Professional Documents
Culture Documents
2010 Analysts Visit Operations Combined Presentation FINAL - 0 PDF
2010 Analysts Visit Operations Combined Presentation FINAL - 0 PDF
2010 Analysts Visit Operations Combined Presentation FINAL - 0 PDF
PROMINENT HILL
ANALYST TOUR
10/11 MAY 2010
IMPORTANT NOTICE
This presentation has been prepared by OZ Minerals Limited (“OZ Minerals”) and consists of written materials/slides for a presentation concerning OZ Minerals. By
reviewing/attending this presentation, you agree to be bound by the following conditions.
No representation or warranty, express or implied, is made as to the fairness, accuracy, or completeness of the information contained in the presentation, or of the views, opinions
and conclusions contained in this material. To the maximum extent permitted by law, OZ Minerals and its related bodies corporate and affiliates, and its respective directors,
officers, employees, agents and advisers disclaim any liability (including, without limitation any liability arising from fault or negligence) for any loss or damage arising from any use
of this material or its contents, including any error or omission therefrom, or otherwise arising in connection with it.
Some statements in this presentation are forward-looking statements within the meaning of the US securities laws. Such statements include, but are not limited to, statements with
regard to capacity, future production and grades, projections for sales growth, estimated revenues and reserves, targets for cost savings, the construction cost of new projects,
projected capital expenditures, the timing of new projects, future cash flow and debt levels, the outlook for minerals and metals prices, the outlook for economic recovery and
trends in the trading environment and may be (but are not necessarily) identified by the use of phrases such as “will”, “expect”, “anticipate”, “believe” and “envisage”. By their
nature, forward-looking statements involve risk and uncertainty because they relate to events and depend on circumstances that will occur in the future and may be outside OZ
Mineral’s control. Actual results and developments may differ materially from those expressed or implied in such statements because of a number of factors, including levels of
demand and market prices, the ability to produce and transport products profitably, the impact of foreign currency exchange rates on market prices and operating costs,
operational problems, political uncertainty and economic conditions in relevant areas of the world, the actions of competitors, activities by governmental authorities such as
changes in taxation or regulation.
Given these risks and uncertainties, undue reliance should not be placed on forward-looking statements which speak only as at the date of the presentation. Subject to any
continuing obligations under applicable law or any relevant stock exchange listing rules, OZ Minerals does not undertake any obligation to publicly release any updates or revisions
to any forward looking statements contained in this presentation, whether as a result of any change in OZ Minerals expectations in relation to them, or any change in events,
conditions or circumstances on which any such statement is based.
Certain statistical and other information included in this presentation is sourced from publicly available third party sources and has not been independently verified.
OZ MINERALS • PAGE 2
SESSION 1:
PROJECT OVERVIEW – MICK WILKES
• Project snapshot
• Health, Safety
• Environment
• Community
• People
OZ MINERALS • PAGE 3
PROMINENT HILL: PROJECT SNAPSHOT
Reserves: 75.7Mt @ 1.19% Cu, 0.59g/t Au (0.9Mt Cu, 1.4Moz Au)
Copper-gold 189.7Mt @ 1.32% Cu, 0.5g/t Au (2.5Mt Cu, 2.9 Moz Au)
resources:
Gold only 78.8Mt @ 0.06% Cu, 1.4g/t Au (0.05Mt Cu, 3.4Moz Au)
resources:
Mine: 55Mtpa open pit, mining contractor Thiess
Ave strip 5-6:1 (waste to ore, tonnes basis, excluding pre-strip)
ratio:
Plant: 8.8Mtpa crush, grind, flotation.
Product: High grade (+50% Cu), high quality, copper concentrate.
Remaining 8 years for open pit.
mine life:
Production 96,310t contained copper, 75,535oz gold.
