engineer,
IPHDivision No.II
Kullu at Bhunter
Rate of Materials
Name of work :
S.No. Description of items unit Rate
1 Cement Tonne 4500 Issue rate
2 Sand Cum 375 Rate at quarry
3 M.S.Flate. Qtl. 4500 M.Rate.
4 Crushed stone Agg.40mm Cum. 440 Rate at crusher
5 --- do------- 20 mm Cum. 465 Rate at crusher
6 -----do------10mm Cum. 475 Rate at crusher
7 Boulder/ plums Cum. 300 At Quarry
8 Building stones Cum. 350 At Quarry
9 Through and bond stone Each 7 At Quarry
10 Bricks Per 1000 7000 At Killan
11 Tor Steel Qtl. 4600 Issue rate
12 R.S. joist Qtl. 4200 M.Rate.
13 M.S. Plates Qtl. 4500 M.Rate.
14 Welding by electric plant Per cm. 2 M.Rate.
15 Barbed wire: Qtl. 2200 M.Rate.
16 Angle iron Qtl. 4500 M.Rate.
2nd class deodar wood:(Scantling) Cum. 50000 M.Rate
2nd class deodar wood :(Planks) Cum. 55000 M.Rate
17 2nd Class Kail wood Scantling Cum. 31240 M.Rate.
18 Ballies,125mm dia Metre 110 M.Rate.
19 Planks (2nd class kail wood) Cum. 29728 M.Rate.
20 C.I. Man hole cover & frame Kg. 30 M.Rate.
21 Drilling equipment Day 2054.69 HPSR-99
22 Special gelatine(80%) Kg. 57 HPSR-99
23 Detonators(ordinary) 100 Nos. 350 HPSR-99
24 Safety fuse wire(coil 10m length) Coil 18 HPSR-99
25 C.I. Rungs Each 30 M.rate
26 RCC Spun vent shaft Each 5500 M.rate
27 Caulking lead : Kg. 65 M.rate
28 Fuel wood : Qtl. 250 M.rate
29 Spun yarn Kg. 25 M.rate.
30 Red Lead oxide Kg. 105 M.rate.
Without With P.H.
Rates of Labour. P.Hol.
1 Beldar Each 225 262.5
2 Bhisti Each 225 262.5
3 Mason Ist class Each 267 311.5
4 Mason II nd class Each 267 311.5
5 Mate Each 225 262.5
6 Black Smith Ist class Each 267 311.5 Approved rate.
7 Carpenter 2 nd class Each 267 311.5
8 Plumber (Fitter) Each 267 311.5
9 Hole Driller Each 225 262.5
10 Blaster Each 225 262.5
11 Stone dresser Each 225 262.5
12 Painter 1st class Each 225 262.5
13 Painter 2nd class Each 240.00 280
14 Stone Chisseler Each 267 311.5
Certified that the rate of material are lowest prevailing
market/issue rates and the rates of labour are approved one.

Executive Engineer,
IPHDivision No.II
Kullu at Bhunter
ANALYSIS OF RATE
Providing & laying cement concrete 1:4:8 (1 cement : 4 Sand 8 graded stone aggregate
40 mm nominal size ) and curing complete excluding cost of centring & shuttering in
foundation & plinth.
DETAIL OF COST FOR 1.00 CUM.
S.No. Desciption Unit Quantity Rate Amount
1 2 3 4 5 6
MATERIALS
1 Stone aggregate 40mm Cum 0.65 440 286.00
2 Stone aggregate 20mm Cum 0.24 465 111.60
3 Sand Cum 0.47 375 176.25
4 Cement Tonne 0.17 4500 765.00
1338.85
CARRIAGE
1 Carriage of aggrergate 40mm
0.00 Km.By mechanical transport Cum 0.65 0.00 0.00
0.5 Km.By head load Cum 0.65 443.11 288.02
2 Stone aggregate 20mm
7.00 Km.By mechanical transport Cum 0.24 277.09 66.50
0 Km.By head load Cum 0.24 0.00 0.00
3 Sand
7.00 Km.By mechanical transport Cum 0.47 277.09 130.23
0 Km.By head load Cum 0.47 0.00 0.00
4 Cement
25.00 Km.By mechanical transport Tonne 0.17 382.17 64.97
0 Km.By head load Tonne 0.17 0.00 0.00
549.72
LABOUR
1 Beldar Each 2.09 262.5 548.63
2 Bhisti Each 0.27 262.5 70.88
3 Mason Ist. Class Each 0.05 311.5 15.58
4 Mason 2nd. Class Each 0.05 311.5 15.58
5 Mate Each 0.04 262.5 10.50
6 Beldar for extra ramming. Each 0.25 262.5 65.63
Sundries. L.S. 15.00
741.78

Total:- 2630.35
Add for water charges @1.5% 39.46
Total:- 2669.80
Add 10% contractor profit & 5% over head charges on 285.72
all except cement .
G.Total:- 2955.53
Cost per Cum Rs. 2955.5

Executive Engineer,
IPHDivision No.II
Kullu at Bhunter
ANALYSIS OF RATE

Providing & laying cement concrete 1:1½:3 (1 cement : 1½ Sand 3 graded stone aggregate
20 mm nominal size ) and curing complete excluding cost of centring & shuttering in
foundation & plinth.
DETAIL OF COST FOR 1.00 CUM.
S.No. Desciption Unit Quantity Rate Amount

MATERIALS
1 Stone aggregate 10mm Cum 0.28 475 133.00
2 Stone aggregate 20mm Cum 0.57 465 265.05
3 Sand Cum 0.425 375 159.38
4 Cement Tonne 0.4 4500 1800.00
2357.43
CARRIAGE
1 Carriage of aggrergate 10mm
7.00 Km.By mechanical transport Cum 0.28 277.09 77.59
0 Km.By head load Cum 0.28 0.00 0.00
2 Stone aggregate 20mm
7.00 Km.By mechanical transport Cum 0.57 277.09 157.94
0 Km.By head load Cum 0.57 0.00 0.00
3 Sand
7.00 Km.By mechanical transport Cum 0.425 277.09 117.76
0 Km.By head load Cum 0.425 0.00 0.00
4 Cement
25.00 Km.By mechanical transport Tonne 0.4 382.17 152.87
0 Km.By head load Tonne 0.4 0.00 0.00
506.16
LABOUR
1 Beldar Each 2.09 262.5 548.63
2 Bhisti Each 0.27 262.5 70.88
3 Mason Ist. Class Each 0.05 311.5 15.58
4 Mason 2nd. Class Each 0.05 311.5 15.58
5 Mate Each 0.04 262.5 10.50
6 Beldar for extra ramming. Each 0.25 262.5 65.63
Sundries. L.S. 15.00
741.80

- Total:- 3605.39
Add for water charges @1.5% 54.08
Total:- 3659.47
Add 10% contractor profit & 5% over head charges on 278.92
all except cement .
G.Total:- 3938.39
Cost per Cum Rs. 3938.4

Executive Engineer,
IPHDivision No.II
Kullu at Bhunter
ANALYSIS OF RATE

Providing & laying cement concrete 1:1½:3 (1 cement : 1½ Sand 3 graded stone aggregate
20 mm nominal size ) and curing complete excluding cost of centring & shuttering in
walls including attached buttresses, pilasters & their caps & base string courses etc.
up to floor two level. DETAIL OF COST FOR 1.00 CUM.
S.No. Desciption Unit Quantity Rate Amount

MATERIALS
1 Stone aggregate 10mm Cum 0.28 475 133.00
2 Stone aggregate 20mm Cum 0.57 465 265.05
3 Sand Cum 0.425 375 159.38
4 Cement Tonne 0.4 4500 1800.00
2357.43
CARRIAGE
1 Carriage of aggrergate 10mm
7.00 Km.By mechanical transport Cum 0.28 277.09 77.59
0 Km.By head load Cum 0.28 0.00 0.00
2 Stone aggregate 20mm
7.00 Km.By mechanical transport Cum 0.57 277.09 157.94
0 Km.By head load Cum 0.57 0.00 0.00
3 Sand
7.00 Km.By mechanical transport Cum 0.425 277.09 117.76
0 Km.By head load Cum 0.425 0.00 0.00
4 Cement
25.00 Km.By mechanical transport Tonne 0.4 382.17 152.87
0 Km.By head load Tonne 0.4 0.00 0.00
506.16
LABOUR
1 Beldar Each 2.09 262.5 548.63
2 Bhisti Each 0.28 262.5 73.50
3 Mason Ist. Class Each 0.06 311.5 18.69
4 Mason 2nd. Class Each 0.06 311.5 18.69
5 Mate Each 0.04 262.5 10.50
6 Beldar for extra ramming. Each 0.25 262.5 65.63
Scaffolding L.S. 25.00
Sundries. L.S. 15.00
775.63

Total:- 3639.21
Add for water charges @1.5% 54.59
Total:- 3693.80
Add 10% contractor profit & 5% over head charges on 284.07
all except cement .
G.Total:- 3977.87
Cost per Cum Rs. 3977.9

Executive Engineer,
IPHDivision No.II
Kullu at Bhunter
ANALYSIS OF RATE

Providing & laying cement concrete 1:1½:3 (1 cement : 1½ Sand 3 graded stone aggregate
20 mm nominal size ) and curing complete excluding cost of form work & reinforcement for RCC
work in : walls (any thickness but not less than 0.10m thickness),attached pilasters , buttresses,
plinth & string courses etc.from top of foundation level up to floor two level :

Detail of cost for a counterfort R.wall,4.5 m height & 6 mtrs. Long: = 9.18 cum.

S.No. Desciption Unit Quantity Rate Amount


1 C.C 1:1.5:3(Detail& rate as per
sub analysis of C.C 1:1.5:3,
in walls) cum. 9.18 3977.9 36516.86

2 Labour( Extra for laying C.C in


RCC work)Detail of cost for 1cum.
(a) Beldar Each 0.10 262.5 26.25
(b) Bhisti Each 0.20 262.5 52.50
© Mason Ist. Class Each 0.04 311.5 12.46
(d) Mason 2nd. Class Each 0.04 311.5 12.46
(e) Mate Each 0.04 262.5 10.50
Total : 114.17
Cost of 9.18 cum. 1048.08
Total 1+2= 37564.94
Add 1.5% water charges on 2: 15.72
37580.66
Add 10%contractor profit and
5% O.H charges except 1: 159.57
Cost for 9.180 cum. = 37740.23
Cost of 1 cum. = 4111.14
Say Rs. 4111.14

Executive Engineer,
IPHDivision No.II
Kullu at Bhunter
ANALYSIS OF RATE

Providing mild steel / tor steel reinforcement for RCC work including bending , binding
and placing in position complete up to floor two level :

DETAIL OF COST FOR 1.00 Quintal


S.No. Desciption Unit Quantity Rate Amount
1 Materials
Tor steel including 5 %
wastage : Qtl. 1.05 4600.00 4830.00

2 Carriage :
25.00 Km.By mechanical transport Tonne 0.105 382.17 40.13
0 Km.By head load Tonne 0.105 0.00 0.00

3 Labour :
Black Smith Ist class Each 1.00 311.5 311.50
Beldar Each 1.00 262.5 262.50
Sundries : L.S. 45.00
Total : 5489.13
Add 1.5% water charges : 82.34
5571.46
Add 10% contractor profit &
5 % o.head charges except 1. 111.22
TOTAL : 5682.68
Cost of 1 Kg. = 56.83
Say Rs. 56.8

Labour rate :( including carriage) 659.13


Add 1.5% Water charses on all : 82.34
Add 10% C.P. & 5% O.H. charges : 111.22
Cost of 100 Kg. : 852.68
Cost of 1 Kg. 8.53

Executive Engineer,
IPHDivision No.II
Kullu at Bhunter
Analysis of Rate
Providing and fixing 1mm thick MS sheet sliding shutters with frame and diagonal braces of 40x40x 6mm
angle iron 3.15mm MS gusset plates at junction and corners 25mm dia pulley 40x40x6mm angle and T.iron
guide at the top and bottonm respectively , including applying a priming coat of red lead paint.
Detail of cost for one double leaf door , size 2.4mx2.4m= 5.76 Sqm.
Description Unit Quantity Rate Amount
Material :
MS sheet 1mm thick 5.76 Sqm @
7.8Kg./Sqm= 45.216 Kg.
Wastage @ 10%= 4.522 Kg. Quintal 0.497 Qtl. 4500 2236.5
Total : 49.738 Kg.or 0.497 Qtl.

Gusset plate 3.15mm Quintal 0.16 Qtl. 4500 720

Anglre iron 40x40x6mm Quintal 1.39 Qtl. 4500 6255

Channel 25x25x6mm Quintal 0.11 Qtl. 4500 495

Pulley 25mm dia Each 8 Nos. 25 200

Applying priming coat of red lead Sqm 18 Sqm 28.79 518.22


paint to MS sheet :

Pulley guide block drilling hole LS 125

Handle & locking arrangement LS 75

Bolts and rivets LS 120

Cement concrete. LS 7

Carriage of steel :
25.00 Km.By mechanical transport Tonne 0.2158 Tonne 382.17 82.47
0 Km.By head load Tonne 0.2158 Tonne 0.00 0
LABOUR :
Fitter Each 2.4 No. 311.5 747.6
Black smith Ist class Each 3.6 No. 311.5 1121.4
Black smith 2nd class Each 4.8 No. 311.5 1495.2
Beldar Each 4.8 No. 262.5 1260
Mason Ist Class Each 0.07 No. 311.5 21.81
Mason IInd class Each 0.07 No. 311.5 21.81
Sundries : LS 40
Total : 15542.01
Add 1.5% water charges except priming coat : 225.36
15767.37
Add 10% conttractor profit & 5% O.H. Charges except priming coat : 2287.37
Cost for 5.760 Sqm. 18054.74

Cost for 1 Sqm. 3134.5

Say Rs. 3135

Executive Engineer,
IPHDivision No.II
Kullu at Bhunter
Analysis of Rate
P/F angle iron door, window,clerestory window frame manufactured from steel iron section of 40x40x6mm,
thickness including hinges jamb, lock jamb,beed and if rerquired angle threshold of mild steel angle 50x25mm
welded or rigidly fixed by mechanical means, lugs with split end tails to each jamb including butt hinges 2.50mm
thick with provision for locking arrangement and shock as specified and applying a coat of approved steel
primer after pretreatment of the surface as directed by the Engineer-in-charge.
Detail of cost for 5 mtrs.
S.No. Description Unit Quantity Rate Amount
MATERIAL:
1 Size of frame : 2+2+1= 5mtrs.
Wt. Of angle iron =5x3.5=17.50Kg.
Wastage 5%= = 0.88 Kg.
Total : 18.38 Kg.
Wt. Per m= 18.38/5= 3.68 Kg.
Hinges : ( 107.5x6)/5= 0.128 Kg./m
Shock absorber= 0.02 Kg./m
Lugs(tail) 0.077Kg./m
Total wt. = 3.883Kg./m
For 5 m= 5x3.887= 19.345Kg. Qtl. 0.1944 Qtl. 4500 874.8

Welding charges by Elect. Plant Cm. 16 Cm. 2.00 32

2 Carriage charges : L.S. 5

3 Labour :
Fitter Each 0.15 No. 311.5 46.73
Beldar Each 0.2 No. 262.5 52.5
Sundries : L.S.
1011.03
Add 10% for contractor profit & 151.65
5% for over head charges : Cost of 5 mtrs. : 1162.68
Cost of 1 Mtr.= 232.536

Say : Rs 233 /- only.

Executive Engineer,
IPHDivision No.II
Kullu at Bhunter
Analysis of Rate
P/F in position collapsible steel shutters with vertical channels 20x10x2mm and braced with flat iron diagonals
20x5mm size with top and bottom rails of T-iron 40x40x6mm with 38mm dia steel pulley complete with bolts &
nuts, locking arrangements, stoppers,handles, including applying a priming coat of red lead paint.
Detail of cost for a gate 2.4mx1.5m= 3.6Sqm
Description Unit Quantity Rate Amount
Material :
MS channels 18 No. on both sides
20x10x2mm@ 0.56Kg./m=
2x18x2.4= 86.40m Quintal 0.53 Qtl. 4200 2226
Wastage @ 10%= 8.64
95.04m @ .56= 53.22 Kg. Or 0.53 Qtl.

MS Tee 40x40x6mm Quintal 0.13 Qtl. 4500 585

20x 5mm flat iron diagonal Quintal 0.6 Qtl. 1900 1140

Applying priming coat of red lead Sqm 10.5 Sqm 28.79 302.3
paint to MS sheet :

Pulley 38mm dia Each 10 Nos. 22 220

Handle & locking arrangement LS 30

Rivets, hooks, washers LS 120

Carriage of steel :
25.00 Km.By mechanical transport Tonne 0.126 Tonne 382.17 48.15
0 Km.By head load Tonne 0.126 Tonne 0.00 0
LABOUR :
Fitter Each 3.6 No. 311.5 1121.4
Black smith Ist class Each 7.2 No. 311.5 2242.8
Black smith 2nd class Each 7.2 No. 311.5 2242.8
Beldar Each 9.6 No. 262.5 2520
Mason Ist Class Each 0.6 No. 311.5 186.9
Mason IInd class Each 0.6 No. 311.5 186.9
Sundries : LS 75
Total : 13247.25
Add 1.5% water charges except priming coat : 194.17
13441.42
Add 10% conttractor profit & 5% O.H. Charges except priming coat : 1970.87
Cost for 3.60 Sqm. 15412.29

Cost for 1 Sqm. 4281.19

Say Rs. 4281

Executive Engineer,
IPHDivision No.II
Kullu at Bhunter
ANALYSIS OF RATE
Prov. Form work with steel plates 3.15mm thick welded with angle iron in frame 30x30x5mm so as
to give a fair finish including centring , shuttering, strutting & propping etc. with wooden battens &
ballies , height of propping & centring below supporting floor to ceiling not exceeding 4 mtrs.&
removal of the same for insitu reinforced concrete & plain concrete work in :
Sub analysis for man. Steel plates for shuttering steel work welded in builtup section I/c cutting &
fixing in position in angles, plates etc. complete.
DETAIL OF COST FOR 0.54 Sqm.
S.No. Desciption Unit Quantity Rate Amount
Material
3.15mm th. M.S.plate=
0.9x0.6m=0.54sqm @24.72kg.
per Sqm.= 13.35 Kg.
Add 5 % wastage : 0.66 Kg.
Total : 14.01 Kg. Qtl. 0.14 4500.00 630.00

Angle iron in frames 30x30x5mm


2(0.9+0.6m)= 3.00 Rmtr. @ Qtl. 0.0693 4500.00 311.85
2.20 Kg./ Rmtr. =6.60kg
wastage @ 5% = 0.33
Total : = 6.93kg.
or 0.0693 Qtl.
CARRIAGE :
Carriage of MS plate& angles:
25.00 Km.By mechanical transport Tonne 0.02 382.17 7.64
0 Km.By head load Tonne 0.02 0.00 0.00

Labour :
Black Smith Ist class Each 0.066 311.5 20.56
Bandhani Each 0.066 262.5 17.33
Beldar Each 0.154 262.5 40.43
Sundries L.S 50.00
Welding charges by E.plant Cm. 300 2 600.00
Total : 1677.80
Add 1.5% water charges : 25.17
Total : 1702.97
Less credit for scrape value
after full use of plate when
become unserviceable. 10%
as reserve price : (-) 94.19
Cost for 0.54 Sqm. = 1608.78
Cost for 1 Sqm. = 2979.23
Say Rs. 2979.2

Executive Engineer,
IPHDivision No.II
Kullu at Bhunter
ANALYSIS OF RATE
Prov. Form work with steel plates 3.15mm thick welded with angle iron in frame 30x30x5mm so as
to give a fair finish including centring , shuttering, strutting & propping etc. with wooden battens &
ballies , height of propping & centring below supporting floor to ceiling not exceeding 4 mtrs.&
removal of the same for insitu reinforced concrete & plain concrete work in :
Flat surfaces such as soffits of suspended floors , roofs , landings & the like .
Floors etc. up to 200 mm in thickness :
Detail of cost for a room 3x3m=9 Sqm & height 3.50m

S.No. Desciption Unit Quantity Rate Amount


1 MATERIAL :
Steel plates fixed with angle Sqm 9.00 2979.23 26813.07
Soft wood centring
2nd class kail wood Cum 0.0709 31240 2214.92
Ballies, 125mm dia. Metre 54.2 110 5962.00
2 Carriage of timber.
3.00 Km.By mechanical transport Cum. 0.735 193.71 142.38
0 Km.By head load Cum. 0.735 0.00 0.00
Total: 35132.37
Assuming that steel plates will
become unserviceable after being used 100 times.
Hence cost for using once : Each 1/100 26813.07 268.13

Add 1 % for using repeatedly I/c repairs, removal


of dents, cleaning conc. Deposits & applying oil
and grease : 268.13

Assuming that timber shall become unserviceable


after being used 16 times . Hence cost for using
once : Each 1/16 8319.29 519.96
Add 5 % wastage for using
repeatedly : 415.96
Total : 1472.18
3 Labour :
For assembling erection &
dismentalling :
Carpenter II nd class : Each 1.01 311.5 314.62
Beldar Each 2.52 262.5 661.50
Sundries taking 10%of labour 97.61
Total : 2545.91
Add 10 % C.P & 5 % O.H
charges except 1/16 of carriage: 380.55
Cost of 9 Sqm. = 2926.46
Cost of 1 Sqm. = 325.16
Say Rs. = 325.2

Executive Engineer,
IPHDivision No.II
Kullu at Bhunter
ANALYSIS OF RATE
Prov. Form work with steel plates 3.15mm thick welded with angle iron in frame 30x30x5mm so as
to give a fair finish including centring , shuttering, strutting & propping etc. with wooden battens &
ballies , height of propping & centring below supporting floor to ceiling not exceeding 4 mtrs.&
removal of the same for insitu reinforced concrete & plain concrete work in :
Vertical surfaces such as walls (any thickness) partitions & the like I/c attached pillasters,
buttresses plinth and string courses and the like :
Detail of cost for a parapet wall 15mtrs. Long & 1.00 m height , for surface area 2x15x1=30 Sqm.

S.No. Desciption Unit Quantity Rate Amount


1 MATERIAL :
Steel plates fixed with angle Sqm 30.00 2979.2 89376.91
Soft wood centring
2nd class kail wood Cum 0.102 31240 3186.48
Ballies, 125mm dia. Metre 63 110 6930.00
2 Carriage of timber.
3.00 Km.By mechanical transport Cum. 0.875 193.71 169.50
0 Km.By head load Cum. 0.875 0.00 0.00
Total: 99662.89
Assuming that steel plates will
become unserviceable after being used 100 times.
Hence cost for using once : Each 1/100 89376.91 893.77

Add 1 % for using repeatedly I/c repairs, removal


of dents, cleaning conc. Deposits & applying oil
and grease : 893.77

Assuming that timber shall become unserviceable


after being used 16 times . Hence cost for using
once : Each 1/16 10285.98 642.87
Add 5 % wastage for using
repeatedly : 514.30
Total : 2944.71
3 Labour :
For assembling erection &
dismentalling :
Carpenter II nd class : Each 3.00 311.5 934.50
Beldar Each 6.00 262.5 1575.00
Sundries taking 10%of labour 250.95
Total : 5705.16
Add 10 % C.P & 5 % O.H
charges except 1/16 of carriage: 854.19
Cost of 30 Sqm. = 6559.35
Cost of 1 Sqm. = 218.64
Say Rs. = 218.6

Executive Engineer,
IPHDivision No.II
Kullu at Bhunter
ANALYSIS OF RATE
Prov. Form work with steel plates 3.15mm thick welded with angle iron in frame 30x30x5mm so as
to give a fair finish including centring , shuttering, strutting & propping etc. with wooden battens &
ballies , height of propping & centring below supporting floor to ceiling not exceeding 4 mtrs.&
removal of the same for insitu reinforced concrete & plain concrete work in :
Sloping or battering surfaces including folded plates : Where inclination to horizontal plane does not exceed 30%
Detail of cost for a room 3.0x3.0m, the slab having an inclination of 15% superficial area of slab = 3.0x3.11=9.33
Sqm.

S.No. Desciption Unit Quantity Rate Amount


1 MATERIAL :
Steel plates fixed with angle Sqm 9.33 2979.2 27796.22
Soft wood centring
2nd class kail wood Cum 0.097 31240 3030.28
Ballies, 125mm dia. Metre 60.5 110 6655.00
2 Carriage of timber.
3.00 Km.By mechanical transport Cum. 0.842 193.71 163.10
0 Km.By head load Cum. 0.842 0.00 0.00
Total: 37644.60
Assuming that steel plates will
become unserviceable after being used 100 times.
Hence cost for using once : Each 1/100 27796.22 277.96

Add 1 % for using repeatedly I/c repairs, removal


of dents, cleaning conc. Deposits & applying oil
and grease : 277.96

Assuming that timber shall become unserviceable


after being used 16 times . Hence cost for using
once : Each 1/16 9848.38 615.52
Add 5 % wastage for using
repeatedly : 492.42
Total : 1663.87
3 Labour :
For assembling erection &
dismentalling :
Carpenter II nd class : Each 1.26 311.5 392.49
Beldar Each 2.80 262.5 735.00
Sundries taking 10%of labour 112.75
Total : 2904.11
Add 10 % C.P & 5 % O.H
charges except 1/16 of carriage: 434.09
Cost of 9.33 Sqm. = 3338.19
Cost of 1 Sqm. = 357.79
Say Rs. = 357.8

Executive Engineer,
IPHDivision No.II
Kullu at Bhunter
Analysis of rate
Providing form work of steel sheets in Columns, pillars, posts and struts : Square, rectangular or polygonal
in plan.
Detail of cost for an area in contact 4x0.30x3.50= 4.20 Sqm.
S.No. Desciption Unit Quantity Rate Amount

Material :
MATERIAL :
Steel plates fixed with angle Sqm 5.46 2979.2 16266.6

Ballies, 125mm dia.( Kail wood) Metre 15.96 110 1755.60

Carriage of timber.
3.00 Km.By mechanical transport Cum. 0.196 193.71 37.97
0 Km.By head load Cum. 0.196 0.00 0.00
Total: 18060.17
Assuming that steel plates will
become unserviceable after being used 100 times.
Hence cost for using once : Each 1/100 16266.6 162.67

Add 1 % for using repeatedly I/c repairs, removal


of dents, cleaning conc. Deposits & applying oil
and grease : 162.67

Assuming that timber shall become unserviceable


after being used 16 times . Hence cost for using
once : Each 1/16 1793.57 112.10
Add 5 % wastage for using
repeatedly : 89.68
Total : 527.11
Labour :
For assembling erection &
dismentalling :
Carpenter II nd class : Each 0.59 311.5 183.79
Beldar Each 1.47 262.5 385.88
Sundries taking 10%of labour 56.97
Total : 1153.73
Add 10 % C.P & 5 % O.H
charges : 172.70
Cost of 4.20 Sqm. = 1326.44
Cost of 1 Sqm. = 315.82
Say Rs. = 315.8

Executive Engineer,
IPHDivision No.II
Kullu at Bhunter
Analysis of rate
Providing form work of steel sheets in Columns, pillars, posts and struts : Circular or curved in plans.
in plan.
Detail of cost for an area in contact 22/7*.30*3.50=3.30sqm.
S.No. Desciption Unit Quantity Rate Amount

Material :
MATERIAL :
Steel plates fixed with angle Sqm 3.74 2979.2 11142.32

Ballies, 125mm dia.( Kail wood) Metre 21.21 110 2333.10

Templet bottom Battens


Second class Kail wood Cum. 0.037 31240 1155.88
Bolts 12mm dia 0.30metre long. Qtl. 0.075 4500 337.50
Carriage of timber.
3.00 Km.By mechanical transport Cum. 0.26 193.71 50.36
0 Km.By head load Cum. 0.26 0.00 0.00
Total: 15019.16
Assuming that steel plates will
become unserviceable after being used 100 times.
Hence cost for using once : Each 1/100 11142.32 111.42

Add 1 % for using repeatedly I/c repairs, removal


of dents, cleaning conc. Deposits & applying oil
and grease : 111.42

Assuming that timber shall become unserviceable


after being used 16 times . Hence cost for using
once : Each 1/16 2383.46 148.97
Add 5 % wastage for using
repeatedly : 119.17
Total : 490.99
Labour :
For assembling erection &
dismentalling :
Carpenter II nd class : Each 0.58 311.5 180.67
Beldar Each 1.46 262.5 383.25
Sundries taking 10%of labour 56.39
Total : 1111.30
Add 10 % C.P & 5 % O.H
charges : 166.22
Cost of 3.30 Sqm. = 1277.52
Cost of 1 Sqm. = 387.13
Say Rs. = 387.13

Executive Engineer,
IPHDivision No.II
Kullu at Bhunter
Analysis of rate
Providing form work of steel sheets in Sides & soffits of beams, beam haunchings,
cantilevers, bressumers and lintels not exceeding 1 mtr. In depth in all heights from floor.
Detail of cost for 8.40 Sqm.
S.No. Desciption Unit Quantity Rate Amount

Material :
MATERIAL :
Steel plates fixed with angle Sqm 9.26 2979.2 27590.65

Ballies, 125mm dia.( Kail wood) Metre 34.65 110 3811.50


( 22.05+ 12.60)= 34.65m
Carriage of timber.
3.00 Km.By mechanical transport Cum. 0.273 193.71 52.88
0 Km.By head load Cum. 0.273 0.00 0.00
Total: 31455.03
Assuming that steel plates will
become unserviceable after being used 100 times.
Hence cost for using once : Each 1/100 27590.65 275.91

Add 1 % for using repeatedly I/c repairs, removal


of dents, cleaning conc. Deposits & applying oil
and grease : 275.91

Assuming that timber shall become unserviceable


after being used 16 times . Hence cost for using
once : Each 1/16 3864.38 241.52
Add 5 % wastage for using
repeatedly : 193.22
Total : 986.56
Labour :
For assembling erection &
dismentalling :
Carpenter II nd class : Each 1.14 311.5 355.11
Beldar Each 2.86 262.5 750.75
Sundries taking 10%of labour 110.59
Total : 2203.00
Add 10 % C.P & 5 % O.H
charges : 329.95
Cost of 8.40 Sqm. = 2532.96
Cost of 1 Sqm. = 301.54
Say Rs. = 301.5

Executive Engineer,
IPHDivision No.II
Kullu at Bhunter
Analysis of rate
Providing form work of steel sheets in : Edges of slabs and breaks in floors and walls
under 20 cm wide.
Detail of cost for 12.00 Rmtr.
S.No. Desciption Unit Quantity Rate Amount

Material :
MATERIAL :
Steel plates fixed with angle Sqm 1.80 2979.2 5362.61

Battens 2nd class Kail wood Cum 0.13 31240 4061.20

Carriage of timber.
3.00 Km.By mechanical transport Cum. 0.131 193.71 25.38
0 Km.By head load Cum. 0.131 0.00 0.00
Total: 9449.19
Assuming that steel plates will
become unserviceable after being used 100 times.
Hence cost for using once : Each 1/100 5362.61 53.63

Add 1 % for using repeatedly I/c repairs, removal


of dents, cleaning conc. Deposits & applying oil
and grease : 53.63

Assuming that timber shall become unserviceable


after being used 16 times . Hence cost for using
once : Each 1/16 4086.58 255.41
Add 5 % wastage for using
repeatedly : 204.33
Total : 566.99
Labour :
For assembling erection &
dismentalling :
Carpenter II nd class : Each 0.30 311.5 93.45
Beldar Each 0.56 262.5 147.00
Sundries taking 10%of labour 24.05
Total : 831.49
Add 10 % C.P & 5 % O.H
charges : 124.49
Cost of 12.00 Rmtr. = 955.97
Cost of 1 Rmtr. = 79.66
Say Rs. = 79.7

Executive Engineer,
IPHDivision No.II
Kullu at Bhunter
ANALYSIS OF RATE
Providing form work of steel sheets : Stair cases with sloping or stepped soffits excluding landing.
Detail of cost for 5.79 Sqm.
S.No. Desciption Unit Quantity Rate Amount
1 MATERIAL :
Steel plates fixed with angle Sqm 5.79 2979.2 17249.74

2nd class kail wood Cum 0.041 31240 1280.84


Ballies, 125mm dia. Metre 6.72 110 739.20
2 Carriage of timber.
3.00 Km.By mechanical transport Cum. 0.123 193.71 23.83
0 Km.By head load Cum. 0.123 0.00 0.00
Total: 19293.61
Assuming that steel plates will
become unserviceable after being used 100 times.
Hence cost for using once : Each 1/100 17249.74 172.50

Add 1 % for using repeatedly I/c repairs, removal


of dents, cleaning conc. Deposits & applying oil
and grease : 172.50

Assuming that timber shall become unserviceable


after being used 16 times . Hence cost for using
once : Each 1/16 2043.87 127.74
Add 5 % wastage for using
repeatedly : 102.19
Total : 574.93
3 Labour :
For assembling erection &
dismentalling :
Carpenter II nd class : Each 0.97 311.5 302.16
Beldar Each 1.51 262.5 396.38
Sundries taking 10%of labour 69.85
Total : 1343.31
Add 10 % C.P & 5 % O.H
charges except 1/16 of carriage: 201.27
Cost of 5.79 Sqm. = 1544.59
Cost of 1 Sqm. = 266.77
Say Rs. = 266.8

Executive Engineer,
IPHDivision No.II
Kullu at Bhunter
ANALYSIS OF RATE
Providing form work of steel sheets : Foundation, footings, basis of columns,etc. & mass concrete.
Detail of cost for 10 Sqm.
S.No. Desciption Unit Quantity Rate Amount
1 MATERIAL :
Steel plates fixed with angle Sqm 10.152 2979.2 30245.15

2nd class kail wood Cum 0.047 31240 1468.28


Ballies, 125mm dia. Metre 9.45 110 1039.50
2 Carriage of timber.
3.00 Km.By mechanical transport Cum. 0.163 193.71 31.57
0 Km.By head load Cum. 0.163 0.00 0.00
Total: 32784.50
Assuming that steel plates will
become unserviceable after being used 100 times.
Hence cost for using once : Each 1/100 30245.15 302.45

Add 1 % for using repeatedly I/c repairs, removal


of dents, cleaning conc. Deposits & applying oil
and grease : 302.45

Assuming that timber shall become unserviceable


after being used 16 times . Hence cost for using
once : Each 1/16 2539.35 158.71
Add 5 % wastage for using
repeatedly : 126.97
Total : 890.58
3 Labour :
For assembling erection &
dismentalling :
Carpenter II nd class : Each 0.52 311.5 161.98
Beldar Each 1.30 262.5 341.25
Sundries taking 10%of labour 50.32
Total : 1444.13
Add 10 % C.P & 5 % O.H
charges except 1/16 of carriage: 216.32
Cost of 10 Sqm. = 1660.46
Cost of 1 Sqm. = 166.05
Say Rs. = 166.0

Executive Engineer,
IPHDivision No.II
Kullu at Bhunter
ANALYSIS OF RATE

Providing & laying cement concrete 1:1.5:3 (1 cement : 1.5 Sand 3 graded stone aggregate
20 mm nominal size ) and curing complete excluding cost of form work & reinforcement for RCC
work in : Stair cases (except spiral stair cases)excluding landing but including preparing of the surface
and finishing of nosing up to floor two level.

Detail of cost for a flight of 3.40m clear span including 1 metre landing ( cost of landing excluding)

S.No. Desciption Unit Quantity Rate Amount


1 C.C 1:1.5:3(Detail& rate as per
sub analysis of C.C 1:1.5:3,
in foundation & plinth) cum. 0.79 3938.4 3111.33

2 Labour( Extra for laying C.C in


RCC work)
(a) Beldar Each 0.10 262.5 26.25
(b) Bhisti Each 0.20 262.5 52.50
© Mason Ist. Class Each 0.04 311.5 12.46
(d) Mason 2nd. Class Each 0.04 311.5 12.46
(e) Mate Each 0.04 262.5 10.50
Extra for finishing
(a) Mason Ist. Class Each 0.5 311.5 155.75
(b) Mason 2nd. Class Each 0.5 311.5 155.75
Extra labour for lifting material :
Beldar Each 0.17 262.5 44.63
Total : 470.30
Total 1+2= 3581.62
Add 1.5% water charges on 2: 7.05
3588.68
Add 10%contractor profit and
5% O.H charges except 1: 71.60
Cost for 0.79 cum. = 3660.28
Cost of 1 cum. = 4633.27
Say Rs. 4633.3

Executive Engineer,
IPHDivision No.II
Kullu at Bhunter
ANALYSIS OF RATE

Providing & laying cement concrete 1:1.5:3 (1 cement : 1.5 Sand 3 graded stone aggregate
20 mm nominal size ) and curing complete excluding cost of form work & reinforcement for RCC
work in : Foundations , footings , bases of the column and the like and mass concrete.

Detail of cost for a counterfort R.wall,4.5 m height & 6 mtrs. Long: =9.18 cum.

S.No. Desciption Unit Quantity Rate Amount


1 C.C 1:1.5:3(Detail& rate as per
sub analysis of C.C 1:1.5:3,
in foundation & plinth) cum. 9.18 3938.4 36154.43

2 Labour( Extra for laying C.C in


RCC work)
(a) Beldar Each 0.10 262.5 26.25
(b) Bhisti Each 0.20 262.5 52.50
© Mason Ist. Class Each 0.04 311.5 12.46
(d) Mason 2nd. Class Each 0.04 311.5 12.46
(e) Mate Each 0.04 262.5 10.50
Total : 114.17
Cost of labor for 9.18 cum 1048.08
Total 1+2= 37202.51
Add 1.5% water charges on 2: 15.72
37218.24
Add 10%contractor profit and
5% O.H charges except 1: 159.57
Cost for 9.180 cum. = 37377.81
Cost of 1 cum. = 4071.66
Say Rs. 4071.7

Executive Engineer,
IPHDivision No.II
Kullu at Bhunter
ANALYSIS OF RATE
P/F precast concrete man hole cover and frame, conforming to IS-12593-Part-I 1888 and IS 12592-Part-II,1991
560mm diameter , Heavy duty.

S.No. Desciption Unit Quantity Rate Amount

1 Material :
Precast concrete man hole cover &
frame heavy duty, 560 mm diameter. Each 1 No. 725.00 725.00
Add 4% HPST 29.00

2 Carriage : LS 100.00

3 Labour :
Labour for laying man hole
cover and frame :
Beldar Each 0.14 No. 262.5 36.75
Total : 890.75
Add 10% contractor profit and
5% over head charges 133.61
Total : 1024.36

Say Rs. 1024.4

Executive Engineer,
IPHDivision No.II
Kullu at Bhunter
P/F precast concrete man hole cover and frame, conforming to IS-12593-Part-I 1888 and IS 12592-Part-II,1991
560mm diameter , Medium duty.

S.No. Desciption Unit Quantity Rate Amount

1 Material :
Precast concrete man hole cover &
frame medium duty, 560 mm diameter. Each 1 No. 605.00 605.00
Add 4% HPST 24.20

2 Carriage : LS 80.00

3 Labour :
Labour for laying man hole
cover and frame :
Beldar Each 0.14 No. 262.5 36.75
Total : 745.95
Add 10% contractor profit and
5% over head charges 111.89
Total : 857.84

Say Rs. 857.8

Executive Engineer,
IPHDivision No.II
Kullu at Bhunter
ANALYSIS OF RATE
Laying in trenches G.M.S tubes and tube fittings (Earth work in trenches to be measured and paid
seperataly).
Unit : 10 Rmtr.
S.No. Desciption Unit Quantity Rate Amount
1 15 mm and 20 mm nominal
Labour :
Plumber( Fitter) Each 0.10 311.5 31.15
Beldar Each 0.19 262.5 49.88
Total : 81.03
Add 10% C.P.& 5%O.H.charges : 12.15
Cost of 10 Rmtr. = Total : 93.18
Cost of 1 Rmtr. = 9.32
Say Rs. 9.3
2 25 mm and 32 mm nominal
Labour :
Plumber( Fitter) Each 0.14 311.5 43.61
Beldar Each 0.3 262.5 78.75
Total : 122.36
Add 10% C.P.& 5%O.H.charges : 18.35
Cost of 10 Rmtr. = Total : 140.71
Cost of 1 Rmtr. = 14.07
Say Rs. 14.1
3 40 mm and 50 mm nominal
Labour :
Plumber( Fitter) Each 0.19 311.5 59.19
Beldar Each 0.4 262.5 105.00
Total : 164.19
Add 10% C.P.& 5%O.H.charges : 24.63
Cost of 10 Rmtr. = Total : 188.81
Cost of 1 Rmtr. = 18.88
Say Rs. 18.9
4 65 mm and 80 mm nominal
Labour :
Plumber( Fitter) Each 0.30 311.5 93.45
Beldar Each 0.79 262.5 207.38
Total : 300.83
Add 10% C.P.& 5%O.H.charges : 45.12
Cost of 10 Rmtr. = Total : 345.95
Cost of 1 Rmtr. = 34.59
Say Rs. 34.6
5 100mm
Labour :
Plumber( Fitter) Each 0.40 311.5 124.60
Beldar Each 1.19 262.5 312.38
Total : 436.98
Add 10% C.P.& 5%O.H.charges : 65.55
Cost of 10 Rmtr. = Total : 502.52
Cost of 1 Rmtr. = 50.25
Say Rs. 50.3

Executive Engineer,
IPHDivision No.II
Kullu at Bhunter
ANALYSIS OF RATE

Providing & laying no fine concrete (1 cement : 4 graded stone aggregate


20 mm nominal size ) and curing complete excluding cost of form work in walls.

DETAIL OF COST FOR 1.00 CUM.


S.No. Desciption Unit Quantity Rate Amount
1 2 3 4 5 6
MATERIALS
1 Stone aggregate 20mm Cum 0.89 440 391.60
2 Cement Tonne 0.32 4500 1440.00
1831.60
CARRIAGE
1 Carriage of aggrergate 20mm
7.00 Km.By mechanical transport Cum 0.89 277.09 246.61
0 Km.By head load Cum 0.89 0.00 0.00
2 Cement
25.00 Km.By mechanical transport Tonne 0.32 382.17 122.29
0 Km.By head load Tonne 0.32 0.00 0.00
368.90
LABOUR
1 Beldar Each 2.09 262.5 548.63
2 Bhisti Each 0.27 262.5 70.88
3 Mason Ist. Class Each 0.05 311.5 15.58
4 Mason 2nd. Class Each 0.05 311.5 15.58
5 Mate Each 0.04 262.5 10.50
6 Beldar for extra ramming. Each 0.25 262.5 65.63
Sundries including scaffolding. L.S. 20.00
746.78

Total:- 2947.28
Add for water charges @1.5% 44.21
Total:- 2991.49
Add 10% contractor profit & 5% over head charges on 232.72
all except cement.
G.Total:- 3224.21
Cost per Cum Rs. 3224.2

Executive Engineer,
IPHDivision No.II
Kullu at Bhunter
ANALYSIS OF RATE

Providing & fixing C.I flanged sluice valve as per IS 780-1986 of nominal pressure
and designation PN -1 with cap : 100 mm dia.

