Professional Documents
Culture Documents
Session 1: Introduction To Production Planning and The Last Planner System
Session 1: Introduction To Production Planning and The Last Planner System
Organizational Project
Management
Project t
Last Activity y
Planner
System Breakdown
Production
the activity
Planning
into smaller
tasks .
Project Management vs. Production Planning
Contractual Requirements
It should be noted that the contract may dictate a certain scheduling process and
system that may differ from the Last Planner System.
Milestones and other schedule points may not be able to be moved as they would
in a full LPS process due to contractual requirements.
However, it is possible for the systems to complement each other, and
contractual requirements should not be used as an excuse to avoid implementing
LPS.
Within the weekly work planning process, there are no ifs, buts or maybes about
the commitments. This is the point where each foreman is asked identify what
work his crew(s) will complete in the next week. A foreman should not commit - "I
will" - until she/he is confident the resources are available to complete the
assignment.
Proactive planning is about making things happen. It focuses on day to- day
functions such that project-level milestones are completed.
An important component is monitoring the percent plan complete so that
changes can be made for work yet to come that will increase the reliability of the
schedule.