METHOD STATEMENT

Of RECTIFICATION ROADWORK D1-1B2

TABLE OF CONTENT

METHOD STATEMENT FOR THE PREPARATION OF FORMATION


LEVEL
A. Construction Operation

1. CONSTRUCTION OF ASPHALTIC CONCRETE WEARING COURSE


A. Construction Operation
B. Quality Control and Approval

1
A. Construction Operation

1. Work shall commence on site upon approval and acceptance of the


rectification method.

2. The defect area shall be determined by the R.E. before proceeding with
the rectification of work

3. The top of wearing course (defect) with at least 40mm shall be cut off
and trimmed to the formation level, which means the top surface of the
subgrade.

4. The trimming or cut of the material shall be carried out by a roller


diamond cutter or other approved mechanical cutter in one process.

5. The haulage of material shall be carried out by a small truck.

6. The removed material shall be transported by a tripper truck to an


approved area.

7. The trimmed surfaces shall be made good by shaping and compaction as


soon as practicable after being corrected and the area to be rectify by
median filling.

8. Compaction shall be carried out using the approved type of compacters.

9. The surface of the newly surface shall be finished to the grade and line
as required by the drawing.

10. On completion of compaction, levels to be checked for compliance with


the specified requirements.

2
C. Construction Plants

PLANTS / MACHINERY NO

10 tonne roller compactor 1


Roller diamond cutter 1
Tipper Trucks 1

D. Responsibility

 Project Manager
 Construction Manager
 P.Engineer
 Supervisor

1. At the end of paving operation the transverse joint shall be feathered


down. Lap joint shall be provided for the next paving operation.

2. Compaction shall be carried out using the specified type of compactor


and the rolling pattern to established on the day of laying.

3. Rolling shall commence from the lower to the higher side of the
carriageway the minimum rolling temperature shall be 100 °C.

4. The surface of the asphalt shall finished to grade and line as stipulated in
the drawing. Joint survey to check the compliance.

2. The surface to receive the asphaltic concrete wearing course shall be


freed of all dirt, loose materials and standing water by sweeping.

3. Tack coat of approved bitumen emulsion shall be applied as per


specification on the prepared surface prior to laying of the asphaltic
concrete wearing course.

3
4. The asphaltic concrete wearing course shall be plant-mixed (Paving
Plant & Processes Continuous Drum Mixer) with bitumen content as
established in the Job Standard Mixture.

5. The approved asphaltic concrete wearing course shall be delivered to


site by tipper trucks. To prevent the loss of heat, the mixture shall be
covered by tarpaulin.

6. The asphaltic concrete wearing shall be laid by ABG Titan 311 or


equivalent in single layer.

7. If the laid surface is open-textured, backcasting shall be carried out and


the bigger size aggregate removed before rolling.

8. At the end of the paving operation, the transverse joint shall be feathered
down. Vertical joint shall be provided for the next operation of paving.

9. Compaction shall be carried out using the specified / equivalent type of


compactors and the rolling pattern shall be as per established during the
trial lay.

10. Shall always commence from the lower to the higher side of the
carriageway. The minimum rolling temperature shall be 120° C.

11. The surface of the asphaltic concrete wearing course shall be finished to
the grade and line as required by the drawings.

12. On completion of laying and compaction joint survey shall be carried


out to check for compliance with he specified requirements.

(a) Compaction shall be carried out using rollers.


(i) Tandem Roller
(ii) Pneumatic Tyre Roller

(b) The rolling pattern shall be as follows :


Breakdown Rolling : 2 passes with static mode
Intermedite : 2 passes with vibratory
Final Rolling : 6 passes with tyre rollers

4
1. The tack coat shall be applied as per required amount as stated in
your specification.

2. The thickness of regulating layer will be controlled by -----control


set.