Unit : Each.
S.No. Desciption Unit Quantity Rate Amount
1 2 3 4 5 6
1 MATERIAL :
C.I sluice valve, 100 mm Each 1 2280.5 2280.50
Add 4% HPST : 91.22
Total: 2371.72
2 Carriage to site
of work : LS 75.00
.
3 Labour for fixing valve : LS 75.00
2521.72
Add 10% contractor profit and
5% over head charges : 378.258
2899.98

Say Rs. 2900

Executive Engineer,
IPHDivision No.II
Kullu at Bhunter
Analysis of Rate
Providing and placing in horizontal layers, filtering media duly graded, screened, washed and
cleaned as specified by the Engineer- in - charge.

S.No. Description of Items Unit Quantity Rate Amount

1 BOTTOM LAYER :
Broken stone 50mm to 75mm

A Rate at quarry Cum. 1.00 440.00 440.00


Add 20% for screening, washing & cum.
cleaning : 88.00
Total : 528.00
Labour for placing filtering media : ( As per HPSR-1993,Vol.-11) 9.20
Add 525% labour hike 48.30
57.50

B Carriage :
0.00 Km.By mechanical transport Cum 1.00 0.00 0
0.5 Km.By head load Cum 1.00 443.11 443.11
443.11
Total A+B : 1028.61
Add 10 % for contractor profit &
5% over head charges 154.29

Total : 1182.90
Say Rs. 1183

Executive Engineer,
IPHDivision No.II
Kullu at Bhunter
1 MIDDLE LAYER
Stone ballast 20mm to 25mm
& 6 mm to 20mm.
A Rate at quarry Cum. 1.00 465.00 465.00
Add 20% for screening, washing & cum.
cleaning : 93.00
Total : 558.00
Labour for placing filtering media : ( As per HPSR-1993,Vol.-11) 9.20
Add 525% labour hike 48.30
615.50

B Carriage :
7.00 Km.By mechanical transport Cum 1.00 277.09 277.09
0 Km.By head load Cum 1.00 0.00 0.00
277.09
Total A+B : 892.59
Add 10 % for contractor profit &
5% over head charges 133.89

Total : 1026.48
Say Rs. 1026

Executive Engineer,
IPHDivision No.II
Kullu at Bhunter
1 Top & 2nd Layer :
Coarse Sand & Fine Sand

A Rate at quarry Cum. 1.00 375.00 375.00


Add 20% for screening, washing & cum.
cleaning : 75.00
Total : 450.00
Labour for placing filtering media : ( As per HPSR-1993,Vol.-11) 6.90
Add 525% labour hike 36.23
493.13

B Carriage :
7.00 Km.By mech. Tansport Cum 1.00 277.09 277.09
0 Km. By head load : Cum 1.00 0.00 0
277.09
Total A+B : 770.22
Add 10 % for contractor profit &
5% over head charges 115.53

Total : 885.75
Say Rs. 886

Executive Engineer,
IPHDivision No.II
Kullu at Bhunter
Providing and placing Ist class bricks in filter bed in two layers so as to make cross drains.

2nd class bricks : Per 1000 1000 Nos. 7000 7000

Labour for placing bricks in 200


filter bed and making drains :
& carriage of material 7200

Add 10% contractor profit & 5 % O.H. charges on labour : 30.00


Cost of 1000 bricks : 7230
Cost of 1 brick : 7.23

Executive Engineer,
IPHDivision No.II
Kullu at Bhunter
Analysis of Rate
Excavation in foundation , trenches etc.,in earth work ,lift up to 1.50 metres stacking the excavated soil not more
than 3 metres clear from the edge of excavation and then returning the excavated soil in 15 cm. Layers , when
required in to plinth , side of foundation etc. consolidating each deposited layer by ranmming and watering and
then disposing of all surplus excavated earth as directed with in a lead of 20 metres.
PICK WORK : Unit Quantity Rate Amount
Detail of cost for 10 cum.
Labour :
Beldar Each 8.32 Nos. 262.5 2184
Bhisti Each 0.28 Nos. 262.5 73.5
2257.5
Add 1.5% water charges: 33.86
2291.36
Add 10% C.P. & 5% O.H. Charges: 343.7
Cost of 10 Cum : 2635.06
Cost of 1 Cum: 263.5
Jumper work :
Drilling equipment Day 0.045 day 2054.69 92.46
Material :
Special gelatine ( 80%) Kg. 0.63 Kg. 57 35.91
Detonators(ordinary) 100 Nos. 3 Nos. 350 10.5
Safety fuse wire Coil 0.25 coil 18 4.50
Labour :
Hole driller Each 0.135 Nos. 262.5 35.44
Blaster Each 0.09 Nos. 262.5 23.63
Beldar Each 16 Nos. 262.5 4200.00
4402.44
Add 10% C.P. & 5% O.H. Charges: 660.37
Cost of 10 Cum : 5062.81
Cost of 1 cum : 506.28

Chiselling work in hard rock : UNIT : 10 Cum.


Labour :
Chiseller/ breaker : Each 37.47 Nos. 311.5 11671.91
Black smith 2 nd class Each 0.59 Nos. 311.5 183.79
Beldar Each 18.74 Nos. 262.5 4919.25
16774.95
Add 10 % C.P. & 5% O.H. Charges : 2516.24
Cost of 10 Cum : 19291.19
Cost of 1 Cum : 1929.12
Per cum cost Classification
Cost of pick work : 263.5 80 % 210.81
Cost of jumper work : 506.28 20 % 101.26 312.07
Cost of chiselling work : 1929.12 0% 0

312.07
Add 5% for diversion of traffic arrangement, fixing night signals & caution boards, 15.60
crossing arrangement for access to houses,fencing, soring and strutting 327.67
whereever required & disposal of surplus earth as per directions: Say Rs. 327.7

Executive Engineer,
IPHDivision No.II
Kullu at Bhunter
ANALYSIS OF RATE
Providing & Laying cement concrete 1:2:4 ( 1 cement : 2 sand : 4graded stone aggregate 20mm
nominal size) and curing complete excluding cost of form work & reinforcement for reinforced
concrete work in (a) Suspended floor roofs landing & shelves & their supportsbalconies,beams,
bressumers & cantilevers upto floor two level.
DETAIL OF COST FOR 1.00 CUM.
S.No. Desciption Unit Quantity Rate Amount
1
MATERIALS
1 Stone aggregate 20mm Cum 0.67 cum 465 311.55
2 Stone aggregate 10mm Cum 0.22 cum 475 104.5
3 Sand Cum 0.445 cum 375 166.88
4 Cement Tonne 0.32 Tonne 4500 1440
2022.93
CARRIAGE
1 Carriage of aggrergate 20mm
7.00 Km.By mechanical transport Cum 0.67 cum 277.09 185.65
0 Km.By head load Cum 0.67 cum 0.00 0
2 Stone aggregate 10mm
7.00 Km.By mechanical transport Cum 0.22 cum 277.09 60.96
0 Km.By head load Cum 0.22 cum 0.00 0
3 Sand
7.00 Km.By mechanical transport Cum 0.445 cum 277.09 123.31
0 Km.By head load Cum 0.445 cum 0.00 0
4 Cement
25.00 Km.By mechanical transport Tonne 0.32 Tonne 382.17 122.29
0 Km.By head load Tonne 0.32 Tonne 0.00 0
Total 492.21
LABOUR
1 Beldar Each 2.09 Nos. 262.5 548.63
2 Bhisti Each 0.27 Nos. 262.5 70.88
3 Mason Ist. Class Each 0.05 Nos. 311.5 15.58
4 Mason 2nd. Class Each 0.05 Nos. 311.5 15.58
5 Mate Each 0.04 Nos. 262.5 10.5
6 Beldar for extra ramming. Each 0.25 Nos. 262.5 65.63
7 Extra labour for laying CC in RCC
Beldar Each 0.1 Nos. 262.5 26.25
Bhisti Each 0.2 Nos. 262.5 52.5
Mason Ist. Class Each 0.04 Nos. 311.5 12.46
Mason 2nd. Class Each 0.04 Nos. 311.5 12.46
Mate Each 0.04 Nos. 262.5 10.5
Extra beldar for lifting materials. Each 0.17 Nos. 262.5 44.63
Sundries. L.S. 15.00
900.6

Total:- 3415.74
Add for water charges @1.5% 51.24
Total:- 3466.98
Add 10% contracto's profit & 5% over head charges on 304.05
all except cement . 3771.03
Cost per Cum. Rs. 3771

Executive Engineer,
IPHDivision No.II
Kullu at Bhunter
ANALYSIS OF RATE
Providing & Laying cement concrete 1:2:4 ( 1 cement : 2 sand : 4graded stone aggregate 20mm
nominal size) and curing complete excluding cost of form work & reinforcement for reinforced
concrete work in (a) Foundations, footings base of columns & the like & mass concrete.
.
DETAIL OF COST FOR 1.00 CUM.
S.No. Desciption Unit Quantity Rate Amount
1
MATERIALS
1 Stone aggregate 20mm Cum 0.67 cum 465 311.55
2 Stone aggregate 10mm Cum 0.22 cum 475 104.5
3 Sand Cum 0.445 cum 375 166.88
4 Cement Tonne 0.32 Tonne 4500 1440
2022.93
CARRIAGE
1 Carriage of aggrergate 20mm
7.00 Km.By mechanical transport Cum 0.67 cum 277.09 185.65
0 Km.By head load Cum 0.67 cum 0.00 0
2 Stone aggregate 10mm
7.00 Km.By mechanical transport Cum 0.22 cum 277.09 60.96
0 Km.By head load Cum 0.22 cum 0.00 0
3 Sand
7.00 Km.By mechanical transport Cum 0.445 cum 277.09 123.31
0 Km.By head load Cum 0.445 cum 0.00 0
4 Cement
25.00 Km.By mechanical transport Tonne 0.32 Tonne 382.17 122.29
0 Km.By head load Tonne 0.32 Tonne 0.00 0
Total 492.21
LABOUR
1 Beldar Each 2.09 Nos. 262.5 548.63
2 Bhisti Each 0.27 Nos. 262.5 70.88
3 Mason Ist. Class Each 0.05 Nos. 311.5 15.58
4 Mason 2nd. Class Each 0.05 Nos. 311.5 15.58
5 Mate Each 0.04 Nos. 262.5 10.5
6 Beldar for extra ramming. Each 0.25 Nos. 262.5 65.63
7 Extra labour for laying CC in RCC
Beldar Each 0.1 Nos. 262.5 26.25
Bhisti Each 0.2 Nos. 262.5 52.5
Mason Ist. Class Each 0.04 Nos. 311.5 12.46
Mason 2nd. Class Each 0.04 Nos. 311.5 12.46
Mate Each 0.04 Nos. 262.5 10.5

Sundries. L.S. 15.00


855.97

Total:- 3371.11
Add for water charges @1.5% 50.57
Total:- 3421.68
Add 10% contracto's profit & 5% over head charges on 297.25
all except cement . 3718.93

Cost per Cum. Rs. 3718.93

Executive Engineer,
IPHDivision No.II
Kullu at Bhunter
ANALYSIS OF RATE
Providing & Laying cement concrete 1:1.5:3 ( 1 cement : 1.5 sand : 3graded stone aggregate 20mm
nominal size) and curing complete excluding cost of form work & reinforcement for reinforced
concrete work in (a) Columns,pillars,posts & struts upto floor two level..
.
DETAIL OF COST FOR 1.00 CUM.
S.No. Desciption Unit Quantity Rate Amount
1
MATERIALS
1 Stone aggregate 20mm Cum 0.57 cum 465 265.05
2 Stone aggregate 10mm Cum 0.28 cum 475 133
3 Sand Cum 0.425 cum 375 159.38
4 Cement Tonne 0.4 Tonne 4500 1800
2357.43
CARRIAGE
1 Carriage of aggrergate 20mm
7.00 Km.By mechanical transport Cum 0.57 cum 277.09 157.94
0 Km.By head load Cum 0.57 cum 0.00 0
2 Stone aggregate 10mm
7.00 Km.By mechanical transport Cum 0.28 cum 277.09 77.59
0 Km.By head load Cum 0.28 cum 0.00 0
3 Sand
7.00 Km.By mechanical transport Cum 0.425 cum 277.09 117.76
0 Km.By head load Cum 0.425 cum 0.00 0
4 Cement
25.00 Km.By mechanical transport Tonne 0.4 Tonne 382.17 152.87
0 Km.By head load Tonne 0.4 Tonne 0.00 0
506.16
LABOUR
1 Beldar Each 3.59 Nos. 262.5 942.38
2 Bhisti Each 0.29 Nos. 262.5 76.13
3 Mason Ist. Class Each 0.1 Nos. 311.5 31.15
4 Mason 2nd. Class Each 0.1 Nos. 311.5 31.15
5 Mate Each 0.04 Nos. 262.5 10.5
6 Beldar for extra ramming. Each 0.25 Nos. 262.5 65.63
7 Scaffolding L.S. 25.00
Extra labour for laying CC in RCC
Beldar Each 0.1 Nos. 262.5 26.25
Bhisti Each 0.2 Nos. 262.5 52.5
Mason Ist. Class Each 0.04 Nos. 311.5 12.46
Mason 2nd. Class Each 0.04 Nos. 311.5 12.46
Mate Each 0.04 Nos. 262.5 10.5
Extra labour for lifting of material: Each 0.17 Nos. 262.5 44.63
Sundries. L.S. 15.00
1355.74

Total:- 4219.33
Add for water charges @1.5% 63.29
Total:- 4282.62
Add 10% contracto's profit & 5% over head charges on 372.39
all except cement . 4655.01

Cost per Cum. Rs. 4655.0

Executive Engineer,
IPHDivision No.II
Kullu at Bhunter
ANALYSIS OF RATE
Brick work using common burnt clay building bricks in foundation & Plinth in cement mortar 1:6
( 1 cement : 6 Sand) 2nd class bricks.
Detail of cost for 1.00 cum.
S.No. Desciption Unit Quantity Rate Amount

MATERIALS
1 2nd class brick 1000 Nos 475 7000 3325
including unloading.
2 Cement mortar 1:6 cum 0.24 2382.31 571.75
3896.75
CARRIAGE
1 Carriage of bricks.
3.00 Km.By mechanical transport 1000 Nos 475 484.28 230.03
0 Km.By head load 1000 Nos 475 0.00 0

LABOUR
1 Mason Ist. Class. Each 0.5 311.5 155.75
2 Mason 2nd. Class Each 0.5 311.5 155.75
3 Beldar Each 1.8 262.5 472.5
4 Bhisti Each 0.2 262.5 52.5
Sundries L.S. 50
886.5

Total:- 5013.28
Add for water charges @1.5% 66.62
Total:- 5079.9
Add 10% contractor's profit & 5% over head charges 676.22
on all except mortar G.Total:- 5756.12
Foundation & plinth. Cost per cubic metre. 5756
Extra for bricks in Super Structure above plinth level up to floor two level:
Mason 1st class. Each 0.08 311.5 24.92
Mason 2nd class Each 0.08 311.5 24.92 (+) 170.96
Beldar Each 0.33 262.5 86.63 Total:- 5926.96
Scaffolding. LS 10.00 Say Rs. 5927.0
146.47
Add 1.5% for water charges. 2.20
148.66
Add 15% for CP & OH charges. 22.30 Executive Engineer,
Cost for One Cum. Total:- 170.96 IPH Division No.II Kullu
ANALYSIS OF RATE
Half brick masonry in common burnt clay building bricks in cement mortar 1:4 ( 1 cement : 4 sand )
Second class brick.
DETAIL OF COST FOR 10.0 Sqm.

S.No. Desciption Unit Quantity Rate Amount


1
MATERIALS
1 Second class brick at kiln. 1000 Nos 565 7000 3955
2 Cement mortae 1:4 Cum. 0.28 3035.39 849.91
4804.91
CARRIAGE
1 Carraiage of bricks
3.00 Km.By mechanical transport 1000 Nos 565 484.28 273.62
0.0 Km.By head load 1000 Nos 565 0.00 0
Total 273.62
LABOUR
1 Mason Ist. Class. Each 1.2 311.5 373.8
2 Beldar Each 2 262.5 525
3 Bhisti Each 0.4 262.5 105
Sundries L.S. 15.00
1018.80

Total:- 6097.33
Add for water charges @1.5% except mortar : 78.71
Total:- 6176.04
Add 10% contractor's profit & 5% over head charges 798.92
on all except mortar G. Total:- 6974.96

Cost of 10 Sqm. 6974.96


Cost per Sqm. 697

Executive Engineer,
IPHDivision No.II
Kullu at Bhunter
ANALYSIS OF RATE
Providing & laying cement concrete 1:5:10 (1 cement : 5 Sand 10 graded stone aggregate
40 mm nominal size ) and curing complete excluding cost of centring & shuttering in
foundation & plinth.
DETAIL OF COST FOR 1.00 CUM.
S.No. Desciption Unit Quantity Rate Amount

MATERIALS
1 Stone aggregate 40mm Cum 0.65 440 286
2 Stone aggregate 20mm Cum 0.24 465 111.6
3 Sand Cum 0.47 375 176.25
4 Cement Tonne 0.13 4500 585.00

CARRIAGE
1 Carriage of aggrergate 40mm
0.00 Km.By mechanical transport Cum 0.65 0.00 0.00
0.5 Km.By head load Cum 0.65 443.11 288.02
2 Stone aggregate 20mm
7.00 Km.By mechanical transport Cum 0.24 277.09 66.50
0 Km.By head load Cum 0.24 0.00 0.00
3 Sand
7.00 Km.By mechanical transport Cum 0.47 277.09 130.23
0 Km.By head load Cum 0.47 0.00 0.00
4 Cement
25.00 Km.By mechanical transport Tonne 0.13 382.17 49.68
0 Km.By head load Tonne 0.13 0.00 0.00

LABOUR
1 Beldar Each 2.09 262.5 548.63
2 Bhisti Each 0.27 262.5 70.88
3 Mason Ist. Class Each 0.05 311.5 15.58
4 Mason 2nd. Class Each 0.05 311.5 15.58
5 Mate Each 0.04 262.5 10.50
6 Beldar for extra ramming. Each 0.25 262.5 65.63
Sundries. L.S. 15.00

Total:- 2435.08
Add for water charges @1.5% 36.53
Total:- 2471.61
Add 10% contractor profit & 5% over head charges on 282.99
all except cement .
G.Total:- 2754.6
Cost per Cum Rs. 2754.60

Executive Engineer,
IPHDivision No.II
Kullu at Bhunter
Analysis of Rate (Item No.9.63(I),a. Page 76
Constructing chamber for sluice valve , with CI surface box 100mm top diameter,160mm bottom diameter and 180mm
deep (inside) with chained lid and RCC top slab 1:2:4 mix , 100mm thick foundation concrete 1:5:10 and inside plastering
with cement mortar 1:3 finished with a floating coat of neat cement : 600x600x750mm inside size with 150 mm thick
walls of RCC 1:2:4 complete with form work and reinforcement with 6 mm bars at not exceeding 150mm centre both way
With 100 mm diameter CI Sluice valve of Kirloskar/Leader/Audco make.
S.No Description Unit Quantity Rate Amount

1 CC 1:5:10,115x115x10 cm.=.13 cum Cum 0.13 cum 2755 358.1

2 150 mm thick walls of RCC 1:2:4


75x75x15 cm. X4 Nos.=0.34 cum. Cum 0.34 cum. 3719 1264.44

3 Providing form work:


60cm x 75 cm x 4 Nos.= 1.80 Sqm. Sqm. 1.8 Sqm. 218.6 393.56

4 Steel @ 80 Kg./cum= Kg. 27 Kg. 56.8 1534.32

5 15 mm th. C.P. 1 :3 Sqm. 2.16 Sqm. 124.1 268.06


240x 75 cm.= 1.80 Sqm.
60 x 60 cm. = 0.36 Sqm.

6 CI surface box with chained lid Each 1 No. 250 250.00


for size 100mm top diameter, 160 ( M.R.)
mm bottom dia, 180mm deep.

7 RCC 1:2:4 slab : cum 0.15 cum 3771 565.65

8 Steel @ 80 Kg./cum= Kg. 11.76 Kg. 56.8 668.28

9 Providing form work: Sqm. 0.84 Sqm. 325.2 273.14

Total : 5575.55
Add 10% C.P. & 5% O.H. charges on
surface box : 37.5
5613.05

Say Rs. 5613

Cost of CI sluice valve,100 mm


diameter: Each 1 No. 3300 3300

Carriage of valve to site of work : Job LS 50

Labour for fixing sluice valve: Job LS 50

3400
Add 10% C.P. & 5% O.H. charges : 510
3910
Total ( A+ B) : 9523

Say Rs. 9523

Executive Engineer,
IPHDivision No.II
Kullu at Bhunter
ANLYSIS OF RATE
Providing and fixing 1.8m high barbed wire fencing with angle iron posts 2.50m high 40x40x4mm
2.50mC/C with 9 horizontal rows and 2 diagonal rows of barbed wire embedded in CC 1:4:8.
Cost of 30m
S.No. Description of items Unit Quantity Rate Amount

1(a) ISA 40x40x4mm@ 2.5mc/c=30/2.5= 12 Nos.


Height of angle= 2.5+0.05+0.030= 2.580 m
Weight of angle iron : 2.40 Kg/m
Total weight of angle iron : 74.304 Kg.
Weight incl. 5% wastage : 78.02 Kg. Qtl. 0.780 4500 3510.00

(b) Cutting of angle iron LS 50.00

© Carriage of angle iron:


25.00 Km.By mechanical transport Tonne 0.078 382.17 29.81
0 Km.By head load Tonne 0.078 0.00 0.00

2 Excavation in foundation :
12x 0.45mx 0.45mx0.85 = 2.07 Cum. Cum. 2.07 312.07 645.98

3 C.C. 1:4:8
12x 0.45mx 0.45mx0.55 = 1.34 Cum Cum. 1.34 2955.53 3960.40

4(a) G.I. Barbed wire


9x30m = 270 m
2x13x2.97m = 71.28 m
Total : 341.28 m
@ 9.38 Kg./100m= 32.01 Kg. Qtl. 0.32 2200 704.00

(b) Carriage of barbed wire


25.00 Km.By mechanical transport Tonne 0.032 382.17 12.23
0 Km.By head load Tonne 0.032 0.00 0.00

5 Labour for fixing and stretching


barbed wire :
Blacksmith 2nd class Each 1.15 311.5 358.23
Beldar Each 1.15 262.5 301.88
Sundries L.S. 50.00

Total: 9622.53
Add 10% contractor profit and 5% over head charges
on item No.1,4 &5: 5016.15 752.42
Cost for 30 Rmtr. 10374.95
Cost for 1 Rmtr. 345.8

Executive Engineer,
IPHDivision No.II
Kullu at Bhunter
ANALYSIS OF RATE
Providing & laying cement concrete 1:3:6 (1 cement : 3 Sand :6 graded stone aggregate
20 mm nominal size ) and curing complete excluding cost of centring & shuttering in
foundation & plinth.
DETAIL OF COST FOR 1.00 CUM.
S.No. Desciption Unit Quantity Rate Amount

MATERIALS
1 Stone aggregate 20mm Cum 0.7 cum. 465 325.5
2 Stone aggregate 10mm Cum 0.24 cum. 475 114
3 Sand Cum 0.47 cum. 375 176.25
4 Cement Tonne 0.22 Tonne 4500 990.00
1605.75
CARRIAGE
1 Carriage of aggrergate 20mm
7.00 Km.By mechanical transport Cum 0.7 cum. 277.09 193.96
0 Km.By head load Cum 0.7 cum. 0.00 0.00
2 Stone aggregate 10mm
7.00 Km.By mechanical transport Cum 0.24 cum. 277.09 66.50
0 Km.By head load Cum 0.24 cum. 0.00 0.00
3 Sand
7.00 Km.By mechanical transport Cum 0.47 cum. 277.09 130.23
0 Km.By head load Cum 0.47 cum. 0.00 0.00
4 Cement
25.00 Km.By mechanical transport Tonne 0.22 Tonne 382.17 84.08
0 Km.By head load Tonne 0.22 Tonne 0.00 0.00
474.77
LABOUR
1 Beldar Each 2.09 No. 262.5 548.63
2 Bhisti Each 0.27 No. 262.5 70.88
3 Mason Ist. Class Each 0.05 No. 311.5 15.58
4 Mason 2nd. Class Each 0.05 No. 311.5 15.58
5 Mate Each 0.04 No. 262.5 10.50
6 Beldar for extra ramming. Each 0.25 No. 262.5 65.63
Sundries. L.S. 10.00
736.80

Total:- 2817.32
Add for water charges @1.5% 42.26
Total:- 2859.58
Add 10% contractor profit & 5% over head charges on 280.44
all except cement .
G.Total:- 3140.02
Cost per Cum Rs. 3140

Executive Engineer,
IPHDivision No.II
Kullu at Bhunter
ANALYSIS OF RATE
Providing and laying cement concrete 1:5:10 (1Cement:5 Sand:10 graded stone aggregate, 40 mm nominal
size) with 15% plum and curing complete excluding cost of form work in retaining walls/breast walls, the size
of plums shall usually be 150mm to 300 mm as per HP.PWD specifications.

DETAIL OF COST FOR 1.00 CUM.


S.No. Desciption Unit Quantity Rate Amount
MATERIAL
(I) Stone aggregate 40 mm (one size) Cum 0.60 Cum 440 264.00

(ii) Stone aggregate , 20mm nominal Cum 0.22 Cum 465 102.30
size.

(iii) Sand Cum 0.43 Cum 375 161.25

(iv) Cement Tonne 0.12 Tonne 4500 538.20

(v) Selected hard stone plums Cum 0.15 Cum 300 45.00

CARRIAGE
(I) Stone aggrergate above 40mm
0.00 Km.By mechanical transport Cum 0.60 cum. 0.00 0.00
0.5 Km.By head load Cum 0.60 cum. 443.11 265.87
(ii) Stone aggregate below 40 mm
7.00 Km.By mechanical transport Cum 0.22 cum. 277.09 60.96
0 Km.By head load Cum 0.22 cum. 0.00 0.00
(iii) Sand
7.00 Km.By mechanical transport Cum 0.43 cum. 277.09 119.15
0 Km.By head load Cum 0.43 cum. 0.00 0.00
(iv) Cement
25.00 Km.By mechanical transport Tonne 0.12 Tonne 382.17 45.71
0 Km.By head load Tonne 0.12 Tonne 0.00 0.00
(v) Soling stone for filling crates
0.00 Km.By mechanical transport Cum 0.15 cum. 0.00 0.00
0.5 Km.By head load Cum 0.15 cum. 409.84 61.48

LABOUR
1 Beldar Each 1.07 No. 262.5 280.88
Beldar (For extra ramming) Each 0.98 No. 262.5 257.25
Bhisti ( For extra ramming ) Each 0.25 No. 262.5 65.63
Mason Ist class. Each 0.17 No. 311.5 52.96
Sundries : L.S. 20.00

Total:- 2340.64
Add for water charges @1.5% 35.11
Total:- 2375.75
Add 10% contractor profit & 5% over head charges on 275.63
all except cement .
G.Total:- 2651.38
Cost per Cum Rs. 2651

Executive Engineer,
IPHDivision No.II
Kullu at Bhunter
ANALYSIS OF RATE
CEMENT MORTAR
S.No. Description of item Unit Quantity Rate Amount
CEMENT MORTAR 1:3
Material :
Cement Tonne 0.51 Tonne 4500 2295
Sand Cum 1.07 Cum 375 401.25
CARRIAGE:
Cement
25.00 Km.By mechanical transport Tonne 0.51 Tonne 382.17 194.91
0 Km.By head load Cum 0.51 Cum 0.00 0.00
Sand
7.00 Km.By mechanical transport Cum 1.07 Cum 277.09 296.49
0 Km.By head load Cum 1.07 Cum 0.00 0.00
LABOUR:
Beldar Each 0.9 No. 262.5 236.25
Bhisti Each 0.08 No. 262.5 21.00
Sundries : L.S. 10.00
Total : 3454.9
Add 1.5% Water charges : 51.82
3506.72
Add 10% C.P. & 5% O.H. Charges except cement : 181.76
3688.48

Executive Engineer,
IPHDivision No.II
Kullu at Bhunter
ANALYSIS OF RATE
CEMENT MORTAR 1:4
Material :
Cement Tonne 0.38 Tonne 4500 1710
Sand Cum 1.07 Cum 375 401.25

CARRIAGE:
Cement
25.00 Km.By mechanical transport Tonne 0.38 Tonne 382.17 145.22
0 Km.By head load Tonne 0.38 Tonne 0.00 0.00
Sand
7.00 Km.By mechanical transport Cum 1.07 Cum 277.09 296.49
0 Km.By head load Cum 1.07 Cum 0.00 0.00

LABOUR:
Beldar Each 0.9 No. 262.5 236.25
Bhisti Each 0.08 No. 262.5 21.00
Sundries : L.S. 10.00
Total : 2820.21
Add 1.5% Water charges : 42.3
2862.51
Add 10% C.P. & 5% O.H. Charges except cement : 172.88
3035.39

Executive Engineer,
IPHDivision No.II
Kullu at Bhunter
ANALYSIS OF RATE
CEMENT MORTAR 1:6
Material :
Cement Tonne 0.25 Tonne 4500 1125
Sand Cum 1.07 Cum 375 401.25
CARRIAGE:
Cement
25.00 Km.By mechanical transport Tonne 0.25 Tonne 382.17 95.54
0 Km.By head load Tonne 0.25 Tonne 0.00 0.00
Sand
7.00 Km.By mechanical transport Cum 1.07 Cum 277.09 296.49
0 Km.By head load Cum 1.07 Cum 0.00 0.00
LABOUR:
Beldar Each 0.9 No. 262.5 236.25
Bhisti Each 0.08 No. 262.5 21.00
Sundries : L.S. 10.00
Total : 2185.53
Add 1.5% water charges : 32.78
Add 10% C.P. & 5% O.H. Charges 2218.31
except cement : 164
2382.31

Executive Engineer,
IPHDivision No.II
Kullu at Bhunter
ANALYSIS OF RATE
Random rubble masonry coursed with hard stone of approved quality in foundation and plinth in R.Walls/B.walls
I/c raking out joints in :Laid dry.
S.No. Description of items Unit Quantity Rate Amount

MATERIAL

Stone at quarry Cum 1.00 Cum 350 350

Through & bond stone Each 7 No. 7.00 49

Carriage of stones
0.00 Km.By mechanical transport Cum 1.21 Cum 0.00 0
1 Km.By head load Cum 1.21 Cum 831.81 1006.49

LABOUR :
Stone dresser Each 0.2 No. 262.5 52.5
Mason Ist class Each 0.1 No. 311.5 31.15
Mason II nd class Each 0.1 No. 311.5 31.15
Beldar Each 1.06 No. 262.5 278.25
Sundries LS 10.00
Total : 1808.54
Add 1.5% for water charges : 27.13
1835.67
Add 10% C.P. & 5% O.H. charges
except on Stones : 215.5
2051.17
Say Rs. 2051 /- only.

Executive Engineer,
IPHDivision No.II
Kullu at Bhunter
ANALYSIS OF RATE
Squared rubble masonry coursed with hard stone of approved quality in foundation and plinth including
raking out joints in :
S.No. Description of items Unit Quantity Rate Amount
CEMENT MORTAR 1:4
MATERIAL
Cement mortar 1:4 Cum 0.3 Cum 3035.39 910.62
Stone at quarry Cum 1.21 Cum 350 423.5
Through & bond stone Each 7 No. 7.00 49

Carriage of stones
0.00 Km.By mechanical transport Cum 1.37 Cum 0.00 0
1 Km.By head load Cum 1.37 Cum 831.81 1139.58

LABOUR :
Stone dresser Each 2.83 No. 262.5 742.88
Mason Ist class Each 1.06 No. 311.5 330.19
Mason II nd class Each 1.06 No. 311.5 330.19
Beldar Each 2.65 No. 262.5 695.63
Sundries LS 35.00
Total : 4656.59
Add 1.5% for water charges except mortar: 56.19
4712.78
Add 10% C.P. & 5% O.H. charges
except on mortar : 570.32
5283.1
Say Rs. 5283

Executive Engineer,
IPHDivision No.II
Kullu at Bhunter
Squared rubble masonry coursed with hard stone of approved quality in foundation and plinth
CEMENT MORTAR1:6
MATERIAL
Cement mortar 1:6 Cum 0.3 Cum 2382.31 714.69
Stone at quarry Cum 1.21 Cum 350 423.5
Through & bond stone Each 7 No. 7.00 49

Carriage of stones
0.00 Km.By mechanical transport Cum 1.37 Cum 0.00 0
1 Km.By head load Cum 1.37 Cum 831.81 1139.58

LABOUR :
Stone dresser Each 2.83 No. 262.5 742.88
Mason Ist class Each 1.06 No. 311.5 330.19
Mason II nd class Each 1.06 No. 311.5 330.19
Beldar Each 2.65 No. 262.5 695.63
Sundries LS 20.00
Total : 4445.66
Add 1.5% for water charges except on mortar. 55.96
4501.62
Add 10% C.P. & 5% O.H. charges
except on mortar : 568.04
5069.66

Executive Engineer,
IPHDivision No.II
Kullu at Bhunter
ANALYSIS OF RATES
Random rubble masonry / polygonal rubble masonry ( uncoursed/ brought to courses) with hard stone of
approved quality in foundation and plinth including levelling up with cement concrete 1:6:12 (1 Cement :
6 sand : 12 graded stone aggregate , 20mm nominal size ) in cement mortar 1:6( 1cement:6 sand)
S.No. Description of items Unit Quantity Rate Amount

Stone at quarry Cum 1 Cum 350 350


Through & bond stone Each 7 No. 7.00 49
Cement mortar 1:6 Cum 0.33 Cum 2382.31 786.16
Carriage of stones
0.00 Km.By mechanical transport Cum 1.16 Cum 0.00 0
1 Km.By head load Cum 1.16 Cum 831.81 964.9

Cement concrete 1:6:12 LS 20.00


LABOUR :
Mason II nd class Each 1.77 No. 311.5 551.36
Beldar Each 2.12 No. 262.5 556.5
Bhisti Each 0.09 No. 262.5 23.63
Sundries LS 15.00
Total : 3316.55
Add 1.5% for water charges except on mortar : 37.96
3354.51
Add 10% C.P. & 5% O.H. charges
except on mortar : 385.25
3739.76
Say Rs 3740.0 only

Executive Engineer,
IPHDivision No.II
Kullu at Bhunter
Analysis of Rate
Poviding 200 mm wide cast iron rungs with chequered or ribbed non slip surface including fixing in man hole
with 200x200x100 mm cement concrete 1:3:6 ( !cement :3 sand :6 graded stone aggregate,20 mm nominal size)

Detail of cost for 1 No.

S.No. Description of item Unit Quantity Rate Amount


Material :
1 C.I. Rung painted evenly with
coal tar. Each 1 No. 30 30.00

2 C.C. 1:3:6
0.20x0.20x0.10 = 0.004 cum. Cum. 0.004 Cum 3140.02 12.56

Labour for fixing C.I. Rungs :

Mason Ist class Each 0.024 No. 311.5 7.48


Mason 2nd class Each 0.024 No. 311.5 7.48
Beldar Each 0.06 No. 262.5 15.75

73.27
Add 1.5% water charges except on CC 1:3:6 0.91
74.18
Add 10% C.P. & 5% O.H. Charges except on 0.09
C.C. 1:3:6. 74.27
Say Rs. 74

Executive Engineer,
IPHDivision No.II
Kullu at Bhunter
Analysis of Rate

Providing RCC spun vent shaft with cowl 140 mm and 200 mm internal and external diameter respectively and top 300
mm and 450 mm internal and external diameter.

S.No. Description of item Unit Quantity Rate Amount

1 RCC spun vent shaft with cowl Each 1 No. 5500 5500
140 mm and 200 mm internal &
external diameter respectively at top 300 mm and
450mm internal & external diameter resp. at
bottom and 9.10 mtrs. Over all length

2 CC 1:4:8 Cum 0.919 cum. 2955.53 2716.13

3 CC 1:2:4 Cum 0.098 cum 3718.93 364.46

4 Carriage of vent shaft complete


including loadin, unloading and carting to LS 500 500
site of work .

Labour :
Mason 1st class Each 0.75 No. 311.5 233.63
Mason 2nd class Each 0.25 No. 311.5 77.88
Badhani Each 2 No. 262.5 525
Beldar Each 2 No. 262.5 525
Sundries including labour for LS 100 100
making connections:
Total : 10542.1

Add 10% contractor profit and 5 % over head charges except item No. 2 &3 : 1119.23
11661.33

Say Rs. 11661.33

Executive Engineer,
IPHDivision No.II
Kullu at Bhunter
ANALYSIS OF RATE
Providing & laying cement concrete 1:3:6 (1 cement :3 Sand : 6 graded stone aggregate
20 mm nominal size ) and curing complete excluding cost of centring & shuttering in
foundation & plinth.
DETAIL OF COST FOR 1.00 CUM.
S.No. Desciption Unit Quantity Rate Amount
A. MATERIALS
1 Stone aggregate 10mm Cum 0.24 475 114
2 Stone aggregate 20mm Cum 0.7 465 325.5
3 Sand Cum 0.47 375 176.25
4 Cement Tonne 0.22 4500 990
1605.75
B. CARRIAGE
1(a) Agg.10mm&20mm
7.00 Km.By mechanical transport Cum 0.94 277.09 260.46
0 Km.By head load Cum 0.94 0.00 0
2(a) Sand
7.00 Km.By mechanical transport Cum 0.47 277.09 130.23
0 Km.By head load Cum 0.47 0.00 0
3(a) Cement
25.00 Km.By mechanical transport Tonne 0.22 382.17 84.08
0 Km.By head load Tonne 0.22 0.00 0
474.77
C LABOUR
1 Beldar Each 2.09 262.5 548.63
2 Bhisti Each 0.27 262.5 70.88
3 Mason Ist. Class Each 0.05 311.5 15.58
4 Mason 2nd. Class Each 0.05 311.5 15.58
5 Mate Each 0.04 262.5 10.5
6 Beldar for extra ramming. Each 0.25 262.5 65.63
Sundries. L.S. 10
Total:- 736.8
Total(A+B+C): 2817.32
Add for water charges @1.5% 42.26
Total:- 2859.58
Add 10% contractor profit & 5% over head charges on 280.44
all except cement . G.Total:- 3140.02

C.C linning 15 cm thick or less for irrigation channels, using cement concrete 1:3:6.
(a) Hand mixed concrete linning in bed :

1 Cement concrete 1:3:6 for linning Cum. 1 3140.02 3140.02


Additional labour for making slab up to 15 cm.
thick.
(a) Mason Ist class. Each 0.17 311.5 52.96
(b) Beldar. Each 0.17 262.5 44.63
97.59
Add 10% contractor profit & 5% over head charges on (a)&(b): 14.64
112.23
Total: 3140.02 + 112.23 3252.25

(b) Hand mixed concrete linning on side slopes :


Additional labour I/c 10% C.P. & 5% O.H. charges required on account of
difficulty of adjusting material on side slopes. 20.00
3272.25
Say Rs. 3272

Executive Engineer,
IPHDivision No.II
Kullu at Bhunter
Analysis of rate.
Excavation in drains and channels etc in earth work including dressing of side slopes & bed of
excavated earth up to a lead of 20 mtrs lift up to 1.50 metres , disposed earth to be levelled
and neatly dressed in Pick work :
DETAIL OF COST FOR 10 CUM.
S.No. Desciption Unit Quantity Rate Amount
1 LABOUR :
(a) Beldar. Each 6.66 262.5 1748.25
(b) Bhisti. Each 0.22 262.5 57.75

Total: 1806
Add 1.5% for water charges: 27.09
1833.09
Add 10% contractor profit & 5% over 274.96
head charges: Cost for 10 Cum : 2108.05

Cost for 1 Cum: 210.81


Say Rs. 210.8

Dressing of bed and prepration of sub grade for linning in pick work :
1 LABOUR :
(a) Beldar. Each 1.3 262.5 341.25
Add 10% contractor profit & 5% over Total: 341.25
head charges: 51.19
Cost for 10 Sqm : 392.44

Cost for 1 Sqm: 39.24


Say Rs. 39.2

Dressing of side slopes and prepration of sub grade for linning in pick work :
1 LABOUR :
(a) Beldar. Each 1.8 262.5 472.5

Total: 472.5
Add 10% contractor profit & 5% over 70.88
head charges: Cost for 10 Sqm : 543.38

Cost for 1 Sqm: 54.34


Say Rs. 54.3

Executive Engineer,
IPHDivision No.II
Kullu at Bhunter
Analysis of Rate.
S.No. Desciption Unit Quantity Rate Amount
Consider a block of 3.05x3.05m=9.30 Sqm.
or 9.30x.15= 1.40 cum.

Kail wood plank 25mm thick=


4x3.05x.15=1.83 Sqm.
Add 10% wastage : 0.18 sqm.
Total : 2.01 Sqm.
or 2.01x25mm=.05 cum. Cum. 0.05 29728 1486.4
Carriage of planks :
3.00 Km.By mechanical transport Cum. 0.05 193.71 9.69
0 Km.By head load Cum. 0.05 0.00 0
1496.09
Add 10% C.P.& 5% O.H. Charges: 224.41
1720.5
Assuming that timber will become unserviceable after
being used 20 times :
Cost for using once : 1720.5 86.03 86.03
20
Sundries : L.S. 20
106.03 (I)
Labour for 7.08 cum.
Carpenter 2nd class : Each 1 311.5 311.5
Beldar: Each 1 262.5 262.5
574
Add 10% C.P.& 5% O.H. Charges: 86.1
660.1
Labour for 1.40 cum. 660.1 x 1.4 130.53 (II)
7.08

Total (I)+(II) : 236.56

Say Rs. 236.6

Executive Engineer,
IPHDivision No.II
Kullu at Bhunter
Analysis of Rate
20 mm cement plaster in single coat on rough side of brick /stone masonry for interior plastering up to floor
two level including arrises, internal rounded angles, chamfers and/or rounded angles not exceeding 80mm in
girth and finished even and smooth .

Detail of cost for 10 Sqm.


