Pump Life Cycle Cost 3 Maintenance Cost Reduction
Pump Life Cycle Cost 3 Maintenance Cost Reduction
Maintenance Strategies
There are several maintenance strategies
used by our end-users.
Run to failure
Preventive Maintenance
Predictive and pro-active Maintenance
Risk based Maintenance management.
Maintenance Strategies
Run to failure
This is a very simple Maintenance Strategy, where
Equipment is taken out of service after it shows a failure.
This can range from a leaking mechanical seal up to a
Catastrophic failure.
Typical used in seasonal processes
Example: - Sugar Mill
- Runs only 3 4 months per year
Maintenance Strategies
Run to failure
This was the very first Maintenance Strategy, where Customer is only
reactive to pump problems and failures.
It is still used in continuous processes like for example Refineries.
(For example: AGIP Refineries in Italy like the PRIOLO Refinery).
Run to failure
Maintenance Strategies
Preventive Maintenance
In this maintenance strategy, equipment and pumps are opened for
inspections and possible repairs on a regular basis.
The process is stopped for these general inspections
(Shut-downs, refineries etc. scheduled plant outage, power-plants)
The period for these preventive inspections is typically lower than the
average Mean Time Between Repairs (MTBR) of equipment.
Typical used for processes with a high economic risk factor to loose
production or processes generating a high safety risk if pumps fail
unscheduled.
Maintenance Strategies
Preventive Maintenance
Preventive maintenance can also be applied during the
operation of the customer process, if pumps are installed
with a 100% spare unit (Redundancy).
Condition monitoring
LYFE CYCLE COST (LCC) Pump Division
Conditioning Monitoring
Process Plant, Chemical Plant, Refinery
Weekly
WeeklyororMonthly
Monthly
data
datataking.
taking.
Hand-hold vibro-meter
Pump P001
mm/sec Alarm Level - - - - - - - - - - - - - - - *
RMS * * * * * *
* * * *
Time
Pump Division
Vibration operational
spectrum (FFT)
LYFE CYCLE COST (LCC) Pump Division
Conditioning Monitoring
Permanent
installed
system
LYFE CYCLE COST (LCC) Pump Division
Conditioning Monitoring
From Measured
Vibration Data we can
produce.
FFT (spectrum) Filtered vibrations, bode plot
with speed variation
Conditioning Monitoring
Conditioning Monitoring
Conditioning Monitoring
Result of database search
Pump Division
Maintenance Strategies
So far we have seen the 3 major maintenance strategies
used on rotating machines / pumps.
Maintenance Strategies
Bad Actors
Maintenance Strategies
You can always produce with your customer the plant
Bad Actor list.
RISK ASSESSMENT
RISK DEFINED BY CONSEQUENCES AND PROBABILITIES
CONSEQUENCES
- SAFETY
- ENVIRONMENT
- PRODUCT LOSSES
PROBABILITIES
- TIME FRAME TO BE USED
- HISTORICAL / STATISTIC DATA
- SOMETIMES COMBINATION OF EVENTS NEEDED
- MITIGATING
WORK TO BE DONE
PROBABILITY
LYFE CYCLE COST (LCC) Pump Division
WORK TO BE DONE
WORK MAY BE
POSTPONED
NO WORK TO BE DONE
PROBABILITY
LYFE CYCLE COST (LCC) Pump Division
Maintenance Strategies
Risk based maintenance management
Can only be applied on a Healthy population
Where bad actors are eliminated as this reduces
The probability in this method.
Repair work can be postponed or cancelled to drive cost down
Some customer are using this method, like for example EXXON Europe.
EXXON Refinery, preventive maintenance (Fawley) pump annual maintenance
cost per year 2800 Euro MTBR 24 months
EXXON Refinery, predictive maintenance, followed by Risk based maintenance
management (Rotterdam)
End 1980 s large investment to reduce bad actors.
1990 2000 predictive maintenance
pump annual cost per year 1200/1300 Euro MTBR 85 months
2000 2005 predictive, risk based maintenance pump annual cost
per year 850 Euro MTBR 85 months.