2009:
Estimated 100,000t to 110,000t contained copper,
average p/a
110,000oz to 120,000oz gold
production
2010-2012
Estimated C1 US$0.80 – US$0.90/lb
costs 2010:
Workforce: 725 (including contractors)
OZ MINERALS • PAGE 4
PROMINENT HILL
VILLAGE
WESTERN NORTHERN WASTE
COPPER DEPOSIT DUMP
ROM PAD
PROCESSING
PLANT PIT
SOUTHERN WASTE
DUMP
TAILINGS
DAM
OZ MINERALS • PAGE 5
PROMINENT HILL VILLAGE
OZ MINERALS • PAGE 6
SAFETY
OZ Minerals Lost Time and Total Recordable Injury Frequency Rate 12 Month Moving Average *
18
16
14
12
Frequency Rate
10
0
Apr-09 May-09 Jun-09 Jul-09 Aug-09 Sep-09 Oct-09 Nov-09 Dec-09 Jan-10 Feb-10 Mar-10
OZ MINERALS • PAGE 7
SAFETY AND HEALTH
• Zero Harm by Choice
• Plant and systems design geared for safety
• Strong reporting culture
• New focus on cognitive based safety (ZIP – Zero Incident Process -
Program being assessed)
• Integrated Safety, Health, Environment, Community, Management
Systems
− Aligned to AS 4801
− 60 Integrated Management Standards
• Upgrading RIMS (Risk Information Management System) to
accommodate contractors information
OZ MINERALS • PAGE 8
PROMINENT HILL: ENVIRONMENT
OZ MINERALS • PAGE 9
PROMINENT HILL: COMMUNITY – MUTUAL BENEFITS
OZ MINERALS • PAGE 10
PROMINENT HILL:
EMPLOYMENT – A DIVERSE WORKFORCE
OZ MINERALS EMPLOYEES: 210
CONTRACTORS: 515
TOTAL EMPLOYEES: 725 10% Female employees
OZ MINERALS • PAGE 11
PROMINENT HILL: SKILLS DEVELOPMENT
• 5 Pre Employment Programs (PEP) completed
− Encouraging local recruitment and
indigenous recruitment
− 5th program tailored for Antakarinja
− 6th program commenced in APY lands
− 42 graduates
− Guaranteed employment
• Local preferential employment policy
• Dedicated skills training team in process plant
• Skills mapping and training programs
developed for processing, mining and geology
OZ MINERALS • PAGE 12
SESSION 2:
MINE GEOLOGY – JIM HODGKISON, MARCEL VAN ECK
OZ MINERALS • PAGE 13
PROMINENT HILL: INTERPRETED GEOLOGY AT THE
UNCONFORMITY
Western
Copper Area
(slide 78)
?
0 500
metres
OZ MINERALS • PAGE 14
PIT GEOLOGY: STAGE 1
100m
OZ MINERALS • PAGE 15
LONGSECTION: ORE SPECIES
Basement
Stage 2 9908RL 2012
Stage 3 9872RL 2014
Chalcocite Chalcocite
Chalcopyrite Gold
Bornite Bornite
Only
Section Looking North
OZ MINERALS • PAGE 16
GRADE DOMAINS: RESOURCE MODEL
Copper Ore
Gold Ore
Au in Dolomite
Western Cu Western Au
Eastern Cu/Au
OZ MINERALS • PAGE 17
GRADE DOMAINS: COPPER – GRADE CONTROL
Copper Ore
Gold Ore
Footwall Volcanics
BN
CC
CC BN
Gold
CC
OZ MINERALS • PAGE 19
PROMINENT HILL: ORE BLEND – LIFE OF MINE
100% LOM
Gold 20%
80%
Chalcopyrite 15%
Blend (% )
20%
0%
2010 2011 2012 2013 2014 2015 2016 2017
Year
OZ MINERALS • PAGE 20
PROMINENT HILL: ORE RECONCILIATION – LIFE TO
DATE (MARCH 2010)
Cu Resource Au Resource
250,000 250,000
Mill+Stocks
209,032
Resource Mill+Stocks
186,638 190,909
200,000 200,000
Resource
158,351
150,000 150,000
Cu (Tonnes)
Au (Oz)
100,000 100,000
50,000 50,000
0 0
OZ MINERALS • PAGE 21
MINERAL RESOURCE: 30 JUNE 2009
Prominent Hill Mineral Resources
Copper Gold Silver Contained Metal
Tonnes Grade Grade Grade Copper Gold Silver
(Mt) (% Cu) (g/t Au) (g/t Ag) ('000t) (Moz) (Moz)
Prominent Hill Copper-gold
Measured 36.6 1.65 0.5 3.6 604 0.6 4.2
Indicated 70.2 1.30 0.5 3.2 910 1.2 7.1
Inferred 83.0 1.18 0.4 2.9 982 1.1 7.6
Total 189.7 1.32 0.5 3.1 2,496 2.9 19.0
Prominent Hill Gold
Measured 8.4 0.10 1.1 1.8 8 0.3 0.5
Indicated 19.0 0.06 1.3 1.1 11 0.8 0.7
Inferred 51.4 0.06 1.4 0.7 31 2.4 1.2
Total 78.8 0.06 1.4 0.9 51 3.4 2.4
Total Resources 2,547 6.3 21.4
Significant figures do not imply precision. Figures are rounded according to JORC guidelines.
