Typical Self Climber Formwork: Access Ladder With Cage
Typical Self Climber Formwork: Access Ladder With Cage
2 Trolley
Truss 12 3 Wallform
Safety screen 11
4 Jack
Hydraulic
5 cylinder
Hydraulic power 10
unit
6 Structural mast
(I Beam)
7 Wall bracket
8 Climbing mast
(RHS)
9 Roller
3-1
MAX
650mm
Top platform 1
(For rebar works)
Max permissble load 3.0KN/m2
Working platform 2
(For formwork works)
Max permissble load 1.5KN/m2
Jack platform 3
(For climbing/jackingworks)
Max permissble load 1.5KN/m2
Recovery platform 4
(For recovering anchorage)
Max permissble load 1.5KN/m2
3-3
(1.1) Cast recoverable anchor (2.1) Hoist jack assembly (3.1) The recovery platform (4.1) Jack platform partially
in position. to lower into the wall which has already been assembled installed
brackets. pre-assembly is placed and inside channel are
below the jack assembly hoisted into position
(1.2) Erect scaffolding to (2.2) Lock the structural mast for installation. and secured.
install wall brackets. to the wall brackets by
inserting the locking (3.2) Install recovery platform. (4.2) Jack platform is
plate. decked out with steel
plate/plywood.
3-4
(5.1) Hoist assembled (6.1) Wall formwork, (7.1) The assembled top (8.1) Access ladders and
working platform and which has been platfrom is then hoisted safety screen are
installed. pre-assembled is complete with truss into installed for the top
then hoisted into position and bolted to platform.
(5.2) Install truss above position. truss connection plate.
working platform.
(6.2) Wallform is (7.2) The wallform is
temporary propped connected to the
by means of geared trolley by
temporary support means of the wallform
and props. hanger.
3-5
(1.1) Casting of wall. (2.1) Rebarworks (3.1) Jacking of climber (4.1) Jack system up to (5.1) Casting of wall.
mast assembly next level.
(2.2) Remove tiebar and (Structural mast
wing nut. and Climbing mast). (4.2) Close formwork.
3-6
3-7