Typical Self Climber Formwork

1 Access ladder with cage

2 Trolley

Truss 12 3 Wallform

Safety screen 11
4 Jack

Hydraulic
5 cylinder
Hydraulic power 10
unit

6 Structural mast
(I Beam)

7 Wall bracket

8 Climbing mast
(RHS)
9 Roller

3-1

Bklet_v5.indd 21 8/15/08 6:48:41 PM


Typical Self Climber Formwork

MAX
650mm

Before rollback After rollback


3-2

Bklet_v5.indd 22 8/15/08 6:48:41 PM


Typical Self Climber Formwork

Top platform 1
(For rebar works)
Max permissble load 3.0KN/m2

Working platform 2
(For formwork works)
Max permissble load 1.5KN/m2

Jack platform 3
(For climbing/jackingworks)
Max permissble load 1.5KN/m2

Recovery platform 4
(For recovering anchorage)
Max permissble load 1.5KN/m2

3-3

Bklet_v5.indd 23 8/15/08 6:48:42 PM


Selfclimber - Assembly Sequence

STAGE - 1 STAGE - 2 STAGE - 3 STAGE - 4

(1.1) Cast recoverable anchor (2.1) Hoist jack assembly (3.1) The recovery platform (4.1) Jack platform partially
in position. to lower into the wall which has already been assembled installed
brackets. pre-assembly is placed and inside channel are
below the jack assembly hoisted into position
(1.2) Erect scaffolding to (2.2) Lock the structural mast for installation. and secured.
install wall brackets. to the wall brackets by
inserting the locking (3.2) Install recovery platform. (4.2) Jack platform is
plate. decked out with steel
plate/plywood.

(4.3) Hydraulic pump, power


unit and asscessories
hoisted to Jack
platform and installed.

3-4

Bklet_v5.indd 24 8/15/08 6:48:42 PM


Selfclimber-Assembly Sequence

STAGE - 5 STAGE - 6 STAGE - 7 STAGE - 8

(5.1) Hoist assembled (6.1) Wall formwork, (7.1) The assembled top (8.1) Access ladders and
working platform and which has been platfrom is then hoisted safety screen are
installed. pre-assembled is complete with truss into installed for the top
then hoisted into position and bolted to platform.
(5.2) Install truss above position. truss connection plate.
working platform.
(6.2) Wallform is (7.2) The wallform is
temporary propped connected to the
by means of geared trolley by
temporary support means of the wallform
and props. hanger.

3-5

Bklet_v5.indd 25 8/15/08 6:48:42 PM


Selfclimber - Climbing Sequence

STAGE - 1 STAGE - 2 STAGE - 3 STAGE - 4 STAGE - 5

(1.1) Casting of wall. (2.1) Rebarworks (3.1) Jacking of climber (4.1) Jack system up to (5.1) Casting of wall.
mast assembly next level.
(2.2) Remove tiebar and (Structural mast
wing nut. and Climbing mast). (4.2) Close formwork.

(2.3) Stripping of (3.2) Remove bottom


formwork and most wall bracket.
rollback.

(2.4) Install wall bracket.

3-6

Bklet_v5.indd 26 8/15/08 6:48:43 PM


Sequence For Recoverable Anchor Self Climber

1 Recoverable anchor attached to panel


face using bolt and nuts

2 Place the panel with anchor at the correct


position and close the formwork

3 Remove panel from recoverable anchor by


unbolt & rollback wall formwork

4 After rollback, fixed wall bracket on the


recoverable anchor

5 Extract recoverable anchor from the wall using


extractor tool

3-7

Bklet_v5.indd 27 8/15/08 6:48:44 PM