Competent person:
Jim Hodgkison: (Member of AusIMM, employee of OZ Minerals)
Cut-off Criteria:
Copper Gold
Open Pit/Near Surface (<480m depth) > 0.3% Cu Open Pit/Near Surface (<480m depth) > 0.5ppm Au and < 0.3% Cu
Underground > 0.8% Cu Underground >1ppm Au and < 0.8% Cu
OZ MINERALS • PAGE 22
MINERAL RESOURCE: 30 JUNE 2009
Copper Gold Contained Metal Change in Contained Metal
Tonnes Grade Grade Copper Gold Copper Equiv * Copper Gold Copper Equiv
Year (Mt) (% Cu) (g/t Au) (Mt) (Moz) (Mt) (Mt) (Moz) (Mt)
2005 97 1.5 0.50 1.46 1.56 1.72
2006 125 1.2 0.64 1.50 2.58 1.93 0.04 1.02 0.21
2007 146 1.3 0.79 1.90 3.72 2.52 0.40 1.14 0.59
2008 283 0.9 0.81 2.55 7.39 3.78 0.65 3.67 1.26
2009 269 1.0 0.76 2.55 6.30 3.59 0.00 -1.09 -0.18
Total Change 1.09 4.74 1.88
1.5
1.0
0.5
0.0
* Copper equivalent tonnes based on $US 1,100/oz Au and $US 3.00/lb Cu. 2005 2006 2007 2008 2009
OZ MINERALS • PAGE 23
MINING LEASE AREA
2km
Eastern Copper/Gold
Western Gold
Western Copper
WA EA
WG
WCZ
ECG
OZ MINERALS • PAGE 24
GOLD AND COPPER POTENTIAL: STAGE 2 – 10076 RL
Plan View
D501W1
D512W2: visible chalcocite
Au in Dolomite Au in Stage 2 outside resource
D501W1:
Au in Stage 2 outside resource
27m @ 0.08% Cu and
1.79g/t Au from 802m dh.
53m @1.74% Cu and
1.03g/t Au from 870m dh.
OZ MINERALS • PAGE 25
RESOURCE DEVELOPMENT DRILLING – WESTERN
COPPER DEPOSIT
• Views of diamond drilling on Western Copper Deposit showing drill density
• Copper shells - >1% Cu
• Drilling density (25 x 25m and 50 x 50m) to increase Resource confidence
North View
Plan View
OZ MINERALS • PAGE 26
RESOURCE DEVELOPMENT DRILLING 2009-2010
SUMMARY
Initial Diamond
Drill-out completed
Western Area 39,500m Eastern Area Extension
Extension Drilling Diamond Drilling
340m
? ?
?
? ?
Extension
Diamond
Drilling
7,200m
Completed
D501W1: 27m @ 0.08% Cu and 1.79g/t Au from
In progress Q2 2010 802m dh
Proposed for 2010 53m @ 1.74% Cu and 1.03g/t Au from 870m dh
OZ Minerals limited: Within this presentation references to exploration results have been provided by Mr Marcel Van Eck who is a full-time employee of OZ Minerals, Mr. Van Eck is a Member of the Australian Institute of Geoscientists and has sufficient experience relevant to the style of
mineralisation and type of deposit under consideration and to the activities undertaken to qualify as a competent person as defined by the JORC code (2004). Mr Van Eck has consented to the inclusion of the material in the form and context in which it appears.
OZ MINERALS • PAGE 27
WESTERN COPPER DEPOSIT – MINERALISATION AND
SIMPLIFIED GEOLOGY
W E
Sandstone, siltstone, volcanics
• View looking North
Fault
F • Showing copper shapes
(>1% Cu) used in May
F 2010 resource estimate
• Most copper occurs
within breccias (see
Breccias next slide)
Felsic Intrusive
rock
Copper shapes
Cu occurs in breccias
F
Section 4200E
Cu in graphitic matrix
No breccia
Conglomerate
OZ MINERALS • PAGE 28
BRECCIAS AT PROMINENT HILL AND WESTERN
COPPER
OZ MINERALS • PAGE 29
WESTERN COPPER DEPOSIT – MINERALISATION
Section 4,200E
S N • An example of the copper
shapes (Cu > 1% Cu) used in
the May 2010 resource
estimate
• Copper intervals and assays
49m @ 3.6% Cu • shown (colour-coded for Cu
grade)
• Lack of internal dilution
Plan View S
OZ MINERALS • PAGE 30
NEAR MINE DRILLING PROGRAMS – 2010+
EL4025
Peculiar Knob North
Kennedy Dam
Calisto
White Hill North
20km
Zeus
Bluebird Taurus
White Hill
Halifax Hill
Umbriel
Prominent Scylla
EL4283 Neptune
Hill Triton
EL3795
Nicholl Well
Danae Hill Mt Hawker
Pluto
WA
WG EA
WCZ
ECG
EL4390
Under-pit Under-pit
OZ MINERALS • PAGE 31
RESOURCE DRILLING SUMMARY
Western Copper Deposit:
• Diamond drilling to Indicated Resource status, 50 x 50m and 25 by 25m.