Pump Division
Wear area s
Overlay welding
Laser hardening
wear rings
HVOF spraying
Diffusion Alloying
LYFE CYCLE COST (LCC) Pump Division
Diffusion Alloying
LYFE CYCLE COST (LCC) Pump Division
MDPR
Mean depth of penetration a
standard measure of resistance to
cavitation damage
LYFE CYCLE COST (LCC) Pump Division
Vibrations
Rotor-dynamic analysis
Lateral critical speed
Unbalance response
Eigen value / stability
Torsional analysis
(transient)
LYFE CYCLE COST (LCC) Pump Division
Vibrations
Structural dynamic analysis
Foundation analysis
Unbalance response
analysis
Structural resonances FEM
LYFE CYCLE COST (LCC) Pump Division
Vibrations
Field measurements
Spectrograms
Signature analysis
Modal analysis
Running mode
analysis
Etc.
LYFE CYCLE COST (LCC) Pump Division
Noise
Noise intensity measurements
LYFE CYCLE COST (LCC) Pump Division
Pulsations
Finite element acoustic analysis
(acoustic resonance)
Field measurements
Spectrograms
Signature analysis
Etc.
LYFE CYCLE COST (LCC) Pump Division
Capabilities
Materials Vibro Hydraulic Mechanical Application
Welding Elastics Design Design Knowledge
Knowledge
Capabilities
Materials Vibro Hydraulic Mechanical Application
Welding Elastics Design Design Knowledge
Knowledge
Test Capabilities
Full load Q-H and NPSH testing up to 20 MWatt available
from high voltage net.
LYFE CYCLE COST (LCC) Pump Division
Capabilities
Materials Vibro Hydraulic Mechanical Application
Welding Elastics Design Design Knowledge
Knowledge
Test Capabilities
Suction eye recirculation testing (pitot tube).
Flow visualization testing.
Cavitations testing by paint removal.
Model testing of vertical cooling water pumps in-take
designs.
Field performance testing with accuracy equal to or close
to test bed testing
Applying torque metering and data logging technology
LYFE CYCLE COST (LCC) Pump Division
Capabilities
Materials Vibro Hydraulic Mechanical Application
Welding Elastics Design Design Knowledge
Knowledge
Capabilities
Materials Vibro Hydraulic Mechanical Application
Welding Elastics Design Design Knowledge
Knowledge
Capabilities
Materials Vibro Hydraulic Mechanical Application
Welding Elastics Design Design Knowledge
Knowledge
Capabilities
Materials Vibro Hydraulic Mechanical Application
Welding Elastics Design Design Knowledge
Knowledge
Capabilities
Materials Vibro Hydraulic Mechanical Application
Welding Elastics Design Design Knowledge
Knowledge
Flowserve has delivered over 3000 100% boiler-feed pumps for 300,
450, 600, 900 MWatt conventional power plants, and feed-water
pumps in Nuclear Power plants from 400 to 1100 MWatt.
Application knowledge is available for:
Nuclear power plants Over 52 MWatt BFP
Conventional power blocks Hydro-test over 650 bar
Supercritical power blocks High speed, 100% pump 300 MWatt
8x10x14 HDB 4 stg 8500 rpm
Co-generation power blocks
10 Mwatt
12.5 Mwatt, 6000 rpm invertors fed
E-motors direct driving BFP s
Etc.
LYFE CYCLE COST (LCC) Pump Division
Capabilities
Materials Vibro Hydraulic Mechanical Application
Welding Elastics Design Design Knowledge
Knowledge
Application Knowledge
Min. flow systems Foundation design
Low-tuned
Deaerator design
Table design
Bleed-off lines (ITO)
Transient operating conditions
Attemperation stages
Warming up systems
Transient plant conditions
Shaft sealing
50% pump run-out evaluation
Throttle bushing T-controlled
Driver related items:
Throttle bushing P controlled
Slow-roll turbine
Mechanical seals
Fluid couplings
Boiler filling
Variable speed E-motors
Intermittent operation
Etc.
Condenser foundation deformation
LYFE CYCLE COST (LCC) Pump Division
Capabilities
Materials Vibro Hydraulic Mechanical Application
Welding Elastics Design Design Knowledge
Knowledge
Application Knowledge
Brite Euram foundation
springs
Pump Division