S.No. Desciption Unit Quantity Rate Amount
In cement mortar 1:3
Material
Cement mortar 1:3
(1cement:3sand) Cum. 0.224 3688.48 826.22
Labour :
Mason II nd class Each 1.00 311.5 311.5
Beldar Each 1.00 262.5 262.50
Bhishti Each 1.06 262.5 278.25
Sundries( Scaffolding etc.) L.S. 10.0
1688.47
Add 1.5% water charges 12.93
1701.4
Add 10% CP & 5% O.H. Charges except cement mortar : 131.28
Cost of 10 Sqm. 1832.68
In cement mortar 1:4 Cost of 1 Sqm. 183.3
Material
Cement mortar 1:4
(1cement:4sand) Cum. 0.224 3035.39 679.93
Labour :
Mason II nd class Each 1.00 311.5 311.5
Beldar Each 1.00 262.5 262.50
Bhishti Each 1.06 262.5 278.25
Sundries( Scaffolding etc.) L.S. 10.0
1542.18
Add 1.5% water charges 12.93
1555.11
Add 10% CP & 5% O.H. Charges except cement mortar : 131.28
Cost of 10 Sqm. 1686.39
In cement mortar 1:6 Cost of 1 Sqm. 168.6
Material
Cement mortar 1:6
(1cement:6sand) Cum. 0.224 2382.31 533.64
Labour :
Mason II nd class Each 1.00 311.5 311.5
Beldar Each 1.00 262.5 262.50
Bhishti Each 1.06 262.5 278.25
Sundries( Scaffolding etc.) L.S. 10.0
1395.89
Add 1.5% water charges 12.93
1408.82
Add 10% CP & 5% O.H. Charges except cement mortar : 131.28
Cost of 10 Sqm. 1540.1
Cost of 1 Sqm. 154.0

Executive Engineer,
IPHDivision No.II
Kullu at Bhunter
Analysis of Rate
20 mm cement plaster in two coats backing coat 15mm & finishing coat 5mm thick on rough side
of brick/stone masonry for interior plastering up to floor two level including arrises, internal rounded angles,
chamfers and/or rounded angles not exceeding 80mm in girth and finished even and smooth .
Detail of cost for 10 Sqm.
S.No. Desciption Unit Quantity Rate Amount
In cement mortar 1:3
Material
Cement mortar 1:3
(1cement:3sand) Cum. 0.231 3688.48 852.04
Labour :
Mason II nd class Each 1.53 311.5 476.6
Beldar Each 1.53 262.5 401.63
Bhishti Each 1.48 262.5 388.50
Sundries( Scaffolding etc.) L.S. 10.0
2128.77
Add 1.5% water charges 19.15
2147.92
Add 10% CP & 5% O.H. Charges except cement mortar : 194.38
Cost of 10 Sqm. 2342.3
In cement mortar 1:4 Cost of 1 Sqm. 234.2
Material
Cement mortar 1:4
(1cement:4sand) Cum. 0.231 3035.39 701.18
Labour :
Mason II nd class Each 1.53 311.5 476.6
Beldar Each 1.53 262.5 401.63
Bhishti Each 1.48 262.5 388.50
Sundries( Scaffolding etc.) L.S. 10.0
1977.91
Add 1.5% water charges 19.15
1997.06
Add 10% CP & 5% O.H. Charges except cement mortar : 194.38
Cost of 10 Sqm. 2191.44
In cement mortar 1:6 Cost of 1 Sqm. 219.1
Material
Cement mortar 1:6
(1cement:6sand) Cum. 0.231 2382.31 550.31
Labour :
Mason II nd class Each 1.53 311.5 476.6
Beldar Each 1.53 262.5 401.63
Bhishti Each 1.48 262.5 388.50
Sundries( Scaffolding etc.) L.S. 10.0
1827.04
Add 1.5% water charges 19.15
1846.19
Add 10% CP & 5% O.H. Charges except cement mortar : 194.38
Cost of 10 Sqm. 2040.57
Cost of 1 Sqm. 204.1

Executive Engineer,
IPHDivision No.II
Kullu at Bhunter
ANALYSIS OF RATE
Providing & laying cement concrete 1:6:12 (1 cement : 6 Sand :12 graded stone aggregate
40 mm nominal size ) and curing complete excluding cost of centring & shuttering in
foundation & plinth.
DETAIL OF COST FOR 1.00 CUM.
S.No. Desciption Unit Quantity Rate Amount
1 2 3 4 5 6
MATERIALS
1 Stone aggregate 40mm Cum 0.65 440 286.00
2 Stone aggregate 20mm Cum 0.24 465 111.60
3 Sand Cum 0.47 375 176.25
4 Cement Tonne 0.11 4500 495.00
1068.85
CARRIAGE
1 Carriage of aggrergate 40mm
0.00 Km.By mechanical transport Cum 0.65 0.00 0.00
0.5 Km.By head load Cum 0.65 443.11 288.02
2 Stone aggregate 20mm
7.00 Km.By mechanical transport Cum 0.24 277.09 66.50
0 Km.By head load Cum 0.24 0.00 0.00
3 Sand
7.00 Km.By mechanical transport Cum 0.47 277.09 130.23
0 Km.By head load Cum 0.47 0.00 0.00
4 Cement
25.00 Km.By mechanical transport Tonne 0.11 382.17 42.04
0 Km.By head load Tonne 0.11 0.00 0.00
526.79
LABOUR
1 Beldar Each 2.09 262.5 548.63
2 Bhisti Each 0.27 262.5 70.88
3 Mason Ist. Class Each 0.05 311.5 15.58
4 Mason 2nd. Class Each 0.05 311.5 15.58
5 Mate Each 0.04 262.5 10.50
6 Beldar for extra ramming. Each 0.25 262.5 65.63
Sundries. L.S. 10.00
736.78

Total:- 2332.42
Add for water charges @1.5% 34.99
Total:- 2367.41
Add 10% contractor profit & 5% over head charges on 280.86
all except cement .
G.Total:- 2648.27
Cost per Cum Rs. 2648.3

Executive Engineer,
IPHDivision No.II
Kullu at Bhunter
ANALYSIS OF RATE
Providing & Laying cement concrete 1:2:4 ( 1 cement : 2 sand : 4graded stone aggregate 20mm
nominal size) and curing complete excluding cost of form work in foundation & plinth

.
DETAIL OF COST FOR 1.00 CUM.
S.No. Desciption Unit Quantity Rate Amount
1
MATERIALS
1 Stone aggregate 20mm Cum 0.67 cum 465 311.55
2 Stone aggregate 10mm Cum 0.22 cum 475 104.5
3 Sand Cum 0.445 cum 375 166.88
4 Cement Tonne 0.32 Tonne 4500 1440
2022.93
CARRIAGE
1 Carriage of aggrergate 20mm
7.00 Km.By mechanical transport Cum 0.67 cum 277.09 185.65
0 Km.By head load Cum 0.67 cum 0.00 0
2 Stone aggregate 10mm
7.00 Km.By mechanical transport Cum 0.22 cum 277.09 60.96
0 Km.By head load Cum 0.22 cum 0.00 0
3 Sand
7.00 Km.By mechanical transport Cum 0.445 cum 277.09 123.31
0 Km.By head load Cum 0.445 cum 0.00 0
4 Cement
25.00 Km.By mechanical transport Tonne 0.32 Tonne 382.17 122.29
0 Km.By head load Tonne 0.32 Tonne 0.00 0
492.21
LABOUR
1 Beldar Each 2.09 Nos. 262.5 548.63
2 Bhisti Each 0.27 Nos. 262.5 70.88
3 Mason Ist. Class Each 0.05 Nos. 311.5 15.58
4 Mason 2nd. Class Each 0.05 Nos. 311.5 15.58
5 Mate Each 0.04 Nos. 262.5 10.5
6 Beldar for extra ramming. Each 0.25 Nos. 262.5 65.63
726.8

Total:- 3241.94
Add for water charges @1.5% 48.63
Total:- 3290.57
Add 10% contracto's profit & 5% over head charges on 277.59
all except cement . 3568.16

Cost per Cum. Rs. 3568

Executive Engineer,
IPHDivision No.II
Kullu at Bhunter
Analysis of Rate
6 mm cement plaster to ceiling in cement mortar 1:3 ( 1 cement : 3 sand)

Detail of cost for 10 Sqm.


S.No. Desciption Unit Quantity Rate Amount
In cement mortar 1:3
Material
Cement mortar 1:3
(1cement:3sand) Cum. 0.072 3688.48 265.57
Labour :
Mason II nd class Each 0.65 311.5 202.48
Beldar Each 0.81 262.5 212.63
Bhishti Each 0.27 262.5 70.88
Sundries( Scaffolding etc.) L.S. 10.0
761.56
Add 1.5% water charges 7.44
769
Add 10% contractor profit & 5% over head charges : 75.51
Cost of 10 Sqm. 844.51
In cement mortar 1:4 Cost of 1 Sqm. 84.5
Material
Cement mortar 1:4
(1cement:4sand) Cum. 0.072 3035.39 218.55
Labour :
Mason II nd class Each 0.65 311.5 202.48
Beldar Each 0.81 262.5 212.63
Bhishti Each 0.27 262.5 70.88
Sundries( Scaffolding etc.) L.S. 10.0
714.54
Add 1.5% water charges 7.44
721.98
Add 10 % contractor profit & 5% over head 75.51
charges except cement mortar : Cost of 10 Sqm. 797.49
Cost of 1 Sqm. 79.7

Executive Engineer,
IPHDivision No.II
Kullu at Bhunter
Analysis of Rate
Kota slab 25 mm thick in risers of steps, skirting dado and pillars laid on 12mm (average) cement mortar
1:3 and jointed with gray cement slurry mixed with pigment to match the shade of slab including rubbing and
polishing complete .
Detail of cost for 10Sqm. Detail of cost for 01 Sqm.
S.No. Desciption Unit Quantity Rate Amount

MATERIAL

25mm thick kota stone slab( polished) Sqm 11.50 350 4025
including 15% wastage.

Cement mortar 1:3


(1cement : 3 sand) Cum 0.144 3688.48 531.14

Cement for slurry :


Tonne 0.064 4500 288.00

Pigment dark shade Kg. 4.5 80 360.00

Carriage of Kota stone :


Km.By mechanical transport Tonne 0.67 382.17 256.05
Km.By head load Tonne 0.67 0.00 0.00
Carriage of cement :
25.00 Km.By mechanical transport Tonne 0.064 382.17 24.46
0 Km.By head load Tonne 0.064 0.00 0.00

Labour :
Mason -2nd class Each 6.5 311.5 2024.75
Beldar Each 10.8 262.5 2835.00
Beldar (skilled ) for rubbing and polishing Each 10.8 262.5 2835.00

Total : 13179.4
Add 1.5% for water charges : 18.97
13198.37
Add 10% for contractor profit and 5% over head charges 1900.08
except cement mortar : Cost of 10 Sqm. 15098.45
Cost of 1 Sqm. 1509.85
Say Rs. 1509.9

Executive Engineer,
IPHDivision No.II
Kullu at Bhunter
i
Analysis of Rate
Kota stone slab flooring 20mm (average) thick base of cement mortar 1:4(1cement:4sand) laid over and jointed'
with grey cement slurry mixed with pigment to match the sahde of the slab including rubbing and polishing
complete.
Detail of cost for 10Sqm. Detail of cost for 1 Sqm.
S.No. Desciption Unit Quantity Rate Amount

MATERIAL

40mm thick kota stone slab( polished) Sqm 11.50 450 5175
including 15% wastage.

Cement mortar 1:4


(1cement : 4 sand) Cum 0.224 3035.39 679.93

Cement for slurry :


For bedding = 44 Kg. Tonne 0.076 4500 342.00
For joints = 32 Kg.
Total : = 76 Kg.
Pigment = (76x3.5)/5=5.3 Kg. Kg. 5.3 80 424.00

Carriage of Kota stone :


25.00 Km.By mechanical transport Tonne 1.07 382.17 408.92
0.00 Km.By head load Tonne 1.07 0.00 0.00
Carriage of cement :
25.00 Km.By mechanical transport Tonne 0.076 382.17 29.04
0 Km.By head load Tonne 0.076 0.00 0.00

Labour :
Mason -2nd class Each 7 311.5 2180.50

Beldar Each 10.8 262.5 2835.00

Beldar (skilled ) for rubbing and polishing Each 10.8 262.5 2835.00
Sundries L-S 150.00

Total : 15059.39
Add 1.5% for water charges : 215.69
15275.08
Add 10% for contractor profit and 5% over head charges 2189.27
except cement mortar : Cost of 10 Sqm. 17464.35
Cost of 1 Sqm. 1746.44

Say Rs. 1746.4

Executive Engineer,
IPHDivision No.II
Kullu at Bhunter
Analysis of Rate
White glazed tiles 6 mm thick in flooring , treads of steps and landing laid on a bed of 12mm thick cement mortar
1:3 ( 1 cement : 3 sand) finished with flush pointing in white cement.

Detail of cost for 1 Sqm.


S.No. Desciption Unit Quantity Rate Amount

MATERIAL
Glazed tiles 152mmx152mmx6mm size= 44.4 Nos.
Add 2.5% for wastage & breakage: 1.1 Nos.
Total : 45.5 Nos.
Say : 46 Nos.
100 46.00 500 230

12 mm thick cement mortar 1:3


(1cement : 3 sand) Cum 0.015 3688.48 55.33

Cement for slurry overhead @


3.3Kg. Per square metre=3.3 Kg. Tonne 0.0033 12000 39.60
or 0.0033 Tonne.

Carriage of tiles/ cement L.S. 30.00

Labour :
Mason -1st class Each 0.7 311.5 218.05
Beldar Each 0.7 262.5 183.75
Sundries 15

Total : 771.73
Add 1.5% for water charges : 10.75
782.48
Add 10% for contractor profit and 5% over head charges 109.07
except cement mortar : 891.55
Say Rs. 891.6

Executive Engineer,
IPHDivision No.II
Kullu at Bhunter
Analysis of Rate
White glazed tiles 6 mm thick in skirting , risers of steps and dado 12mm thick cement mortar
1:3 ( 1 cement : 3 sand) & jointed with cement slurry.

Detail of cost for 1 Sqm.


S.No. Desciption Unit Quantity Rate Amount

MATERIAL
Glazed tiles 152mmx152mmx6mm size= 44.4 Nos.
Add 2.5% for wastage & breakage: 1.1 Nos.
Total : 45.5 Nos.
Say : 46 Nos.
100 Nos. 46.00 600 276

12 mm thick cement mortar 1:3


(1cement : 3 sand) Cum 0.015 3688.48 55.33

Cement for slurry overhead @


3.3Kg. Per square metre=3.3 Kg. Tonne 0.0033 12000 39.60
or 0.0033 Tonne.

Carriage of tiles/ cement L.S. 30.00

Labour :
Mason -1st class Each 0.77 311.5 239.86
Beldar Each 0.77 262.5 202.13
Sundries L.S. 10.00

Total : 852.92
Add 1.5% for water charges : 11.96
864.88
Add 10% for contractor profit and 5% over head charges 121.43
except cement mortar : 986.31

Say Rs. 986.3 /- only.

Executive Engineer,
IPHDivision No.II
Kullu at Bhunter
Analysis of Rate
15 mm cement plaster in single coat on rough side of brick/stone masonry for interior plastering up to
floor two level including arrises, internal rounded angles, chamfers and/or rounded angles not
exceeding 80mm in girth and finished even and smooth .
Detail of cost for 10 Sqm.
S.No. Desciption Unit Quantity Rate Amount
In cement mortar 1:3
Material
Cement mortar 1:3
(1cement:3sand) Cum. 0.172 3688.48 634.42
Labour :
Mason II nd class Each 0.83 311.5 258.55
Beldar Each 0.83 262.5 217.88
Bhishti Each 0.98 262.5 257.25
Sundries( Scaffolding etc.) L.S. 10.0
1378.1
Add 1.5% water charges 11.16
1389.26
Add 10% CP & 5% O.H. Charges except cement mortar : 113.23
Cost of 10 Sqm. 1502.49
In cement mortar 1:4 Cost of 1 Sqm. 150.2
Material
Cement mortar 1:4
(1cement:4sand) Cum. 0.172 3035.39 522.09
Labour :
Mason II nd class Each 0.83 311.5 258.55
Beldar Each 0.83 262.5 217.88
Bhishti Each 0.98 262.5 257.25
Sundries( Scaffolding etc.) L.S. 10.0
1265.77
Add 1.5% water charges 11.16
1276.93
Add 10% CP & 5% O.H. Charges except cement mortar : 113.23
Cost of 10 Sqm. 1390.16
In cement mortar 1:6 Cost of 1 Sqm. 139.0
Material
Cement mortar 1:6
(1cement:6sand) Cum. 0.172 2382.31 409.76
Labour :
Mason II nd class Each 0.83 311.5 258.55
Beldar Each 0.83 262.5 217.88
Bhishti Each 0.98 262.5 257.25
Sundries( Scaffolding etc.) L.S. 10.0
1153.44
Add 1.5% water charges 11.16
1164.6
Add 10% CP & 5% O.H. Charges except cement mortar : 113.23
Cost of 10 Sqm. 1277.83
Cost of 1 Sqm. 127.78

Executive Engineer,
IPHDivision No.II
Kullu at Bhunter
Analysis of Rate
15 mm cement plaster in single coat on fair side f brick/stone masonry for interior plastering up to
floor two level including arrises, internal rounded angles, chamfers and/or rounded angles not
exceeding 80mm in girth and finished even and smooth .
Detail of cost for 10 Sqm.
S.No. Desciption Unit Quantity Rate Amount
In cement mortar 1:3
Material
Cement mortar 1:3
(1cement:3sand) Cum. 0.165 3688.48 608.6
Labour :
Mason II nd class Each 0.80 311.5 249.2
Beldar Each 0.80 262.5 210.00
Bhishti Each 0.98 262.5 257.25
Sundries( Scaffolding etc.) L.S. 10.0
1335.05
Add 1.5% water charges 10.9
1345.95
Add 10% CP & 5% O.H. Charges except cement mortar : 110.6
Cost of 10 Sqm. 1456.55
In cement mortar 1:4 Cost of 1 Sqm. 145.7
Material
Cement mortar 1:4
(1cement:4sand) Cum. 0.165 3035.39 500.84
Labour :
Mason II nd class Each 0.80 311.5 249.2
Beldar Each 0.80 262.5 210.00
Bhishti Each 0.98 262.5 257.25
Sundries( Scaffolding etc.) L.S. 10.0
1227.29
Add 1.5% water charges 10.9
1238.19
Add 10% CP & 5% O.H. Charges except cement mortar : 110.6
Cost of 10 Sqm. 1348.79
In cement mortar 1:6 Cost of 1 Sqm. 134.9
Material
Cement mortar 1:6
(1cement:6sand) Cum. 0.165 2382.31 393.08
Labour :
Mason II nd class Each 0.80 311.5 249.2
Beldar Each 0.80 262.5 210.00
Bhishti Each 0.98 262.5 257.25
Sundries( Scaffolding etc.) L.S. 10.0
1119.53
Add 1.5% water charges 10.9
1130.43
Add 10% CP & 5% O.H. Charges except cement mortar : 110.6
Cost of 10 Sqm. 1241.03
Cost of 1 Sqm. 124.1

Executive Engineer,
IPHDivision No.II
Kullu at Bhunter
Analysis of Rate
15 mm cement plaster in two coats backing coat 15mm & finishing coat 5mm on fair side of
brick/stone masonry for interior plastering up to floor two level including arrises,nternal rounded angles,
I/c chamfers and/or rounded angles not exceeding 80mm in girth and finished even and smooth .

Detail of cost for 10 Sqm.


S.No. Desciption Unit Quantity Rate Amount
In cement mortar 1:3
Material
Cement mortar 1:3
(1cement:3sand) Cum. 0.165 3688.48 608.6
Labour :
Mason II nd class Each 1.30 311.5 404.95
Beldar Each 1.30 262.5 341.25
Bhishti Each 1.48 262.5 388.50
Sundries( Scaffolding etc.) L.S. 10.0
1753.3
Add 1.5% water charges 17.17
1770.47
Add 10% CP & 5% O.H. Charges except cement mortar : 174.28
Cost of 10 Sqm. 1944.75
In cement mortar 1:4 Cost of 1 Sqm. 194.48
Material
Cement mortar 1:4
(1cement:4sand) Cum. 0.165 3035.39 500.84
Labour :
Mason II nd class Each 1.30 311.5 404.95
Beldar Each 1.30 262.5 341.25
Bhishti Each 1.48 262.5 388.50
Sundries( Scaffolding etc.) L.S. 10.0
1645.54
Add 1.5% water charges 17.17
1662.71
Add 10% CP & 5% O.H. Charges except cement mortar : 174.28
Cost of 10 Sqm. 1836.99
In cement mortar 1:6 Cost of 1 Sqm. 183.7
Material
Cement mortar 1:6
(1cement:6sand) Cum. 0.165 2382.31 393.08
Labour :
Mason II nd class Each 1.30 311.5 404.95
Beldar Each 1.30 262.5 341.25
Bhishti Each 1.48 262.5 388.50
Sundries( Scaffolding etc.) L.S. 10.0
1537.78
Add 1.5% water charges 17.17
1554.95
Add 10% CP & 5% O.H. Charges except cement mortar : 174.28
Cost of 10 Sqm. 1729.23
Cost of 1 Sqm. 172.92

Executive Engineer,
IPHDivision No.II
Kullu at Bhunter
Analysis of Rate
Providing wood work in frames of doors, windows,clerestory windows and other frames wrought ,framed &
fixed in position :

Detail of cost for a chowkhat of a door 206.75x117.5cm.


S.No. Desciption Unit Quantity Rate Amount

MATERIAL :
2st class deodar wood : Cum. 0.038 50000 1900
Carriage :
3.00 Km.By mechanical transport Cum. 0.038 193.71 7.36
0 Km.By head load Cum. 0.038 0.00 0
Labour :
Carpenter Ist class Each 0.4 311.5 124.6
Beldar Each 0.2 262.5 52.5
Mason-II nd class Each 0.02 311.5 6.23

2090.69
Add 10% C.P. & 5% O.H. Charges : 313.6
Cost of 0.038 cum : 2404.29
Cost of 1 cum : 63271
Say Rs. 63271.0 /- only.

Executive Engineer,
IPHDivision No.II
Kullu at Bhunter
Analysis of Rate
P/F panelled glazed or panelled and glazed shutters for doors, windows and clerestory windows including
black enamelled iron butt hinges with necessary screws etc. complete.
40mm thick 2nd class Deodar wood :
Detail of cost for 200x108 cm. = 2.16 Sqm.
S.No. Desciption Unit Quantity Rate Amount

MATERIAL :
2nd class deodar wood : Cum. 0.076 55000 4180
Glasses ( 2mm to 3mm thick) Sqm. 0.99 280.00 277.2
Iron Hinges 100x58x1.90mm 10 Nos. 6 80 48
Iron hinges 50x37x1.5mm 10 Nos. 2 50 10
Screws 40mm 100 Nos. 48 35 16.8

Screws 20mm 100 Nos. 8 35 2.8

Carriage of wood :
3.00 Km.By mechanical transport Cum 0.076 193.71 14.72
0 Km.By head load Cum 0.076 0.00 0

Labour :
Carpenter Ist class Each 3.02 311.5 940.73
Beldar Each 0.86 262.5 225.75
Sundries : LS 50

5766
Add 10% C.P. & 5% O.H. Charges : 864.9
Cost of 2.16 Sqm. 6630.9
Cost of 1 Sqm. 3069.86
Say Rs. 3069.86 /- only.

Executive Engineer,
IPHDivision No.II
Kullu at Bhunter
b Analysis of Rate
P/F wire gauge shutters using galvanised M.S. wire gauge of I.S. gauge designation 85 G. with wire
of dia 0.56mm for doors, windows and clerestory windows including bright finished black enamelled iron hinges
with necessary screws :40mm thick 2nd class Deodar wood :
Detail of cost for 200x108 cm. = 2.16 Sqm.
S.No. Desciption Unit Quantity Rate Amount

MATERIAL :
2nd class deodar wood : Cum. 0.057 55000 3135
Wire gauge Sqm. 1.41 165.00 232.65
Iron Hinges 100x58x1.90mm 10 Nos. 6 70 42
Iron hinges 50x37x1.5mm 10 Nos. 2 55 11
Screws 40mm 100 Nos. 48 35 16.8
Screws 20mm 100 Nos. 8 25 2

Carriage of wood :
3.00 Km.By mechanical transport Cum 0.057 193.71 11.04
0 Km.By head load Cum 0.057 0.00 0

Labour :
Carpenter Ist class Each 0.75 311.5 233.63
Carpenter II class Each 0.75 311.5 233.63
Beldar Each 0.57 262.5 149.63
Sundries : LS 20

4087.38
Add 10% C.P. & 5% O.H. Charges : 613.11
Cost of 2.16 Sqm. 4700.49
Cost of 1 Sqm. 2176.15
Say Rs. 2176.15 /- only.

Executive Engineer,
IPHDivision No.II
Kullu at Bhunter
Analysis of Rate
P/F 12mm thick 150mm wide pelmet with 25mm diametre wooden curtain rods and brackets including fixing
25x3mm MS flat at 10cm. Long and plugs etc. complete.
1std class deodar wood :
Detail of cost for a pelmet 2 meter long.
S.No. Desciption Unit Quantity Rate Amount

MATERIAL :
1st class deodar wood : Cum. 0.00847 50000 423.5

Wooden plugs I/c cutting masonry; Each 2 15.00 30

MS flat 25x3mm and 10cm. Long LS 10

Carriage of wood :
3.00 Km.By mechanical transport Cum 0.00847 193.71 1.64
0 Km.By head load Cum 0.00847 0.00 0

Labour :
Carpenter Ist class Each 0.2 311.5 62.3
Carpenter II class Each 0.12 311.5 37.38
Beldar Each 0.2 262.5 52.5
Sundries : LS 15

632.32
Add 10% C.P. & 5% O.H. Charges : 94.85
Cost of 2.00 m 727.17
Cost of 1 m 363.59
Say Rs. 363.59 /- only.

Executive Engineer,
IPHDivision No.II
Kullu at Bhunter
Analysis of Rate
Providing and fixing MS grills of required pattern in wooden frames of windows etc. with MS flats, square or
rounded bars with round headed bolts and nuts or by screrws.

Plain grill, Detail of cost for grill 90x120cm= 1.08 Sqm.

S.No. Description of items Unit Qty. Rate Amount

1 Materials :
(a) MS bars 16mm dia : Qtl. 0.165 4600 759

(b) MS flats : Qtl. 0.04 4500 180

2 Carriage :
25.00 Km.By mechanical transport Tonne 0.0205 382.17 7.83
0 Km.By head load Tonne 0.0205 0.00 0

3 Labour :

Black smith Ist class Each 0.86 311.5 267.89

Beldar Each 1.1 262.5 288.75

1503.47
Add 10% CP & 5% O.H. Charges : 225.52
Cost for 18.540 Kg. 1728.99
Cost for 1 Kg. 93.26

Say Rs. 93.3 per kg.

Executive Engineer,
IPHDivision No.II
Kullu at Bhunter
Analysis of Rate
Providing 40x3mm flat iron hold fast 40cm. Long including fixing to frame with 10mm diameter bolts, nuts and
wooden plugs and embedding in cement concrete block 30x10x15cm. ( 1 cement: 3 sand:6 graded stone
aggregate,20mm nominal size)
Details of cost for one hold fast.

S.No. Description of items Unit Qty. Rate Amount

MATERIAL :
MS flat 40x3mm, 40cm. Long Qtl. 0.004 4500 18.00

Cement concrete 1:3:6 Cum 0.005 3140.02 15.70

Bolts and nuts . LS 3.00

Carriage of MS flat & nut bolts etc. LS 2.00

Labour :
Black smith Ist class Each 0.032 311.5 9.97
Mason Ist class Each 0.032 311.5 9.97
Beldar Each 0.003 262.5 0.79

59.43
Add 10% CP & 5% O.H. Charges except CC: 6.56
65.99

Say Rs. 66.00

Executive Engineer,
IPHDivision No.II
Kullu at Bhunter
Analysis of Rate
Providing plinth protection 50mm thick in cement concrete 1:3:6( 1cement :3 sand:6 graded stone aggregate,
20mm nominal size).
Detail of cost for 10Sqm.

S.No. Description Unit Quantity Rate Amount

MATERIAL:
1 CC 1:3:6 cum 0.5 3140.02 1570.01

Total : Cost for 10 Sqm 1570.01

Cost for 1 Sqm. 157.00

Providing under layer for plinth protection of 75mm thick( unconsolidated) bed dry brick/stone aggregate 40mm
nominal size well rammed and consolidated and grouted with fine sand including preperation of ground.
Detail of cost for 10Sqm.

S.No. Description Unit Quantity Rate Amount

MATERIAL :

Brick aggregate 40mm nominal size; Cum 0.75 440 330.00

Sand : Cum 0.06 375 22.50

CARRIAGE
Carriage of agg above 40mm
0.00 Km.By mechanical transport Cum 0.75 0.00 0.00
0.5 Km.By head load Cum 0.75 443.11 332.33
Carriage of sand
7.00 Km.By mechanical transport Cum 0.06 277.09 16.63
0 Km.By head load Cum 0.06 0.00 0.00

Labour :
Labour for laying ,ramming &
consolidation :
Beldar : Each 3.25 262.5 853.13

1554.59
Add 1.5% for water charges : 23.32
1577.91
Add 10% CP & 5% OH charges : 236.69
Cost of 10Sqm. 1814.60
Cost of 1 Sqm. 181.46

Say Rs. 181.5 /- only

Executive Engineer,
IPHDivision No.II
Kullu at Bhunter
Analysis of Rate
Providing and laying 20cm. Thick composit stone masonry with stone facing of chisel dressed stones one
line dressed in cement mortar 1:6 (1cement :6sand) and concrete backing with cement concrete 1:3:6
(1cement:3sand:6graded stone aggregate,20mm nominal size)on inner face of walls including centring ,
shuttering and propping complete up to floor two level.

Detail of cost for 1 Square metre.


S.No. Description Unit Quantity Rate Amount
A MATERIAL :
1 S/R masonry coursed with hard stone of
approved quality in superstructure in Cum 0.15 5314.49 797.17
CM 1:6

2 CC 1:3:6 in walls : Cum 0.05 3185.35 159.27

3 Providing form work with steel plates


in vertical surfaces : Sqm 1.00 218.6 218.64

B Labour :
Extra labour for two line dressing :
Mason 1st class Each 0.54 311.50 168.21
Beldar Each 0.13 262.50 34.13
Blacksmith 2nd class Each 0.06 311.5 18.69
Extra labour for super structure : 405.79
Mason II nd class Each 0.25 311.5 77.88
Beldar Each 0.35 262.50 91.88
Scaffolding LS 15.00

1580.87
Add 10% CP & 5% O.H. Charges on Rs. 405.79 60.87
1641.74

Say Rs. 1641.74 /- only.

Executive Engineer,
IPHDivision No.II
Kullu at Bhunter
Analysis of rate

Filling in plinth with sand under floors including watering, ramming, consolidating and dressing complete.
Detail of cost for 10cum
S.No. Description of items Unit Quantity Rate Amount

MATERIAL :

Sand Cum 10 375 3750

Carriage :
7.00 Km.By mechanical transport Cum 10 277.09 2770.9
0 Km.By head load Cum 10 0.00 0

Labour :
Beldar Each 2.28 262.5 598.5
Bhishti Each 0.48 262.5 126

7245.4
Add 1.5% for water charges : 108.68
7354.08
Add 10% for C.P. & 5% for overhead charges : 1103.11
Cost of 10 Cum. 8457.19
Cost of 1 cum 845.72

Say Rs 845.72 /- only.

Executive Engineer,
IPHDivision No.II
Kullu at Bhunter
Boulder filling dry hand packed tightly under floors
Detail of cost for 1 cum
S.No. Description of items Unit Quantity Rate Amount

MATERIAL :

Stone Cum 1.00 300.00 300.00

Carriage :
0.00 Km.By mechanical transport Cum 1.00 0.00 0
0.5 Km.By head load Cum 1.00 409.84 409.84

Labour :
Beldar Each 0.80 262.50 210.00

919.84

Add 10% for C.P. & 5% for overhead charges : 137.98


Cost of 1 Cum. 1057.82

Say Rs. 1058.0 /- only.

Executive Engineer,
IPHDivision No.II
Kullu at Bhunter
Analysis of Rate
Providing form work of ordinary timber plankings so as to give a rough finish including centring, shuttering, strutting
and propping etc. height of propping and centring below supporting floor to ceiling not exceeding 4 metres and removal
of the same for insitu reinforced concrete and plain concrete work in :
Flat surfaces such as soffits of suspended floors, roofs landing and the like : Floors etc. up to 200mm in thickness:

Detail of cost for a room 3 x 3 = 9 Sqm and height 3.5 metres:


S.No. Description of items Unit Quantity Rate Amount
MATERIAL
Soft wood centring :
Battens 75mmx100mm( 2nd class Kail wood
or equivalent soft wood )
4x3x.075x10=0.0090 cum.
Add 5% wastage : 0.004 cum Cum 0.094 31240 2936.56
Total : 0.094 cum

Planks 38mm thick


3mx3mx0.038m= 0.342 cum
Add wastage 5% = 0.017 cum Cum 0.359 29728 10672.35
Total : 0.359 cum
Ballies 125mm dia
Vertical 16x 3.5m= 56.00 m
Braces 12x1.2 m = 14.4 m
Total : 70.40 m
5% wastage : 3.5 m Metre 73.9 110 8129.00
Total : 73.90 m

Carriage of timber :
3.00 Km.By mechanical transport Cum 1.363 193.71 264.03
0 Km.By head load Cum 1.363 0.00 0.00
22001.94
Assuming that timber shall become unserviceable
after being used 16 times . Hence cost for
using once : Each 1/16 22001.94 1375.12
Add 5% wastage for usage repeatedly : 1100.10
Total : 2475.22
Labour :
Carpenter 2nd class : Each 2.52 311.5 784.98
Beldar : Each 2.52 262.5 661.50
Sundries : LS 25.00
Total : 3946.70
Add 10% CP & 5% O.H. Charges : 592.01
Cost for 9 Sqm. 4538.71
Cost for 1 Sqm : 504.3

Executive Engineer,
IPHDivision No.II
Kullu at Bhunter
Analysis of Rate
Providing form work of ordinary timber plankings so as to give a rough finish including centring, shuttering, strutting
and propping etc. height of propping and centring below supporting floor to ceiling not exceeding 4 metres and removal
of the same for insitu reinforced concrete and plain concrete work in :
Vertical surfaces such as walls ( any thickness) :
Detail of cost for a parapet wall 15m long & 1m high
Surface area : 2x15x1m=30 Sqm.
S.No. Description of items Unit Quantity Rate Amount
MATERIAL

Planks 38mm thick


2x15x1= 30 Sqm
Add wastage 5% = 1.50Sqm Cum 1.197 29728 35584.42
Total : 31.50Sqm
(31.50Sqm x 0.038)= 1.197 Cum

Battens 75mmx50mm

2x13x.075x0.05=0.098 cum.
Add 5% wastage : 0.004 cum Cum 0.102 31240 3186.48
Total : 0.102 cum

Ballies 125mm dia


13x 1.5m= 19.50 m
13 x 4.5 m = 58.5 m
Total : 78.00 m
5% wastage : 3.9 m Metre 81.9 110 9009.00
Total : 81.90 m

Carriage of timber :
3.00 Km.By mechanical transport Cum 2.304 193.71 446.31
0 Km.By head load Cum 2.304 0.00 0.00
48226.21
Assuming that timber shall become unserviceable
after being used 16 times . Hence cost for
using once : Each 1/16 48226.21 3014.14
Add 5% wastage for usage repeatedly : 2411.31
Total : 5425.45
Labour :
Carpenter 2nd class : Each 7.50 311.5 2336.25
Beldar : Each 6.00 262.5 1575.00
Sundries : LS 25.00
Total : 9361.70
Add 10% CP & 5% O.H. Charges : 1404.26
Cost for 30 Sqm. 10765.96
Cost for 1 Sqm : 358.87
Say Rs 358.9 /-only

Executive Engineer,
IPHDivision No.II
Kullu at Bhunter
Analysis of Rate
Providing form work of ordinary timber plankings so as to give a rough finish including centring, shuttering, strutting
and propping etc. height of propping and centring below supporting floor to ceiling not exceeding 4 metres and removal
of the same for insitu reinforced concrete and plain concrete work in :
Sloping or battering surfaces including folded plates.Where inclination to horizintal plan does not exceed 30degree
requiring shuttering only on the under side.
Detail of cost for a room3x3m,the slab having an inclination of 15%. Suerficial area of slab3x3.11= 9.33 Sqm
Minimum height= 3.5m
S.No. Description of items Unit Quantity Rate Amount
MATERIAL
Soft wood centring :
Battens 75mmx100mm( 2nd class Kail wood
or equivalent soft wood )
4x3.11x.075x10=0.0093 cum.
Add 5% wastage : 0.004 cum Cum 0.097 31240 3030.28
Total : 0.097 cum

Planks 38mm thick


3mx3mx11x0.038m= 0.355 cum
Add wastage 5% = 0.018 cum Cum 0.373 29728 11088.54
Total : 0.373 cum
Ballies 125mm dia
Vertical 16x 3.902m= 62.43 m
Braces 12x1.2 m = 14.4 m
5% wastage : 3.84m
Total : 80.67 m Metre 81 110 8910.00
Say : 81m

Carriage of timber :
3.00 Km.By mechanical transport Cum 1.464 193.71 283.59
0 Km.By head load Cum 1.464 0.00 0.00
23312.41
Assuming that timber shall become unserviceable
after being used 16 times . Hence cost for
using once : Each 1/16 23312.41 1457.03
Add 5% wastage for usage repeatedly : 1165.62
Total : 2622.65
Labour :
Carpenter 2nd class : Each 3.15 311.5 981.23
Beldar : Each 2.8 262.5 735.00
Sundries : LS 25.00
Total : 4363.88
Add 10% CP & 5% O.H. Charges : 654.58
Cost for 9.33 Sqm. 5018.46
Cost for 1 Sqm : 537.88

Executive Engineer,
IPHDivision No.II
Kullu at Bhunter
Analysis of Rate
Providing form work of ordinary timber plankings so as to give a rough finish including centring, shuttering, strutting
and propping etc. height of propping and centring below supporting floor to ceiling not exceeding 4 metres and removal
of the same for insitu reinforced concrete and plain concrete work in :
i Arches exceeding 6 mtr. Span.
Detail of cost for 33.31 Sqm.

S.No. Description of items Unit Quantity Rate Amount


MATERIAL
As per HPSR 1999 (0801050200) Cum 7.458 29728 221711.42
Fitting: 3 way strap
As per HPSR 1999 (0801050200) Qtl. 0.7 4200 2940.00
Bolts 16mm dia 255mm long
As per HPSR 1999 (0801050200) Qtl. 0.64 4500 2880.00
Carriage of timber :
3.00 Km.By mechanical transport Cum 7.458 193.71 1444.69
0 Km.By head load Cum 7.458 0.00 0.00
Carriage of Steel:
25.00 Km.By mechanical transport tone 0.134 382.17 51.21
0 Km.By head load tone 0.134 0.00 0.00
229027.32
Assuming that timber shall become unserviceable
after being used 8 times . Hence cost for
using once : Each 1/8 229027.32 28628.42
Add 5% wastage for usage repeatedly : 11451.37
Total : 40079.79
Labour :
Carpenter 2nd class : Each 28.00 311.5 8722.00
Beldar : Each 24.00 262.5 6300.00
Sundries : LS 50.00
Total : 55151.79
Add 10% CP & 5% O.H. Charges : 8272.77
Cost for 33.310 Sqm. 63424.56
Cost for 1 Sqm : 1904.07

Executive Engineer,
IPHDivision No.II
Kullu at Bhunter
Analysis of Rate
Providing form work of ordinary timber plankings so as to give a rough finish including centring, shuttering, strutting
and propping etc. height of propping and centring below supporting floor to ceiling not exceeding 4 metres and removal
of the same for insitu reinforced concrete and plain concrete work in :
i Arches Upto 6 mtr. Span.
Detail of cost for 20.37 Sqm.
S.No. Description of items Unit Quantity Rate Amount
1 MATERIAL
1 (i) Soft wood centring :
As per HPSR 1999 (0801050100) Cum 1.79 31240 55919.60
1 (ii) Planks 38mm thick
As per HPSR 1999 (0801050100)
Cum 0.929 29728 27617.31
1 (iii) Ballies 125mm Dia.
As per HPSR 1999 (0801050100) Metre 123.5 110 13585.00
2 Carriage of timber :
2 (i) 3.00 Km.By mechanical transport Cum 4.24 193.71 821.33
2 (ii) 0 Km.By head load Cum 4.24 0.00 0.00
97943.24
Assuming that timber shall become unserviceable
after being used 16 times . Hence cost for
using once : Each 1/8 97943.24 12242.91
Add 5% wastage for usage repeatedly : 4897.16
Total : 17140.07
3 Labour :
Carpenter 2nd class : Each 16 311.5 4984.00
Beldar : Each 13 262.5 3412.50
Sundries : LS 50.00
Total : 25586.57

Add 10% CP & 5% O.H. Charges : 3837.99


Cost for 20.37 Sqm. 29424.56
Cost for 1 Sqm : 1444.5

Executive Engineer,
IPHDivision No.II
Kullu at Bhunter
Analysis of Rate
Extra for providing form work with sheathing of steel sheets For Flat Surfaces

Detail of cost for 10 Sqm.


S.No. Description of items Unit Quantity Rate Amount
MATERIAL
Batten for extra frame work
2nd class Kail wood Cum 0.139 31240 4342.36
GI sheet 1mm thick Qtl. 0.826 4500 3717.00
Carriage of timber :
3.00 Km.By mechanical transport Cum 0.139 193.71 26.93
0 Km.By head load Cum 0.139 0.00 0.00
Carriage of Steel:
25.00 Km.By mechanical transport tone 0.0826 382.17 31.57
0 Km.By head load tone 0.0826 0.00 0.00
8117.86
Assuming that timber shall become unserviceable
after being used 16 times . Hence cost for
using once : Each 1/16 8117.86 507.37
Total : 507.37
Labour :
Carpenter 2nd class : Each 0.60 311.5 186.90
Beldar : Each 0.60 262.5 157.50
Sundries : LS 20.00
Total : 871.77
Add 10% CP & 5% O.H. Charges : 130.77
Cost for 10 Sqm. 1002.54
Cost for 1 Sqm : 100.25

Executive Engineer,
IPHDivision No.II
Kullu at Bhunter
Analysis of Rate
Extra for providing form work with sheathing of steel sheets For Archees

Detail of cost for 20.37 Sq


S.No. Description of items Unit Quantity Rate Amount
MATERIAL
GI sheet 1mm thick Qtl. 1.68 4500 7560.00
Carriage of Steel:
25.00 Km.By mechanical transport tone 0.1680 382.17 64.20
0 Km.By head load tone 0.168 0.00 0.00
7624.20
Assuming that timber shall become unserviceable
after being used 16 times . Hence cost for
using once : Each 1/16 7624.20 476.51
Total : 476.51
Labour :
Carpenter 2nd class : Each 2.50 311.5 778.75
Beldar : Each 2.50 262.5 656.25
Sundries : LS 30.00
Total : 1941.51
Add 10% CP & 5% O.H. Charges : 291.23
Cost for 20.37 Sqm 2232.74
Cost for 1 Sqm : 109.61

Executive Engineer,
IPHDivision No.II
Kullu at Bhunter
Conversion of timber

Detail of cost for 1 cum


S.No. Description of items Unit Quantity Rate Amount
1 KAIL WOOD
MATERIAL :
Second class Kail wood
In sleepers to Planks 1 Cum 1.18 27930.00 32957.40
Add waistage @18% 0.18
Total 1.18
Sawing Charges Of Wood: Cum 1.18 850.00 1003.00
Total: 33960
2 KAIL WOOD
MATERIAL :
Second class Kail wood
In sleepers to Scantling 1 Cum 1.15 27930.00 32119.50
Add waistage @15% 0.15
Total 1.15
Sawing Charges Of Wood: Cum 1.15 600.00 690.00
Total: 32810
3 DEODAR WOOD
MATERIAL :
Second class Kail wood
In sleepers to Planks 1 Cum 1.18 28760.00 33936.80
Add waistage @18% 0.18
Total 1.18
Sawing Charges Of Wood: Cum 1.18 850.00 1003.00
Total: 34940
4 DEODAR WOOD
MATERIAL :
Second class Kail wood
In sleepers to Scantling 1 Cum 1.15 28760.00 33074.00
Add waistage @15% 0.15
Total 1.15
Sawing Charges Of Wood: Cum 1.15 600.00 690.00
Total: 33764

Executive Engineer,
IPHDivision No.II
Kullu at Bhunter
Analysis of Rate
Providing form work of ordinary timber plankings so as to give a rough finish including centring, shuttering, strutting
and propping etc. height of propping and centring below supporting floor to ceiling not exceeding 4 metres and removal
of the same for insitu reinforced concrete and plain concrete work in :
Sloping or battering surfaces including folded plates .Where inclination to horizintal plan does not exceed 30degree where shutering
may be provided both on under side and upper side if required only the area of under side shall be measured for payment).