• Drilling program complete (up to 4 rigs)
• Coherent copper accumulation associated mainly with breccias
• Good Cu grades, locally high (>3g/t) Au
• Only minor internal dilution evident in higher grade portions
• Visually competent ground
• N-S structures apparent, addressed by changed drill orientations
• Some upside is a reality
• Resource estimate completed – final checks in progress
Under-pit Drilling:
• Major (underground) prospectivity under pit – 2 rigs mainly
• Cu intersections already made – assays awaited – support for underground mining of Main UG
• Drilling to continue in 2010+
OZ MINERALS • PAGE 32
SESSION 3: MINING – TREVOR MCILWAINE
OZ MINERALS • PAGE 33
PROMINENT HILL: MINING FLEET MAY 2010 –
UPDATE MANNING
Thiess contractor – scheduled rates
• 30% fixed cost (fleet and admin)
• 70% variable cost, based on BCM’s
− 3 x Liebherr 996s
− 23 x CAT 793s (240t)
− 1 x CAT 994
− 3 x CAT 785s (140t)
− 2 x Cubex
− 2 x Drilltek SKSS
− 6 x dozers
− 2 x graders
− 2 x CAT777 watercarts
OZ MINERALS • PAGE 34
PROMINENT HILL: FOUR MINING STAGES
Stage 3
Stage 4
Stage 2
Hanging Wall fault
Stage 1
zone CCBN Cu
Mineralisation
Prominent Hill
Shear Zone CCBN
Cu Mineralisation
Other Cu
Mineralisation
Gold Only
OZ MINERALS • PAGE 35
PROMINENT HILL:
LOM – 66% OF OVERBURDEN REMOVED
Average
2006 2007 2008 2009 2010 2011 2012 Total
2013 to 2016
Ore (Mt) 5 9 7 7 7 9 76
Overburden (Mt) 10 67 52 18 32 39 12 0 230
Fresh Waste (Mt) 13 20 28 36 60 33 286
Total (Mt) 10 67 70 47 67 82 79 42 597
NB Assumes 4th mining fleet from Q3 2010 for 24 months
Basement
Stage 2 9908RL 2012
Stage 3 9872RL 2014
OZ MINERALS • PAGE 36
PROMINENT HILL:
ORE SUPPLY - 3 MONTHS COPPER ORE ON ROM PAD
Dispatch System
• Low Precision GPS / no dispatcher – haul truck, excavators,
service fleets
• Increasing direct crusher feed from the pit
• High Precision GPS – H1 2010 on excavators and dozers fleets
• Dispatchers – H2 2010
• Blending
• Excavator/Haul Truck Matching
OZ MINERALS • PAGE 37
PROMINENT HILL: GEOTECHNICAL
OZ MINERALS • PAGE 39
OVERVIEW OF OPERATIONS: PROCESS FLOW SHEET
CRUSHING AND STOCKPILE GRINDING
Gyratory Crusher
From Mine
Screen
Crushed Ore
SAG Mill
FLOTATION
Rougher Flotation
Primary
Cyclones
Regrind
Cyclones
Ball Mill
Cleaner
Flotation 2
Tailings
Thickening
Cleaner
Flotation 3
OZ MINERALS • PAGE 40
OVERVIEW OF OPERATIONS: GRINDING
Duty
• Design rate = 8Mtpa
• Current rate = 8.8Mtpa
• Size reduction to 80% passing 106µm
Key Statistics
• SAG Mill – 10.4m x 4.7m. 12MW Installed
• Ball Mill – 7.3m x 10.4m. 12MW Installed
Recent Improvements
• Dec ’09. Commissioning of an expert control
system to balance load between both mills.
System has allowed throughput increase
without recovery loss, grind size is minimised
and SAG mill liner wear has decreased.
• Mar ’10. Sustained periods at 1150tph. Water
recycle bottleneck identified.
