This Minute of Meeting Is For Follow Up Only and Does Not Supersede Any Contractual Obligations
This Minute of Meeting Is For Follow Up Only and Does Not Supersede Any Contractual Obligations
MOM
Progress Summary (as of May 3, 2019) Estimated by CRSE
THIS WEEK CUMULATIVE
02 Procurement
3.0 Quality
Concrete and Asphalt Plant Status
Plant Approval Remarks
Al Yamama Approved
Al Awdah Concrete Approved
Saudi Ready Mix Concrete Awaiting Re-approval Awaiting results of uniformity test
3.20 QMD advised to scan all approved WIR to be submitted on end of April 2019 Yes CRSE 28-Mar-19 30-Apr-19 On going
CRSE QC inspector are instructed not to leave the site after asphalting, recheck the area for
3.30
any defects and make sure that the area is properly barricated. Yes CRSE 11-Apr-19 Closed
SAQMD follow up the ISO 9001: 2015 certification of CRSE QA/QC Manager. Fail to provide June 10, 2019
3.40
after 3 months of his conditionally approval, QMD will revoke the approval. Yes CRSE 11-Apr-19 Tentative Awaiting Certificate
CRSE planning of recovery plan (night shift or holidays) should include the QC inspector at
3.50
site Yes CRSE 11-Apr-19
CRSE should require the Fugro Suhaimi to release all the test results on time to avoid
3.60
delays in submission to Aramco Yes CRSE 11-Apr-19 30-Jun-19
3.70 CRSE to provide a schedule for time in-out during Ramadan Yes CRSE 18-Apr-19 Closed
3.80 CRSE will takecare regarding the extraction equipment for laboratory Yes CRSE 18-Apr-19 25-May-19
3.90 CRSE should not submit WIR if ITP not approved Yes CRSE 9-May-19
CRSE should seek clearance from mechanical, electrical before starting road base
4.00
preparation (before compaction). Any damage happen must report immediately to SAPMT. Yes CRSE 9-May-19
4.10 CRSE need to provide additional manpower within one week or two weeks maximum Yes CRSE 9-May-19
Page 1 of 2
Contract No: 6600041801 WQM #: WQM/0034
Prepared By Contractor:
Name: Cecil Alfaro (CRSE QAQC Manager ) Signature: Date:16-May-19
Name: Mr. Mumtaz Nazir - Lead Project Engineer - SAPMT Signature: Date:16-May-19
These Minutes do Not Constitute a Waiver of Any Right or Duty assigned to The Parties Under The Contract Documents
Distribution:
✘
✘
CRS
QMSAP
ED MT
Attachement
Sr No Description of Attachment
1 Two week look ahead
2 INCR Log
3 LBE Log
4 Project Quality Audit Schedule.
5 WIR Status
Page 2 of 2