Detail of cost forcovering a room 4mx3m,folded plates with inclination of 45%. Superficial area of slab 4x3x1x1.76=
21.12Sqm. Soft wood centering of kail wood or equivalent local wood.

S.No. Description of items Unit Quantity Rate Amount


MATERIAL
Soft wood centring :
Battens 75mmx100mm( 2nd class Kail wood
or equivalent soft wood )
Deyail as per HPSR 1999(08010402
Cum 0.37 31240 11558.80
Planks 38mm thick
Deyail as per HPSR 1999(08010402
Cum 1.341 29728 39865.25
Ballies 125mm dia
Deyail as per HPSR 1999(08010402
Metre 171 110 18810.00
Carriage of timber :
3.00 Km.By mechanical transport Cum 3.81 193.71 738.04
0 Km.By head load Cum 3.81 0.00 0.00
70972.09
Assuming that timber shall become unserviceable
after being used 16 times . Hence cost for
using once : Each 1/16 70972.09 4435.76
Add 5% wastage for usage repeatedly : 3548.60
Total : 7984.36
Labour :
Carpenter 2nd class : Each 12 311.5 3738.00
Beldar : Each 10.5 262.5 2756.25
Sundries : LS 25.00
Total : 14503.61
Add 10% CP & 5% O.H. Charges : 2175.54
Cost for 21.125 Sqm. 16679.15
Cost for 1 Sqm : 789.55
Add. Extra for with sheathing of steel sheats 44.4
833.95
Add. Average for extra lifting/ providing of = @15% 125.09
shuteringat more than 15mtr. Height from G.L. 959.04
Say Rs. 692.05 per Sqmt.

Executive Engineer,
IPHDivision No.II
Kullu at Bhunter
Analysis of Rate
Providing wood work in trusses,purlins,rafters posts,post plates,wall plates and the like wrought framed,hoisted and fixed in position

Detail of cost for 0.042 Cum


S.No. Desciption Unit Quantity Rate Amount

MATERIAL :
2nd class deodar wood : Cum. 0.044 55000 2420
Carriage :
3.00 Km.By mechanical transport Cum. 0.044 193.71 8.52
0 Km.By head load Cum. 0.044 0.00 0
Labour :
Carpenter Ist class Each 0.38 311.5 118.37
Beldar Each 0.46 262.5 120.75
Mason-II nd class Each 0.02 311.5 6.23

2673.87
Add 10% C.P. & 5% O.H. Charges : 401.08
Cost of 0.042 cum : 3074.95
Cost of 1 cum : 73213
Say Rs. 73213.0 /- only.

Executive Engineer,
IPHDivision No.II
Kullu at Bhunter
Analysis of Rate
Providing form work of ordinary timber plankings so as to give a rough finish including centring, shuttering, strutting
and propping etc. height of propping and centring below supporting floor to ceiling not exceeding 4 metres and removal
of the same for insitu reinforced concrete and plain concrete work in :
Edges of slabs and breaks in floors and walls: under 20 cm wide.Detail of cost 12 meter
S.No. Description of items Unit Quantity Rate Amount
Materials
Planks 30 mm thick 2nd class
Kail wood CUM 0.057 29728 1694.5
Battens 75% CUM 0.131 31240 4092.44

Carriage
3.00 Km.By mechanical transport Cum 0.188 193.71 36.42
0 Km.By head load Cum 0.188 0.00 0.00
5823.36
Assuming that timber shall become unserviceable
after being used 16 times . Hence cost for
using once : Each 1/16 5823.36 363.96
Add 5% wastage for usage repeatedly : 291.17

Labour :
Carpenter 2nd class : Each 0.75 311.5 233.63
Beldar : Each 0.56 262.5 147.00
Sundries : LS 15.00
1050.76
Add 10% CP & 5% O.H. Charges : 0.15 157.61
Cost for 12 Rmt. 1208.37
Cost per mt. 12 100.7
Analysis of Rate
Providing form work of ordinary timber plankings so as to give a rough finish including centring, shuttering, strutting
and propping etc. height of propping and centring below supporting floor to ceiling not exceeding 4 metres and removal
of the same for insitu reinforced concrete and plain concrete work in :
Beams,cantilivers,girders and lintels.
Sides and Soffits of beams,beam,haunchings cantiliver girders bressumers and lintels not exceeding 1 mt.in depth.
DETAIL OF COST FOR 8.40 Sqm
S.No. Description of items Unit Quantity Rate Amount
Materials
Planks 30 mm thick 2nd class
Kail wood CUM 0.369 29728 10969.63
Ballies 125mm dia
Deyail as per HPSR 1999(08010402
Metre 22.05 100 2205.00
Triangular Ballies bracing for supports 80 mm dia for supports
Metre 12.6 100 1260.00
Carriage
3.00 Km.By mechanical transport Cum 0.702 193.71 135.98
0 Km.By head load Cum 0.702 0.00 0.00
14570.61
Assuming that timber shall become unserviceable
after being used 16 times . Hence cost for
using once : Each 1/16 14570.61 910.66
Add 5% wastage for usage repeatedly : 728.53
Labour :
Carpenter 2nd class : Each 2.86 311.5 890.89
Beldar : Each 2.86 262.5 750.75
Sundries : LS 30.00
3310.83
Add 10 % CP & 5% OH 0.15 496.62
Cost for 8.40 Sqm 3807.45
Cost per Sqm 8.4 453.27
Providing and fixing anodized aluminium sliding door bolt anodized colour and shade with bolts
and nuts
screws etc complete.
Details of cost for 10 Nos.
Materials
i) 300x16 mm 10 Nos 150 Each 1500
Steel Screws 25 mm 100 16 Nos 18 100 2.88

Carriage
Carriage of materials LS 4
Labour
Carpenter 1st class 0.5 Nos 311.5 Each 155.75
1662.63
Add 10%CP5%OHCharges 249.39
Cost for 10 Nos 1912.02
Cost per Nos 10 191.2
Providing and fixing anodized aluminium sliding door bolt anodized colour and shade with bolts
and nuts

Details of cost for 10 Nos.


Materials
ii) 250x16 mm 10 Nos 95 Each 950
Steel Screws 25 mm 100 16 Nos 20 100 3.2
Carriage
Carriage of materials LS 4
Labour
Carpenter 1st class 0.5 Nos 311.5 Each 155.75
1112.95
Add 10%CP5%OHCharges 166.94
Cost for 10 Nos 1279.89
Cost per Nos 10 127.99
Providing and fixing aluminium tower bolts(barrel type) anodized trans parent or dyed to required
shade and colour with screws etc. complete.
Details of cost for 10 Nos.
Materials
Aluminium tower bolt (Barrel
type)
300x10 10 10 Nos 55 Each 55
Steel Screws 25 mm 100 80 Nos 30 100 24
Carriage
Carriage of materials LS 4
Labour
Carpenter 1st class 0.1 Nos 311.5 Each 31.15
114.15
Add 10%CP5%OHCharges 17.12
Cost for 10 Nos 131.27
Cost per Nos 10 13.13
Providing and fixing aluminium tower bolts(barrel type) anodized trans parent or dyed to required
shade and colour with screws etc. complete.

Details of cost for 10 Nos.


Materials

Aluminium tower bolt (Barrel


type)
250x10 10 10 Nos 50 Each 50

Steel Screws 25 mm 100 80 Nos 30 100 24


Carriage

Carriage of materials LS 4
Labour
Carpenter 1st class 0.1 Nos 311.5 Each 31.15

109.15
Add 10%CP5%OHCharges 16.37
Cost for 10 Nos 125.52
Cost per Nos 10 12.55
Providing and fixing aluminium tower bolts(barrel type) anodized trans parent or dyed to required
shade and colour with screws etc. complete.
Details of cost for 10 Nos.
Materials

Aluminium tower bolt (Barrel


type)
200x10 10 10 Nos 45 Each 45
Steel Screws 25 mm 100 80 Nos 30 100 24

Carriage
Carriage of materials LS 4

Labour
Carpenter 1st class 0.1 Nos 311.5 Each 31.15
104.15
Add 10%CP5%OHCharges 15.62
Cost for 10 Nos 119.77
Cost per Nos 10 11.98
Providing and fixing aluminium tower bolts(barrel type) anodized trans parent or dyed to required
shade and colour with screws etc. complete.
Details of cost for 10 Nos.
Materials

Aluminium tower bolt (Barrel


type)
150x10 10 10 Nos 40 Each 40
Steel Screws 25 mm 100 80 Nos 30 100 24

Carriage
Carriage of materials LS 4

Labour
Carpenter 1st class 0.1 Nos 311.5 Each 31.15
99.15
Add 10%CP5%OHCharges 14.87
Cost for 10 Nos 114.02
Cost per Nos 10 11.4
Providing and fixing aluminium tower bolts(barrel type) anodized trans parent or dyed to required
shade and colour with screws etc. complete.

Details of cost for 10 Nos.


Materials

Aluminium tower bolt (Barrel


type)
100x10 10 Nos 40 Each 400
Steel Screws 25 mm 100 80 Nos 15 100 12

Carriage
Carriage of materials LS 4

Labour
Carpenter 1st class 0.1 Nos 311.5 Each 31.15
447.15
Add 10%CP5%OHCharges 67.07
Cost for 10 Nos 514.22
Cost per Nos 10 51.42
Sar Rs. 51
Providing and fixing aluminium handles anodized transparent or dyed to required colour of shade
with necessary screws etc. complete
Detail of cost for 10 Nos.
Material

Aluminium handle anodized 10 10 Nos 85 85


transparent or dyed 125 mm

Anodised steel screw 25 mm 100 40 30 12


CARRIAGE
Carriage of materials 2
LABOUR .

Carpenter 1st class 0.06 Nos 311.5 18.69

117.69
Add 10% CP & 5% OH Charges 0.15 17.65
Cost for 10 Nos. 135.34

Cost Per 10 13.534


Providing and fixing aluminium handles anodized transparent or dyed to required colour of shade
with necessary screws etc. complete

Detail of cost for 10 Nos.


Material

Aluminium handle anodized 10 10 Nos 80 80


transparent or dyed 100 mm
Anodised steel screw 25 mm 100 40 25 10
CARRIAGE
Carriage of materials 2

LABOUR .

Carpenter 1st class 0.06 Nos 311.5 18.69

110.69
Add 10% CP & 5% OH Charges 0.15 16.6

Cost for 10 Nos 127.29


Cost per Nos 10 12.729
Providing and fixing aluminium handles anodized transparent or dyed to required colour of shade
with necessary screws etc. complete

Detail of cost for 10 Nos.


Material
Aluminium handle anodized 10 10 Nos 25 25
transparent or dyed 75 mm
Anodised steel screw 25 mm 100 40 18 7.2
CARRIAGE
Carriage of materials 2
LABOUR .
Carpenter 1st class 0.06 Nos 311.5 18.69

52.89
Add 10% CP & 5% OH Charges 0.15 7.93
Cost for 10 Nos 60.82
Cost per 10 6.082
CARRIAGE
By Mech.Tran. By Head Load
Km. Rate Km. Rate
25.00 382.17 0.0 0.00
7.00 277.09 0.0 0.00

0.00 0.00 0.5 443.11


7.00 277.09 0.0 0.00
7.00 277.09 0.0 0.00
0.00 0.00 0.5 409.84
0.00 0.00 1.0 831.81
0.00 0.00 1.0 831.81
3.00 484.28 0.0 0.00
25.00 382.17 0.0 0.00
25.00 382.17 0 0.00
25.00 382.17 0 0.00

25.00 382.17 0.0 0.00


25.00 382.17 0 0.00
3.00 193.71 0 0.00
3.00 193.71 0 0.00
3.00 193.71 0 0.00
3.00 193.71 0 0.00
3.00 193.71 0 0.00
25.00 382.17 0 0.00
ANALYSIS OF RATE

Providing & laying cement concrete 1:1½:3 (1 cement : 1½ Sand 3 graded stone aggregate
20 mm nominal size ) and curing complete excluding cost of form work & reinforcement for RCC
work in : walls (any thickness but not less than 0.10m thickness),attached pilasters , buttresses,
plinth & string courses etc.from top of foundation level up to floor two level :

Detail of cost for 1 Cum.

S.No. Desciption Unit Quantity Rate Amount

Material:-
Cement concrete 1:1.5:3 cum 1 3938.39 3938.39

Labour (Extra for Laying CC in RCC work) cum 1 114.17

Labour (Extra for lifting Material)

Beldar Each 1.7 81.67 138.84

Executive Engineer,
IPHDivision No.II
Kullu at Bhunter
Analysis of rate
Providing form work of steel sheets in : Chullah hoods,weather shades chhajjas corbels etc including edges.
under 20 cm wide.
Detail of cost for .954
S.No. Desciption Unit Quantity Rate Amount

Material :
MATERIAL :
Steel plates fixed with angle Sqm 1.04 2979.2 3086.48

Battens 2nd class Kail wood Cum 0.013 31240 406.12


Ballies 125 mm Meter 5.25 90 472.50
Carriage of timber.
3.00 Km.By mechanical transport Cum. 0.077 193.71 14.92
0 Km.By head load Cum. 0.077 0.00 0.00
Total: 3980.02
Assuming that steel plates will
become unserviceable after being used 100 times.
Hence cost for using once : Each 1/100 3086.48 30.86

Add 1 % for using repeatedly I/c repairs, removal


of dents, cleaning conc. Deposits & applying oil
and grease : 30.86

Assuming that timber shall become unserviceable


after being used 16 times . Hence cost for using
once : Each 1/16 893.54 55.85
Add 5 % wastage for using
repeatedly : 44.68
Total : 162.25
Labour :
For assembling erection &
dismentalling :
Carpenter II nd class : Each 0.30 311.5 93.45
Beldar Each 0.56 262.5 147.00
Sundries taking 10%of labour 24.05
Total : 426.75
Add 10 % C.P & 5 % O.H
charges : 63.87
Cost of .954Sqm = 490.62
514.28
Say Rs. = 514.3

Executive Engineer,
IPHDivision No.II
Kullu at Bhunter
0
ANALYSIS OF RATE
Brick work using common burnt clay building bricks in superstructure in cement mortar 1:6
( 1 cement : 3 Sand) 1st class bricks.
Detail of cost for 1.00 cum.
S.No. Desciption Unit Quantity Rate Amount

MATERIALS
1 1st class brick 1000 Nos 475 7000 3325
including unloading.
2 Cement mortar 1:3 cum 0.24 3688.48 885.24
4210.24
CARRIAGE
1 Carriage of bricks.
3.00 Km.By mechanical transport 1000 Nos 475 484.28 230.03
0.0 Km.By head load 1000 Nos 475 0.00 0
230.03
LABOUR
1 Mason Ist. Class. Each 0.5 311.5 155.75
2 Mason 2nd. Class Each 0.5 311.5 155.75
3 Beldar Each 1.8 262.5 472.5
4 Bhisti Each 0.2 262.5 52.5
Sundries L.S. 30
866.5

Total:- 5306.77
Add for water charges @1.5% 66.32
Total:- 5373.09
Add 10% contractor's profit & 5% over head charges 673.18
on all except mortar G.Total:- 6046.27

Cost per Cum. 6046

Executive Engineer,
IPHDivision No.II
Kullu at Bhunter
ANALYSIS OF RATE
Brick work using common burnt clay building bricks in Foundation & plinth in cement mortar 1:4
( 1 cement :4 Sand) 2nd class bricks.
Detail of cost for 1.00 cum.
S.No. Desciption Unit Quantity Rate Amount

MATERIALS
1 2nd class brick 1000 Nos 475 7000 3325
including unloading.
2 Cement mortar 1:4 cum 0.24 3035.39 728.49
4053.49
CARRIAGE
1 Carriage of bricks.
3.00 Km.By mechanical transport 1000 Nos 475 484.28 230.03
0 Km.By head load 1000 Nos 475 0.00 0

LABOUR
1 Mason Ist. Class. Each 0.5 311.5 155.75
2 Mason 2nd. Class Each 0.5 311.5 155.75
3 Beldar Each 1.8 262.5 472.5
4 Bhisti Each 0.2 262.5 52.5
Sundries L.S. 50
886.5

Total:- 5170.02
Add for water charges @1.5% 66.62
Total:- 5236.64
Add 10% contractor's profit & 5% over head charges 676.22
on all except mortar G.Total:- 5912.86

Foundation & plinth Cost per Cum. 5913


Extra for bricks in Super Structure above plinth level up to floor two level: (+) 170.96
Total;- 6084

Executive Engineer,
IPHDivision No.II
Kullu at Bhunter
ANALYSIS OF RATE

Half brick masonry in common burnt clay building bricks in cement mortar 1:3 ( 1 cement : 3 sand )
Second class brick.
DETAIL OF COST FOR 10.0 Sqm.

S.No. Desciption Unit Quantity Rate Amount


1
MATERIALS
1 Second class brick at kiln. 1000 Nos 565 7000 3955
2 Cement mortae 1:3 Cum. 0.28 3688.48 1032.77
4987.77
CARRIAGE
1 Carraiage of bricks
3.00 Km.By mechanical transport 1000 Nos 565 484.28 273.62
0.0 Km.By head load 1000 Nos 565 0.00 0
Total 273.62
LABOUR
1 Mason Ist. Class. Each 1.2 311.5 373.8
2 Beldar Each 2 262.5 525
3 Bhisti Each 0.4 262.5 105
Sundries L.S. 15.00
1018.80

Total:- 6280.19
Add for water charges @1.5% except mortar : 78.71
Total:- 6358.90
Add 10% contractor's profit & 5% over head charges 798.92
on all except mortar G. Total:- 7157.82

Cost of 10 Sqm. 7157.82


Cost per Sqm. 716

Executive Engineer,
IPHDivision No.II
Kullu at Bhunter
Analysis of rate
Constructing manhole with RCC top slab in 1:2:4 mix 20 mm nominal size foundation concrete 1:4:8 40 mm nominal size
inside plastering 15 mm thick with cement mortar 1:3 finished with a floating coat of neat cement and making channels in
cement concrete 1:2:4 20 mm nominal size finished smooth complete i/c curing and testing.
Inside size 800x800x500 mm deep including CI Cover with frame LD With 200 mm thick wall of brick masonry in cm 1:3
Detail of cost for one manhole
S.No Description Unit Quantity Rate Amount

1 CC 1:4:8 Cum 0.34 cum 2956 1004.88

2 200 mm thick brick walls Cum 0.32 cum. 0 0

3 CC 1:2:4 Cum 0.15 cum. 3568.12


4 15 mm th. C.P. 1 :3 Sqm. 1.36 Sqm. 150.2 204.34
5 RCC 1:2:4 Sqm. 0.174 Sqm. 3771.0 656.16

6 Steel @ 55 Kg./cum= Kg. 9.5 Kg. 56.8 539.86

9 Providing form work: Sqm. 0.64 Sqm. 504.3 322.75

6 CI Cover with frame Each 1 No. 1000 1000.00


( M.R.)
Carriage 20

Labour
Extra Labour for making channel Each 0.06 81.67 4.90
Mason 1st class Each 0.06 130.67 7.84
Sundries 20

Total : 3780.7304
Add 1.5 % O.H Charges 56.71
3837.44
Add 10% C.P. & 5% O.H. charges on 157.91
1000+20+4.9+7.84+20=1052.74 1052.74 3995.35

Say Rs. 0

Executive Engineer,
IPHDivision No.II
Kullu at Bhunter
ANLYSIS OF RATE
Providing and fixing 1.8m high barbed wire fencing with angle iron posts 2.50m high 40x40x4mm ,2.50mC/C with
9 horizontal rows and 2 diagonal rows of barbed wire
Cost of 30m
S.No. Description of items Unit Quantity Rate Amount

1(a) ISA 40x40x4mm@ 2.5mc/c=30/2.5= 12 Nos.


Height of angle= 2.5+0.05+0.030= 2.580 m
Weight of angle iron : 2.40 Kg/m
Total weight of angle iron : 74.304 Kg.
Weight incl. 5% wastage : 78.02 Kg. Qtl. 0.780 0.00

(b) Cutting of angle iron LS 0.00

© Carriage of angle iron:


0.00 Km.By mechanical transport Tonne 0.078 0.00
0 Km.By head load Tonne 0.078 0.00

4(a) G.I. Barbed wire


9x30m = 270 m
2x13x2.97m = 71.28 m
Total : 341.28 m
@ 9.38 Kg./100m= 32.01 Kg. Qtl. 0.32 2200 704.00

(b) Carriage of barbed wire


25.00 Km.By mechanical transport Tonne 0.032 382.17 12.23
0 Km.By head load Tonne 0.032 0.00 0.00

5 Labour for fixing and stretching


barbed wire :
Blacksmith 2nd class Each 1.15 103.67 119.22
Beldar Each 1.15 81.67 93.92
Sundries L.S. 50.00

Total: 979.37
Add 10% contractor profit and 5% over head charges
on item No.1,4 &5: 979.37 146.91
Cost for 30 Rmtr. 1126.28
Cost for 1 Rmtr. 37.5

Executive Engineer,
IPHDivision No.II
Kullu at Bhunter
ANALYSIS OF RATE
Providing & laying cement concrete 1:3:6 (1 cement : 3 Sand :6 graded stone aggregate
20 mm nominal size ) and curing complete excluding cost of centring & shuttering in
walls i/c attached buttresses pillasters and their caps .
DETAIL OF COST FOR 1.00 CUM.

Material:-
Rate as per CC 1:3:6 1605.75

Carriage :-
Rate as per CC 1:3:6 474.77

Labour:-
1 Beldar Each 2.09 262.5 548.63
2 Bhisti Each 0.28 262.5 73.50
3 Mason Ist. Class Each 0.06 311.5 18.69
4 Mason 2nd. Class Each 0.06 311.5 18.69
5 Mate Each 0.04 262.5 10.50
6 Beldar for extra ramming. Each 0.25 262.5 65.63
Sundries. L.S. 15.00
scaffolding L.S. 30.00
780.63
Total:- 2861.15
Add 1.5% water charges 42.92
2904.07
Add 15% CP & OH charges. 435.61
Cxost for one cum Rs. 3339.68

Executive Engineer,
IPHDivision No.II
Kullu at Bhunter
ANALYSIS OF RATE
Squared rubble masonry coursed with hard stone of approved quality in foundation and plinth including
raking out joints in :
S.No. Description of items Unit Quantity Rate Amount
CEMENT MORTAR 1:3
MATERIAL
Cement mortar 1:3 Cum 0.3 Cum 3035.39 910.62
Stone at quarry Cum 1.21 Cum 350 423.5
Through & bond stone Each 7 No. 7.00 49

Carriage of stones
0.00 Km.By mechanical transport Cum 1.37 Cum 0.00 0
1.0 Km.By head load Cum 1.37 Cum 831.81 1139.58

LABOUR :
Stone dresser Each 2.83 No. 262.5 742.88
Mason Ist class Each 1.06 No. 311.5 330.19
Mason II nd class Each 1.06 No. 311.5 330.19
Beldar Each 2.65 No. 262.5 695.63
Sundries LS 35.00
Total : 4656.59
Add 1.5% for water charges except mortar: 56.19
4712.78
Add 10% C.P. & 5% O.H. charges
except on mortar : 570.32
5283.1

Executive Engineer,
IPHDivision No.II
Kullu at Bhunter
Squared rubble masonry coursed with hard stone of approved quality in foundation and plinth including
CEMENT MORTAR1:5
MATERIAL
Cement mortar 1:5 Cum 0.3 Cum 2382.31 714.69
Stone at quarry Cum 1.21 Cum 0 0
Through & bond stone Each 7 No. 0.00 0

Carriage of stones
0.00 Km.By mechanical transport Cum 1.37 Cum 0.00 0
0 Km.By head load Cum 1.37 Cum 0.00 0

LABOUR :
Stone dresser Each 2.83 No. 262.5 742.88
Mason Ist class Each 1.06 No. 311.5 330.19
Mason II nd class Each 1.06 No. 311.5 330.19
Beldar Each 2.65 No. 262.5 695.63
Sundries LS 35.00
Total : 2848.58
Add 1.5% for water charges except on mortar. 32.01
2880.59
Add 10% C.P. & 5% O.H. charges
except on mortar : 324.89
3205.48

Executive Engineer,
IPHDivision No.II
Kullu at Bhunter
ANALYSIS OF RATES
Demolition below G.L. up to 1.50 mtrs., depth and disposal of unserviceable materials with in
all leads and lifts.
Unreinforcement cement concrete up to 15cm thickness.

Detail of cost for one cum.


S.No. Description of items Unit Quantity Rate Amount

Labour:-

Mate Each 0.24 262.50 63.00


Beldar Each 2.69 262.50 706.13
Sundries L.S. 10.00
779.13
Add 105% for water charges. 11.69
790.81
Add 15% CP & OH charges. 118.62
Cost for One cubic metre. Rs. 909.43

Say Rs. 909.4

Executive Engineer,
IPHDivision No.II
Kullu at Bhunter
ANALYSIS OF RATES
Demolition of stone masonry above G.L. up to floor two level including atacking of serviceable
materialsand disposal of unserviceable materials with in all leads and lifts.
R Rubble masonry in cement mortar.

Detail of cost for one cum.


S.No. Description of items Unit Quantity Rate Amount

Labour:-

Mate Each 0.204 262.50 53.55


Beldar Each 3.65 262.50 958.13
Scaffolding L.S. 10.00
Sundries L.S. 10.00
1031.68
Add 105% for water charges. 15.48
1047.15
Add 15% CP & OH charges. 157.07
Cost for One cubic metre. 1204.22
Say Rs. 1204.00

Executive Engineer,
IPHDivision No.II
Kullu at Bhunter
Analysis of rate
constructing course rubble hammer dressd 'U' shape open surface drain with side wall 15x22 cm
in cement mortar 1;6 (1 cement:6 sand) and inside plastering 1:3 (1 cement :3 sand) including earth
work and laying 10cm cement concrete in 1:5:10 (1cement:5 sand: 10 graded stone aggregate ) of
40mm nominal size and 7.5 cm cement conc. 1;2:4(1cement:2sand:4graded stone agg. 20mm nomi-
nal size) and finished with a floating coat of neat cement comp. as per standard design.
S.No. Desciption Unit Quantity Rate Amount
MATERIAL
1 Earth work in excavation i/c refilling exca-
vated earth and disposal of surplus earth
1x100x2x10/12=167 cft or 4.73 cum 1 cum 4.73 196.099 927.55
sand: 10 hard
2 Cement concrete 1:5:10 (1 cement : 5
sand:10 hard stone agg. 40mm nominal size).
1x100x2x1/3=66.66 cft. 1 cum 1.89 2754.58 5206.15

3 HDCR masonry in cement mortar 1:6


(1 cement : 6 sand)
2(100x1/2x3/4)=75 cft or 2.12 cum. 1 cum 2.12 5087.16 10784.79

4 20mm thick cement plaster 1 : 3 (1 cement


: 3 sand) finished with a floating coat of
neat cement.
2x(100x5/4) 250sft or 23.23 sqm. 1 sqm. 23.23 183.27 4257.31

5 cement conc. 1 :2 :4 ( 1 cement ; 2 sand


4 hard stone ballast 20mm and down
gauge)
100x1/2x1/4 =12.50 cft.
Deduction:-
1/2x22/7(1/2x1/2)1/4x100=9.90 cft.
Net Qty:- 2.60 cft. Or .07 cum.` 1 cum 0.07 3568.12 249.77

6 Neat cement finishing over conc.


100x22/7x1/2x1/2 =79 cft. Or 7.34 sqm. 1 sqm. 7.34 25 183.5

LABOUR;-
Extra for rounding corner. L.S. 35.00

Total:- 21644.07
Add for water charges @ 1.5 % . 324.66
Total:- 21968.73
Add 15 % CP and OH charges. 3295.31
Total:- 25264.04
Cost for 30.48 metre.

Cost per Running Metre. 828.87

Executive Engineer,
IPHDivision No.II
Kullu at Bhunter
Analysis of Rate
Repairs to plaster in patches of 2.50 sqm and under and 10 to 15mm thick including cutting the patch
in proper shape and replastering the surface of the wall including disposal of rubbish to the
dumping ground with in all leads and lifts:- in cement mortar 1:6
Detail of cost for 10 Sqm.
S.No. Desciption Unit Quantity Rate Amount

Material
Cement mortar 1:6 cum 0.172 2382.31 409.76

Total:- 409.76

Labour:-
Mason 2nd class Each 1.62 311.5 504.63
Bhishti Each 0.32 262.5 84
Beldar Each 2.27 262.5 595.88

Scaffolding LS 15
Sundries LS 30
1229.51
Total:- 1639.26
Add for water charges @1.5% 18.44
1657.70
Add 15% CP & OH Charges 187.19

Cost for 10 Sqm:- Rs. 1844.90

Cost for one sqm Rs. 184.49

Executive Engineer,
IPHDivision No.II
Kullu at Bhunter
ANALYSIS OF RATES
P/F 15 cm wide 45 cm overall semicircular plain GI sheet gutter with iron brackets 40x3mm size bolts
and nuts and washers etc., i/c making necessary connection with rain water complete as per design
0.80mm thick sheet.

Detail of cost for 9.40 Rmt.

S.No. Desciption Unit Quantity Rate Amount

Material

0.80mm thick sheet Qtl 0.329 3500.00 1152.00

Flat iron brackets 40x3mm with nuts bolts and Each 10.00 40.00 400.00
washers.

Carriage

PGI Sheet
25.00 Km by mech transport Tonne 0.0329 382.17 13.00
0.0 Km by head load Tonne 0.0329 0.00 0.00

Labour

Carpenter 1st class Each 0.35 311.5 109.00


Black smith 1st class Each 0.90 311.5 280.00
Black smith 2nd class Each 0.90 311.5 280.00
Beldar Each 2.10 262.5 551.00
Sundries LS 10.00

2795.00

Add 15% CP & OH charges 419.25

Cost for 9.40 Rmt Rs. 3214.25

Cost for 1 Rmt. Rs 341.94

Executive Engineer,
IPHDivision No.II
Kullu at Bhunter
ANALYSIS OF RATES
P/F MS holder bat clamps of approved design to CI or SCI pipes

Detail of cost for 5 Nos.

S.No. Desciption Unit Quantity Rate Amount

Material

MS holder bat clamp 75mm each 5 25.00 125.00

CC block 1:2:4 Cum 0.005 3568.16 18.00

Carriage LS 3.00

Labour

Fitter Each 0.125 311.5 39.00


Mason 2nd class Each 0.75 311.5 234.00
Beldar Each 0.50 262.5 131.00

Sundries LS 5.00

555.00

Add 15% CP & OH charges 537.00 80.55

Cost for 5 Nos. Rs. 635.55

Cost for 1 Rmt. Rs 127.11

Say Rs. 127.00

Executive Engineer,
IPHDivision No.II
Kullu at Bhunter
Analysis of Rate
40mm thick marble chips flooring rubbed and polished to granolethic finish with under 30mm thick cement
concrete 1:2:4 and top layer 10mm th. With marble chips of required sizes laid cement marble powder by weight
in proporation of 4:7 ( 4 cement marble powder mix: 7 marble chips by volume):-
Light shade pigment with ordinary cement ( In top layer only)
S.No. Desciption Unit Quantity Rate Amount
MATERIAL Detail of cost for 10 Sqm.
For 30mm thick under layer cum 0.272 600.00 163.20
10mm and downgauge stone aggregate.
Sand Cum 0.136 375 51.00
Cement Tonne 0.0977 4500 439.65
For 10mm th. Marble chips Qtl 1.576 250 394.00
Cement Tonne 0.0636 4500 286.20
Marble powder cum 0.014 1800 25.20
Dark shade pigment Kg 4.45 100 445.00
Carriage :
Stone Aggregate
7.00 Km.By mechanical transport Cum 0.272 277.09 75.37
0.0 Km.By head load Cum 0.272 0.00 0.00
Cement
25.00 Km.By mechanical transport Tonne 0.67 159.65 106.97
0.0 Km.By head load Tonne 0.67 0.00 0.00
Marble chips
4.00 Km.By mechanical transport cum 0.064 159.65 10.22
0.0 Km.By head load cum 0.064 0.00 0.00
Marble Powder 0.00
4.00 Km.By mechanical transport cum 0.014 159.65 2.24
0.0 Km.By head load cum 0.014 0.00 0.00
Sand
7.00 Km.By mechanical transport cum 0.136 277.09 37.68
0.0 Km.By head load cum 0.136 0.00 0.00
Labour: Mason for tarrazo work Each 2.16 311.5 672.84
Beldar Each 3.78 262.5 992.25
Beldar (skilled ) for rubbing and polishing Each 9.72 262.5 2551.50
Sundries LS 100
Add difference of cost due to using light shade KG 4.45 40 178.00
Add difference of cost due to using white shade Tonne 0.0636 12000 763.20
Total : 7294.52
Add 1.5% for water charges : 109.42
7403.94
Add 10% for contractor profit and 5% over head charges 725.85 1001.71
except cement mortar : Cost of 10 Sqm. 8405.65
Cost of 1 Sqm. 840.57
Say Rs. 840.6

Executive Engineer,
IPH Division No-II
i Kullu at Bhunter.
Analysis of Rate
Providing and laying marble work(Table rubbed & polished) in flooring 20mm thick base in cement
mortar 1 :3 i/c jointing with CM 1:2(1White Cement:2 marble dust)with an admixure of pigment
to match the shade of the marble 20 mm thick white makrana marble.
Detail of cost for 10Sqm.
S.No. Desciption Unit Quantity Rate Amount

MATERIAL

20mm thick Marble stone cudm 10 240.00 600 14400


Finished work=200 cudm
Addwastage20% 40cudm=240cudm
Cement mortar 1:3
(1cement : 3 sand) Cum 0.224 3688.48 826.22

Cement for slurry :


For bedding = 44 Kg. Tonne 0.064 4500 288.00
For joints = 20 Kg.
Total : = 64 Kg.
Pigment = (64x3.5)/5=4.5 Kg. Tonne 0.0045 12000 54.00

Carriage of Stone Slab


0.00 Km.By mechanical transport Tonne 0.8 382.17 305.74
0.0 Km.By head load Tonne 0.8 0.00 0.00
Carriage of cement :
25.00 Km.By mechanical transport Tonne 0.064 382.17 24.46
0 Km.By head load Tonne 0.064 0.00 0.00

Labour :
Mason -1st class Each 13.5 311.5 4205.25
Black Smith 1st class Each 1.1 311.5 342.65
Beldar Each 4.1 262.5 1076.25
Bandhani Each 4.5 262.5 1181.25
Beldar (skilled ) for rubbing and polishing Each 4.5 262.5 1181.25
Mason2nd class Each 5.4 311.5 1682.10
Beldar Each 8.21 262.5 2155.13
Beldar Each 6.3 262.5 1653.75
Sundries 120.00
Total : 29496.05
Add 1.5% for water charges : 430.05
29926.1
Add 10% for contractor profit and 5% over head charges 4364.98
except cement mortar : Cost of 10 Sqm. 34291.08
Cost of 1 Sqm. 3429.11

Say Rs. 3429.1

Executive Engineer,
IPHDivision No.II
Kullu at Bhunter
Analysis of Rate
P/F veneered decorative plywood lining with decorative surface on one face with butt
jointing and nails.
4mm thick ply - 3 ply.
Detail of cost for 10 Sqm.
S.No. Desciption Unit Quantity Rate Amount
Materials:-

4mm thick 3ply grade-1 10.0000 sqm


Add 5 % wastage 0.50000
10.500000 cum 10.50000 275.00 2887.50
20mm long nail without head LS 50.00

Carriage:-
Carriage of kit ply LS 20.00

Labour:-
Carpenter 1st class Each 0.74 311.5 230.51

Beldar Each 0.74 262.5 194.25


Sundries, LS 15.00
Total:- 3397.26

Add 15% CP & OH charges. 509.59

Cost for 10 sqm Rs. 3906.85

Cost for One Sqm Rs. 390.68

Say Rs. 391.00

Executive Engineer,
IPHDivision No.II
Kullu at Bhunter
Analysis of Rate
Providing and laying 20mm thick acid proof tiles of size upto 300x300 mm of specified shade in floors treads of
and landing laid on a bed of 12 mm thick cement mortar 1:3 (1cement : 3 Sand) jointing with cement slurry mixed with
pigment to match the shade of tiles.
Detail of cost for 1 Sqm.
S.No. Desciption Unit Quantity Rate Amount

MATERIAL
Acid proof tiles 150x150x18mm
Add 2.5% for wastage & breakage: 1.1 Nos.
Total : 45.5 Nos.
Say : 46 Nos.
1 Nos 46.00 15 690

Acid proof mortar Powder o.80


solvent 3.63 1 Set 0.076 780 59.28
4.43
3.00 By Mech,Trans. Brick tiles 1000 46 382.17 17.58
0.0 By Head Load 1000 46 0.00 0
3.00 By Mech,Trans. Acid proof mortar 1 Tonne 0.0044 382.17 1.68
0 By Head Load 1 Tonne 0.0044 0.00 0

Labour :
Mason -1st class Each 0.7 311.5 218.05
Beldar Each 0.7 262.5 183.75
Sundries L.S. 10.00

Total : 1180.34
Add 1.5% for water charges : 1.5 17.71
1198.05
Add 10% for contractor profit and 5% over head charges 179.71
except cement mortar : 1377.76

Say Rs. 1377.8 /- only.

Executive Engineer,
IPHDivision No.II
Kullu at Bhunter
Analysis of Rate
P/F 19mm thick commercial board water proof shutters for cup board i/ c fixing with
nockle plated piano hinges with screwa etc., complete.

Detail of cost for 2.20 Sqm.


S.No. Desciption Unit Quantity Rate Amount
Materials:-
19mm thick commercial board
2.20x1.00 2.20 sqm
Add 5 % wastage 0.11
2.31 Sqm 2.31 785.00 1813.35
Nickle plated bright finished piano hinges Mtr. 4.4 50 220.00
Iron screws 100Nos. 125 25 31.25
Carriage:-
Carriage of ply LS 25.00

Labour;-
Carpenter 1st class Each 0.74 311.5 230.51
Beldar each 0.74 262.5 194.25

Sundries LS 15.00
Total:- 2529.36

Add 15% CP & OH charges. 379.40

Cost for 2.20 sqm Rs. 2908.76

Cost for One sqm Rs. 1322.17

Say Rs. 1322.00

Executive Engineer,
IPHDivision No.II
Kullu at Bhunter
Analysis of Rate
P/F commercial ply board ceiling of approved quality with butt jointing and nails ( frame work and cover
fillets to be measured and paid separately).
6mm thick
Detail of cost for 10 Sqm.
S.No. Desciption Unit Quantity Rate Amount
Materials:-
commercial ply wood of 6mm thick
Thickness 10.00 sqm
Add 5 % wastage 0.50
10.50 sqm 10.50 170.00 1785.00
Nails. LS 15.00

Carriage:-
Carriage of ply LS 10.00

Labour;-
Carpenter 1st class Each 0.54 311.5 168.21
Beldar each 0.13 262.5 34.13
Scaffolding LS 15.00
Sundries LS 8.00

2035.34
Add 15% CP & OH charges except carriage i.e Rs 2025.34 303.80

Cost for 10 sqm Rs. 2339.14

Cost for One sqm Rs. 233.91

say Rs. 233.9

Executive Engineer,
IPHDivision No.II
Kullu at Bhunter
Analysis of Rate
Providing CGI sheet roofing fixed with GI J or L hooks bolts and nuts 8mm diameter with bitumen
and GI washers filled with white lead complete excluding the cost of purlins rafters and trusses.
0.80mm thick.
Detail of cost for a area of roof 2x18.09x5.10m =184.518 sqm.
S.No. Desciption Unit Quantity Rate Amount
Material:-
Detail of length and breadth
Length 18.09 Mtrs
Breadth 5.1 Mtrs.

CGI sheet 854.38 Kg


PGI sheet 956.80 kg.
1811.18 kg.
Add 5% wastage. 90.56 kg.
1901.74 kg.
or 19.01 Qtl 1 qtl 19.01 6000.00 114060.00

GI seam nuts and bolts. 10Nos 884.00 20.00 1768.00


GI J or l hooks. 10 Nos. 810.00 35.00 2835.00
Limpet washers. 100Nos. 1694.00 18.00 304.92
Bitumen washers. 100Nos. 1694.00 15.00 254.10
Carriage:-
CGI sheet:-
25.00 Km by head load Tonne 1.902 382.17 726.89
0.0 Km by head load Tonne 1.902 0.00 0.00
Nuts bolts and washers.
25.00 Km by head load Tonne 0.45 382.17 171.98
0.0 Km by head load Tonne 0.45 0.00 0.00
Labour:-
Black smith 2nd class Each 1.30 311.5 404.95
Carpenter 2nd class Each 14.75 311.5 4594.63
Beldar Each 14.75 262.5 3871.88
Sundries. LS 30.00

Total Rs. 129022.33

Add 15% CP & OH Charges. 19353.35

Cost for 184.520 sqm Rs. 148375.68

Cost for One sqm Rs. 804.12

Say Rs. 804.12

Executive Engineer,
IPHDivision No.II
Kullu at Bhunter
Analysis of Rate
Providing and fixing plain jafri of 40x12 mm latha placed 40mm apart (frame to be paid separately including
fixing 50x12 mm beading complete with 2nd class Deodar Wood

Detail of cost for a jafri 200x100cm.= 2.20 sqm


S.No. Desciption Unit Quantity Rate Amount

MATERIAL :
2st class deodar wood : Cum. 0.037 50000 1850
Carriage :
3.00 Km.By mechanical transport Cum. 0.037 193.71 7.17
0 Km.By head load Cum. 0.037 0.00 0
Labour :
Carpenter Ist class Each 0.75 311.5 233.63
Beldar Each 1.1 262.5 288.75
Mason-II nd class Each 0.5 311.5 155.75
Sundries 10
2545.3
Add 10% C.P. & 5% O.H. Charges : 381.8
Cost of 2.20 sqm 2927.1
Cost of 1 sqm 1330.5
Say Rs. 0.0 /- only.