OZ MINERALS • PAGE 41
OVERVIEW OF OPERATIONS: FLOTATION
Duty
• Design Cu Rec = 88% Chalcocite & 80% Bornite
• Current Cu Rec = 89% YTD on a 45:55 Blend*
• Design Cu Con = 54% Chalcocite & 34% Bornite
• Current Cu Con = 51% YTD on a 45:55 Blend
*Excludes Gold Ore
Key Statistics
• 6 x 150m3 Rougher Cells
• 14 x 50 & 20m3 Cleaner Cells
• Ethyl Xanthate collector
• PPG-Alcohol Blend frother
Recent Improvements
• Nov ’09. Collector and frother changes have
improved froth stability across all ore types.
Recovery has increased and concentrate
quality has improved.
• Dec ’09. Introduction of 10-15% Gold Ore into blend.
OZ MINERALS • PAGE 42
OVERVIEW OF OPERATIONS: ISAMILL AND JAMESON CELL
Duty
• Regrind rougher con to 80% passing 20µm
• Jameson produces 30% of final concentrate
• Penalty element rejection to below required levels.
Key Statistics
• M10,000 Isamill (3MW installed power)
• Inert ceramic grinding media reduces iron
contamination, thereby increasing recovery.
• Jameson froth washing reduces entrained penalty
elements.
Recent Improvements
• Nov ’09. Reagent changes have allowed deeper
froth and higher wash water rate on Jameson
resulting in lower penalty element content
OZ MINERALS • PAGE 43
PERFORMANCE TO DATE: KEY EVENTS
Jun ‘09 Tonnage ramp up complete. Mill can consistently achieve 1100tph.
May – Aug ‘09 Recovery levels off in low 80’s. Difficulty in treating Bornite ore type.
Sep – Dec ‘09 Engineered Chalcocite stockpile strategy introduced to reduce feed variability.
Recovery increases to high 80’s.
Nov – Dec ‘09 Weaker collector and stronger frother introduced to improve froth stability. This
allows Bornite to be re-introduced to feed.
Dec ‘09 Gold ore introduced to feed blend. Initially as 10%, now as 15% of feed.
Dec ‘09 Mill expert system commissioned improving grinding circuit stability and reducing
grind size
OZ MINERALS • PAGE 44
Milling Rate (tph) Cu (%), Au (g/t)
0.0
0.5
1.0
1.5
2.0
2.5
0
200
400
600
800
1000
1200
1400
Feb-09
Feb-09
Mar-09
Mar-09
Apr-09
Apr-09
May-09
May-09
Jun-09
OZ MINERALS • PAGE 45
Jun-09
Jul-09
Jul-09
Copper
Aug-09 Aug-09
Gold
Milling Rate
Sep-09 Sep-09
Mill Head Grade
Oct-09 Oct-09
Nov-09 Nov-09
Dec-09 Dec-09
Jan-10 Jan-10
Feb-10 Feb-10
Mar-10 Mar-10
PERFORMANCE TO DATE: MILL
0
100
200
300
400
500
600
700
800
900
Feb-09 Feb-09
Mar-09 Mar-09
Apr-09 Apr-09
May-09 May-09
Jun-09 Jun-09
Jul-09 Jul-09
Aug-09 Aug-09
Sep-09 Sep-09
Tonnes Milled
Mill Availability
Oct-09 Oct-09
Nov-09 Nov-09
Dec-09 Dec-09
Jan-10 Jan-10
Feb-10 Feb-10
Mar-10 Mar-10
Copper in Concentrate (kt) Recovery
0
2
4
6
8
10
12
14
16
0
10
20
30
40
50
60
70
80
90
100
Feb-09
Feb-09
Mar-09
Mar-09
Apr-09
Apr-09
May-09
May-09
Jun-09
Jun-09
OZ MINERALS • PAGE 46
Jul-09 Jul-09
Copper
Aug-09 Aug-09
Recovery
Sep-09
Gold
Sep-09
Copper in Concentrate
Oct-09 Oct-09
Nov-09 Nov-09
Dec-09 Dec-09
Jan-10 Jan-10
Feb-10 Feb-10
Mar-10 Mar-10
0
2
4
6
8
10
12
14
16
18
20
Feb-09 Feb-09
PERFORMANCE TO DATE: FLOTATION
Mar-09 Mar-09
Apr-09 Apr-09
May-09 May-09
Jun-09 Jun-09
Jul-09 Jul-09
Aug-09 Aug-09
Sep-09 Sep-09
Concentrate Grade
Gold in Concentrate
Oct-09 Oct-09
Nov-09 Nov-09
Dec-09 Dec-09
Jan-10 Jan-10
Feb-10 Feb-10
Mar-10 Mar-10
KPI’S: Q1 2010 VS FORECAST
OZ MINERALS • PAGE 47
KPI’S: Q1 2010 VS FORECAST
OZ MINERALS • PAGE 48
PRIORITY PROJECTS: RECOVERY
• Routine mineralogy and diagnostics
suggest that an additional 2% copper
recovery and 4% gold recovery may be
available from the rougher tails.
OZ MINERALS • PAGE 49
PRIORITY PROJECTS: THROUGHPUT
• Plant throughput limited by the ability to recycle process water from the tailings thickener back to
the grinding circuit. A 1% increase in thickener density will allow a further 50tph to be processed.
2. Improve the distribution and mixing of reagent and slurry in the thickener feed.
OZ MINERALS • PAGE 50
MILL RE-LINE SHUTDOWNS
SAG mill every 13 weeks, Ball Mill every 12 months
Management
• Full Time Shutdown Planner
• Logistics coordinator
• OZ Minerals personnel supervise contractors by plant area
• Quality performance review conducted after each shutdown to drive more improvement of
the next
OZ MINERALS • PAGE 51
PLANT MAINTENANCE STRATEGY 2010
Improve plant availability to achieve 93%
– Goal is to run between SAG reline shutdowns without a
planned stoppage.
– The two major focus areas:
• Mill motor brush wear
• Isamill shell liner wear
OZ MINERALS • PAGE 52
MAJOR RELIABILITY IMPROVEMENTS
SAG Discharge Screen Spring Failure
– New rubber encapsulated springs installed with no failures
to date
Trash Screen Panel Wear
– New Urethane coated panels now in use with life in excess
of 12 weeks
SAG Discharge Screen Discharge Chute Wear
– Steps were installed inside the chute face to slow velocity of
recycle product and reduce chute wear.
Ball Mill Chopper Drive Faults
– No over voltage trips on start up have been observed since
making the modifications supplied by the OEM last
December
OZ MINERALS • PAGE 53
CURRENT RELIABILITY FOCUS
IsaMill
Extend Wet End Component Life – Target of 13 weeks (align
with SAG Reline Shutdowns)
• Shell Liner.
− Life of 26 weeks but requires a turn every 8 weeks
• Discs 1,2,3,4.
− 13 weeks
• Disc 5
− 24 weeks
80
60
40
20
0
01/07/09 01/08/09 01/09/09 01/10/09 01/11/09 01/12/09 01/01/10 01/02/10 01/03/10
OZ MINERALS • PAGE 54
CURRENT RELIABILITY FOCUS
Mill motor carbon brush wear
• Two different carbon brush grades have been
successfully trialled doubling the life of motor
brushes. More trials planned.
OZ MINERALS • PAGE 55
SESSION 5:
COSTS – JASON DE ROSS
OZ MINERALS • PAGE 56
OVERVIEW – VERY COMPETITIVE COST STRUCTURE
A$ million C2C A$/t milled C1 USc/lb
Prominent Hill Actual Actual Actual
Production Costs 2009Q4 2010Q1 2009Q4 2010Q1 2009Q4 2010Q1
Mining A$/t Mined 3.2 3.3
Mining 44.3 46.2 19.4 20.9 51.8 61.1
Deferred Mining 12.9 -13.5 5.6 -6.1 15.0 -17.9
Ore Inventory Adjustment -15.5 12.7 -6.8 5.7 -18.0 16.7
Total Mining 41.7 45.3 18.3 20.5 48.8 59.9
Processing 21.4 20.6 9.4 9.3 25.0 27.3
Site G&A 9.8 11.7 4.3 5.3 11.4 15.5
Cost to Concentrate 73.0 77.6 31.9 35.1 85.2 102.7
Notional TC and Transport 25.8 24.1
Notional Net By-Product Credits -47.5 -69.4
Total C1 Costs (Brook Hunt Methodology) 63.5 57.4
Total Mined (mT) 13.9 14.0
Ore Milled (mT) 2.3 2.2
AUD:USD (Average) 0.91 0.90
Cu Payable Metal (Mlbs) 77.8 68.4
• Increase in cost to concentrate due to higher mining costs offset by higher by-product credits due to higher gold
grades (more gold only ore in the blend) and recoveries.