Executive Engineer,
IPHDivision No.II
Kullu at Bhunter
Analysis of Rate
Providing wood work in frames of false celling partitions etc.

Detail of cost for celling for room 3x3 m


S.No. Desciption Unit Quantity Rate Amount

MATERIAL :
1st class deodar wood : Cum. 0.166 55000 9130
Carriage :
3.00 Km.By mechanical transport Cum 0.166 193.71 32.16
0 Km.By head load Cum 0.166 0.00 0
Labour :

Carpenter 2nd class Each 1.01 103.83 104.87


Beldar Each 1.01 262.5 265.13
Sundries 25

9557.16
Add 10% C.P. & 5% O.H. Charges : 1433.57
Cost of .158 cum : 10990.73
Cost of 1 cum : 69561.582
Say Rs. 69561.6 /- only.

Executive Engineer,
IPHDivision No.II
Kullu at Bhunter
Analysis of Rate
Providing and fixing plain asbostos cement sheet ceiling of approved quality with butt jointing and
wood screws ( frame work and fillets to be measured and paid for separately)
6 mm thick.
Detail of cost for 10 SQM.
MATERIAL:-
Asbostos cement sheets 10 sqm
add wastage @ 10% 1 Sqm
Toatl:- 11 sqm.
sqm 11.00 160 1760
Wood screws (20mm) 100 Nos. 260 30 78

CARRIAGE
steel, CGI, Asbostos sheets
25.00 km by Mech. Transport Tonne 0.132 382.17 50
0.0 km by head load Tonne 1.132 0.00 0

LABOUR
Carpenter 1st class Each 0.72 311.5 224
Beldar Each 0.36 262.5 95

Scaffolding LS 50
Sundries LS 50
Total:- 2307
Add 15 % CP & OH charges. 346.05

Cost for 10 sqm Rs 2653.05

Cost for One sqm. Rs. 265.31

Say Rs. 265.00

Executive Engineer,
IPHDivision No.II
Kullu at Bhunter
Analysis of rate
P/F board partition with butt jointing and nails(Frame work and cover fillets to be measured and
paid for separately) Particle board bwp phenol bonded exterior/interior grade in partitions.

Detail of cost for 10 Sqm.


S.No. Desciption Unit Quantity Rate Amount
Materials
12 mm thick partical board Sqm 10.5 420 4410

CARRIAGE
Carriage of Partical board L.S 20

LABOUR
Carpenter 1st Class Each 0.5 311.5 155.75
Beldar Each 0.5 262.5 131.25
Sundries L.S 10
4727
Add 10% CP & 5% OH Charges 0.15 709.05
Cost for 10 SQM 5436.05
Cost Per Sqm 10 543.61

Executive Engineer,
IPHDivision No.II
Kullu at Bhunter
Analysis of rate
Providing and fixing 75 mm x 60 mm round hand rails in straight length complete etc.
!st class indian teak wood.
Detail of cost for 3.o5 meter run
S.No. Description of items Unit Qty. Rate Amount

Material
1st class indian teak wood cum 0.0151 65000 981.5

Carriage of wood :
3.00 Km.By mechanical transport Cum 0.0151 193.71 2.93
0.00 Km.By head load Cum 0.0151 0.00 0

LABOUR
Carpenter 1st class Each 1.13 311.5 352
Beldar Each 0.29 262.5 76.13
Sundries 25
1437.56
Add 10 % CP & 5 % OH Charges on Rs. 1180.47 177.07
1614.6305
Cost for 3.050 meter 3.05
Cost per Mt. 529.39

Executive Engineer,
IPHDivision No.II
Kullu at Bhunter
Analysis of rate.
P/F brass curtain rail with rollers stop ends and brackets in pelmets instead of wooden curtain rod
25mm dia and brackets of first class deodar wood
Detail of cost for 2 mt. long.
S.No. Description of items Unit Qty. Rate Amount

Materials
Brass curtain rails with rollers stop ends and brackets
mt 2 100 200
Deduct cost of ist class Deodar wood 0
wooden curtain rods i/c brackets cum 0.00143 50000 71.5

Labour 5
276.5
Add 10 % CP & 5% OH Charges 253.28 37.992
314.492
Cost for 2.00 meter
Cost per mt. 157.25

Executive Engineer,
IPHDivision No.II
Kullu at Bhunter
Analysis of Rate
Providing and fixing MS round or square bar with MS flat at required spacing in wooden frames of window
and clerestory windows.

DETAIL OF COST FOR A WINDOW 140X110 CM.


S.No. Description Unit Quantity Rate Amount
Material
MS bar 16mm dia 13x135cm =17.68 M.@
1.57Kg /M = 27.93 Kg.
add for wastage @ 10% = 2.97 Kg
Total:- 30.72 Kg
30.72 Kg or 0.307 quintal Qtl 0.307 3200 982.40

MS Flat 40x6mm 2x96cm = 192cm


1x110cm = 110cm
Total 302cm
302cm or 3.02 M @ 1.90 Kg/Mtr= 5.74 Kg
Add for wastage @ 10% = 0.57 Kg
total 6.31 Kg
6.31 Kg or 0.063 quintal Qtl. 0.063 3500 220.50
1202.90
Carriage-
25.00 Km by Mech Transport Tonne 0.0307 382.17 11.73
0.0 Km by head load Tonne 0.0307 0.00 0.00
11.73
Labour:-
Black smith 2nd class Each 1.32 311.5 411.18
Carpenter 2nd class Each 0.38 311.5 118.37
Beldar Each 0.72 262.5 189.00
718.55
Total:- 1933.18
Add 15 % for CP & OH Charges. 289.98
Cost for 33.67 Kg. = Rs. 2223.16

Cost For One Kg = Rs. 66.03

Say Rs. 66.00 Per Kg.

Executive Engineer,
IPHDivision No.II
Kullu at Bhunter
Analysis of Rate
Brick edging brick laid on edge to plinth protection with bricks including grouting with cement mortar 1:4
With modular bricks size 19cmx9cmx9cm.

Detail of cost for 10 Rmt.

Description Unit Quantity Rate Amount


Material:-

Modular bricks size (19cmx9cmx9cm) 1000 Nos. 50 7000 350

Cement Mortar 1:4. Cum 0.03 5283.1 158.49

Excavation and disposal of earth. LS 5.00

Carriage.

Bricks.

3.00 Km. by Mech Transport. 1000 Nos. 50 484.28 24.21

0.0 Km by head load 1000 Nos. 50 0.00 0

Labour

Mason 1st class Each 0.12 311.5 37.38


Beldar Each 0.12 262.5 31.5
Bhisti Each 0.04 262.5 10.5
Total 617.09
Add 1.5% for water charges. 9.26
626.34
Add 15% CP and OH Charges. 93.95

Cost for 10 Rmt. Total Rs. 720.29

Cost for per Rmt Rs. 72.03

Executive Engineer,
IPHDivision No.II
Kullu at Bhunter
Analysis of Rate
Providing CGI sheet roofing fixed with GI J or L hooks bolts and nuts 8mm diameter with bitumen
and GI washers filled with white lead complete excluding the cost of purlins rafters and trusses.
0.63mm thick.
Detail of cost for a area of roof 2x18.09x5.10m =184.518 sqm.
S.No. Desciption Unit Quantity Rate Amount
Material:-
Detail of length and breadth
Length 18.09 Mtrs
Breadth 5.1 Mtrs.

CGI sheet 692.28 Kg


PGI sheet 775.44 kg.
1467.72 kg.
Add 5% wastage. 73.39 kg.
1541.11 kg.
or 15.41 Qtl 1 qtl 15.41 6200.00 95542.00

GI seam nuts and bolts. 10Nos 884.00 50.00 4420.00


GI J or l hooks. 10 Nos. 810.00 50.00 4050.00
Limpet washers. 100Nos. 1694.00 100.00 1694.00
Bitumen washers. 100Nos. 1694.00 100.00 1694.00
Carriage:-
CGI sheet:-
25.00 Km by head load Tonne 1.902 382.17 726.89
0.0 Km by head load Tonne 1.902 0.00 0.00
Nuts bolts and washers.
25.00 Km by head load Tonne 0.45 382.17 171.98
0.0 Km by head load Tonne 0.45 0.00 0.00
Labour:-
Black smith 2nd class Each 1.30 311.5 404.95
Carpenter 2nd class Each 14.75 311.5 4594.63
Beldar Each 14.75 262.5 3871.88
Sundries. LS 50.00

Total Rs. 117220.31

Add 15% CP & OH Charges. 17583.05

Cost for 184.520 sqm Rs. 134803.36

Cost for One sqm Rs. 730.56

Say Rs. 731.00

Executive Engineer,
IPHDivision No.II
Foundation, footing, bases of columns etc and mass concrete .
Detail of cost for 10 Sqm and area of contact with concrete
( 2.5 m x2.5 mx1m high).
S.No. Description of items Unit Quantity Rate Amount
MATERIAL

Planks 38mm thick ( second class Kail wood or equivent local wood
2X2.576X1= .152sqm 2 Nos X2.50X1 =5.00 sqm Total= 10.152 sqm
Add wastage 5% = 0.508Sqm Cum 0.4051 29728 12042.81
Total : 10.660 Sqm
10.660X0.038=0.4051Cum

Battens

8NosX1.00mX0.10m=0.0600Cum
Add 5% wastage : 0.0030 cum Cum 0.063 31240 1968.12
Total : 0.0630 cum

Ballies 125mm dia for strutting two each face 8 NosX1.50 long= 12.0m

5% wastage : 0.60m Metre 12.6 110 1386.00


Total : 12.60 m

Carriage of timber :
1.00 Km.By mechanical transport Cum 0.622 69.65 43.32
0.1 Km.By head load Cum 0.622 32.58 20.26
15460.51
Assuming that timber shall become unserviceable
after being used 16 times . Hence cost for
using once : Each 1/16 15460.51 966.28
Add 5% wastage for usage repeatedly : 773.03
Total : 1739.31
Labour :
Carpenter 2nd class : Each 1.30 311.5 404.95
Beldar : Each 1.30 262.5 341.25
Sundries : LS 25.00
Total : 2510.51
Add 10% CP & 5% O.H. Charges : 376.58
Cost for 10 Sqm. 2887.09
Cost for 1 Sqm : 288.71
Say Rs 288.7 /-only

Executive Engineer,
IPHDivision No.II
Kullu at Bhunter
Analysis of Rate
Providing form work of ordinary timber plankings so as to give a rough finish including centring, shuttering, strutting
and propping etc. height of propping and centring below supporting floor to ceiling not exceeding 4 metres and removal
of the same for insitu reinforced concrete and plain concrete work in :
Columns Pillars, Posts and struts etc.
Detail of cost for a coloumn 30 cm squareand 3.50 m high contact area
4X0.30X3.50=4.20Sqm
S.No. Description of items Unit Quantity Rate Amount
MATERIAL

Kail wood Planks 38mm thick


2X0.30X3.50= .2.10 sqm 2 X0.48X3.50 =3.36 sqm Total= 5.46 sqm
Add wastage 5% = 0.27Sqm Cum 0.218 29728 6480.70
Total : 5.73 Sqm
Cubical Contents = 5.73X0.038=0.218 Cum

Ballies 125mm dia for struttis


4X3.80 m = 15.2 m
5% wastage : 0.76m Metre 15.96 110 1755.60
Total : 15.96 m
Carriage of timber :
Planks=0.218 Cum
Ballies=15.96X22/7X1/4(0.125m2)
Total : 0.414Cum
1.00 Km.By mechanical transport Cum 0.414 69.65 28.84
0.1 Km.By head load Cum 0.414 32.58 13.49
8278.63
Assuming that timber shall become unserviceable
after being used 16 times . Hence cost for
using once : Each 1/16 8278.63 517.41
Add 5% wastage for usage repeatedly : 413.93
Total : 931.34
Labour :
Carpenter 2nd class : Each 1.47 311.5 457.91
Beldar : Each 1.47 262.5 385.88
Sundries : LS 25.00
Total : 1800.13
Add 10% CP & 5% O.H. Charges : 270.02
Cost for 4.20 Sqm. 2070.15
Cost for 1 Sqm : 492.89
Say Rs 492.9 /-only

Executive Engineer,
IPHDivision No.II
Kullu at Bhunter
Analysis of Rate
P/F 12mm thick prelaminated board both side bwp phenol bonded exterior/ interior grade shutter with frame of 1st class
D/wood for cup board i/c nickle plated bright piano hinges 25mm thick frame

Detail of cost for 2.16 sqm

S.No. Description of items Unit Quantity Rate Amount


MATERIAL
1st class deodar wood Cum 0.026 55000 1430.00

Prelaminated board sqm 2.27 800 1816.00

Nickle plated bright finished pia Mtr 4.00 40 160.00

Screws 25mm 100 nos 48 20.00 9.60

Carriage:-
25.00 Km.By mechanical transport Cum 0.053 193.71 10.27
0 Km.By head load Cum 0.053 0.00 0.00

Labour :
Carpenter 1st class : Each 1.65 311.5 513.98
Carpenter 2nd class : Each 1.22 311.5 380.03
Beldar Each 1.29 262.5 50.00
Total : 4369.88
Add 10% CP & 5% O.H. Charges : 655.48
Cost for 2.16 Sqm. 5025.36
Cost for 1 Sqm : 2326.56

Say Rs 2327

Executive Engineer,
IPHDivision No.II
Kullu at Bhunter
Analysis of Rate
Providing eaves board 200mmx25mm thick i/c fixing in position:-
1st class deodar wood.

Detail of cost for 10 Rmt.

S.No. Description of items Unit Quantity Rate Amount


MATERIAL
1st class deodar wood Cum 0.055 55000 3025.00

Carriage:-
25.00 Km.By mechanical transport Cum 0.055 193.71 10.65
0 Km.By head load Cum 0.055 0.00 0.00

Labour :
Carpenter 1st class : Each 0.66 311.5 205.59
Carpenter 2nd class : Each 0.66 311.5 205.59
Beldar Each 0.98 262.5 50.00
Sundries 15
Total : 3511.83
Add 10% CP & 5% O.H. Charges : 526.77
Cost for 10 Rmt 4038.60
Cost for 1 Rmt 403.86

Say Rs 404

Executive Engineer,
IPHDivision No.II
Kullu at Bhunter
Analysis of Rate
Providing and fixing bright finished heap and stapples (Safety type) with necessary screws.
150mm

Detail of cost for 10 Nos.

S.No. Description of items Unit Quantity Rate Amount


MATERIAL
Bright finished heap & stapples 10 Nos. 10 700 700.00
brass screws 25mm 100 nos 80 70 56.00
Carriage:-
LS 2.00

Labour :
Carpenter 1st class : Each 0.08 311.5 24.92

Total : 782.92
Add 10% CP & 5% O.H. Charges : 117.44
Cost for 10 Nos 900.36
Cost for 1 Nos. 90.04

Say Rs 90

Executive Engineer,
IPHDivision No.II
Kullu at Bhunter
Analysis of Rate
Providing and fixing bright finished or / and black enamelled iron helical door spring 150mm

Detail of cost for 10 Nos.

S.No. Description of items Unit Quantity Rate Amount


MATERIAL
Bright finished helical door spri Each 10 50 500.00
brass screws 50mm 100 nos 40 40 16.00
iron screw 25mm 100 nos 20 20 4.00

Carriage:-
LS 1.00
Labour :
Carpenter 2nd class : Each 0.40 311.5 124.60
Beldar Each 0.20 262.5 52.50

Total : 698.10
Add 10% CP & 5% O.H. Charges : 104.72
Cost for 10 Nos 802.82
Cost for 1 Nos. 80.28

Say Rs 80

Executive Engineer,
IPHDivision No.II
Kullu at Bhunter
Providing and fixing oxidized M.S sliding door bolt with nuts and screws

screws etc complete.


Details of cost for 10 Nos.
Materials
i) 300x16 mm 10 Nos 90 Each 900
Bolts & nuts 50x6 0 40 Nos 4 Each 160
Oxidized iron screws 25 mm 100 120 20 24
Carriage
Carriage of materials LS 3
Labour
Carpenter 2nd class 0.5 Nos 311.5 Each 155.75
1242.75
Add 10%CP5%OHCharges 186.41
Cost for 10 Nos 1429.16
Cost per Nos 10 142.92
Say Rs. 143
Analysis of Rate.
P/F 100mm bright finished brass floor door stopper with rubber cushion.

Details of cost for 10 Nos.

Materials
ii) Brass door stopper 10 Nos 150 Each 1500
brass screws 40mm 100 40 Nos 160 Each 64
Carriage
Carriage of materials LS 2
Labour
Carpenter 1st class 0.07 Nos 311.5 Each 21.81
1587.81
Add 10%CP5%OHCharges 238.17
Cost for 10 Nos 1825.98
Cost per Nos 10 182.6
Providing and fixing M.S Tower bolts(barrel type) with necessary screws etc. complete.

Details of cost for 10 Nos.


Materials

Oxidized M.S tower


bolt (Barrel type)
150x10 10 Nos 15 Each 150

Iron Screws 25 mm 100 80 Nos 20 100 nos 16


Carriage

Carriage of materials LS 3
Labour
Carpenter 2nd class 0.1 Nos 311.5 Each 31.15

200.15
Add 10%CP5%OHCharges 30.02
Cost for 10 Nos 230.17
Cost per Nos 10 23.02
Providing and fixing M.S Tower bolts(barrel type) with necessary screws etc. complete.

Details of cost for 10 Nos.


Materials

Oxidized M.S tower


bolt (Barrel type)
250x10 10 Nos 30 Each 300
Iron Screws 25 mm 100 80 Nos 18 100nos 14.4

Carriage
Carriage of materials LS 2

Labour
Carpenter 2nd class 0.1 Nos 311.5 Each 31.15
347.55
Add 10%CP5%OHCharges 52.13
Cost for 10 Nos 399.68
Cost per Nos 10 39.97
Say Rs. 40
Providing and fixing oxidized M.S Handles with necessary screws etc. complete

Detail of cost for 10 Nos.


Material

oxidized M.S handle 0 10 Nos 25 250


125 mm

Iron screw 25 mm 100 40 20 8


CARRIAGE
Carriage of materials 2
LABOUR .

Carpenter 2nd class 0.06 Nos 311.5 18.69

278.69
Add 10% CP & 5% OH Charges 0.15 41.8
Cost for 10 Nos 320.49

Cost per Nos 10 32.049


Providing and fixing oxidized M.S Handles with necessary screws etc. complete

Detail of cost for 10 Nos.


Material

oxidized M.S handle 0 10 Nos 25 250


100 mm
Iron screw 25 mm 100 40 20 8
CARRIAGE
Carriage of materials 2

LABOUR .

Carpenter 2nd class 0.06 Nos 311.5 18.69

278.69
Add 10% CP & 5% OH Charges 0.15 41.8

Cost for 10 Nos 320.49


Cost per Nos 10 32.049

Say Rs. 32.1


ANALYSIS OF RATE

Providing & laying cement concrete 1:1½:3 (1 cement : 1½ Sand 3 graded stone aggregate
20 mm nominal size ) and curing complete excluding cost of form work & reinforcement for RCC
work in : Lintels,beam,girders and cantilevers up to floor two level.

Detail of cost for 1 Cum.

S.No. Desciption Unit Quantity Rate Amount

Material:-
Cement concrete 1:1.5:3 cum 1 3938.39 3938.39

Labour (Extra for Laying CC in RCC work) cum 1 114.17 114.17

Labour (Extra for lifting Material)

Beldar Each 1.7 81.67 138.84


Total: 4191.40
Add 1.5% for water charges except C.C.1:1.5:3 on Rs. 175.99 2.64
Total: 4194.04
Add 15% C.P. & O.H.charges on Rs. 175.99 26.40
Total: 4220.44

Cost of One cum 4220.44


Say Rs. 4220.00

Executive Engineer,
IPHDivision No.II
Kullu at Bhunter
ANALYSIS OF RATES
P/F 15 cm wide 45 cm overall semicircular plain GI sheet gutter with iron brackets 40x3mm size bolts
and nuts and washers etc., i/c making necessary connection with rain water complete as per design
0.63mm thick sheet.

Detail of cost for 9.40 Rmt.

S.No. Desciption Unit Quantity Rate Amount

Material

0.63mm thick sheet Qtl 0.2564 5500.00 1410.00

Flat iron brackets 40x3mm with nuts bolts and Each 10.00 50.00 500.00
washers.

Carriage

PGI Sheet
25.00 Km by mech transport Tonne 0.0329 382.17 13.00
0.00 Km by head load Tonne 0.0329 0.00 0.00

Labour

Carpenter 1st class Each 0.35 311.5 109.00


Black smith 1st class Each 0.90 311.5 280.00
Black smith 2nd class Each 0.90 311.5 280.00
Beldar Each 2.10 262.5 551.00
Sundries LS 10.00

3153.00

Add 15% CP & OH charges 472.95

Cost for 9.40 Rmt Rs. 3625.95

Cost for 1 Rmt. Rs 385.74

Executive Engineer,
IPHDivision No.II
Kullu at Bhunter
ANALYSIS OF RATES
Slate roofing with 7.5cm single lap single layer fixed on wooden batten.

With slates 40x20 cm size.

Detail of cost for 10 sqm.

S.No. Desciption Unit Quantity Rate Amount

Material

40x20cm slate 100 Nos. 259 1000.00 2590.00

Lime mortar 1:3 Cum 0.030 3688.48 111.00


Carriage
Slate
25.00 Km by mech transport 1000 nos. 259 74.78 3.00
0 Km by head load 1000 nos. 259 0
Labour

Mason 2nd class Each 1.61 311.5 502.00


Beldar Each 0.75 262.5 197.00
Sundries LS 40.00

3443.00

Add 1.5% for water charges 51.65


3494.65
Add 15% for CP & OH charges. 524.20
Cost for 10 sqm Rs:- 4018.84

Cost for 1 sqm Rs. 402.00

Executive Engineer,
IPHDivision No.II
Kullu at Bhunter
Analysis of Rate
Marble chips skirting or dado up to 30cm height rubbed or polished to granolithic finish laid in cement marble
powder by weight in proporation of 4:7 ( 4 cement marble powder mix: 7 marble chips by volume in top layer.
Light shade pigment with ordinary cement ( In top layer only)

S.No. Desciption Unit Quantity Rate Amount


MATERIAL Detail of cost for 10 Sqm.
For under layer 14mm thick cum 0.193 3500.00 675.50

Extra for top layer 6mm thick Qtl 0.872 250 218.00
Cement Tonne 0.0405 4500 182.25

Marble powder cum 0.007 1800 12.60


Dark shade pigment Kg 2.84 100 284.00

Carriage :
Cement
25.00 Km.By mechanical transport Tonne 0.0405 382.17 15.48
0.0 Km.By head load Tonne 0.0405 0.00 0.00
Marble chips
4.00 Km.By mechanical transport cum 0.051 159.65 8.14
0.0 Km.By head load cum 0.051 0.00 0.00
Marble Powder 0.00
4.00 Km.By mechanical transport cum 0.007 159.65 1.12
0.0 Km.By head load cum 0.007 0.00 0.00
Carriage of Pigment LS 5.00
Labour:
Bhisti Each 0.55 262.50
Mason for tarrazo work Each 2.7 311.5 841.05
Beldar Each 4.05 262.5 1063.13
Beldar (skilled ) for rubbing and polishing Each 9.7 262.5 2546.25
Sundries LS 100
Add difference of cost due to using light shade KG 2.84 40 113.60
Add difference of cost due to using white shade Tonne 0.0405 12000 486.00
Total : 6552.12
Add 1.5% for water charges : 98.28
6650.40
Add 10% for contractor profit and 5% over head charges 964.86
except cement mortar : Cost of 10 Sqm. 7615.26
Cost of 1 Sqm. 761.53
Say Rs. 761.5

Executive Engineer,
IPH Division No-II
i Kullu at Bhunter.
Analysis of Rate
Providing and laying granite stone in flooring 20mm(Average) thickness base of cement
mortar 1 :3 (1cement:3 sand)laid over and jointed with grey cement slurry mixed with pigment
to match the shade of granite stone i/c rubbing and polishing complete.20mm thick.
Detail of cost for 10Sqm.
S.No. Desciption Unit Quantity Rate Amount

MATERIAL

20mm thick granite stone=10 sqm


Add wastage 15% =1.50 sqm
Total: =11.50 sqm 1 Sqm 11.50 3229.00 37133.50
Cement mortar 1:3
(1cement : 3 sand) 1 Cum 0.224 3688.48 826.22

Cement for slurry :


1 Tonne 0.064 4500 288.00

Grey Pigment 1 Kg 4.50 65.00 292.50

Carriage of Granite Stone Slab


25.00 Km.By mechanical transport Tonne 0.644 382.17 246.12
0.0 Km.By head load Tonne 0.644 0.00 0.00
Carriage of cement :
25.00 Km.By mechanical transport Tonne 0.064 382.17 24.46
0 Km.By head load Tonne 0.064 0.00 0.00

Labour :

Mason2nd class Each 5.40 311.5 1682.10


Beldar Each 8.21 262.5 2155.13
Beldar Each 10.8 262.5 2835.00
Sundries 80.00
Total : 45563.03
Add 1.5% for water charges : 671.05
46234.08
Add 10% for contractor profit and 5% over head charges 6811.18
except cement mortar : Cost of 10 Sqm. 53045.26
Cost of 1 Sqm. 5304.53

Say Rs. 5304.5

Executive Engineer,
IPHDivision No.II
Kullu at Bhunter
Analysis of Rate
P/F moulded hand rail of MS hollow pipe 50mm dia welded in straight length over MS flat at top
of vertical balusters i/c one coat of red oxide priming coat complete.( MS flat & baluster of railing
shall be paid separately)
Detail of cost for 6 Rmt.
S.No. Desciption Unit Quantity Rate Amount
Materials:-
MS hollow pipe 50mm dia Rmt. 6.00 50.00 300.00
Priming coat ( Red oxide)
3.142x5.25/100x6 0.99 sqm. Sqm. 0.99 28.79 28.50

Welding charges.
Two ends circular & semicircular
2 5.25 10.5
4 5.25/2 10.5
Bottom welding
600 5/100x2 60
Total:- 81 CM 81.00 2.00 162.00
Carriage:-
Carriage of materials. LS 20.00
Labour:-
Black smith 1st class Each 0.30 311.50 93.00
Beldar. Each 0.30 262.50 79.00
Sundries( Brushed, sandpaper etc) LS 25.00
Total:- 707.50
Add 15% CP & OH charges. 679.00 101.85

Cost for 6 Rmt. Rs. 809.35

Cost for One Sqm Rs. 134.89

Say Rs. 135


Analysis of Rate
P/F 4mm thick water proof kit ply of standard quality ISI mark and approved shade and
colour in wall lining i/c mitring at junctions , butt jointing and nails complete.

Detail of cost for 10 Sqm.


S.No. Desciption Unit Quantity Rate Amount
Materials:-
4mm thick water proof kit ply.
10.0000 sqm
Add 5 % wastage 0.50000
10.500000 Sqm 10.50000 260.00 2730.00
20mm long nail without head LS 50.00

Carriage:-
Carriage of kit ply LS 20.00

Labour:-
Carpenter 1st class Each 0.74 311.5 230.51

Beldar Each 0.74 262.5 194.25


Sundries, LS 15.00
Total:- 3239.76

Add 15% CP & OH charges. 485.96

Cost for 10 sqm Rs. 3725.72

Cost for One Sqm Rs. 372.57

Say Rs. 373.00

Executive Engineer,
IPHDivision No.II
Kullu at Bhunter
Analysis of Rate
P/F square edges cover fillets ( beading) 19mmx6mm scetion i/c mitring junction with
wood screws and nails complete.

Detail of cost for 100 Mtrs.


S.No. Desciption Unit Quantity Rate Amount
Materials:-
1st class Indian teak wood.
100x0.019x0.006 0.0114 sqm
Add 5 % wastage 0.00100
0.012400 cum 0.01240 98625.00 1222.95
Screws 20mm long 100 Nos. 660 25 165.00

Carriage:- Timber
3.00 km by Mech transport cum 0.01240 193.71 2.40
0.00 km by head load cum 0.01240 0.00 0.00
Labour;-
Carpenter 1st class Each 2.00 311.5 623.00
Carpenter 2nd class Each 2.00 311.5 623.00
Beldar Each 4.00 262.5 1050.00
Sundries+scaffolding LS 15.00
Total:- 3701.35

Add 15% CP & OH charges. 555.20

Cost for 100 mtrs. Rs. 4256.55

Cost for One Mtr. Rs. 42.57

Say Rs. 43.00

Executive Engineer,
IPHDivision No.II
Kullu at Bhunter
Analysis of Rate
P/F0.60 cm overall valley , 0.63mm thick prepainted steel sheet in roofing with hot dipping metallic zinc coated sheet
with top coat of regular modified polyster (RNP) organic coating of 20 micron over 5 micron priming .
0.63mm thick.
Detail of cost for 9.325
S.No. Desciption Unit Quantity Rate Amount
Material:-
Prepainted sheet .60 cm overall
9.325 Rmt

Total:- 9.325
Add 5% wastage. 0.47
9.79 sqm

sqm 9.79 300.00 2937.38

Prepainted bolts and nuts 10Nos 12.00 45.00 54.00


Limpet washers. 100 Nos. 12.00 50.00 6.00
bitumen washers 100 Nos 12.00 25.00 3.00

Carriage:-
Prepainted sheet
25.00 Km by head load Tonne 0.047 382.17 17.96
0.00 Km by head load Tonne 0.047 0.00 0.00
Nuts bolts and washers. LS 5.00

Labour:-
carpenter 1st class Each 0.40 311.5 124.60
Black smith 1st class Each 1.04 311.5 323.96
Black smith 1st class Each 1.04 311.5 323.96
Beldar Each 2.4 262.5 30.00
Sundries LS 20
Total Rs. 3845.86

Add 15% CP & OH Charges. 576.88

Cost for 9.325sqm Rs. 4422.74

Cost for One sqm Rs. 474.29

Say Rs. 474.29

Executive Engineer,
IPHDivision No.II
Kullu at Bhunter
Analysis of Rate
P/F 0.63mm thick prepainted steel sheet in roofing with hot dipping metallic zinc coated sheet
with top coat of regular modified polyster (RNP) organic coating of 20 micron over 5 micron priming .
0.63mm thick.
Detail of cost for a area of roof 2x18.09x5.10m =184.518 sqm.
S.No. Desciption Unit Quantity Rate Amount
Material:-
Prepainted sheet 0.63mm thick.
54*2.5*.80 108 sqm
54*2.8*.8 120.96 Mtrs.
Total:- 228.96
Add 5% wastage. 11.45
240.41 sqm

sqm 240.41 500.00 120204.00

Prepainted bolts and nuts 10Nos 884.00 45.00 3978.00


Prepainted J or L hooks 10 Nos. 810.00 60.00 4860.00
Limpet washers. 100 Nos 1694.00 40.00 677.60

Carriage:-
Prepainted sheet
25.00 Km by head load Tonne 1.902 382.17 726.89
0.00 Km by head load Tonne 1.902 0.00 0.00
Nuts bolts and washers.
25.00 Km by head load Tonne 0.45 382.17 171.98
0.0 Km by head load Tonne 0.45 0.00 0.00
Labour:-
Black smith 2nd class Each 1.30 311.5 404.95
Carpenter 2nd class Each 14.75 311.5 4594.63
Beldar Each 14.75 262.5 3871.88
Sundries. LS 30.00

Total Rs. 139519.91

Add 15% CP & OH Charges. 20927.99

Cost for 184.520 sqm Rs. 160447.90

Cost for One sqm Rs. 869.54

Say Rs. 869.54

Executive Engineer,
IPHDivision No.II
Kullu at Bhunter
Analysis of Rate
P/F on wall face PVC ( D-plast)accessories for rain water pipe
PVC plain bend 150mm dia

Detail of cost for 1 No.


S.No. Desciption Unit Quantity Rate Amount

MATERIAL :
PVC plain bend 150mm dia Each 1 240 240
Approved adhesive LS 5

Carriage of bend LS 4
Labour :

Labour LS 6

255
Add 10% C.P. & 5% O.H. Charges : 38.25
Cost of 1 No. 293.25

Say Rs. 293.25 /- only.

Executive Engineer,
IPH Division, Mandi.
District Mandi HP.
MATERIAL :
1st class indian teak wood Cum. 0.055 65000 3575
Carriage :
5.00 Km.By mechanical transport Cum 0.055 121.78 6.7
200 Km.By head load Cum 0.055 46.40 2.55
Labour :
Carpenter 1st class Each 0.99 130.67 129.36
Carpenter 2nd class Each 0.99 103.83 102.79
Beldar Each 1.47 262.5 385.88
Sundries 30

4232.28
Add 10% C.P. & 5% O.H. Charges : 634.84
Cost of 10 Rmt 4867.12
Cost of 1 rmt 486.712
Say Rs. 486.71 /- only.

Executive Engineer,
IPH Division, Mandi.
District Mandi HP.
Analysis of Rate
P/F on wall face PVC ( D-plast)accessories for rain water pipe
PVC Shoe 150mm dia

Detail of cost for 1 No.


S.No. Desciption Unit Quantity Rate Amount

MATERIAL :
PVC Shoe 150mm dia Each 1 125 125
Approved adhesive LS 5

Carriage of bend LS 4
Labour :

Labour LS 6

140
Add 10% C.P. & 5% O.H. Charges : 21
Cost of 1 No. 161

Say Rs. 161.00 /- only.

Executive Engineer,
IPH Division, Mandi.
District Mandi HP.
Analysis of rate
P/F oxidized MS single acting spring hinges with necessary screws
150mm

Detail of cost for 10 Sqm.


Desciption Unit Quantity Rate Amount
Materials
MS single acting spring Each 10 85 850
Iron screws 50mm 100 Nos 80 40 32
CARRIAGE
Carriage of materials L.S 2

LABOUR
Carpenter 2ndClass Each 0.4 311.5 124.6
Beldar Each 0.2 262.5 52.5

Total:- 1061.1
Add 10% CP & 5% OH Charges 0.15 159.165
Cost for 10 Nos. 1220.265
Cost Per Sqm 10 122.03
Say Rs. 122

Executive Engineer,
IPHDivision No.II
Kullu at Bhunter
Analysis of rate
Providing and fixing chamfered edged cover fillets ( beading) 50mmx12mm section
with wood screws in ceiling and lining i/c mitring at junction
Detail of cost for 100 metre.
S.No. Description of items Unit Qty. Rate Amount

Material
1st class deodar wood cum 0.066 59640 3936.24
Screw 50mm long 100Nos. 660 60 396.00
Carriage of wood :
3.00 Km.By mechanical transport Cum 0.066 193.71 12.78
0.00 Km.By head load Cum 0.066 0.00 0.00

LABOUR
Carpenter 1st class Each 1.68 311.5 523.32
Carpenter 2nd class Each 1.68 311.5 523.32
Beldar Each 3.33 262.5 874.13
Sundries+scaffolding LS 15.00
Total:- 6280.79
Add 10 % CP & 5 % OH Charges on Rs. 1180.47 942.12
Cost for 100 meter 7237.9085

Cost per Mt. Rs:- 72.38

Executive Engineer,
IPHDivision No.II
Kullu at Bhunter
Analysis of rate.
P/F MS round holding down or anchor bolts with nuts and washers plates

Detail of cost for 0.024 Qtls.


S.No. Description of items Unit Qty. Rate Amount

Materials
16mm dia MS round 1.20 Mtr@ 1.58 kg/mtr
1.896 or 0.019 Qtl 0.019 4300 81.7
Plates 100x100x6mm @ 47kg /sqm
=.47 or .005 qtl Qtl 0.005 4500 22.5

Carriage:- LS 1.00

Labour
black smith 2nd class Each 0.03 311.5 9.345
fixing charges LS 5.00
119.55
Add 1.5 % for water charges 1.793
121.34
add 15% CP & OH charges 18.2
cost for 0.024 qtl:- 139.54

Cost for 1 Qtl 5814.09

Say Rs. 5814

Executive Engineer,
IPHDivision No.II
Kullu at Bhunter
Analysis of Rate
Providing and fixing MS BP sheet 1.66mm to 2mm thick in eaves board/facia/soffits/ceiling i/c cutting
and welding to sheet roof members and applying a coat of red lead primer.

DETAIL OF COST FOR 6.50 sqm


S.No. Description Unit Quantity Rate Amount
Material
BP sheet
front facia=1x10 1 10 0.2 2.0
Soffits 1 10 0.45 4.5
Total:- Total 6.5
weight 6.50x15.69kg/sqm 102
5% wastage 5.1
Total 107.1
Welding charges KG 107.1 55.00 5890.5
front side 25% of length
1x10x25% 2.5 250 cm
Base member @ 30cm C/C
10/0.30+1=34*5*2 340 cm
Total:- 590 CM 290.00 2.00 580.00
Priming coat=2x6.50 sqm 13.00 28.79 374.27
Carriage-
25.00 Km by Mech Transport Tonne 0.107 382.17 40.89
0.00 Km by head load Tonne 0.107 0.00 0.00

Labour:-
Black smith 1stclass Each 0.5 311.5 155.75
Beldar Each 0.5 262.5 131.25
Bandhani Each 0.2 262.5 52.50
sundries LS 50.00
Total:- 7275.16
Add 15 % for CP & OH Charges. 1091.27
Cost for 6.5 sqm = Rs. 8366.44

Cost For 1 sqm = Rs. 1287.14

Say Rs. 1287.00 Per sqm.

Executive Engineer,
IPHDivision No.II
Kullu at Bhunter
Analysis of rate
Providing and fixing 50mm bright finished brass cup board or ward rob knob

Detail of cost for 10 Nos.


Description of items Unit Qty. Rate Amount

Material
Bright finished brass cup board or Each 10 32 320
ward robe nobe.
Carriage :
Carriage of Materials LS 1.5

LABOUR
Carpenter 1st class Each 0.14 311.5 43.61

Total:- 365.11
Add 10 % CP & 5 % OH Charges . 54.77
Cost for 10 Nos 419.88

Cost per Mt. Rs:- 41.99

Executive Engineer,
IPHDivision No.II
Kullu at Bhunter
Providing and fixing brass sliding door bolt with nuts and screws

screws etc complete.


Details of cost for 10 Nos.
Materials
i) 300x16 mm 10 Nos 190 Each 1900

Carriage
Carriage of materials LS 3
Labour
Carpenter 1st class 0.4 Nos 130.67 Each 52.27
1955.27
Add 10%CP5%OHCharges 293.29
Cost for 10 Nos 2248.56
Cost per Nos 10 224.86
Providing and fixing brass sliding door bolt with nuts and screws
screws etc complete.
Details of cost for 10 Nos.

Materials
i) 250x16 mm each 10 180 Each 1800

Carriage
Carriage of materials LS 2
Labour
Carpenter 1st class 0.4 Nos 130.67 Each 52.27
1854.27
Add 10%CP5%OHCharges 278.14
Cost for 10 Nos 2132.41
Cost per Nos 10 213.24
Providing and fixing brass tower bolts(barrel type) with screws etc. complete.
Details of cost for 10 Nos.

Material
s
Aluminium tower bolt
(Barrel type)
250x10 10 Nos 125 Each 1250
Steel Screws 25 mm 100 Nos 80 100 80
Carriag
e
Carriage of materials LS 4
Labour

Carpenter 1st class 0.1 Nos 130.67 Each 13.07


1347.07
Add 202.06
10%CP5%OHCharges
Cost for 10 Nos 1549.13
Cost per Nos 10 154.91
Providing and fixing brass tower bolts(barrel type) with screws etc. complete.

Details of cost for 10 Nos.


Material
s
Aluminium tower bolt
(Barrel type)
200x10 10 Nos 105 Each 1050
Steel Screws 25 mm 80 Nos 80 100 64
Carriag
e
Carriage of materials LS 4
Labour

Carpenter 1st class 0.1 Nos 130.67 Each 13.07


1131.07
Add 169.66
10%CP5%OHCharges
Cost for 10 Nos 1300.73
Cost per Nos 10 130.07
Providing and fixing brass tower bolts(barrel type) with screws etc. complete.

Details of cost for 10 Nos.


Material
s
Brass tower bolt (Barrel
type)
150x10 10 Nos 85 Each 850
Brass Screws 25 mm 60 Nos 80 100 48
Carriag
e
Carriage of materials LS 4
Labour

Carpenter 1st class 0.08 Nos 130.67 Each 10.45


912.45
Add 136.87
10%CP5%OHCharges
Cost for 10 Nos 1049.32
Cost per Nos 10 104.93
Providing and fixing brass tower bolts(barrel type) with screws etc. complete.

Details of cost for 10 Nos.


Material
s
Brass tower bolt (Barrel
100x10 type) 10 Nos 65 Each 650
Brass Screws 25 mm 60 Nos 80 100 48
Carriag
e
Carriage of materials LS 4
Labour

Carpenter 1st class 0.08 Nos 130.67 Each 10.45


712.45
Add 106.87
10%CP5%OHCharges
Cost for 10 Nos 819.32
Cost per Nos 10 81.93
Providing and fixing bright finished brass handles with necessary screws etc. complete

Detail of cost for 10 Nos.


Material

Bright finished brass 10 Nos 90 900


handles 125 mm

Brass screw 25 mm 40 Nos 80 100 32


CARRIAGE
Carriage of materials 2
LABOU .
R
Carpenter 1st class 0.06 Nos 130.67 7.84

941.84
Add 10% CP & 5% OH 0.15 141.28
CostCharges
for 10 Nos. 1083.12

Cost 10 108.312
Per
Providing and fixing bright finished brass handles with necessary screws etc. complete

Detail of cost for 10 Nos.


Material

Bright finished brass 10 Nos 75 750


handles 100 mm
Brass screw 25 mm 40 Nos 80 100 32
CARRIAGE
Carriage of materials 2

LABOU .
R
Carpenter 1st class 0.05 Nos 130.67 6.53

790.53
Add 10% CP & 5% OH 0.15 118.58
Charges
Cost for 10 Nos. 909.11
Cost 10 90.911
Per
CARRIAGE OF MATERIALS

A CEMENT : Unit : Per Tonne. A STEEL: Unit : Per Tonne.