• Full year guidance C1 range US80-90c/lb is higher than first quarter C1 at US57.4c/lb due to declining scheduled
milled grades
OZ MINERALS • PAGE 57
PRICE VOLUME EFFICIENCY FOR COPPER
60.00
50.00
40.00
Higher gold head grade Lower copper head
and recoveries grade
30.00 `
OZ MINERALS • PAGE 58
COST COMPOSITION – MINING
Other Comments –
• Unit costs up to 25%
higher for fresh rock than
overburden due to
increased blasting
requirements and longer
haulage distances.
OZ MINERALS • PAGE 59
COST COMPOSITION – PROCESSING & MAINTENANCE
Other Comments –
• Capacity and recoveries are
still being improved (above
nameplate capacity)
OZ MINERALS • PAGE 60
COST COMPOSITION – SITE G&A
Other Comments –
• General services includes
maintenance on roads,
borefields and facilities
and site support village
and travel costs
OZ MINERALS • PAGE 61
SESSION 6:
MARKETING
OZ MINERALS • PAGE 62
OZ MINERALS: PRODUCT SALES & MARKET
OVERVIEW
OZ MINERALS • PAGE 63
SALE OF COPPER CONCENTRATES
To Port of Darwin
• Sales Plans are set for 2-5 yr periods
• Sales terms negotiated annually
− frame, annual & spot
• Timing of sales adjusted to match production
• Logistics
− All transport in ‘kibbles’ approx 12t each
− 5-6 trains/wk to Darwin (600-1,000t each)
− 48 hrs to Darwin
− 1 truck/day (75t) to Olympic Dam
− 2-3 ships/mth plus domestic sales
− Trial shipping via Adelaide; improve
flexibility, reduce reliance on single
logistics chain
− 2 weeks to major Asian ports
Port Adelaide
OZ MINERALS • PAGE 64
CONCENTRATES SALES PLANNING
• Initial strategy: establish export mkts first Prominent Hill sales commitment [% of forecast production]
− Asia focus (China/India)
2009
• Domestic smelters (1 or 2)
ommitted balance total committed balance total
Europe
Domestic
India
Domestic Traders
28%
14%
Europe
12%
OZ MINERALS • PAGE 65
PROMINENT HILL CONCENTRATES:
COMPETITIVE ADVANTAGES
Highest grade Cu Exported copper concentrate grades – Chile
Monthly average, copper concentrate grade, % Cu
– Cu levels globally declining
– Lower freight/handling costs per unit/metal
– Less slag per unit of metal
OZ MINERALS • PAGE 66
CONCENTRATES – A TYPICAL SALES TRANSACTION
Typical:
• Delivered (CIF, CIP, FIS)
• 90% of global trade is LME basis
− Concentrates: LME minus TC/RC (Treatment Charge & Refining Charge)
» Benchmark 2010 $46.50/4.65c/lb
OZ MINERALS • PAGE 67
CUSTOM SMELTING INDUSTRY – OUR MARKET
Year-on-year Copper Demand Growth by Region
20,000
2,000 2,000
1,000 1,000
55%
10,000
500 500
43%
'000 tonnes
0 0
2009e 2010f 2011f 2012f 2013f 2014f 2015f
5,000
-500 -500
19%
-1,000 -1,000
-
Mine production Refining Refined consumption
-1,500 -1,500
OZ MINERALS • PAGE 68
SESSION 7:
BUSINESS PLAN
• Underground Development
• LOM business plan
OZ MINERALS • PAGE 69
Underground Development Strategy
• Continue to increase resources - Prominent Hill orebody open at depth and along strike
OZ MINERALS • PAGE 70
UNDERGROUND DEVELOPMENT CONCEPT
OZ MINERALS • PAGE 71
LIFE OF MINE BUSINESS PLAN
OZ MINERALS • PAGE 72
SESSION 8:
EXPLORATION – MARCEL VAN ECK
OZ MINERALS • PAGE 73
2010+ EXPLORATION PROGRAM - AIM
Target is 100Mt @1% Cu. Success through exploration at PH will be our No.1 Value adder.
OZ MINERALS • PAGE 74
TENEMENT LOCATIONS
480,000 mE
500,000 mE
520,000 mE
540,000 mE
560,000 mE
580,000 mE
600,000 mE
6,820,000 m N
20km
OZ 4100 sq km
EL4132
EL4429
6,780,000 m N
magnetics
EL4025
6,760,000 m N
EL4429
20km
6,740,000 m N
EL4429
6,720,000 m N
EL4283 M L6228
6,700,000 m N
EL4390
%
0 100 200 EL3795
K ilo metres
6,680,000 m N
magnetics
OZ MINERALS • PAGE 75
EXPLORATION OVERVIEW 2009-2010
480,000 mE
500,000 mE
520,000 mE
540,000 mE
560,000 mE
580,000 mE
600,000 mE
2009 PROGRAM 6,820,000 m N
• 20 prospects 20km
• 14 tested (5 months)
6,800,000 m N
• 13,120m drilled
EL4132
EL4429
6,780,000 m N
2010 PROGRAM
months)
6,760,000 m N
EL4429
• 8,000m drilled
6,740,000 m N
EL4429
6,720,000 m N
IP surveys
6,700,000 m N
EL4390
Diamond Drilling
EL3795
magnetics
OZ MINERALS • PAGE 76
2009-2010 EXPLORATION PROGRESS - STUDIES
• Geophysics
• Structure
Geophysics EM
• Stratigraphy
• Dating
• Fluids MSc
• Alteration
• BSc Honours x2
Geophysics IP
• Geochemistry
BSc
Geophysics IP
Stratigraphy
BSc
Dating
Structure Magnetics
Fluids MSc Basement Map
OZ MINERALS • PAGE 77
EVOLVING BASEMENT-SURFACE GEOLOGY MAP
A work in progress - Accuracy decreases eastward from Western Copper area and to south
4000E 5000E 6000E
Magnetite
Pit Crest
HW Fault
Western Copper
OZ MINERALS • PAGE 78
79
OZ MINERALS • PAGE 79
GRAVITY, MAGNETICS AND IP
• Infill gravity (contours – 2nd
horizontal derivative)
Drilling February to July, 2002
• Ground Magnetics (image)
• Downhole IP and Dipole -
dipole IP. Strong IP
anomaly coincides with
peak of gravity anomaly –
not magnetic anomaly.
• 14 diamond drill holes.
First follow up hole
targeted peak of IP/gravity
- barren.
• DP 003: 30m @ 2.72%Cu,
0.45g/tAu.
DP 005: 209m @ 1.54%Cu,
0.93g/tAu.
DP010: 57m @ 7.70g/tAu.
• High-grade Cu
mineralization confined to
area adjacent to &
immediately south of the
magnetic anomaly.
Highlights separate magnetic and gravity signatures and different drilling results; early drilling misses due to
exploration philosophy concentrating on magnetics.
OZ MINERALS • PAGE 80
EXPLORATION SELECTED RESULTS TO DATE
EL4025
Peculiar Knob North
Kennedy Dam
Taurus. 4m @ 1ppm Pt, 2.4 ppm Pd.
Calisto
White Hill North
106m @ 0.13% Cu
15m @ 0.77% Cu, 1.2ppm Pt, 0.7ppm Pd
20km
Zeus. 3m @ 1.45% Cu
2m @ 0.7% Ni. Zeus
Bluebird Taurus
Manxman. 287m @ 0.23% Cu.
EL4390
OZ MINERALS • PAGE 81
EXPLORATION PROGRAMS – 2010+ SOUTHERN AREA
EL4025
Peculiar Knob North
Kennedy Dam
Calisto
White Hill North
20km
Prospect IP testing
Zeus
White Hill
Basement geology map
Halifax Hill
Umbriel
WA EA
Continue Research Programs to
WCZ
WG improve Exploration Program
ECG EL4390
Under-Pit
OZ MINERALS • PAGE 82
EXPLORATION PROGRAM – 2010+ NORTH – INCLUDES
IMX JV
480,000 mE
500,000 mE
520,000 mE
540,000 mE
560,000 mE
580,000 mE
600,000 mE
• IMX JV - Selection of targets 6,820,000 m N
EL4025
6,760,000 m N
EL4429
6,740,000 m N
EL4429
6,700,000 m N
IP surveys EL4390
6,680,000 m N
magnetics
OZ MINERALS • PAGE 83
EXPLORATION SUMMARY
2010 Budget
• $20million resource development
• $20million regional exploration
– $13 million OZ Minerals tenements
– $7 million IMX JV
• 6 diamond drill rigs (2 year contract since late July 2009 – 100,000m E+RD)
• 1 more diamond rig from end May 2010 (15,000m)
• 1 rig for IMX (possibly 2) later in 2010
• 24,000km airborne geophysical survey now underway
• 2 ground gravity crews on site
• 2 IP crews (1 on site, 1 imminent)
• Technical experts
• Research
• Prospective Iron Oxide Copper Gold (IOCG) address
• Abundant Fe and Cu (REE, F, U) at many prospects
• A systematic approach to exploration targeting and assessment
OZ MINERALS • PAGE 84