AV. LEAD : By Mech. 25 Km. AV. LEAD : By Mech. 25 Km.
By Head : 0 Km. By Head : 0 Km.
1 By Mech. Nos. Rate/ Km. 1 By Mech. Nos. Rate/ Km.
1 Km. 0 98.28 0.00 1 Km. 0 98.28 0.00
2 Km. 0 113.79 0.00 2 Km. 0 113.79 0.00
3 Km. 0 129.14 0.00 3 Km. 0 129.14 0.00
4 Km. 0 144.07 0.00 4 Km. 0 144.07 0.00
5 Km. 1 158.32 158.32 5 Km. 1 158.32 158.32
5- 10 Km. 5 13.21 66.05 5- 10 Km. 5 13.21 66.05
10-20 Km. 10 11.09 110.90 10-20 Km. 10 11.09 110.90
Beyond 20 Km. 5 9.38 46.90 Beyond 20 Km. 5 9.38 46.90
TOTAL : 382.17 TOTAL : 382.17
2 By Head load 2 By Head load
1st. 1 Km. 0 453.26 0.00 1st. 1 Km. 0 957.01 0.00
1st. 100 Mtr 0 72.02 0.00 1st. 100 Mtr 0 152.05 0.00
Bey:1 Km.Per 1/2Km. 0 226.63 0.00 Bey:1 Km.Per 1/2Km. 0 478.51 0.00
Bey:100 Mtr Per 50 Mtr 0 21.18 0.00 Bey:100 Mtr Per 50 Mtr 0 44.72 0.00
Total : 0.00 Total : 0.00

G.Total: 1+2= 382.17 Per Tonne. G.Total: 1+2= 382.17 Per Tonne.

A Sand: Stone aggregate below


Unit : Per Cum. A 40mm.: Unit : Per Cum.
AV. LEAD : By Mech. 7 Km. AV. LEAD : By Mech. 7 Km.
By Head : 0 Km. By Head : 0 Km.
1 By Mech. Nos. Rate/ Km. 1 By Mech. Nos. Rate/ Km.
1 Km. 0 147.42 0.00 1 Km. 0 147.42 0.00
2 Km. 0 170.69 0.00 2 Km. 0 170.69 0.00
3 Km. 0 193.71 0.00 3 Km. 0 193.71 0.00
4 Km. 0 216.11 0.00 4 Km. 0 216.11 0.00
5 Km. 1 237.47 237.47 5 Km. 1 237.47 237.47
5- 10 Km. 2 19.81 39.62 5- 10 Km. 2 19.81 39.62
10-20 Km. 0 16.64 0.00 10-20 Km. 0 16.64 0.00
Beyond 20 Km. 0 14.07 0.00 Beyond 20 Km. 0 14.07 0.00
TOTAL : 277.09 TOTAL : 277.09
2 By Head load 2 By Head load
1st. 1 Km. 0 769.34 0.00 1st. 1 Km. 0 769.34 0.00
1st. 100 Mtr 0 122.24 0.00 1st. 100 Mtr 0 122.24 0.00
Bey:1 Km.Per 1/2Km. 0 384.67 0.00 Bey:1 Km.Per 1/2Km. 0 384.67 0.00
Bey:100 Mtr Per 50 Mtr 0 35.95 0.00 Bey:100 Mtr Per 50 Mtr 0 35.95 0.00
Total : 0.00 Total : 0.00

G.Total: 1+2= 277.09 Per cum.. G.Total: 1+2= 277.09 Per cum..

A Stone aggregate A Building stone:


40mm and above: Unit : Per Cum. Unit : Per Cum.
AV. LEAD : By Mech. 0 Km. AV. LEAD : By Mech. 0 Km.
By Head : 0.5 Km. By Head : 1 Km.

1 By Mech. Nos. Rate/ Km. 1 By Mech. Nos. Rate/ Km.


1 Km. 0 159.55 0.00 1 Km. 0 159.55 0.00
2 Km. 0 184.73 0.00 2 Km. 0 184.73 0.00
3 Km. 0 209.65 0.00 3 Km. 0 209.65 0.00
4 Km. 0 233.88 0.00 4 Km. 0 233.88 0.00
5 Km. 0 257.01 0.00 5 Km. 0 257.01 0.00
5- 10 Km. 0 21.44 0.00 5- 10 Km. 0 21.44 0.00
10-20 Km. 0 18.01 0.00 10-20 Km. 0 18.01 0.00
Beyond 20 Km. 0 15.23 0.00 Beyond 20 Km. 0 15.23 0.00
TOTAL : 0.00 TOTAL : 0.00
2 By Head load 2 By Head load
1st. 1 Km. 0 831.81 0.00 1st. 1 Km. 1 831.81 831.81
1st. 100 Mtr 1 132.15 132.15 1st. 100 Mtr 0 132.15 0.00
Bey:1 Km.Per 1/2Km. 0 415.91 0.00 Bey:1 Km.Per 1/2Km. 0 415.91 0.00
Bey:100 Mtr Per 50 Mtr 8 38.87 310.96 Bey:100 Mtr Per 50 Mtr 0 38.87 0.00
Total : 443.11 Total : 831.81

G.Total: 1+2= 443.11 Per cum.. G.Total: 1+2= 831.81 Per cum..
A Soling Stone: A Heavy material and
Unit : Per Cum. pipe below 100mm. Unit : Per Tonne.
AV. LEAD : By Mech. 0 Km. AV. LEAD : By Mech. 25 Km.
By Head : 0.5 Km. By Head : 0 Km.
1 By Mech. Nos. Rate/ Km. 1 By Mech. Nos. Rate/ Km.
1 Km. 0 173.44 0.00 1 Km. 0 98.28 0.00
2 Km. 0 200.81 0.00 2 Km. 0 113.79 0.00
3 Km. 0 227.90 0.00 3 Km. 0 129.14 0.00
4 Km. 0 254.24 0.00 4 Km. 0 144.07 0.00
5 Km. 0 279.38 0.00 5 Km. 1 158.32 158.32
5- 10 Km. 0 23.31 0.00 5- 10 Km. 5 13.21 66.05
10-20 Km. 0 19.57 0.00 10-20 Km. 10 11.09 110.90
Beyond 20 Km. 0 16.55 0.00 Beyond 20 Km. 5 9.38 46.90
TOTAL : 0.00 TOTAL : 382.17
2 By Head load 2 By Head load
1st. 1 Km. 0 769.34 0.00 1st. 1 Km. 0 561.75 0.00
1st. 100 Mtr 1 122.24 122.24 1st. 100 Mtr 0 89.25 0.00
Bey:1 Km.Per 1/2Km. 0 384.67 0.00 Bey:1 Km.Per 1/2Km. 0 280.88 0.00
Bey:100 Mtr Per 50 Mtr 8 35.95 287.60 Bey:100 Mtr Per 50 Mtr 0 26.25 0.00
Total : 409.84 Total : 0.00
G.Total: 1+2= 409.84 Per cum.. G.Total: 1+2= 382.17 Per Tonne.
A Timber
Unit : Per Cum.
A Bricks: AV. LEAD : By Mech. 3 Km.
Unit : Per 1000.Nos. By Head : 0 Km.
AV. LEAD : By Mech. 3 Km. 1 By Mech. Nos. Rate/ Km.
By Head : 0 Km. 1 Km. 0 147.42 0.00
2 Km. 0 170.69 0.00
1 By Mech. Nos. Rate/ Km. 3 Km. 1 193.71 193.71
1 Km. 0 368.56 0.00 4 Km. 0 216.11 0.00
2 Km. 0 426.73 0.00 5 Km. 0 237.47 0.00
3 Km. 1 484.28 484.28 5- 10 Km. 0 19.81 0.00
4 Km. 0 540.27 0.00 10-20 Km. 0 16.64 0.00
5 Km. 0 593.69 0.00 Beyond 20 Km. 0 14.07 0.00
5- 10 Km. 0 49.53 0.00 TOTAL : 193.71
10-20 Km. 0 41.60 0.00 2 By Head load
Beyond 20 Km. 0 35.17 0.00 1st. 1 Km. 0 615.25 0.00
TOTAL : 484.28 1st. 100 Mtr 0 97.75 0.00
Bey:1 Km.Per 1/2Km. 0 307.63 0.00
2 By Head load Bey:100 Mtr Per 50 Mtr 0 28.75 0.00
1st. 1 Km. 0 1436.16 0.00 Total : 0.00
1st. 100 Mtr 0 228.18 0.00
Bey:1 Km.Per 1/2Km. 0 718.08 0.00 G.Total: 1+2= 193.71 Per cum..
Bey:100 Mtr Per 50 Mtr 0 67.11 0.00
Total : 0.00

G.Total: 1+2= 484.28 Per 1000.


A RCC,AC,Hume & Steel A RCC,AC,Hume & Steel
Pipes.150 mm Unit : Per 100 Mt. Pipes. 250 mm Unit : Per 100 Mt.
AV. LEAD : By Mech. 0 Km. AV. LEAD : By Mech. 0 Km.
By Head : 0 Km. By Head : 0 Km.
1 By Mech. Nos. Rate/ Km. 1 By Mech. Nos. Rate/ Km.
1 Km. 0 402.79 0.00 1 Km. 0 915.44 0.00
2 Km. 0 466.37 0.00 2 Km. 0 1059.92 0.00
3 Km. 0 529.27 0.00 3 Km. 0 1202.88 0.00
4 Km. 0 590.46 0.00 4 Km. 0 1341.95 0.00
5 Km. 0 648.84 0.00 5 Km. 0 1474.63 0.00
5- 10 Km. 0 54.13 0.00 5- 10 Km. 0 123.03 0.00
10-20 Km. 0 45.46 0.00 10-20 Km. 0 103.32 0.00
Beyond 20 Km. 0 38.44 0.00 Beyond 20 Km. 0 87.36 0.00
TOTAL : 0.00 TOTAL : 0.00
2 By Head load 2 By Head load
1st. 1 Km. 0 618.02 0.00 1st. 1 Km. 0 1629.83 0.00
1st. 100 Mtr 0 98.18 0.00 1st. 100 Mtr 0 258.95 0.00
Bey:1 Km.Per 1/2Km. 0 309.01 0.00 Bey:1 Km.Per 1/2Km. 0 814.92 0.00
Bey:100 Mtr Per 50 Mtr 0 28.88 0.00 Bey:100 Mtr Per 50 Mtr 0 76.16 0.00
Total : 0.00 Total : 0.00
G.Total: 1+2= 0.00 Per 100 Mt. G.Total: 1+2= 0.00 Per 100 Mt.
A RCC,AC,Hume & Steel A RCC,AC,Hume & Steel
Pipes.300 mm Unit : Per 100 Mt. Pipes. 350 mm Unit : Per 100 Mt.
AV. LEAD : By Mech. 0 Km. AV. LEAD : By Mech. 0 Km.
By Head : 0 Km. By Head : 0 Km.
1 By Mech. Nos. Rate/ Km. 1 By Mech. Nos. Rate/ Km.
1 Km. 0 1184.68 0.00 1 Km. 0 1678.30 0.00
2 Km. 0 1371.67 0.00 2 Km. 0 1943.19 0.00
3 Km. 0 1556.67 0.00 3 Km. 0 2205.28 0.00
4 Km. 0 1736.64 0.00 4 Km. 0 2460.25 0.00
5 Km. 0 1908.34 0.00 5 Km. 0 2703.48 0.00
5- 10 Km. 0 159.21 0.00 5- 10 Km. 0 225.55 0.00
10-20 Km. 0 133.70 0.00 10-20 Km. 0 189.41 0.00
Beyond 20 Km. 0 113.05 0.00 Beyond 20 Km. 0 160.15 0.00
TOTAL : 0.00 TOTAL : 0.00
2 By Head load 2 By Head load
1st. 1 Km. 0 2039.62 0.00 1st. 1 Km. 0 2915.96 0.00
1st. 100 Mtr 0 324.04 0.00 1st. 100 Mtr 0 463.28 0.00
Bey:1 Km.Per 1/2Km. 0 1019.81 0.00 Bey:1 Km.Per 1/2Km. 0 1457.98 0.00
Bey:100 Mtr Per 50 Mtr 0 95.31 0.00 Bey:100 Mtr Per 50 Mtr 0 136.26 0.00
Total : 0.00 Total : 0.00
G.Total: 1+2= 0.00 Per 100 Mt. G.Total: 1+2= 0.00 Per 100 Mt.
A RCC,AC,Hume & Steel
Pipes.400 mm Unit : Per 100 Mt.
AV. LEAD : By Mech. 0 Km.
By Head : 0 Km.
1 By Mech. Nos. Rate/ Km.
1 Km. 0 1122.74 0.00
2 Km. 0 1301.21 0.00
3 Km. 0 1477.78 0.00
4 Km. 0 1649.64 0.00
5 Km. 0 1813.66 0.00
5- 10 Km. 0 152.19 0.00
10-20 Km. 0 128.05 0.00
Beyond 20 Km. 0 108.50 0.00
TOTAL : 0.00
2 By Head load
1st. 1 Km. 0 3392.98 0.00
1st. 100 Mtr 0 539.08 0.00
Bey:1 Km.Per 1/2Km. 0 1696.49 0.00
Bey:100 Mtr Per 50 Mtr 0 158.55 0.00 Executive Engineer,
Total : 0.00 IPHDivision No.II
G.Total: 1+2= 0.00 Per 100 Mt. Kullu at Bhunter
CARRIAGE OF MATERIAL BY MECHANICAL TRANSPORT
Sl.No. Average speed Km/hour(s) No.of No.of Litre of Litre of Litres of Cost of Cost of Hire Total cost Cost per trip Increase Average
Lead Trips Km. diesel Diesel @ M.Oil M.Oil@ 6 Charges of Col.No6+8+ in Cost cost per
inK.M. No. done consum-ed per Ltr. consum- per litre Beldar@ Truk@ per 9+10 per Km additional
(L) 2NL+6 ed per day day over Km.after
previous five Km.
Km.

58 250 262.5 2200


1 2 3 4 5 6 7 8 9 10 11 12 13 14
1 12 5.65 17.30 5.77 334.66 0.22 55 1575 2200 4164.66 737.11
2 12.75 5.12 26.48 8.83 512.14 0.33 82.5 1575 2200 4369.64 853.45 116.34
3 13.12 4.69 34.14 11.38 660.04 0.43 107.5 1575 2200 4542.54 968.56 115.11
4 13.5 4.34 40.72 13.57 787.06 0.51 127.5 1575 2200 4689.56 1080.54 111.98
5 13.88 4.06 46.60 15.53 900.74 0.58 145 1575 2200 4820.74 1187.37 106.83
6 14.25 3.82 51.84 17.28 1002.24 0.65 162.5 1575 2200 4939.74 1293.13 105.76
7 14.63 3.62 56.68 18.89 1095.62 0.71 177.5 1575 2200 5048.12 1394.51 101.38
8 15.1 3.46 61.36 20.45 1186.10 0.77 192.5 1575 2200 5153.60 1489.48 94.97
9 15.38 3.31 65.58 21.86 1267.88 0.82 205 1575 2200 5247.88 1585.46 95.98
10 15.75 3.17 69.40 23.13 1341.54 0.87 217.5 1575 2200 5334.04 1682.66 97.20 99.06
11 16.13 3.06 73.32 24.44 1417.52 0.92 230 1575 2200 5422.52 1772.07 89.41
12 16.5 2.96 77.04 25.68 1489.44 0.96 240 1575 2200 5504.44 1859.61 87.54
13 16.88 2.87 80.62 26.87 1558.46 1.01 252.5 1575 2200 5585.96 1946.33 86.72
14 17.25 2.78 83.84 27.95 1621.10 1.05 262.5 1575 2200 5658.60 2035.47 89.14
15 17.63 2.71 87.30 29.1 1687.80 1.09 272.5 1575 2200 5735.30 2116.35 80.88
16 18 2.64 90.48 30.16 1749.28 1.13 282.5 1575 2200 5806.78 2199.54 83.19
17 18.38 2.58 93.72 31.24 1811.92 1.18 295 1575 2200 5881.92 2279.81 80.27
18 18.75 2.52 96.72 32.24 1869.92 1.21 302.5 1575 2200 5947.42 2360.09 80.28
19 19.13 2.47 99.86 33.29 1930.82 1.25 312.5 1575 2200 6018.32 2436.57 76.48
20 19.5 2.42 102.80 34.27 1987.66 1.29 322.5 1575 2200 6085.16 2514.53 77.96 83.19
21 19.88 2.38 105.96 35.32 2048.56 1.32 330 1575 2200 6153.56 2585.53 71.00
22 20.25 2.34 108.96 36.32 2106.56 1.36 340 1575 2200 6221.56 2658.79 73.26
23 20.63 2.30 111.80 37.27 2161.66 1.4 350 1575 2200 6286.66 2733.33 74.54
24 21 2.26 114.48 38.16 2213.28 1.43 357.5 1575 2200 6345.78 2807.87 74.54
25 21.38 2.23 117.50 39.17 2271.86 1.48 370 1575 2200 6416.86 2877.52 69.65
26 21.75 2.20 120.40 40.13 2327.54 1.51 377.5 1575 2200 6480.04 2945.47 67.95
27 22.13 2.17 123.18 41.06 2381.48 1.54 385 1575 2200 6541.48 3014.51 69.04
28 22.5 2.14 125.84 41.95 2433.10 1.57 392.5 1575 2200 6600.60 3084.39 69.88
29 22.88 2.11 128.38 42.79 2481.82 1.6 400.00 1575 2200 6656.82 3154.89 70.50
30 23.25 2.09 131.40 43.8 2540.40 1.64 410 1575 2200 6725.40 3217.89 63.00 70.34
Sl.No. Average speed Km/hour(s) No.of No.of Litre of Litre of Litres of Cost of Cost of Hire Total cost Cost per trip Increase Average
Lead Trips Km. diesel Diesel @ M.Oil M.Oil@ 6 Charges of Col.No6+8+ in Cost cost per
inK.M. No. done consum-ed per Ltr. consum- per litre Beldar@ Truk@ per 9+10 per Km additional
(L) 2NL+6 ed per day day over Km.after
previous five Km.
Km.

58 250 262.5 2200


1 2 3 4 5 6 7 8 9 10 11 12 13 14

CARRIAGE OF MATERIAL BY MECHANICAL TRANSPORT INCLUDING LOADING/UNLOADINGAND STACKING OF MATERIALS


S.No MATERIALS CAPACI NET UNITS COST PER UNIT MATERIAL/DISTANCE GIVEN BELOW
QTY.TO
TY BE PAID 1 Km. 2Km. 3Km. 4Km. 5Km. BEYOND BEYOND BEYOND 20Km /Km.
5Km.UP TO 10 10Km.UP TO 20
AFTER Km. Km.
DEDUCTI
ON OF
VOIDS.
737.11 853.45 968.56 1080.54 1187.37 99.06 83.19 70.34
1 2 3 4 5 6 7 8 9 10 11 12 13
Lime, moorum , building
1 6 cu.m 6 1 cu.m 122.85 142.24 161.43 180.09 197.90 16.51 13.87 11.72
rubish.
2 .Earth work. 6 cu.m 4.8 1 cu.m 153.56 177.80 201.78 225.11 247.37 20.64 17.33 14.65

3 Manure or sludge 6 cu.m 5.52 1 cu.m 133.53 154.61 175.46 195.75 215.10 17.95 15.07 12.74

4 Excavated rock. 6 cu.m 3 1 cu.m 245.70 284.48 322.85 360.18 395.79 33.02 27.73 23.45
Sand,stone agg. below
5 5 cu.m 5 1 cu.m 147.42 170.69 193.71 216.11 237.47 19.81 16.64 14.07
40mm
Stone agg.40mm & above,build.
6 Stones. 5 cu.m 4.62 1 cu.m 159.55 184.73 209.65 233.88 257.01 21.44 18.01 15.23
Soling stone, stone block & stone
7 for filling crates 5 cu.m 4.25 1 cu.m 173.44 200.81 227.90 254.24 279.38 23.31 19.57 16.55
2000Nos
8 Bricks. 2000 1000 Nos. 368.56 426.73 484.28 540.27 593.69 49.53 41.60 35.17
.
3200Nos
9 Bricks tiles. 3200 1000 Nos. 230.35 266.70 302.68 337.67 371.05 30.96 26.00 21.98
.
10 Slates. 14450Nos. 14450 1000 Nos. 51.01 59.06 67.03 74.78 82.17 6.86 5.76 4.87
2500Nos
11 Terrazzo Tiles. 2500 1000 Nos. 294.84 341.38 387.42 432.22 474.95 39.62 33.28 28.14
.
Cement G.I. CI. AC. CC pipes
12 below 100mm dia & other heavy 7.50 Tonne 7.5 1 Tonne 98.28 113.79 129.14 144.07 158.32 13.21 11.09 9.38
materials.

13 Steam Coal 5.5 Tonne 5.5 1 Tonne 134.02 155.17 176.10 196.46 215.89 18.01 15.13 12.79

14 Steel i/c C.G.I & A.C.sheet. 7.50 Tonne 7.5 1 Tonne 98.28 113.79 129.14 144.07 158.32 13.21 11.09 9.38
Sl.No. Average speed Km/hour(s) No.of No.of Litre of Litre of Litres of Cost of Cost of Hire Total cost Cost per trip Increase Average
Lead Trips Km. diesel Diesel @ M.Oil M.Oil@ 6 Charges of Col.No6+8+ in Cost cost per
inK.M. No. done consum-ed per Ltr. consum- per litre Beldar@ Truk@ per 9+10 per Km additional
(L) 2NL+6 ed per day day over Km.after
previous five Km.
Km.

58 250 262.5 2200


1 2 3 4 5 6 7 8 9 10 11 12 13 14
15 Timber 5 cu.m 5 1 cu.m 147.42 170.69 193.71 216.11 237.47 19.81 16.64 14.07
4.50
16 Tar Bitumen etc. 4.5 1 Tonne 163.80 189.66 215.24 240.12 263.86 22.01 18.49 15.63
Tonne
R.C.C.,A.C. Hume, steel
17 C.I.Pipes:- 80 mm dia 329.40m 329.4 100m 223.77 259.09 294.04 328.03 360.46 30.07 25.26 21.35

18 100 mm dia 292.80m 292.8 100m 251.75 291.48 330.79 369.04 405.52 33.83 28.41 24.02
19 125 mm dia 219.6m 219.6 100m 335.66 388.64 441.06 492.05 540.70 45.11 37.88 32.03
20 150 mm dia 183m 183 100m 402.79 466.37 529.27 590.46 648.84 54.13 45.46 38.44
21 200 mm dia 109.80m 109.8 100m 671.32 777.28 882.11 984.10 1081.39 90.22 75.77 64.06
22 250 mm dia 80.52m 80.52 100m 915.44 1059.92 1202.88 1341.95 1474.63 123.03 103.32 87.36
23 300 mm dia 62.22m 62.22 100m 1184.68 1371.67 1556.67 1736.64 1908.34 159.21 133.70 113.05
24 350 mm dia 43.92m 43.92 100m 1678.30 1943.19 2205.28 2460.25 2703.48 225.55 189.41 160.15
25 400 mm dia 32.94m 32.94 100m 2237.74 2590.92 2940.38 3280.33 3604.64 300.73 252.55 213.54

26 450 /500mmdia 25.62m 25.62 100m 2877.09 3331.19 3780.48 4217.56 4634.54 386.65 324.71 274.55

27 600,700,750&800mm dia 18.30m 18.3 100m 4027.92 4663.66 5292.68 5904.59 6488.36 541.31 454.59 384.37
900,1000,1100&1200mm
28 11.00m 11 100m 6701.00 7758.64 8805.09 9823.09 10794.27 900.55 756.27 639.45
dia
Page 335 of 453

CARRIAGE OF MATERIAL BY MANUAL LABOUR INCLUDING LOADING/UNLOADINGAND STACKING OF MATERIALS


S.No MATERIALS CAPACIT NET UNITS COST OF COST OF CARRIGE INCLUDING LOADING AND STACCKING
QTY.TO BE
Y PAID
8 HOURS
AFTER FOR FOR EVERY FOR 100 FOR 1 BEYOND
DEDUCTIO FIRST 50 ADD. LEAD
OF 50
MTR KM. 1
N OF
VOIDS. MTR MTRS OR KM./EVE
PART RY 1/2
THERE OF KM.
BEYOND 50
MTRS UP
TO 0.50 KM

1 2 3 4 5 6 7 8 9 10 11
Beldar (A) 7.67 262.5 2013.38 (B) 1006.69 2818.73 2416.05
1 Lime, moorum and building rubish. 35 cu.m 35 1 cu.m 69.03 28.76 97.79 615.47 307.74
2 .Earth work. 35 cu.m 28 1 cu.m 86.29 35.95 122.24 769.34 384.67
3 Manure or sludge 35cu.m 32.2 1 cu.m 75.03 31.26 106.29 668.97 334.49
4 Excavated rock. 35 cu.m 17.5 1 cu.m 138.06 57.53 195.59 1231.13 615.57
5 Sand,stone agg.below 40mm size. 28 cu.m 28 1 cu.m 86.29 35.95 122.24 769.34 384.67
6 Stone agg.40mm & above,build. Stones. 28 cu.m 25.9 1 cu.m 93.28 38.87 132.15 831.81 415.91
7 Soling stone, stone block & stone for filling crates 28 cu.m 28 1 cu.m 86.29 35.95 122.24 769.34 384.67
Bricks. 15000 15000 1000 Nos. 161.07 67.11 228.18 1436.16 718.08
8
Nos
Bricks tiles. 24000 24000 1000 Nos. 100.67 41.95 142.62 897.72 448.86
9
Nos.
80000 80000 1000 Nos. 30.20 12.58 42.78 269.22 134.61
10
Nos.
Terrazzo Tiles. 15000 15000 1000 Nos. 161.07 67.11 228.18 1436.16 718.08
11
Nos
Page 336 of 453

S.No MATERIALS CAPACIT NET UNITS COST OF COST OF CARRIGE INCLUDING LOADING AND STACCKING
QTY.TO BE
Y PAID
8 HOURS
AFTER FOR FOR EVERY FOR 100 FOR 1 BEYOND
DEDUCTIO FIRST 50 ADD. LEAD
OF 50
MTR KM. 1
N OF
VOIDS. MTR MTRS OR KM./EVE
PART RY 1/2
THERE OF KM.
BEYOND 50
MTRS UP
TO 0.50 KM

1 2 3 4 5 6 7 8 9 10 11
Beldar (A) 9.2 262.5 2415.00 (B) 1207.50 3381.00 2898.00
Stone blocks G.I,C.C. pipes below 100mm
1 46 Tonne 46 1 Tonne 63.00 26.25 89.25 561.75 280.88
dia & other heavy materials.
2 cement 57 Tonne 57 1 Tonne 50.84 21.18 72.02 453.26 226.63
3 Steel including C.G.I & asbestos sheet. 27 Tonne 27 1 Tonne 107.33 44.72 152.05 957.01 478.51
4 Timber 42 cu.m 42 1 cu.m 69.00 28.75 97.75 615.25 307.63
5 Tar Bitumen etc. 46 Tonne 46 1 Tonne 63.00 26.25 89.25 561.75 280.88
1 2 3 4 5 6 7 8 9 10 11
Concrete, R.C.C. Hume, steel C.I.Pipes:- 100mm
6 dia 1702m 1702 100m 170.27 70.95 241.22 1518.32 759.16
Concrete, R.C.C. Hume, steel C.I.Pipes:-
7 1391m 1391 100m 208.34 86.81 295.15 1857.73 928.87
125mm dia
Concrete, R.C.C. Hume, steel C.I.Pipes:-
8 1208m 1208 100m 239.90 99.96 339.86 2139.14 1069.57
150mm dia
Concrete, R.C.C. Hume, steel C.I.Pipes:-
9 805m 805 100m 360.00 150.00 510.00 3210.00 1605.00
200mm dia
Concrete, R.C.C. Hume, steel C.I.Pipes:-
10 458m 458 100m 632.75 263.65 896.40 5642.10 2821.05
250mm dia
Concrete, R.C.C. Hume, steel C.I.Pipes:-
11 366m 366 100m 791.80 329.92 1121.72 7060.28 3530.14
300mm dia
Concrete, R.C.C. Hume, steel C.I.Pipes:-
12 256m 256 100m 1132.03 471.68 1603.71 10093.95 5046.98
350mm dia
Concrete, R.C.C. Hume, steel C.I.Pipes:-
13 220m 220 100m 1317.27 548.86 1866.13 11745.61 5872.81
400mm dia
Concrete, R.C.C. Hume, steel C.I.Pipes:-
14 165m 165 100m 1756.36 731.82 2488.18 15660.94 7830.47
450mm,500mm dia
Concrete, R.C.C. Hume, steel C.I.Pipes:-
15 150m 150 100m 1932.00 805.00 2737.00 17227.00 8613.50
600,700,750&800mm dia
Concrete, R.C.C. Hume, steel C.I.Pipes:-
16 900,1000,1100&1200mm dia 125m 125 100m 2318.40 966.00 3284.40 20672.40 10336.20
Page 337 of 453

S.No MATERIALS CAPACIT NET UNITS COST OF COST OF CARRIGE INCLUDING LOADING AND STACCKING
QTY.TO BE
Y PAID
8 HOURS
AFTER FOR FOR EVERY FOR 100 FOR 1 BEYOND
DEDUCTIO FIRST 50 ADD. LEAD
OF 50
MTR KM. 1
N OF
VOIDS. MTR MTRS OR KM./EVE
PART RY 1/2
THERE OF KM.
BEYOND 50
MTRS UP
TO 0.50 KM

1 2 3 4 5 6 7 8 9 10 11
Asbestes cement pipes: - 50mm dia
17 =5032 pipes of 2m length 10064m 10064m 10064 100m 28.80 12.00 40.80 256.80 128.40

As bestes cement pipes: - 80mm dia 1620


18 pipes of 2m length=3660 3660m 3660 100m 79.18 32.99 112.17 705.99 353.00

As bestes cement pipes:- 100mm dia


19 1281 pipes of 2m length=2562m 2562m 2562 100m 113.11 47.13 160.24 1008.58 504.29

As bestes cement pipes:- 125mm dia


20 2200m 2200 100m 131.73 54.89 186.62 1174.64 587.32
1100 pipes of 2m length= 2200m
As bestes cement pipes:- 150mm dia 915
21 1830m 1830 100m 158.36 65.98 224.34 1411.98 705.99
pipes of 2m length =1830m
As bestes cement pipes:- 200mm dia 800
22 pipes of 2m length= 1600m 1600m 1600 100m 181.13 75.47 256.60 1615.06 807.53

As bestes cement pipes:- 250mm dia 700


23 pipes of 2m length= 1400m 1400m 1400 100m 207.00 86.25 293.25 1845.75 922.88

As bestes cement pipes:- 300mm dia 600


24 pipes of 2m length= 1200m 1200m 1200 100m 241.50 100.63 342.13 2153.47 1076.74
LEAD CHART
Name ofg work:-

1 Cement,Steel, G.I. Pipes By Mechanical Transport By Head Load


Store_Shamshi 25 Km. 0 Km

2 Sand By Mechanical Transport By Head Load


Quarry_Hurla 7 Km. 0 Km

3 Agg. Below 40mm. By Mechanical Transport By Head Load


Quarry_Hurla 7 Km. 0 Km

4 Agg. 40mm & above By Mechanical Transport By Head Load


Quarry_Local 0 Km. 0.5 Km

5 Stone By Mechanical Transport By Head Load


Quarry_Local 0 Km. 1 Km

6 Bricks By Mechanical Transport By Head Load


Bhunter 3 Km. 0 Km

7 Timber By Mechanical Transport By Head Load


_________ 3 Km. 0 Km

8 RCC pipe By Mechanical Transport By Head Load


_________ 0 Km. 0 Km

Executive Engineer,
IPHDivision No.II
Kullu at Bhunter
MATERIAL RATES.
S.No. Description of items Unit Rate

1 Cast Iron spun spigot (1.83 Mtr each) Each 250.00 Market Rate
(50mm nominal size)
(75mm nominal size)Each 300.00 -----do--------
(100mm nominal sizeEach 350.00 -----do--------
2 Cast Iron Holder Bat (50mm nominal si Each 75.00 -----do--------
(75mm nominal size)Each 100.00 -----do--------
100mm nominal size)Each 125.00 -----do--------
3 C.I Bends (50mm) Required degree: Each 250.00 -----do--------
with ovel access
(75mm )Required degree --doEach 275.00 -----do--------
(100mm )Required degree do--Each 325.00 -----do--------
4 C.I Bends (50mm ) Reqd degree :-PlainEach 250.00 -----do--------
(75mm )Reqd degree :- Plain Each 275.00 -----do--------
(100mm ) reqd. degree:- Plain Each 325.00 -----do--------
5 Loose Socket 50mm Each 225.00 -----do--------
75mm Each 250.00 -----do--------
100mm Each 275.00 -----do--------
6 CI Cowl 50mm Each 110.00 -----do--------
75mm Each 125.00 -----do--------
100mm Each 145.00 -----do--------
7 Lead caulked joints:- Pig Lead Kg. 150.00 -----do--------
Spun Yarn. Kg. 150.00 -----do--------
8 Floor Trap :- 50mm Each 375.00 -----do--------
75mm Each 410.00 -----do--------
100mm Each 450.00 -----do--------
9 Vetreous china water closet :- ORRIS Each 2190.00 -----do--------
10 10/12.50/15 ltrs flushing cistern Each 1060.00 -----do--------
11 32mm dia pipe for high level cistern Each 110.00 -----do--------
12 Plastic seat ( Solid type) For water closeEach 0.00 -----do--------
13 Pillar trap for wash basin (FLAT BLACK)Each 3410.00 -----do--------
14 Padestal Each 1850.00 -----do--------
15 CI or MS bracket Each 45.00 -----do--------
16 50cm long chain (32mm) Each 100.00 -----do--------
(40mm) Each 115.00 -----do--------
17 Brass waste (32mm) Each 150.00 -----do--------
(40mm) Each 160.00 -----do--------
18 MI Union :- 32mm Each 60.00 -----do--------
40mm Each 80.00 -----do--------
19 600x450 edge miror Each 1400.00 -----do--------
20 Towel rail 150x20mm Each 840.00 -----do--------
21 600x120mm Glass self Each 500.00 -----do--------
22 Toilet Paper each 400.00 -----do--------
23 Liquid Soap Cointainer Each 400.00 -----do--------
24 Charomium plated for soap dish Each 400.00 -----do--------
25 Brass Shower rose 100mm Each 300.00 -----do--------
26 Tooth Brush Holder Each 150.00 -----do--------
27 CP brass bib tap with capstan head Each 240.00 -----do--------
28 Angular Valve 15mm Each 500.00 -----do--------
29 Mixer for Kitchen Each 2275.00 -----do--------
30 Wall mixer faucet shower Each 2890.00 -----do--------
31 Bath Shower (15mm) Each 1620.00 -----do--------
32 Hand Shower Angular Each 1360.00 -----do--------
33 Wall ceiling and floor GMS Tube (MG) Rmt. 80.00 -----do--------
34 Kitchen Sink Each 2750.00 -----do--------
35 AC or Ply Sheet. Sqm 300.00 -----do--------
36 Wooden plug Each 5.00 -----do--------

Without With P.H.


Rates of Labour. P.Hol.
1 Beldar Each 225 262.50
2 Bhisti Each 225 262.50
3 Mason Ist class Each 267 311.50
4 Mason II nd class Each 267 311.50
5 Mate Each 225 262.50
6 Black Smith Ist class Each 267 311.50 Approved rate.
7 Carpenter 2 nd class Each 267 311.50
8 Plumber (Fitter) Each 267 311.50
9 Hole Driller Each 225 262.50
10 Blaster Each 225 262.50
11 Stone dresser Each 225 262.50
12 Painter 1st class Each 267 311.50
13 Painter 2nd class Each 240 280.00
14 Stone Chisseler Each 225 262.50

Certified that the rate of material are


lowest prevailing market/issue rates
and the rates of labour are approved
rates.

Executive Engineer,
IPHDivision Thunag
ANALYSIS OF RATE
P/F sand cast/ cast iron spun spigot and socketed soil waste and ventilating pipes ( Lead caulked
joints to be paid separately)
S.No. Description Unit Qty Rate Amount.

a) 50mm nominal size


DETAIL OF COST FOR 17.35 METRES.
Materials:-
100mm sand cast iron pipes (1.83 Each 10 Nos. 250.00 2500
metrs long)
5% for wastage 125
Total:- 2625
Carriage:-
Wt.=11.41x10+5%=114.41+5.70=119.
80 kg=0.12 tonne.

15 Km by Mechnical Transport Tonne 0.12 Tonne 295.76 35.49


0.5 Km by Head load Tonne 1.12 Tonne 299.25 335.16

Total:- 370.65
Labour:-
Plumber (Fitter) Each 0.34 Nos. 311.5 105.91
Bandhani Each 0.17 Nos. 262.5 44.63
Beldar Each 0.67 Nos. 262.5 175.88
Scaffolding LS 20.00
Total:- 346.42
G.Total 3342.07
Add 15% CP & OH charges except 3342.07 501.31
carriage.
Total; 3843.38
Add GST @ 12% 461.21
4304.59
Add Labour Cess @ 1% 38.43
Cost for 17.35 Metre. 4343.02
Cost for One Metre. Rs. 250.00

Executive Engineer,
IPH DivisionThunag
ANALYSIS OF RATE
P/F sand cast/ cast iron spun spigot and socketed soil waste and ventilating pipes ( Lead caulked
joints to be paid separately)
S.No. Description Unit Qty Rate Amount.
b) 75mm nominal size
DETAIL OF COST FOR 17.35 METRES.
Materials:-
50mm sand cast iron pipes (1.83 metrs Each 10 Nos. 300.00 3000
long)
5% for wastage 150
Total:- 3150
Carriage:-
Wt.=16.52x10+5%=165.20+8.26=173.
46 kg=0.173 tonne.

15 Km by Mechnical Transport Tonne 0.173 Tonne 295.76 51.17


0.5 Km by Head load Tonne 0.173 Tonne 299.25 51.77
Total:- 102.94
Labour:-
Plumber (Fitter) Each 0.42 Nos. 311.5 130.83
Bandhani Each 0.2 Nos. 262.5 52.5
Beldar Each 0.84 Nos. 262.5 220.5
Scaffolding LS 20.00
Total:- 423.83
G.Total 3676.77
Add 15% CP & OH charges except 3573.83 536.07
carriage.
Total; 4212.84
Add GST @ 12% 505.54
4718.38
Add Labour Cess @ 1% 47.18
Cost for 17.35 Metre. 4765.56
Cost for One Metre. Rs. 275.00

Executive Engineer,
IPH Division Thunag
ANALYSIS OF RATE
79.00 P/F sand cast/ cast iron spun spigot and socketed soil waste and ventilating pipes ( Lead caulked
joints to be paid separately)
S.No. Description Unit Qty Rate Amount.
c) 100mm nominal size
DETAIL OF COST FOR 17.35 METRES.
Materials:-
100mm sand cast iron pipes (1.83 Each 10 Nos. 750.00 7500
metrs long)
5% for wastage 375
Total:- 7875
Carriage:-
Wt.=21.67x10+5%=216.70+10.84=227
.54 kg=0.228 tonne.

15 Km by Mechnical Transport Tonne 0.228 Tonne 295.76 67.43


0.5 Km by Head load Tonne 0.228 Tonne 299.25 68.23
Total:- 135.66
Labour:-
Plumber (Fitter) Each 0.50 Nos. 311.5 155.75
Bandhani Each 0.25 Nos. 262.5 65.63
Beldar Each 1.00 Nos. 262.5 262.5
Scaffolding LS 20.00
Total:- 503.88
G.Total 8514.54
Add 15% CP & OH charges except 8378.88 1256.83
carriage. Total; 9771.37
Add GST @ 12% 1172.56
10943.93
Add Labour Cess @ 1% 109.44
Cost for 17.35 Metre. 11053.37
Cost for One Metre. Rs. 637.00

Executive Engineer,
IPH Division Thunag
ANALYSIS OF RATE
P/F cast iron holder bat i/c steel bolts to sand cast iron / cast (spun) iron pipes embeded in and i/c
CC block 100x100x100mm of 1:2:4 mix ( 1cement;2sand:4graded stone aggregate 20mm
nominal size)i/c cost of cutting holes and making good the walls.

S.No. Description Unit Qty Rate Amount.


a) 50mm nominal size
DETAIL OF COST FOR 5 CLAMPS
Materials:-
Clamps for 50mm pipes Each 5 Nos. 75.00 375
CC blocks of CC cum 0.005 cum 0 0
1:2:4(5x.10x.10x.10m)=.005 cum
Carriage:-
Carriage of material. LS 1.50
Labour:-
Fitter Each 0.125 Nos. 311.5 38.94
Mason 2nd class Each 0.75 Nos. 311.5 233.63
Beldar Each 0.50 Nos. 262.5 131.25
Sundries. LS 5.00
Total:- 785.32
Add 15% CP & OH charges except CC = 783.82 117.57
& Carriage ie
Total: 902.89
Add GST @ (Except CC block) 12% 902.89 108.35
1011.24
Add Labour Cess @ (Except CC 1% 1011.24 10.11
block)
Cost for 5 Clamps. Rs. 1021.35
Cost for 1 clamps. Rs. 204.00

Executive Engineer,
IPH Division Thunag
ANALYSIS OF RATE
P/F cast iron holder bat i/c steel bolts to sand cast iron / cast (spun) iron pipes embeded in and i/c
CC block 100x100x100mm of 1:2:4 mix ( 1cement;2sand:4graded stone aggregate 20mm
nominal size)i/c cost of cutting holes and making good the walls.
S.No. Description Unit Qty Rate Amount.
b) 75mm nominal size
DETAIL OF COST FOR 5 CLAMPS
Materials:-
Clamps for 75mm pipes Each 5 Nos. 100.00 500
CC blocks of CC cum 0.005 cum 0
1:2:4(5x.10x.10x.10m)=.005 cum
Carriage:-
Carriage of material. LS 1.50
Labour:-
Fitter Each 0.125 Nos. 311.5 38.94
Mason 2nd class Each 0.75 Nos. 311.5 233.63
Beldar Each 0.50 Nos. 262.5 131.25
Sundries. LS 5.00
Total:- 910.32
Add 15% CP & OH charges except CC = 908.82 136.32
& Carriage ie
Total: 1046.64
Add GST @ (Except CC block) 12% 1046.64 125.60
1172.24
Add Labour Cess @ (Except CC 1% 1172.24 11.72
block)
Cost for 5 Clamps. Rs. 1183.96
Cost for 1 clamps. Rs. 237.00

Executive Engineer,
IPH Division Thunag
ANALYSIS OF RATE
P/F cast iron holder bat i/c steel bolts to sand cast iron / cast (spun) iron pipes embeded in and i/c
CC block 100x100x100mm of 1:2:4 mix ( 1cement;2sand:4graded stone aggregate 20mm
nominal size)i/c cost of cutting holes and making good the walls.
S.No. Description Unit Qty Rate Amount.
c) 100mm nominal size
DETAIL OF COST FOR 5 CLAMPS
Materials:-
Clamps for 100mm pipes Each 5 Nos. 125.00 625
CC blocks of CC cum 0.005 cum 0
1:2:4(5x.10x.10x.10m)=.005 cum
Carriage:-
Carriage of material. LS 1.50
Labour:-
Fitter Each 0.125 Nos. 311.5 38.94
Mason 2nd class Each 0.75 Nos. 311.5 233.63
Beldar Each 0.50 Nos. 262.5 131.25
Sundries. LS 5.00
Total:- 1035.31
Add 15% CP & OH charges except CC = 1033.81 155.07
& Carriage ie
Total: 1190.38
Add GST @ (Except CC block) 12% 1190.38 142.85
1333.23
Add Labour Cess @ (Except CC 1% 1333.23 13.33
block)
Cost for 5 Clamps. Rs. 1346.56
Cost for 1 clamps. Rs. 269.00

Executive Engineer,
IPHDivision Thunag
ANALYSIS OF RATE
P/F sand cast iron/ cast iron spun fittings and accessories.
a Bends of required degree ( any radious) :-With oval access door insertion rubber washers 3mm
thick bolts and nuts complete.
S.No. Description Unit Qty Rate Amount.

a) 50mm nominal size


DETAIL OF COST FOR One BENDS.
Materials:-
50mm sand cast iron bend Each 1 No. 250.00 250.00
Insertion of rubber washers 3mm thick Each 1 No. 3.00 3.00
Carriage:-
Carriage of materials. LS 1.00
Labour:-
Fixing charges. LS 2.00
Total: 256.00
Add 15% CP & OH charges except on Rs. 255.00 38.25
carriage. i.e
Total:- 294.25
Add GST @ 12% 35.31
329.56
Add Labour Cess @ 1% 3.30
Cost for One Bend Rs. 332.86
Say Rs:- 333.00

Executive Engineer,
IPH Division Thunag
ANALYSIS OF RATE
P/F sand cast iron/ cast iron spun fittings and accessories.
a Bends of required degree ( any radious) :-With oval access door insertion rubber washers 3mm
thick bolts and nuts complete.
S.No. Description Unit Qty Rate Amount.
a) 75mm nominal size
DETAIL OF COST FOR One BENDS.
Materials:-
75mm sand cast iron bend Each 1 No. 275.00 275.00
Insertion of rubber washers 3mm thick Each 1 No. 3.00 3.00

Carriage:-
Carriage of materials. LS 1.00
Labour:-
Fixing charges. LS 2.00
Total: 281.00
Add 15% CP & OH charges except on Rs. 280.00 42.00
carriage. i.e
Total:- 323.00
Add GST @ 12% 38.76
361.76
Add Labour Cess @ 1% 3.62
Cost for One Bend Rs. 365.38
Say Rs:- 365.00

Executive Engineer,
IPH Division Thunag
ANALYSIS OF RATE
P/F sand cast iron/ cast iron spun fittings and accessories.
a Bends of required degree ( any radious) :-With oval access door insertion rubber washers 3mm
thick bolts and nuts complete.
S.No. Description Unit Qty Rate Amount.
a) 100mm nominal size
DETAIL OF COST FOR One BENDS.
Materials:-
100mm sand cast iron bend Each 1 No. 325.00 325.00
Insertion of rubber washers 3mm thick Each 1 No. 3.00 3.00

Carriage:-
Carriage of materials. LS 1.00
Labour:-
Fixing charges. LS 2.00
Total: 331.00
Add 15% CP & OH charges except on Rs. 330.00 49.50
carriage. i.e
Total:- 380.50
Add GST @ 12% 45.66
426.16
Add Labour Cess @ 1% 4.26
Cost for One Bend Rs. 430.42
Say Rs:- 430.00

Executive Engineer,
IPH Division Thunag
ANALYSIS OF RATE
P/F sand cast iron/ cast iron spun fittings and accessories.
a Bends of required degree ( any radious) :-Plain
S.No. Description Unit Qty Rate Amount.
a) 50mm nominal size
DETAIL OF COST FOR One BENDS.
Materials:-
50mm sand cast iron bend Each 1 No. 250.00 250.00
Carriage.
Carriage of material LS 1.00
Labour;-
Fixing charges. LS 2.00
Total: 253.00
Add 15% CP & OH charges except on Rs. 252.00 37.80
carriage. i.e
Total:- 290.80
Add GST @ 12% 34.90
325.70
Add Labour Cess @ 1% 3.26
Cost for One Bend Rs. 328.96
Say Rs:- 329.00

Executive Engineer,
IPH Division Thunag
ANALYSIS OF RATE
P/F sand cast iron/ cast iron spun fittings and accessories.
a Bends of required degree ( any radious) :-Plain
S.No. Description Unit Qty Rate Amount.
a) 75mm nominal size
DETAIL OF COST FOR One BENDS.
Materials:-
75mm sand cast iron bend Each 1 No. 275.00 275.00
Carriage.
Carriage of material LS 1.00
Labour;-
Fixing charges. LS 2.00
Total: 278.00
Add 15% CP & OH charges except on Rs. 277.00 41.55
carriage. i.e
Total:- 319.55
Add GST @ 12% 38.35
357.90
Add Labour Cess @ 1% 3.58
Cost for One Bend Rs. 361.48
Say Rs:- 361.00

Executive Engineer,
IPH Division Thunag
ANALYSIS OF RATE
P/F sand cast iron/ cast iron spun fittings and accessories.
a Bends of required degree ( any radious) :-Plain
S.No. Description Unit Qty Rate Amount.
a) 100mm nominal size
DETAIL OF COST FOR One BENDS.
Materials:-
100mm sand cast iron bend Each 1 No. 325.00 325.00
Carriage.
Carriage of material LS 1.00
Labour;-
Fixing charges. LS 2.00
Total: 328.00
Add 15% CP & OH charges except on Rs. 327.00 49.05
carriage. i.e
Total:- 377.05
Add GST @ 12% 45.25
422.30
Add Labour Cess @ 1% 4.22
Cost for One Bend Rs. 426.52
Say Rs:- 427.00

Executive Engineer,
IPH Division Thunag
ANALYSIS OF RATE
P/F sand cast iron/ cast iron spun fittings and accessories.
a LOOSE SOCKET
S.No. Description Unit Qty Rate Amount.
a) 50mm nominal size
DETAIL OF COST FOR ONE
Materials:-
50mm cast iron socket Each 1 No. 225.00 225.00
Carriage.
Carriage of material LS 1.00
Labour;-
Fixing charges. LS 2.00
Total: 228.00
Add 15% CP & OH charges except on Rs. 227.00 34.05
carriage. i.e
Total:- 262.05
Add GST @ 12% 31.45
293.50
Add Labour Cess @ 1% 2.94
Cost for One Rs. 296.44
Say Rs:- 296.00

Executive Engineer,
IPH Division Thunag
ANALYSIS OF RATE
P/F sand cast iron/ cast iron spun fittings and accessories.
a LOOSE SOCKET
S.No. Description Unit Qty Rate Amount.
a) 75mm nominal size
DETAIL OF COST FOR ONE
Materials:-
75mm cast iron socket Each 1 No. 250.00 250.00
Carriage.
Carriage of material LS 1.00
Labour;-
Fixing charges. LS 2.00
Total: 253.00
Add 15% CP & OH charges except on Rs. 252.00 37.80
carriage. i.e
Total:- 290.80
Add GST @ 12% 34.90
325.70
Add Labour Cess @ 1% 3.26
Cost for One Rs. 328.96
Say Rs:- 329.00

Executive Engineer,
IPH Division Thunag
ANALYSIS OF RATE
P/F sand cast iron/ cast iron spun fittings and accessories.
a LOOSE SOCKET
S.No. Description Unit Qty Rate Amount.
a) 100mm nominal size
DETAIL OF COST FOR ONE
Materials:-
100mm cast iron socket. Each 1 No. 275.00 275.00
Carriage.
Carriage of material LS 1.00
Labour;-
Fixing charges. LS 2.00
Total: 278.00
Add 15% CP & OH charges except on Rs. 277.00 41.55
carriage. i.e
Total:- 319.55
Add GST @ 12% 38.35
357.90
Add Labour Cess @ 1% 3.58
Cost for One Rs. 361.48
Say Rs:- 361.00

Executive Engineer,
IPH Division Thunag
ANALYSIS OF RATE
P/F sand cast iron/ cast iron .
a Cast Iron Cowl
S.No. Description Unit Qty Rate Amount.
a) 50mm nominal size
DETAIL OF COST FOR ONE No.
Materials:-
50mm galvanised steel wire ballon Each 1 No. 110.00 110.00
Carriage.
Carriage of material LS 1.00
Labour;-
Fixing charges. LS 2.00
Total: 113.00
Add 15% CP & OH charges except on Rs. 112.00 16.80
carriage. i.e
Total:- 129.80
Add GST @ 12% 15.58
145.38
Add Labour Cess @ 1% 1.45
Cost for One Rs. 146.83
Say Rs:- 147.00

Executive Engineer,
IPH Division Thunag
ANALYSIS OF RATE
P/F sand cast iron/ cast iron .
a CAST IRON COWL
S.No. Description Unit Qty Rate Amount.
a) 75mm nominal size
DETAIL OF COST FOR ONE No.
Materials:-
75mm galvanised steel wire ballon Each 1 No. 125.00 125.00
Carriage.
Carriage of material LS 1.00
Labour;-
Fixing charges. LS 2.00
Total: 128.00
Add 15% CP & OH charges except on Rs. 127.00 19.05
carriage. i.e
Total:- 147.05
Add GST @ 12% 17.65
164.70
Add Labour Cess @ 1% 1.65
Cost for One Rs. 166.35
Say Rs:- 166.00

Executive Engineer,
IPH Division Thunag
ANALYSIS OF RATE
P/F sand cast iron/ cast iron.
a CAST IRON COWL
S.No. Description Unit Qty Rate Amount.
a) 100mm nominal size
DETAIL OF COST FOR ONE No.
Materials:-
100mm galvanised steel wire ballon Each 1 No. 145.00 145.00
Carriage.
Carriage of material LS 1.00
Labour;-
Fixing charges. LS 2.00
Total: 148.00
Add 15% CP & OH charges except on Rs. 147.00 22.05
carriage. i.e
Total:- 170.05
Add GST @ 12% 20.41
190.46
Add Labour Cess @ 1% 1.90
Cost for One Rs. 192.36
Say Rs:- 192.00

Executive Engineer,
IPH Division Thunag
ANALYSIS OF RATE
Providing lead caulked joints to sand cast iron / cast (spun) iron pipes and fittings i/c testing of
joints.

S.No. Description Unit Qty Rate Amount.


a) 50mm nominal size
DETAIL OF COST FOR ONE JOINT
Materials:-
Pig lead Kg 0.77 kg 150.00 115.50
spun yarn Kg 0.06 kg 150.00 9.00
Kerisene oil fiel etc. LS 1.50
Carriage.
Carriage of material LS 1.00
Labour;-
Plumber (Fitter) Each 0.05 No. 311.5 15.58
Plumber Asstt. (Fitter Asstt.) Each 0.06 No. 262.5 15.75
Beldar Each 0.06 No. 262.5 15.75
Sundries. LS 1.50
Total 175.58

Add for water charges @ 1.5% 2.63


Total: 178.21
Add 15% CP & OH charges except on 177.21 26.58
carriage. i.e
TotalRs. 204.79
Add GST @ 12% 24.57
229.36
Add Labour Cess @ 1% 2.29
Cost for One Joint Rs. 231.65
Say Rs:- 232.00

Executive Engineer,
IPH Division Thunag
ANALYSIS OF RATE
Providing lead caulked joints to sand cast iron / cast (spun) iron pipes and fittings i/c testing of
joints.

S.No. Description Unit Qty Rate Amount.


a) 75mm nominal size
DETAIL OF COST FOR ONE JOINT
Materials:-
Pig lead Kg 0.88 kg 150.00 132.00
spun yarn Kg 0.09 kg 150.00 13.50
Kerisene oil fiel etc. LS 1.50
Carriage.
Carriage of material LS 1.00
Labour;-
Plumber (Fitter) Each 0.05 No. 311.5
Plumber Asstt. (Fitter Asstt.) Each 0.06 No. 262.5
Beldar Each 0.11 No. 262.5
Sundries. LS 1.50
Total 149.50

Add for water charges @ 1.5% 2.24


Total: 151.74
Add 15% CP & OH charges except on 150.74 22.61
carriage. i.e
TotalRs. 174.35
Add GST @ 12% 20.92
195.27
Add Labour Cess @ 1% 1.95
Cost for One Joint Rs. 197.22
Say Rs:- 197.00

Executive Engineer,
IPH Division Thunag
ANALYSIS OF RATE
Providing lead caulked joints to sand cast iron / cast (spun) iron pipes and fittings i/c testing of
joints.

S.No. Description Unit Qty Rate Amount.


a) 100mm nominal size
DETAIL OF COST FOR ONE JOINT
Materials:-
Pig lead Kg 0.98 kg 150.00 147.00
spun yarn Kg 0.11 kg 150.00 16.50
Kerisene oil fiel etc. LS 1.50
Carriage.
Carriage of material LS 1.00
Labour;-
Plumber (Fitter) Each 0.07 No. 311.5 21.81
Plumber Asstt. (Fitter Asstt.) Each 0.07 No. 262.5 18.38
Beldar Each 0.14 No. 262.5 36.75
Sundries. LS 1.50
Total 244.43

Add for water charges @ 1.5% 3.67


Total: 248.10
Add 15% CP & OH charges except on 247.10 37.06
carriage. i.e
TotalRs. 285.16
Add GST @ 12% 34.22
319.38
Add Labour Cess @ 1% 3.19
Cost for One Joint Rs. 322.57
Say Rs:- 323.00

Executive Engineer,
IPHDivision Thunag
ANALYSIS OF RATE
P/F CI floor trap of self cleaning designwith sand cast iron screwed down or hinged grating with
out vent arm complete i/c cost of cutting and making goods the walls and floors.
S.No. Description Unit Qty Rate Amount.
a) 50mm nominal size
DETAIL OF COST FOR ONE FLOOR TRAP
Materials:-
50mm CI trap with grating complete Each 1 No. 375.00 375.00
Cement,Sand & grit etc. LS 2.00
Carriage:
Carriage of materials LS 1.00
Labour:
Mason 1st class Each 0.60 Nos. 311.5 186.90
Beldar each 0.60 Nos. 262.5 157.50
Total:- 722.40

add for water charges @ 1.5% 10.84


Total: 733.24
Add 15% CP & OH charges except on Rs. 732.24 109.84
carriage. i.e
Total; 843.07
Add GST @ 12% 101.17
944.24
Add Labour Cess @ 1% 9.44
Cost for One Floor Trap Rs. 953.68
Say Rs:- 954.00

Executive Engineer,
IPH Division Thunag
ANALYSIS OF RATE
P/F CI floor trap of self cleaning designwith sand cast iron screwed down or hinged grating with
out vent arm complete i/c cost of cutting and making goods the walls and floors.
S.No. Description Unit Qty Rate Amount.
a) 75mm nominal size
DETAIL OF COST FOR ONE FLOOR TRAP
Materials:-
75mm CI trap with grating complete Each 1 No. 410.00 410.00
Cement,Sand & grit etc. LS 2.00
Carriage:
Carriage of materials LS 1.00
Labour:
Mason 1st class Each 0.60 Nos. 311.5 186.90
Beldar each 0.60 Nos. 262.5 157.50

G Total 757.40
add for water charges @ 1.5% 11.36
Total: 768.76
Add 15% CP & OH charges except on Rs. 767.76 115.16
carriage. i.e
Total; 883.93
Add GST @ 12% 106.07
990.00
Add Labour Cess @ 1% 9.90
Cost for One Floor Trap Rs. 999.90
Say Rs:- 1000.00

Executive Engineer,
IPH Division Thunag
ANALYSIS OF RATE
P/F CI floor trap of self cleaning designwith sand cast iron screwed down or hinged grating with
out vent arm complete i/c cost of cutting and making goods the walls and floors.
S.No. Description Unit Qty Rate Amount.
a) 100mm nominal size
DETAIL OF COST FOR ONE FLOOR TRAP
Materials:-
100mm CI trap with grating complete Each 1 No. 450.00 450.00
Cement,Sand & grit etc. LS 2.00
Carriage:
Carriage of materials LS 1.00
Labour:
Mason 1st class Each 0.60 Nos. 311.5 186.90
Beldar each 0.60 Nos. 262.5 157.50

G Total 797.40
add for water charges @ 1.5% 11.96
Total: 809.36
Add 15% CP & OH charges except on Rs. 808.36 121.25
carriage. i.e
Total; 930.62
Add GST @ 12% 111.67
1042.29
Add Labour Cess @ 1% 10.42
Cost for One Floor Trap Rs. 1052.71
Say Rs:- 1053.00

Executive Engineer,
IPHDivision Thunag
ANALYSIS OF RATE
P/F vitreous China water closet squatting pan (European type WC pan) size 580mm (earth work,
bed conc., foot rest and trap to be measured and paid for separately)

S.No. Description Unit Qty Rate Amount.


1) European Type
DETAIL OF COST FOR ONE No.
Material:
White vetreous china Orrisa pattern
water closet
squatting pan size 580mm Each 1 No. 1350.00 1350.00
Cement sand and grit etc. LS 10.00
Total:
Carriage;
Carriage of material LS 5.00
Labour:
Mason 1st class Each 0.60 Nos, 311.5 186.90
Beldar Each 0.60 Nos, 262.5 157.50

G.Total 1709.40
Add for water charges @ 1.5% 25.64
Total: 1735.04
Add 15% for CP & OH charges except Rs. 1730.04 259.51
on carriage i.e
Total:- 1994.55
Add GST @ 12% 239.35
2233.90
Add Labour Cess @ 1% 19.95
Cost for One Rs. 2253.85
Say Rs:- 2254.00

Executive Engineer,
IPH Division Thunag
ANALYSIS OF RATE
P/F 10/12.5/15 litres vitreous china low level flushing cistern with a pair of CI or mild steel brackets
complete with fittings such as lead valve less syphon 15mm nominal size brass ball valve with
polythene float CP brass handle unions and couplings for connection with inlet , out let and over
flow pipes 40mm dia CP flush bend including cutting holes in walls and making good the same
and connecting the flush bend with cistern and closet (overflow) pipe to be measured and paid for
separately.

S.No. Description Unit Qty Rate Amount.


a) Vitreos China in whte colour.
DETAIL OF COST FOR ONE No.
Material;
10/12.5/15 litres vitreous china low Each 1 No. 2800.00 2800.00
level flushing cistern.
C.I or MS brackets Pair 1 Pair 45.00 45.00
Cement sand white lead etc. LS 3.00
Total: 2848.00
Carriage:
Carriage of materials. LS 3.00
Labour:
Plumber (Fitter) Each 0.60 Nos, 311.5 186.90
Beldar Each 0.60 Nos. 262.5 157.50
Total: 344.40
Gtotal: 3195.40
Add for water charges @ 1.5% 47.93
Total: 3243.33
Add 15% for CP & OH charges except Rs. 3240.33 486.05
on carriage i.e
Total:- 3729.38
Add GST @ 12% 929.38 111.53
3840.91
Add Labour Cess @ 1% 38.41
Cost for One Rs. 3879.32
Say Rs:- 3879.00

Executive Engineer,
IPH Division Thunag
ANALYSIS OF RATE
P/F in position with clamps, etc. 32mm nominal internal diameter galvanised steel tube flush pipe
for high level flushing cistern including connection the flush pipe with cistern and closet and
making good the walls and floors.
S.No. Description Unit Qty Rate Amount.
DETAIL OF COST FOR TWO METRE
Material;
32mm diameter GS tube flush pipe
with brass galvanised steel check nut.
(Assume 2 metre approxi) Each 1 No. 550.00 550.00
Cement, sand grit and red lead etc. LS 2.00
Total:- 552.00
Carriage:
Carriage of materials. LS 3.00
Labour:
Fitter Each 0.07 Nos. 311.5 21.81
Mason 1st class Each 0.07 Nos. 311.5 21.81
Beldar Each 0.30 Nos. 262.5 78.75
Total:- 122.36
Gtotal 677.36
Add for water charges @ 1.5% 10.16
Total: 687.52
Add 15% for CP & OH charges except Rs. 684.52 102.68
on carriage i.e
Total:- 790.20
Add GST @ 12% 240.20 28.82
819.02
Add Labour Cess @ 1% 8.19
Cost for Two Metre Rs. 827.21
Cost for One Meter. Rs. 413.61
Say Rs. 414.00

Executive Engineer,
IPH Division Thunag
ANALYSIS OF RATE
P/F plastic seat (Solid/Hollow type) and cover for wash down water closet with CP Brass hinges
and rubber buffers:-
S.No. Description Unit Qty Rate Amount.
a) SOLID TYPE:- Coloured plastic seat and
cover. DETAIL OF COST FOR ONE NUMBER
Material;
Coloured plastic seat and cover with Each 1 No. 550.00 550
CP brass hinges and rubber buffers.
Carriage:
Carriage of materials. LS 3.00
Labour:
Labour for fixing LS 3.00
Total: 556
Add 15% for CP & OH charges except Rs. 553.00 82.95
on carriage i.e
Total:- 638.95
Add GST @ 12% 88.95 10.67
649.62
Add Labour Cess @ 1% 6.50
Cost for One Rs. 656.12
Say Rs:- 656.00

Executive Engineer,
IPH Division Thunag
ANALYSIS OF RATE
P/F vitreous china wash basin with single hole for pillar tap with CI or MS brackets painted white
including cutting holes and making good the same but excludinf fitting.
S.No. Description Unit Qty Rate Amount.
a) Flat Black:- 630x450mm
DETAIL OF COST FOR ONE NUMBER
Materials:
White vetreous china Flat Black wash Each 1 No. 4.80 4.80
basin
CI or MS brackets. Pair 1 Pair. 50.00 50.00
Red lead/ white lead LS 5.00
Cement, sand etc. LS 5.00
Painting of brackets. LS 5.00
Total: 69.80
Carriage:-
Carriage of materials. LS 50.00
Labour:-
Plumber (Fitter) Each 0.40 Nos. 311.5 124.60
Mason 1st class Each 0.40 Nos. 311.5 124.60
Beldar Each 0.80 Nos. 262.5 210.00
Total: 459.20
G Total; 579.00
Add for water charges @ 1.5% 8.69
Total: 587.69
Add 15% for CP & OH charges except Rs. 537.69 80.65
on carriage i.e
Total:- 668.34
Add GST @ 12% 663.54 79.62
747.96
Add Labour Cess @ 1% 6.68
Cost for One Rs. 754.64
Say Rs:- 755.00

Executive Engineer,
IPH Division Thunag
ANALYSIS OF RATE
P/F vitreous china wash basin with single hole for pillar tap with CI or MS brackets painted white
including cutting holes and making good the same but excludinf fitting.
S.No. Description Unit Qty Rate Amount.
a) White:- 550x440mm
DETAIL OF COST FOR ONE NUMBER
Materials:
White vetreous china Flat Black wash Each 1 No. 1100.00 1100.00
basin
CI or MS brackets. Pair 1 Pair. 50.00 50.00
Red lead/ white lead LS 5.00
Cement, sand etc. LS 5.00
Painting of brackets. LS 5.00
Total: 1165.00
Carriage:-
Carriage of materials. LS 50.00
Labour:-
Plumber (Fitter) Each 0.40 Nos. 311.50 124.60
Mason 1st class Each 0.40 Nos. 311.50 124.60
Beldar Each 0.80 Nos. 262.50 210.00
Total: 459.20
G Total; 1674.20
Add for water charges @ 1.5% 25.11
Total: 1699.31
Add 15% for CP & OH charges except Rs. 1649.31 247.40
on carriage i.e
Total:- 1946.71
Add GST @ 12% 846.71 101.61
2048.32
Add Labour Cess @ 1% 19.47
Cost for One Rs. 2067.79
Say Rs:- 2068.00

Executive Engineer,
IPH Division Thunag
ANALYSIS OF RATE
73.00 P/F vitreous china padestal for wash basin complete recessed at the back for the reception of
pipes and fittings.

S.No. Description Unit Qty Rate Amount.


Vitreous China in white colour
DETAIL OF COST FOR ONE NUMBER
Materials:
White vitreous china pedestal Each 1 No. 140.00 140.00
White cement mortar. LS 8.00

Carriage:-
Carriage of materials. LS 5.00
Labour:-
Labour for fixing LS 6.00

G Total 159.00
Add for water charges @ 1.5% 2.39
Total: 161.39
Add 15% for CP & OH charges except Rs. 156.39 23.46
on carriage i.e
Total:- 184.84
Add GST @ 12% 44.84 5.38
190.22
Add Labour Cess @ 1% 1.85
Cost for One Rs. 192.07
Say Rs:- 192.00

Executive Engineer,
IPH Division Thunag
ANALYSIS OF RATE
P/F kitchen sink with CI or MS brackets, painted white including cutting holes in walls and making
good the same but excluding fittings

S.No. Description Unit Qty Rate Amount.


White Glazes Fire Clay:-
610x510x200mm
DETAIL OF COST FOR ONE NUMBER
Materials:
White glazed fire clay sink Each 1 No. 3000.00 3000
CI or MS brackets. Pair 1 Pair. 45.00 45
Cement, sand etc. LS 6.00
Total: 3051
Carriage:-
Carriage of materials. LS 5.00
Labour:-
Plumber (Fitter) Each 0.26 Nos. 311.5 80.99
Mason 1st class Each 0.40 Nos. 311.5 124.6
Beldar. Each 0.67 Nos. 262.5 175.875
Total: 381.465
G Total: 3437.47
Add for water charges @ 1.5% 51.56
Total: 3489.03
Add 15% for CP & OH charges except Rs. 3484.03 522.6
on carriage i.e
Total:- 4011.63
Add GST @ 12% 481.40
4493.03
Add Labour Cess @ 1% 40.12
Cost for One Rs. 4533.15
Say Rs:- 4533.00

Executive Engineer,
IPH Division Thunag
ANALYSIS OF RATE
P/F CP Brass chain 50cm long and rubber plug of following sizes for sink or wash basin
S.No. Description Unit Qty Rate Amount.
i) 32mm dia.
DETAIL OF COST FOR ONE NUMBER
Materials:
CP Brass chain 50cm long and rubber Each 1 No. 100.00 100.00
plug
Carriage:-
Carriage of materials. LS 1.00
Labour:
Labour for fixing LS 2.00
Total: 103.00
Add 15% for CP & OH charges except Rs. 102.00 15.30
on carriage i.e
Total:- 118.30
Add GST @ 12% 14.20
132.50
Add Labour Cess @ 1% 1.33
Cost for One Rs. 133.83
Say Rs:- 134.00

Executive Engineer,
IPH Division Thunag
ANALYSIS OF RATE
P/F CP Brass chain 50cm long and rubber plug of following sizes for sink or wash basin
S.No. Description Unit Qty Rate Amount.
i) 40mm dia.
DETAIL OF COST FOR ONE NUMBER
Materials:
CP Brass chain 50cm long and rubber Each 1 No. 115.00 115.00
plug
Carriage:-
Carriage of materials. LS 1.00
Labour:
Labour for fixing LS 2.00
Total: 118.00
Add 15% for CP & OH charges except Rs. 117.00 17.55
on carriage i.e
Total:- 135.55
Add GST @ 12% 16.27
151.82
Add Labour Cess @ 1% 1.52
Cost for One Rs. 153.34
Say Rs:- 153.00

Executive Engineer,
IPH Division Thunag
ANALYSIS OF RATE
P/F CP brass waste pipe for wash basin and sink.
S.No. Description Unit Qty Rate Amount.
i) 32mm dia.
DETAIL OF COST FOR ONE NUMBER
Materials:
CP brass waste for wash basin and Each 1 No. 175.00 175.00
sink.
Carriage:-
Carriage of materials. LS 1.00
Labour:
Labour for fixing LS 2.00
Total: 178.00
Add 15% for CP & OH charges except Rs. 177.00 26.55
on carriage i.e
Total:- 204.55
Add GST @ 12% 29.55 3.55
208.10
Add Labour Cess @ 1% 2.05
Cost for One Rs. 210.15
Say Rs:- 210.00

Executive Engineer,
IPH Division Thunag
ANALYSIS OF RATE
P/F CP brass waste for wash basin and sink.
S.No. Description Unit Qty Rate Amount.
i) 40mm dia.
DETAIL OF COST FOR ONE NUMBER
Materials:
CP brass waste for wash basin and Each 1 No. 200.00 200.00
sink.
Carriage:-
Carriage of materials. LS 1.00
Labour:
Labour for fixing LS 2.00
Total: 203.00
Add 15% for CP & OH charges except Rs. 202.00 30.30
on carriage i.e
Total:- 233.30
Add GST @ 12% 28.00
261.30
Add Labour Cess @ 1% 2.61
Cost for One Rs. 263.91
Say Rs:- 264.00

Executive Engineer,
IPH Division Thunag
ANALYSIS OF RATE
P/F MICP brass bottle trap for wash basin or sink
S.No. Description Unit Qty Rate Amount.
i) 32mm dia.
DETAIL OF COST FOR ONE NUMBER
Materials:
MI Union for wash basin or sink Each 1 No. 75.00 75.00
Carriage:-
Carriage of materials. LS 2.00
Labour:
Labour for fixing LS 5.00
Total: 82.00
Add 15% for CP & OH charges except Rs. 80.00 12.00
on carriage i.e
Total:- 94.00
Add GST @ 12% 11.28
105.28
Add Labour Cess @ 1% 0.94
Cost for One Rs. 106.22
Say Rs:- 106.00

Executive Engineer,
IPH Division Thunag
ANALYSIS OF RATE
P/F MI Union for wash basin or sink
S.No. Description Unit Qty Rate Amount.
i) 40mm dia.
DETAIL OF COST FOR ONE NUMBER
Materials:
MI Union for wash basin or sink Each 1 No. 80.00 80.00
Carriage:-
Carriage of materials. LS 1.00
Labour:
Labour for fixing LS 2.00
Total: 83.00
Add 15% for CP & OH charges except Rs. 82.00 12.30
on carriage i.e
Total:- 95.30
Add GST @ 12% 11.44
106.74
Add Labour Cess @ 1% 1.07
Cost for One Rs. 107.81
Say Rs:- 108.00

Executive Engineer,
IPH Division Thunag
ANALYSIS OF RATE
P/F 600x450mm bevelled edge miror of superior glass mounted on 6mm thick AC sheet or ply
wood sheet and fixed to wooden plug with CP brass screwed and washers.

S.No. Description Unit Qty Rate Amount.


DETAIL OF COST FOR ONE NUMBER
Materials:
Bevelled edge moror 600mmx450mm Each 1 No. 750.00 750.00
600mmx450mm th. AC or ply wood sqm 0.27 sqm 100.00 27.00
sheet
Wooden plug Each 4.00 Nos. 5.00 20.00
CP brass serews LS 1.00
Washers LS 1.00
Total: 799.00
Carriage:-
Carriage of materials. LS 1.00
Labour:
Carpenter 2nd class Each 0.40 Nos. 311.5 124.60
Beldar Each 0.40 Nos. 262.5 105.00
Total: 1029.60
Add 15% for CP & OH charges except Rs. 1028.60 154.29
on carriage i.e
Total:- 1183.89
Add GST @ 12% 433.89 52.07
1235.96
Add Labour Cess @ 1% 11.84
Cost for One Rs. 1247.80
Say Rs:- 1248.00

Executive Engineer,
IPH Division Thunag
ANALYSIS OF RATE
P/F CP brass towel rail complete with
CP brass brackets fixed to wooden
S.No. Description Unit Qty Rate Amount.
plug with CP brass.
i) 750mmx20mm
DETAIL OF COST FOR ONE
NUMBER
Materials:
750mmx20mm CP brass towel rail Each 1 Nos. 450.00 450.00
Wooden plug Each 2 Nos. 5.00 10.00
CP brass screw LS 1.00
Total: 461.00
Carriage:-
Carriage of materials. LS 2.00
Labour:
Carpenter 2nd class Each 0.20 Nos. 311.5 62.30
Beldar Each 0.20 Nos. 262.5 52.50
Total: 114.80
G Total 577.80

Add 15% for CP & OH charges except Rs. 575.80 86.37


on carriage i.e
Total:- 664.17
Add GST @ 12% 214.17 25.70
689.87
Add Labour Cess @ 1% 6.90
Cost for One Rs. 696.77
Say Rs:- 697.00

Executive Engineer,
IPH Division Thunag
ANALYSIS OF RATE
P/F 600mm x120mm glass self with CP brass brackets and guard rail complete,
fixed to wooden plug with CP brass screws.
S.No. Description Unit Qty Rate Amount.
DETAIL OF COST FOR ONE
NUMBER
Materials:
600mmx120mm glass self with CP Each 1 No. 750.00 750.00
brass
Woodenguard
plugsoil and brass brackets. Each 2 Nos. 5.00 10.00
CP brass screws LS 1.50
Total; 761.50
Carriage:-
Carriage of materials. LS 2.00
Labour:
Carpenter 2nd class Each 0.30 Nos. 311.5 93.45
Beldar Each 0.30 Nos. 262.5 78.75
Total: 172.20
G Total 935.70
Add 15% for CP & OH charges except Rs. 933.70 140.06
on carriage i.e
Total:- 1075.76

1075.76
Add Labour Cess @ 1% 10.76
Cost for One Rs. 1086.52
Say Rs:- 1087.00

Executive Engineer,
IPH Division Thunag
ANALYSIS OF RATE
P/F toilet paper holder.
S.No. Description Unit Qty Rate Amount.
a) CP Brass.
DETAIL OF COST FOR ONE NUMBER
Materials:
CP Brass toiler paper holder of Each 1 No. 300.00 300.00
standard size..
Wooden plug Each 2 Nos. 5.00 10.00
CP brass screws LS 1.00
Carriage:-
Carriage of materials. LS 2.00
Labour:
Carpenter 2nd class Each 0.14 Nos. 311.5 43.61
Beldar Each 0.14 Nos. 262.5 36.75

G Total 393.36
Add 15% for CP & OH charges except Rs. 391.36 58.70
on carriage i.e
Total:- 452.06
Add GST @ 12% 152.06 18.25
470.31
Add Labour Cess @ 1% 4.52
Cost for One Rs. 474.83
Say Rs:- 475.00

Executive Engineer,
IPH Division Thunag
ANALYSIS OF RATE
P/F liquid soap container with CP brass lid and brackets fixed to wooden plug with CP brass
screws.
S.No. Description Unit Qty Rate Amount.
a) Glass Container.
DETAIL OF COST FOR ONE NUMBER
Materials:
Liquid soap container of glass with CP Each 1 No. 400.00 400
brass lid and brackets.
Wooden plug Each 2 Nos. 5.00 10
CP brass screws LS 1.00
Total 411.00
Carriage:-
Carriage of materials. LS 2.00
Labour:
Carpenter 2nd class Each 0.14 Nos. 311.5 43.61
Beldar Each 0.14 Nos. 262.5 36.75
Total: 80.36
G Total 493.36
Add 15% for CP & OH charges except Rs. 491.36 73.704
on carriage i.e
Total:- 567.06
Add GST @ 12% 68.05
635.11
Add Labour Cess @ 1% 6.35
Cost for One Rs. 641.46
Say Rs:- 641.00

Executive Engineer,
IPH Division Thunag
ANALYSIS OF RATE
81.00 P/F Charomium plated brass soap dish with CP brass brackets fixed to wooden cleats with CP
brass screws.
S.No. Description Unit Qty Rate Amount.
DETAIL OF COST FOR ONE NUMBER
Materials:
Charomium plated brass soap dish Each 1 No. 485.00 485.00
with CP brass brackets
Wooden plug Each 1 No. 5.00 5.00
CP brass screws. LS 1.00
Carriage:-
Carriage of materials. LS 2.00
Labour:
Carpenter 2nd class Each 0.14 Nos. 311.5 43.61
Beldar Each 0.14 Nos. 262.5 36.75

G Total 573.36
Add 15% for CP & OH charges except Rs. 571.36 85.70
on carriage i.e
Total:- 659.06

659.06
Add Labour Cess @ 1% 6.59
Cost for One Rs. 665.65
Say Rs:- 666.00

Executive Engineer,
IPH Division Thunag
ANALYSIS OF RATE
P/F CP brass shower rose with 15mm or 20mm inlet.
S.No. Description Unit Qty Rate Amount.
100mm dia.
DETAIL OF COST FOR ONE NUMBER
Materials:
100mm dia CP brass shower rose. Each 1 No. 550.00 550.00
Carriage:-
Carriage of materials. LS 1.00
Labour:
Carpenter 2nd class Each 0.14 Nos. 311.5 43.61
Beldar Each 0.14 Nos. 262.5 36.75

G Total 631.36
Add 15% for CP & OH charges except Rs. 630.36 94.55
on carriage i.e
Total:- 725.91
Add GST @ 12% 87.11
813.02
Add Labour Cess @ 1% 8.13
Cost for One Rs. 821.15
Say Rs:- 821.00

Executive Engineer,
IPH Division Thunag
ANALYSIS OF RATE
P/F tooth brush and tumbler holder ( vitreous china)
S.No. Description Unit Qty Rate Amount.
DETAIL OF COST FOR ONE NUMBER
Materials:
Tooth brush tumbler holder Each 1 No. 150.00 150.00
Wooden plug Each 1 No. 5.00 5.00
CP brass screws LS 1.00
Carriage:-
Carriage of materials. LS 1.00
Labour:
Labour for fixing. LS 1.00
Total:- 158.00
Add 15% for CP & OH charges except Rs. 157.00 23.55
on carriage i.e
Total:- 181.55
Add GST @ 12% 21.79
203.34
Add Labour Cess @ 1% 2.03
Cost for One Rs. 205.37
Say Rs:- 205.00
Executive Engineer,
IPH Division Thunag
ANALYSIS OF RATE
80.00 Providing and fixing CP Brass bib tap with capstan head.
S.No. Description Unit Qty Rate Amount.
15mm
DETAIL OF COST FOR ONE NUMBER
Materials:
CP Brass bib tap with capstan head. Each 1 No. 790.00 790.00
15mm dia weight 400gms.
Carriage:-
Carriage of materials. LS 1.00
Labour:
Labour for fixing. LS 1.00
Total:- 792.00
Add 15% for CP & OH charges except Rs. 791.00 118.65
on carriage i.e
Total:- 910.65
Add GST @ 12% 109.28
1019.93
Add Labour Cess @ 1% 10.20
Cost for One Rs. 1030.13
Say Rs:- 1030.00

Executive Engineer,
IPH Division Thunag
ANALYSIS OF RATE
P/F brass angle valve 15mm without nuts and pipes.
S.No. Description Unit Qty Rate Amount.
DETAIL OF COST FOR ONE NUMBER
Materials:
Angle valve 15mm without nuts and Each 1 No. 825.00 825.00
pipes.
Carriage:-
Carriage of materials. LS 1.00
Labour:
Labour for fixing. LS 1.00
Total:- 827.00
Add 15% for CP & OH charges except Rs. 826.00 123.90
on carriage i.e
Total:- 950.90
Add GST @ 12% 125.90 15.11
966.01
Add Labour Cess @ 1% 9.51
Cost for One Rs. 975.52
Say Rs:- 976.00

Executive Engineer,
IPH Division Thunag
ANALYSIS OF RATE
P/F Mixer for kitchen sink with casted swining spout at top.

S.No. Description Unit Qty Rate Amount.


DETAIL OF COST FOR ONE NUMBER
Materials:
Mixer for kitchen sink with casted Each 1 No. 1400.00 1400.00
swining spout at top.
Carriage:-
Carriage of materials. LS 1.00
Labour:
Labour for fixing. LS 1.00
Total:- 1402.00
Add 15% for CP & OH charges except Rs. 1401.00 210.15
on carriage i.e
Total:- 1612.15
Add GST @ 12% 212.15 25.46
1637.61
Add Labour Cess @ 1% 16.12
Cost for One Rs. 1653.73
Say Rs:- 1654.00

Executive Engineer,
IPH Division Thunag
ANALYSIS OF RATE
P/F wall mixing faucet for shower and bath hand shower with Angular and Rest Holder.

S.No. Description Unit Qty Rate Amount.


DETAIL OF COST FOR ONE NUMBER
Materials:
Wall mixing faucet for shower and bath Each 1 No. 650.00 650.00
hand shower with Angular and Rest
Holder.
Carriage:-
Carriage of materials. LS 1.00
Labour:
Labour for fixing. LS 1.00
Total:- 652.00
Add 15% for CP & OH charges except Rs. 651.00 97.65
on carriage i.e
Total:- 749.65
Add GST @ 12% 99.65 11.96
3.00
Add Labour Cess @ 1% 0.03
Cost for One Rs. 3.03
Say Rs:- 3.00

Executive Engineer,
IPH Division Thunag
ANALYSIS OF RATE
P/F Bath Shower.
S.No. Description Unit Qty Rate Amount.
DETAIL OF COST FOR ONE NUMBER
Materials:
15mm bath shower. Each 1 No. 850.00 850.00
Carriage:-
Carriage of materials. LS 1.00
Labour:
Labour for fixing. LS 1.00
Total:- 852.00
Add 15% for CP & OH charges except Rs. 851.00 127.65
on carriage i.e
Total:- 979.65
Add GST @ 12% 129.65 15.56
995.21
Add Labour Cess @ 1% 9.95
Cost for One Rs. 1005.16
Say Rs:- 1005.00

Executive Engineer,
IPH Division Thunag
ANALYSIS OF RATE
P/F hand shower with Angular and Rest Holder.
S.No. Description Unit Qty Rate Amount.
DETAIL OF COST FOR ONE NUMBER
Materials:
Hand shower with Angular and Rest Each 1 No. 1360.00 1360.00
Holder.
Carriage:-
Carriage of materials. LS 1.00
Labour:
Labour for fixing. LS 1.00
Total:- 1362.00
Add 15% for CP & OH charges except Rs. 1361.00 204.15
on carriage i.e
Total:- 1566.15
Add GST @ 12% 187.94
1754.09
Add Labour Cess @ 1% 17.54
Cost for One Rs. 1771.63
Say Rs:- 1772.00

Executive Engineer,
IPH Division Thunag
ANALYSIS OF RATE
P/F to wall ceiling and floor galvanised mild steel tubes (Medium Grade) tube fittings and clamps
including making good the wall , ceiling and floor.
S.No. Description Unit Qty Rate Amount.
20mm nominal bore.
DETAIL OF COST FOR 10 Rmt.
Materials:
20mm tube = 10.00
Mtrs.
Add 15% for fittings and wastage.=
1.50 Mtr.
Total:- = 11.50 Mtrs. 11.50 Mtrs. 242.00 2783.00
Mtrs.
White lead, hemp oil etc. LS 3.00
Total:- 2786.00
Carriage.
25 Km by Mechnical transport Tonne 0.015 Tonne 382.17 5.73
0 Km by Head Load Tonne 0.015 Tonne. 0.00 0.00
Total; 5.73
Labour:
Plumber (Fitter) Each 1.40 Nos. 311.50 436.10
Beldar Each 2.00 Nos. 262.50 525.00
Total : 961.10
G Total 3752.83
Add 1.5% for water charges. 56.29
Total 3809.13
Add 15% CP & OH charges except Rs. 3803.39 570.51
carriage i.e on
Total:- 4379.63
Add GST @12% 1593.63 191.24
4570.87
Add Labour Cess @ 1% 43.80
Cost For 10 Rmt. Rs. 4614.67
Cost for 1 Rmt Rs. 461.00

Executive Engineer,
IPH Division Thunag
ANALYSIS OF RATE

P/F to wall ceiling and floor galvanised mild steel tubes (Medium Grade) tube fittings and clamps
including making good the wall , ceiling and floor.
S.No. Description Unit Qty Rate Amount.

15mm nominal bore.


DETAIL OF COST FOR 10 Rmt.
Materials:
15mm tube = 10.00
Mtrs.
Add 5% for fittings and wastage.=
0.50 Mtr.
Total:- = 10.50 Mtrs. Mtrs. 10.50 Mtrs. 94.00 987.00
White lead, hemp oil etc. LS 3.00
Total:- 990.00
Carriage.
15 Km by Mechnical transport Tonne 0.015 Tonne 295.76 4.44

0.5 Km by Head Load Tonne 0.015 Tonne. 299.25 4.49


Total; 8.93
Labour:
Plumber (Fitter) Each 0.80 Nos. 311.50 249.20
Beldar Each 0.80 Nos. 262.50 210.00
Total : 459.20
G Total 1458.13
Add 1.5% for water charges. 21.87
Total 1480.00
Add 15% CP & OH charges except Rs. 1480.00 222.00
carriage i.e on
Total:- 1702.00
Add GST @12% 1702.00 204.24
1906.24
Add Labour Cess @ 1% 17.02
Cost For 10 Rmt. Rs. 1923.26
Cost for 1 Rmt Rs. 192.00

Executive Engineer,
IPH Division Thunag
ANALYSIS OF RATE
P&F stainless utensils rack of size 900mmx900mm

S.No. Description Unit Qty Rate Amount.


DETAIL OF COST FOR ONE
NUMBER
Materials:
Utensils rack of size 900mmx900mm Each 1 No. 2000.00 2000.00

Carriage:-
Carriage of materials. LS 15.00
Labour:
Labour for fixing. LS 25.00
Total:- 2040.00
Add 15% for CP & OH charges except Rs. 2025.00 303.75
on carriage i.e Total:- 2343.75

Add Labour Cess @ 1% 23.44


Cost for One Rs. 2367.19
Say Rs:- 2367.00

Executive Engineer,
IPH Division Thunag
ANALYSIS OF RATE
P/F one hole CP brass wash basin mixing faucet
S.No. Description Unit Qty Rate Amount.
DETAIL OF COST FOR ONE NUMBER
Materials:
15mm dia CP one hole basin mixer Each 1 No. 1400.00 1400.00
Carriage:-
Carriage of materials. LS 5.00
Labour:
Labour for fixing. LS 25.00
Total:- 1430.00
Add 15% for CP & OH charges except Rs. 1425.00 213.75
on carriage i.e
Total:- 1643.75
Add GST @ 12% 243.75 29.25
1673.00
Add Labour Cess @ 1% 16.73
Cost for One Rs. 1689.73
Say Rs:- 1690.00

Executive Engineer,
IPH Division Thunag
ANALYSIS OF RATE
P/F 100mm dia nominal size PVC floor trap with
S.No. Description Unit Qty Rate Amount.
DETAIL OF COST FOR ONE NUMBER
Materials:
100mm dia PVC floor trap with grating Each 1 No. 180.00 180.00

Cement abd grit etc.


Carriage:-
Carriage of materials. LS 5.00
Labour:
Labour for fixing. LS 5.00
Total:- 190.00
Add 15% for CP & OH charges except Rs. 185.00 27.75
on carriage i.e
Total:- 217.75
Add GST @ 12% 26.13
Add Labour Cess @ 1% 2.18
Cost for One Rs. 246.06
Say Rs:- 246.00

Executive Engineer,
IPH Division Thunag
ANALYSIS OF RATE
P/F 100mm dia nominal size PVC floor trap with
S.No. Description Unit Qty Rate Amount.
DETAIL OF COST FOR ONE NUMBER
Materials:
100mm dia PVC floor trap with grating Each 1 No. 180.00 180.00

Cement abd grit etc.


Carriage:-
Carriage of materials. LS 5.00
Labour:
Labour for fixing. LS 5.00
Total:- 190.00
Add 15% for CP & OH charges except Rs. 185.00 27.75
on carriage i.e
Total:- 217.75

Add Labour Cess @ 1% 2.18


Cost for One Rs. 219.93
Say Rs:- 220.00

Executive Engineer,
IPH Division Thunag
Analysis of Rate
P/F 110 mm dia PVC single equal branch with cess door
Detail of cost for 1 No.
Desciption Unit Quantity Rate Amount

MATERIAL :
PVC sibgle equal branch 110 mm dia Each 1.00 240.00 240.00
Approved adhesive LS 5.00

Carriage of bend LS 2.00


Labour :

Labour LS 10.00
257.00
Add 10% C.P. & 5% O.H. Charges : 38.55
295.55
Add 12% GST 35.47
331.02
Add 1% labour cess 2.96
Cost for one no. 333.97

Say Rs. 334.00 /- only.

Executive Engineer,
IPH Division, Thunag
Analysis of Rate
P/F 75 mm dia PVC door bend with oval access door
Detail of cost for 1 No.
Desciption Unit Quantity Rate Amount

MATERIAL :
PVC door bend with oval access door Each 1.00 400.00 400.00
Approved adhesive LS 5.00

Carriage of bend LS 2.00


Labour :

Labour LS 10.00
417.00
Add 10% C.P. & 5% O.H. Charges : 62.55
479.55
Add 12% GST 57.55
537.10
Add 1% labour cess 4.80
Cost for one no. 541.89

Say Rs. 542.00 /- only.

Executive Engineer,
IPH Division, Thunag
Analysis of Rate
P/F 100 mm dia PVC door bend with oval access door
Detail of cost for 1 No.
Desciption Unit Quantity Rate Amount

MATERIAL :
PVC door bend with oval access door Each 1.00 142.00 142.00
Approved adhesive LS 10.00

Carriage of bend LS 15.00


Labour :

Labour LS 15.00
182.00
Add 10% C.P. & 5% O.H. Charges : 27.30
209.30
Add 12% GST 25.12
234.42
Add 1% labour cess 2.09
Cost for one no. 236.51

Say Rs. 237.00 /- only.

Executive Engineer,
IPH Division, Thunag
Analysis of Rate
P/F 110 mm dia PVC Collar
Detail of cost for 1 No.
Desciption Unit Quantity Rate Amount

MATERIAL :
PVC coller with oval access door Each 1.00 95.00 95.00
Approved adhesive LS 5.00

Carriage of bend LS 2.00


Labour :

Labour LS 10.00
112.00
Add 10% C.P. & 5% O.H. Charges : 16.80

128.80
Add 12% GST 15.46
144.26
Add 1% labour cess 1.29
Cost for one no. 145.54

Say Rs. 146.00 /- only.

Executive Engineer,
IPH Division, Thunag
Analysis of Rate
P/F 100 mm dia PVC plain bend
Detail of cost for 1 No.
Desciption Unit Quantity Rate Amount

MATERIAL :
PVC plain bend with oval access door Each 1.00 70.00 70.00
Approved adhesive LS 5.00

Carriage of bend LS 2.00


Labour :

Labour LS 10.00
87.00
Add 10% C.P. & 5% O.H. Charges : 13.05
100.05
Add 12% GST 12.01
112.06
Add 1% labour cess 1.00

Cost for one no. 113.06

Say Rs. 113.00 /- only.

Executive Engineer,
IPH Division, Thunag
Analysis of Rate
P/F 110 mm dia PVC clamp
Detail of cost for 1 No.
Desciption Unit Quantity Rate Amount

MATERIAL :
PVC clamp Each 1.00 35.00 35.00
Approved adhesive LS 5.00

Carriage of bend LS 2.00


Labour :

Labour LS 10.00
52.00
Add 10% C.P. & 5% O.H. Charges : 7.80
59.80
Add 12% GST 7.18
66.98
Add 1% labour cess 0.60
Cost for one no. 67.57

Say Rs. 68.00 /- only.

Executive Engineer,
IPH Division, Thunag
Analysis of Rate
P/F white glazed fire clay stall urinal with automatic C.I. flushing cistern with fitting RS or C
Ibrackets standard size , spreaders with union and clamp C.I. trap with outlet grating and coupling
in CP brass
Detail of cost for one no.
Material Qty. Rate Unit Amount
Flat black of angular lipped front urinal 1.00 1170.00 Each 1170.00
basin of 430x430x350mm and
340x430x265mm respective each of
white viterous china

10ltrs. PVC automatic flushing cistern 1.00 85.00 Each 85.00


with fitting standard size galvanised
steel flush pipe and spreders with
brass union and clamps including
fitting
White lead and gasket plug 1 150 Each 150.00
Screws LS 10.00
Cement sand and grit LS 20.00
Total:- 1435.00

Carriage LS 20
Labour
Fitter 2.40 311.50 Each 747.60

Masson 1st class 2.40 311.50 Each 747.60


Beldar 3.60 262.50 Each 945.00
3895.20
Add 1.5% water charges 58.428
3953.63
Add 15%CP & OH charges 593.04
4546.67
Add 12% GST 545.60066
5092.27
Add 1% labour cess 45.47
5137.74
Say Rs. 5138.00 only

Executive Engineer,
IPH Division, Thunag
Analysis of Rate
P/F CP brass connection pipe for flushing pipe/spreader for urinal with fitting complete in all
respect
Detail of cost for one no.
Material Qty. Rate Unit Amount
CP brass connection pipe 32mm dia 1.00 165.00 Each 165.00

Carriage LS 2.00
Labour LS 5.00
Total:- 172.00

Add 1.5% water charges 2.58


174.58
Add 15%CP & OH charges 26.19
200.77
Add 12% GST 24.09
224.86
Add 1% labour cess 2.01
226.87
Say Rs. 227.00 only

Executive Engineer,
IPH Division, Thunag
ANALYSIS OF RATE
Providing and fixing pillar tap bib tap with capstan head.
S.No. Description Unit Qty Rate Amount.
15mm
DETAIL OF COST FOR ONE NUMBER
Materials:
CP Brass bib tap with capstan head. Each 1 No. 790.00 790.00
15mm dia weight 400gms.
Carriage:-
Carriage of materials. LS 1.00
Labour:
Labour for fixing. LS 1.00
Total:- 792.00
Add 15% for CP & OH charges except Rs. 791.00 118.65
on carriage i.e
Total:- 910.65
Add GST @ 12% 109.28
1019.93
Add Labour Cess @ 1% 9.11
Cost for One Rs. 1029.04
Say Rs:- 1029.00
Executive Engineer,
IPH Division Thunag
ANALYSIS OF RATE
Providing and fixing top cock with capstan head.
S.No. Description Unit Qty Rate Amount.
15mm
DETAIL OF COST FOR ONE NUMBER
Materials:
CP Brass bib tap with capstan head. Each 1 No. 790.00 790.00
15mm dia weight 400gms.
Carriage:-
Carriage of materials. LS 1.00
Labour:

Labour for fixing. LS 1.00


Total:- 792.00
Add 15% for CP & OH charges except Rs. 791.00 118.65
on carriage i.e
Total:- 910.65
Add GST @ 12% 109.28
1019.93
Add Labour Cess @ 1% 9.11
Cost for One Rs. 1029.04
Say Rs:- 1029.00

Executive Engineer,
IPH Division Thunag
ANALYSIS OF RATE
P/F brass full way valve
S.No. Description Unit Qty Rate Amount.
DETAIL OF COST FOR ONE NUMBER
Materials:
Brass full way valve 15mm dia Each 1 No. 275.00 275.00
Carriage:-
Carriage of materials. LS 5.00
Labour:
Labour for fixing. LS 5.00
Total:- 285.00
Add 15% for CP & OH charges except 42.75
on carriage i.e
Total:- 327.75
Add GST @ 12% 39.33
367.08
Add Labour Cess @ 1% 3.28
Cost for One Rs. 370.36
Say Rs:- 370.00

Executive Engineer,
IPH Division Thunag
ANALYSIS OF RATE
P/F brass full way valve
S.No. Description Unit Qty Rate Amount.
DETAIL OF COST FOR ONE NUMBER
Materials:
Brass full way valve 20mm dia Each 1 No. 350.00 350.00
Carriage:-
Carriage of materials. LS 5.00
Labour:
Labour for fixing. LS 5.00
Total:- 360.00
Add 15% for CP & OH charges except 54.00
on carriage i.e
Total:- 414.00
Add GST @ 12% 49.68
463.68
Add Labour Cess @ 1% 4.14
Cost for One Rs. 467.82
Say Rs:- 468.00

Executive Engineer,
IPH Division Thunag
ANALYSIS OF RATE
P/f PTMT coloured/white high density/polythene/poly proliters capacity(full flush) European standard
control lowlevel flushing system with a pair of racket with fitting such as lead valve syphon 15mm nominal
size valve with polythene float with push button coupling for connection with inlet and overflow pipe 40mm
dia
Sr. CP
No. flash bend Description
i/c cutting hole and making good
of items and connectiing
Unit Quantity the flush bend
Rate cistern and closet(over
Amount

1 Automatic low level flushing Each 1 850.00 850.00


CI or MS brackets Pair 1 25.00 25.00
Cement sand etc. LS
Carriage of materials LS

Labour
Plumber(fitting) Each 0.20 311.50 62.30
Mason 1st class Each 0.40 311.50 124.60
Beldar Each 0.40 262.50 105.00
Total:- 1166.90

Add 15% CP& OH charges 175.035


Total:- 1341.94
Add GST 12% 161.0322
Total:- 1502.97
Add 1% labour cess 13.42
G.Total:- 1516.39
Say Rs. 1516.00 only

Executive Engineer,
IPH Division Thunag
ANALYSIS OF RATE
P/F PTMT waste coupling for wash basin or sink 32mm dia i/c all accessories of superiors quality as
approved by the Engineer in Charge

Sr. No. Description of items Unit Quantity Rate Amount

1 Brass waste coupling pipe Each 1 250.00 250.00


Carriage of materials LS 2.00

Labour for fixing LS 5.00


Total:- 257.00

Add 15% CP& OH charges 38.55


Total:- 295.55
Add GST 12% 35.466
Total:- 331.02
Add 1% labour cess 2.96
G.Total:- 333.97
Say Rs. 334.00 only

Executive Engineer,
IPH Division Thunag
Analysis of Rate
P/F Division Plate for urinals 600x330mm vitreous China
Detail of cost for one no.
Material Qty. Rate Unit Amount
Division Plate for urinals 600x330mm 1.00 1690.00 Each 1690.00

Carriage LS 2.00
Labour LS 5.00
Total:- 1697.00

Add 1.5% water charges 25.455


1722.46
Add 15%CP & OH charges 258.37
1980.82
Add 12% GST 237.70
2218.52
Add 1% labour cess 19.81
2238.33
Say Rs. 2238.00 only

Executive Engineer,
IPH Division, Thunag
ANALYSIS OF RATE
P/F brass ball valve
S.No. Description Unit Qty Rate Amount.
DETAIL OF COST FOR ONE NUMBER
Materials:
Brass ball valve 15mm dia Each 1 No. 350.00 350.00
Carriage:-
Carriage of materials. LS 5.00
Labour:
Labour for fixing. LS 5.00
Total:- 360.00
Add 15% for CP & OH charges except 54.00
on carriage i.e
Total:- 414.00
Add GST @ 12% 49.68
463.68
Add Labour Cess @ 1% 4.14
Cost for One Rs. 467.82
Say Rs:- 468.00

Executive Engineer,
IPH Division Thunag
ANALYSIS OF RATE
P/F brass ball valve

S.No. Description Unit Qty Rate Amount.


DETAIL OF COST FOR ONE NUMBER
Materials:
Brass full way valve 20mm dia Each 1 No. 350.00 350.00
Carriage:-
Carriage of materials. LS 5.00
Labour:
Labour for fixing. LS 5.00
Total:- 360.00
Add 15% for CP & OH charges except 54.00
on carriage i.e
Total:- 414.00
Add GST @ 12% 49.68
463.68
Add Labour Cess @ 1% 4.14
Cost for One Rs. 467.82
Say Rs:- 468.00

Executive Engineer,
IPH Division Thunag
ANALYSIS OF RATE
P/f PTMT coloured/white high density/polythene/poly proliters capacity(full flush) European standard
control lowlevel flushing system with a pair of racket with fitting such as lead valve syphon 15mm nominal
size valve with polythene float with push button coupling for connection with inlet and overflow pipe 40mm
dia
Sr. CP
No. flash bend Description
i/c cutting hole and making good
of items and connectiing
Unit Quantity the flush bend
Rate cistern and closet(over
Amount

1 Automatic low level flushing Each 1 1250.00 1250.00

Carriage LS 10.00
Fixing charges LS 10.00
1270.00
Add 15% CP& OH charges 190.5
Total:- 1460.50
Add GST 12% 175.26
Total:- 1635.76
Add 1% labour cess 14.61
G.Total:- 1650.37
Say Rs. 1650.00 only

Executive Engineer,
IPH Division Thunag
ANALYSIS OF RATE
76.00 P/F on wall face PVC door bend (D-Plast) with oval acces door, insertaion rubber wsher 3 mm
thick bolts and nuts ISI marked complete i/c with approved adhesive complete with in all leads
and lift 10 kg/sqm working pressure PVC pipe

S.No. Description Unit Qty Rate Amount.


DETAIL OF COST FOR ONE NUMBER
Materials:
110mm dia PVC bend Each 1 No. 95.00 95.00
Rubber washer 3mm thick LS 5.00
Approved adhesive LS 5.00
Carriage:-
Carriage of materials. LS 2.00
Labour:
Labour for fixing. LS 5.00
Total:- 112.00
Add 15% for CP & OH charges except 16.80
on carriage i.e
Total:- 128.80
Add GST @ 12% 15.46
144.26
Add Labour Cess @ 1% 1.29
Cost for One Rs. 145.55
Say Rs:- 146.00

Executive Engineer,
IPH Division Thunag
ANALYSIS OF RATE
P/F 110mm PVC soil waste and ventilating pipe including cost of jointing adhesive

S.No. Description Unit Qty Rate Amount.


DETAIL OF COST FOR ONE NUMBER
Materials:
110mm dia soil waste PVC pipe per 6 No. 140.00 840.00
pipe
(each pipe 6.0 mtr long)
5% allowance for wastage 42.00

Carriage LS 5.00
Labour:
Labour for jointing LS 10.00
Cost of jointing adhesive LS 10.00
Total:- 897.00
Add 15% for CP & OH charges except 134.55
on carriage i.e
Total:- 1031.55
Add GST @12% 123.79
1155.34
Add Labour Cess @ 1% 10.32
Cost for 6 rmt Rs. 1165.65
Say Rs:- 194.00

Executive Engineer,
IPH Division Thunag
ANALYSIS OF RATE
P/F 150mm PVC soil waste and ventilating pipe including cost of jointing adhesive

S.No. Description Unit Qty Rate Amount.


DETAIL OF COST FOR ONE NUMBER
Materials:
150mm dia soil waste PVC pipe per 6 No. 285.00 1710.00
pipe
(each pipe 6.0 mtr long)
5% allowance for wastage 85.50

Carriage LS 5.00
Labour:
Labour for jointing LS 10.00
Cost of jointing adhesive LS 10.00
Total:- 1810.50
Add 15% for CP & OH charges except 271.58
on carriage i.e
Total:- 2082.08
Add GST @12% 249.85
2331.92
Add Labour Cess @ 1% 20.82
Cost for 6 rmt Rs. 2352.74
Say Rs:- 392.00

Executive Engineer,
IPH Division Thunag
CARRIAGE
A Heavy material and pipe below
100mm. Unit : Per Tonne.
AV. LEAD : By Mech. 25 Km.

By Head : 0 Km.

1 By Mech. Nos. Rate/ Km.


1 Km. 0 98.28 0.00
2 Km. 0 113.79 0.00
3 Km. 0 129.14 0.00
4 Km. 0 144.07 0.00
5 Km. 1 158.32 158.32

5- 10 Km. 5 13.21 66.05


10-20 Km. 10 11.09 110.90
Beyond 20 Km. 5 9.38 46.90
TOTAL : 382.17

2 By Head load
1st. 1 Km. 0 561.75 0.00
1st. 100 Mtr 0 89.25 0.00
Bey:1 Km.Per 1/2Km. 0 280.88 0.00
Bey:100 Mtr Per 50 Mtr 0 26.25 0.00
Total : 0.00

Total: 0.00

Executive Engineer,
IPHDivision Thunag
ANALYSIS OF RATE
Providing and fixing 100mm size P or S trap for water closet( squatting pan) including jointing
the trap with the pan and soil pipe in cement mortar 1:1 (1cement :1 sand) Vitreous China
S.No. Description Unit Qty Rate Amount.

DETAIL OF COST FOR 1 No.


Materials:-
100mm P or S Trap Each 1 No. 1850.00 1850.00

Carriage:-
Carriage of materials. LS 2.00

Labour:-

Labour for fixing LS 10.00


1862.00
Add 15% CP and OH charges 279.3

2141.30
Add GST @ 12% 256.96
2398.26
Add Labour cess @ 1% 21.41
Cost for 1 No. 2419.67

Say Rs:- 2420.00

Executive Engineer,
IPH DivisionThunag
ANALYSIS OF RATE
Providing and fixing 30 cm long PVC connection pipe 15mm dia with brass union of superior
quality
S.No. Description Unit Qty Rate Amount.
DETAIL OF COST FOR 1 No.
Materials:-
30cm long PVC connection Each 1 No. 90 90.00

Carriage:-
Carriage of materials. LS 0.50

Labour:-

Labour for fixing LS 2.00


92.50
Add 15% CP and OH charges 13.88
106.38
Add GST @ 12% 16.38 1.9656
108.35
Add Labour cess @ 1% 1.08
Cost for 1 No. 109.43

Say Rs:- 109.00

Executive Engineer,
IPH DivisionThunag
ANALYSIS OF RATE
Providing and fixing bath room jet in water closet complete in all respect including PVC
connection pipe with brass check nut and all other accessories contingent
S.No. Description Unit Qty Rate Amount.
DETAIL OF COST FOR 1 No.
Materials:-
Bath room Jet Each 1 No. 300 300.00

Carriage:-
Carriage of materials. LS 0.50

Labour:-

Labour for fixing LS 1.00


301.50
Add 15% CP and OH charges 45.23
346.73
Add GST @ 12% 41.61
388.34
Add Labour cess @ 1% 3.47
Cost for 1 No. 391.81

Say Rs:- 392.00

Executive Engineer,
IPH DivisionThunag
ANALYSIS OF RATE
Providing and fixing C.P. consild angle cock ISI marked

S.No. Description Unit Qty Rate Amount.


DETAIL OF COST FOR 1 No.
Materials:-
CP consild angle cock Each 1 No. 400 400.00

Carriage:-

Carriage of materials. LS 0.50

Labour:-
Labour for fixing LS 1.00
401.50
Add 15% CP and OH charges 60.23
461.73
Add GST @ 12% 55.41
517.14

Add Labour cess @ 1% 5.17


Cost for 1 No. 522.31

Say Rs:- 522.00

Executive Engineer,
IPH DivisionThunag
ANALYSIS OF RATE
Providing and fixing CP brass bib cock of 15mm dia of superior quality.

S.No. Description Unit Qty Rate Amount.


DETAIL OF COST FOR 1 No.
Materials:-
CP brass bib cock 15mm Each 1 No. 0.00 0.00

Carriage:-

Carriage of materials. LS 2.00

Labour:-
Labour for fixing LS 20.00
22.00
Add 15% CP and OH charges 3.3
25.30
Add GST @ 12% 25.30 3.036
28.34

Add Labour cess @ 1% 0.28


Cost for 1 No. 28.62

Say Rs:- 29.00

Executive Engineer,
IPH DivisionThunag
ANALYSIS OF RATE
Providing and fixing Chromium plated brass waste coupling for wash basin or sink 32mm dia
including all accessories of superior quality .

S.No. Description Unit Qty Rate Amount.


DETAIL OF COST FOR 1 No.
Materials:-
brass waste coupling for wash Each 1 No. 175 175.00
basin or sink 32mm
Carriage:-

Carriage of materials. LS 0.50

Labour:-
Labour for fixing LS 2.00
177.50
Add 15% CP and OH charges 26.63
204.13
Add GST @ 12% 24.5
228.63

Add Labour cess @ 1% 2.29


Cost for 1 No. 230.92

Say Rs:- 231.00

Executive Engineer,
IPH DivisionThunag
ANALYSIS OF RATE
Providing and fixing PVC pipe ISI marked100 mm dia in all leads and lifts.
S.No. Description Unit Qty Rate Amount.

DETAIL OF COST FOR 1 No.

Materials:-
PVC pipe 100mm Rmt 1 Rmt 140.00 140.00

Carriage:-
Carriage of materials. LS 5.00

Labour:-
Labour for fixing LS 5.00
150.00
Add 15% CP and OH charges 22.5
172.50

Add GST @ 12% 32.50 3.9


176.40
Add Labour cess @ 1% 1.73
Cost for 1 No. 178.13

Say Rs:- 178.00

Executive Engineer,
IPH DivisionThunag
ANALYSIS OF RATE
Providing and fixing GI union 15mm dia ISI marked in all leads and lifts.
S.No. Description Unit Qty Rate Amount.

DETAIL OF COST FOR 1 No.


Materials:-
G.I union 15mm sia Each 1 No. 65.00 65.00

Carriage:-
Carriage of materials. LS 0.50

Labour:-
Labour for fixing LS 0.50
66.00
Add 15% CP and OH charges 9.9
75.90

Add GST @ 12% 75.90 9.108


85.01
Add Labour cess @ 1% 0.76
Cost for 1 No. 85.77

Say Rs:- 86.00

Executive Engineer,
IPH DivisionThunag
ANALYSIS OF RATE
Providing and fixing GI Elbow 15mm dia ISI marked in all leads and lifts.
S.No. Description Unit Qty Rate Amount.

DETAIL OF COST FOR 1 No.


Materials:-
G.I Elbow 15mm dia Each 1 No. 80.00 80.00

Carriage:-
Carriage of materials. LS 0.50

Labour:-
Labour for fixing LS 0.50
81.00
Add 15% CP and OH charges 12.15
93.15

Add GST @ 12% 93.15 11.178


104.33
Add Labour cess @ 1% 0.93
Cost for 1 No. 105.26

Say Rs:- 105.00

Executive Engineer,
IPH DivisionThunag
ANALYSIS OF RATE
Providing and fixing Tee 15mm equal ISI marked in all leads and lifts.
S.No. Description Unit Qty Rate Amount.
DETAIL OF COST FOR 1 No.
Materials:-
G.I Tee 15mm dia Each 1 No. 75.00 75.00

Carriage:-
Carriage of materials. LS 0.50

Labour:-
Labour for fixing LS 0.50
76.00
Add 15% CP and OH charges 11.4

87.40
Add GST @ 12% 87.40 10.488
97.89
Add Labour cess @ 1% 0.98
Cost for 1 No. 98.87

Say Rs:- 99.00

Executive Engineer,
IPH DivisionThunag
ANALYSIS OF RATE
Providing and fixing Socket 15mm dia ISI marked in all leads and lifts.
S.No. Description Unit Qty Rate Amount.
DETAIL OF COST FOR 1 No.
Materials:-
G.I Socket 15mm sia Each 1 No. 30.00 30.00

Carriage:-
Carriage of materials. LS 0.50

Labour:-
Labour for fixing LS 0.50
31.00
Add 15% CP and OH charges 4.65

35.65
Add GST @ 12% 4.28
39.93
Add Labour cess @ 1% 0.40
Cost for 1 No. 40.33

Say Rs:- 40.00

Executive Engineer,
IPH DivisionThunag
ANALYSIS OF RATE
Providing and fixing G.I nipple 15mm dia ISI marked in all leads and lifts.
S.No. Description Unit Qty Rate Amount.
DETAIL OF COST FOR 1 No.
Materials:-
G.I Nipple 15mm sia Each 1 No. 48.00 48.00

Carriage:-
Carriage of materials. LS 0.50

Labour:-
Labour for fixing LS 0.50
49.00
Add 15% CP and OH charges 7.35

56.35
Add GST @ 12% 6.76
63.11
Add Labour cess @ 1% 0.56
Cost for 1 No. 63.67

Say Rs:- 64.00

Executive Engineer,
IPH DivisionThunag
ANALYSIS OF RATE
Providing and fixing PVC water tank complete in all respect in all leads and lifts.
S.No. Description Unit Qty Rate Amount.
DETAIL OF COST FOR 1 No.
Materials:-
PVC water tank 1000 ltrs ( 1 No.) Ltr. 1000 Ltr. 4.80 4800.00
(R.C.)
Carriage:-
Carriage of materials. LS 1000.00

Labour:-
Labour for fixing LS 1000.00
6800.00
Add 15% CP and OH charges 2000.00 300.00

7100.00
Add GST @ 12% 7100.00 852.00
7952.00
Add Labour cess @ 1% 71.00
Cost for 1 No. 8023.00
Say Rs. 8023.00
Cost for 1 Ltr. 16.05

Executive Engineer,
IPH DivisionThunag
ANALYSIS OF RATE
Providing pillar type heater for chowkidar and pump house
S.No. Description Unit Qty Rate Amount.
DETAIL OF COST FOR 1 No.
Materials:-
Pillar type heater Each 1 No. 4100 4100.00

Carriage:-
Carriage of materials. LS 0.50

Labour:-
Labour for fixing LS 0.00
4100.50
Add 15% CP and OH charges 615.08

4715.58
Add GST @ 12% 565.87
5281.45
Add Labour cess @ 1% 52.81
Cost for 1 No. 5334.26

Say Rs:- 5334.00

Executive Engineer,
IPH DivisionThunag
ANALYSIS OF RATE
Providing and fixing vitreous china wash down water closet (European type W.C. pan)
with integral 'P' or 'S' trap including jointing the trap with soil pipe in cement mortar
1:1(1cement :1sand) seat and cover to be measured and paid for separately

S.No. Description Unit Qty Rate Amount.


1) European Type
DETAIL OF COST FOR ONE No.
Material:
White vetreous china Orrisa
pattern water closet
squatting pan size 580mm Each 1 No. 1350.00 1350.00
Cement sand and grit etc. LS 10.00
Total:
Carriage;
Carriage of material LS 5.00
Labour:
Mason 1st class Each 0.60 Nos, 311.5 186.90
Beldar Each 0.60 Nos, 262.5 157.50

G.Total 1709.40
Add for water charges @ 1.5% 25.64
Total: 1735.04
Add 15% for CP & OH charges Rs. 1730.04 259.51
except on carriage i.e
Total:- 1994.55
Add GST @ 12% 644.55 77.35
2071.89
Add Labour Cess @ 1% 19.95
Cost for One Rs. 2091.84
Say Rs:- 2092.00

Executive Engineer,
IPH Division Thunag
ANALYSIS OF RATE
69.00 Providing and fixing automatic flushing cistern with a pair of C.I. or M.S. brackets
complete with fittings including C.I. syphonic apparatus, masquito proof lid, C.P. Brass
unions and coupling for connections with inlet, outlet and over flow pipes including
cutting holes and making good the same (over flow pipe to be measured and paid for
separately) 5 ltrs. capacity

S.No. Description Unit Qty Rate Amount.


a) Vitreos China in whte colour.
DETAIL OF COST FOR ONE No.
Material;
flushing cistern Each 1 No. 2800.00 2800.00

C.I or MS brackets Pair 1 Pair 20.00 20.00


Cement sand white lead etc. LS 3.00
Total: 2823.00
Carriage:
Carriage of materials. LS 3.00
Labour:
Plumber (Fitter) Each 0.60 Nos, 311.5 186.90
Beldar Each 0.60 Nos. 262.5 157.50
Total: 344.40
Gtotal: 3170.40
Add for water charges @ 1.5% 47.56
Total: 3217.96
Add 15% for CP & OH charges Rs. 3214.96 482.24
except on carriage i.e
Total:- 3700.20
Add GST @ 12% 444.02
4144.22
Add Labour Cess @ 1% 37.00
Cost for One Rs. 4181.22
Say Rs:- 4181.00

Executive Engineer,
IPH Division Thunag
ANALYSIS OF RATE
P/F PVC brass waste pipe for wash basin and sink.
S.No. Description Unit Qty Rate Amount.
i) 32mm dia.
DETAIL OF COST FOR ONE NUMBER
Materials:
CP brass waste for wash basin Each 1 No. 220.00 220.00
and sink.
Carriage:-
Carriage of materials. LS 1.00
Labour:
Labour for fixing LS 2.00
Total: 223.00
Add 15% for CP & OH charges Rs. 222.00 33.30
except on carriage i.e
Total:- 256.30
Add GST @ 12% 36.30 4.36
260.66
Add Labour Cess @ 1% 2.61
Cost for One Rs. 263.27
Say Rs:- 263.00

Executive Engineer,
IPH Division Thunag
ANALYSIS OF RATE
P/F PVC frame with three glass self
S.No. Description Unit Qty Rate Amount.
DETAIL OF COST FOR ONE NUMBER
Materials:

Glass self Each 1 No. 400.00 400.00


Wooden plug Each 2 Nos. 5.00 10.00
CP brass screws LS 1.50
Total; 411.50
Carriage:-
Carriage of materials. LS 2.00
Labour:
Carpenter 2nd class Each 0.30 Nos. 311.5 93.45
Beldar Each 0.30 Nos. 262.5 78.75
Total: 172.20
G Total 585.70
Add 15% for CP & OH charges Rs. 583.70 87.56
except on carriage i.e
Total:- 673.26

673.26
Add Labour Cess @ 1% 6.73
Cost for One Rs. 679.99
Say Rs:- 680.00

Executive Engineer,
IPH Division Thunag
ANALYSIS OF RATE
Providing and fixing Gun Metal gate valve 15 mm dia

Detail of Cost for 1 No.

Sr. No. Discription of item Qty. Rate Unit Amount


MATERIAL :

Gun metal gate valve 15 mm dia 1.00 No 300.00 Each 300.00


(M.R.)
Carriage L.S. 10.00

Total:- 310.00
Add for 10% C.P. and 5% O.H. Charges 310.00 46.50
Total:- 356.50
Add GST @12% 12% 42.78
399.28
Add Labour cess @ 1% 3.57

Cost for 1No. 402.85


Say Rs. 403.00 /-Only

Executive Engineer,
IPH Division Thunag
ANALYSIS OF RATE

P/F P/S trap

71.00 S.No. Description Unit Qty Rate Amount.

DETAIL OF COST FOR ONE NUMBER


Materials:
100mm dia PVC P&S trap Each 1 No. 250.00 250.00
Cement abd grit etc.

Carriage:-

Carriage of materials. LS 5.00


Labour:
Labour for fixing. LS 5.00
Total:- 260.00
Add 15% for CP & OH charges Rs. 255.00 38.25
except on carriage i.e
Total:- 298.25

Add Labour Cess @ 1% 2.98


Cost for One Rs. 301.23
Say Rs:- 301.00

Executive Engineer,
IPH Division Thunag
Analysis of Rate
P/F 75 mm dia PVC plain bend
Detail of cost for 1 No.
Descipt Unit Quantity Rate Amount

MATERIAL :
PVC plaEach 1.00 40.00 40.00
ApproveLS 5.00

Carriag LS 2.00
Labour :

Labour LS 10.00
57.00
Add 10% C.P. & 5% O.H. Charges : 8.55
65.55
Add 12% GST 7.87
73.42
Add 1% labour cess 0.66

Cost for one no. 74.07

Say Rs. 74.00 /- only.

Executive Engineer,
IPH Division, Thunag
ANALYSIS OF RATE
Providing and fixing PVC connection pipe 300x450x600mm 15mm nominal size dia with brass
union of superior quality
S.No. Description Unit Qty Rate Amount.
DETAIL OF COST FOR 1 No.
Materials:-
PVC connection Each 1 No. 110 110.00

Carriage:-
Carriage of materials. LS 0.50

Labour:-
Labour for fixing LS 2.00
112.50
Add 15% CP and OH charges 16.88
129.38
Add GST @ 12% 19.38 2.3256
131.71
Add Labour cess @ 1% 1.29
Cost for 1 No. 133.00

Say Rs:- 133.00

Executive Engineer,
IPH DivisionThunag
ANALYSIS OF RATE
75.00 PROVIDING & FIXING ON WALL FACE PVC ( D-Plast) rain water pipes for working pressure
not less 4.5 kg / sqcm
DETAIL OF COST FOR 8.70 Mtr.)
S.No. Description of item Qty. Rate Unit Amount
(A) MATERIAL:- 110 mm and length 1.83 mtr.
PVC pipe 110 mm 8.7 Mtr 100.00 Rmt. 870.00
Adhesive LS 30.00
TOTAL 900.00
(B) CARRIAGE:- LS 25.00
TOTAL 25.00
(c ) LABOUR:-
FITTER 0.40 311.50 Ecah 124.60

BELDAR 0.40 262.50 Ecah 105.00


BANDHANI 0.10 262.50 Ecah 26.25
SCAFFOLDING LS 30.00
TOTAL 285.85
TOTAL (1 to 3) 1210.85
ADD 10 % CP & 5 % OHC except carriage 1185.85 177.88
COST FOR 8.70 Mtr. TOTAL 1388.73
Add GST @ 12% 166.65
1555.37
Add Labour Cess @ 1% 13.89
COST FOR 8.70 Mtr. 1569.26
Cost Per Mtr 180.38
Say Rs: 180.00

Executive Engineer,
IPH Division Thunag
Carriage of Pipe.
Labour Rates RATES. PIPE H/Oil
Analysis of Rate(G.I Pipe) Fitter (grade-I) 178.50 Dia LEAD IN KM. Mech. H/Load
RATE
RATE
(G.I Pipe) Bellow100mm. Fitter (grade-II) 178.50 15 25 0 382.17 0.00 44.00 10.00
Beldar 140.00 20 382.17 0.00 63.00 10.00
25 382.17 0.00 83.00 10.00
DO NOT REDUCE OR 32 382.17 0.00 97.00 10.00
INCREASE THE COLUMN OR 40 382.17 0.00 124.00 10.00
CELL SIZE AND CHANGE THE 50 382.17 0.00 150.00 10.00
REQUIRED DATA FROM THE 65 382.17 0.00 220.00 10.00
DATA SHEET ONLY ONLY 80 382.17 0.00 320.00 10.00
CHANGE THE FIGURES .
100 382.17 0.00 411.00 10.00
125
150
Analysis of Rate (G.I Pipe)
PROVIDING ,LAYING,JOINTING &TESTING IN TRENCHES G.I PIPE. (DETAIL OF COST FOR 10 Rmt.).
15mm dia (light class) 20mm dia (light class) 25mm dia (light class)
S.No. DESCRIPTION OF ITEMS UNIT
Qty. Rate. Amount. Qty. Rate. Amount. Qty. Rate. Amount.
1 MATERIAL:
G.I. Tube = 10 Rmt.
Add 2% for fitting and wa 0.20
Total: 10.20 Rmt. Rmt. 10.20 44.00 448.80 10.2 242.0 2468.40 10.20 83.00 846.60
White lead,Hemp oil etc. : LS. 10.00 LS. 10.00 LS. 10.00

2 CARRIAGE:
25.00 Km.By mechanical transport Per Tone. 0.01 382.17 3.82 0.02 382.17 5.73 0.0217 382.17 8.29
0 Mtr.By head load. Per Tone. 0.01 0.00 0.00 0.02 0.00 0.00 0.0217 0.00 0.00

3 LABOUR:
PLUMBER (FITTE each. 0.10 178.50 17.85 0.10 178.50 17.85 0.14 178.50 24.99
BELDAR each. 0.19 140.00 26.60 0.19 140.00 26.60 0.30 140.00 42.00

GRAND TOTAL: 507.072 2528.583 931.88

Add 10% Contractor profit and 5% over head charges.(EXCEPT ON G.I PIPE): 8.74 9.03 12.79

Total: 515.81 2537.61 944.68

Cost per Rmt. 51.58 253.76 94.47

Say Rs.:- 51.58 253.76 94.47


Quantity
Mech. H/Load

0.01 0.01
0.015 0.015
0.0217 0.0217
0.0279 0.0279
0.0352 0.0352
0.0447 0.0447
0.0622 0.0622
0.0746 0.0746
0.1020 0.1020
).
32mm dia (light class) 40mm dia (light class) 50mm dia (light class) 65mm dia (light class) 80mm dia (light class) 100mm dia (light class)
Qty. Rate. Amount. Qty. Rate. Amount. Qty. Rate. Amount. Qty. Rate. Amount. Qty. Rate. Amount. Qty. Rate. Amount.

10.20 97.00 989.40 10.20 124 1264.80 10.20 150 1530.00 10.20 220 2244.00 10.20 320.00 3264.00 10.20 411.00 4192.20
LS. 10.00 LS. 10.00 LS. 10.00 LS. 10.00 LS. 10.00 LS. 10.00

0.03 382.17 10.66 0.04 382.17 13.45 0.0447 382.17 17.08 0.06 382.17 23.77 0.07 382.17 28.51 0.1020 382.17 38.98
0.03 0.00 0.00 0.04 0.00 0.00 0.0447 0.00 0.00 0.06 0.00 0.00 0.07 0.00 0.00 0.1020 0.00 0.00

0.14 178.50 24.99 0.19 178.50 33.92 0.19 178.50 33.92 0.3 17.85 5.36 0.30 178.50 53.55 0.40 178.50 71.40
0.30 140.00 42.00 0.40 140.00 56.00 0.40 140.00 56.00 0.79 140.00 110.60 0.79 140.00 110.60 1.19 140.00 166.60

1077.0525 1378.167 1647.00 2393.73 3466.66 4479.18

13.15 17.01 17.55 22.46 30.40 43.05

1090.20 1395.17 1664.55 2416.18 3497.06 4522.23

109.02 139.52 166.45 241.62 349.71 452.22

109.02 139.52 166.45 241.62 349.71 452.22


CARRIAGE OF MATERIAL

A Heavy material and pipe below 100mm.


Unit : Per Tonne.
LEAD : By Mech. 25 Km.
By Head 0 Km.
1 By Mech.Nos. Rate/ Km.
1 Km. 0 98.28 0
2 Km. 0 113.79 0
3 Km. 0 129.14 0
4 Km. 0 144.07 0
5 Km. 1 158.32 158.32
5- 10 Km. 5 13.21 66.05
10-20 Km 10 11.09 110.9
Beyond 2 5 9.38 46.9
TOTAL : 382.17
2 By Head load
1st. 1 Km 0 561.75 0
1st. 100 0 89.25 0
Bey:1 Km 0 280.88 0
Bey:100 M 0 26.25 0
Total : 0
G.Total: 1+2= 1262.52 Per Tonne.

You might also like