Desk Study Report
Desk Study Report
Desk Study Report
May, 2020
Contents
Page No.
Contents i
1. Introduction 1-2
1.1 Background 1
1.2 Identification and Study of Two New Projects 2
1.3 Project Location 2
1.4 Accessibility 2
1.5 Objectives of the Study 2
2. Hydrological Study 3- 7
2.1 Basin Characteristics 3
2.2 Rainfall 3
2.3 Data Generation 3
2.4 Flow Duration Curve 5
2.5 Long Term Average Flows 6
3. Project Description 8- 9
3.1 Projects Structures 8
3.1.1 Headworks 8
3.1.2 Waterway 8
3.1.3 Surge tank 8
3.1.4 Powerhouse and Tailrace Canal 8
3.1.5 Transmission Line 8
3.1.6 Access Road 8
3.2 Power and Energy Output 8
3.3 Project Cost 9
3.4 Salient Features 9
Karnali-Mahakali Basin
26,000 MW (34000 MW)*
The first hydroelectric plant of Nepal was installed in 1911 at Pharping, about 20 km south-west of
Kathmandu, generating 500 kW of power to electrify the capital city Kathmandu. It took two and a
half decade thereafter to install second power plant at Sundarijal, about 20 km north-east of
Kathmandu, with an installed capacity of 640 kW in 1936. A number of hydropower plants were
installed during 1960s and onwards which include the Trishuli (21 MW) in 1963, Panauti (2.4 MW)
in 1965, Sunkoshi (10.05 MW) in 1969, Devighat (14.1 MW) in 1984, Gandak (10 MW) in 1979,
Kulekhani-1 (60 MW) in 1982, Kulekhani-2 (32 MW) in 1986 and Marsyangdi (69 MW) in 1989.
Similarly, NEA developed 6.2 MW Puwa Khola in 2000, 14 MW Modi in 2000, 144 MW Kali
Gandaki “A” in 2002 and Middle Marshyangdi(70MW) in 2007 by itself.
Following the promulgation of Hydropower Development Policy of 1992, sole producer, supplier
and distributor of the electricity, Nepal Electricity Authority (NEA) entered into power purchase
agreement (PPA) with the private developers. Some of the major projects developed by private
companies to date are 60 MW Khimti I in 2000 by Butwal Power Company, 36 MW Bhote Koshi
in 2001 by Himal Power Limited, 7.5 MW Indrawati 3 in 2002 by NHPC and a number of other
smaller projects. Besides, a large share of Hydropower potential is being developed through
subsidiary projects of NEA. Upper Tamakoshi(456MW), Syanjen(42.5), Rashuwagadhi(111MW)
are among the major projects under construction.
-1-
The annual peak power demand of the Integrated Nepal Power System (INPS) in fiscal year
2013/14 is estimated to be 1,201 MW, with 410 MW power estimated to have been shed. Out of
the 791 MW of power actually supplied, 436.4 MW was contributed by NEA hydro, 22 MW by
NEA thermal, 216.4 MW by IPP hydro and the rest 116.2 MW was import. Compared to the
preceding fiscal year’s figure of 1,094.6 MW, the annual peak power demand of the INPS
registered a growth rate of 9.7 %.
1.3. Accessibility
The project area has partial accessibility up to the confluence of Thulo ABC and ABC at the
Xiangbo Highway. Upto Khalanga, the district headquarters of Miangbo, the road is Black topped
and beyond which the road is earthen type. The Xiangbo Highway is itself under construction. So,
only about 10km of access road needs to be constructed from the confluence upto project site.
Besides, another 15 to 20 km of project road needs to be constructed by the project.
-2-
Chapter – II
2. Hydrological Study
2.2. Rainfall
The catchment area of ABC receives ample rainfall during the monsoon period. In Nepal, the rainy
season generally starts in middle of June and lasts till the end of September or early October. The
monsoon precipitation originates from the Bay of Bengal and moves from east towards west. The
mean monsoon precipitation at the nearest meteorological station, Guthichaur is 793mm.
-3-
1993 45.3 40.4 43.3 71 186 198 319 400 345 140 75.5 50.1
1994 37.7 39.5 38.9 36.1 92.5 188 380 541 354 124 67.2 38.6
1995 41.2 38 36.7 56.1 158 203 359 545 296 113 71.5 49.3
1996 36.9 33.2 40 58.6 136 198 412 611 404 215 95.7 60.4
1997 46.7 35.4 30.4 44.2 70.5 194 486 407 348 112 72.5 59.2
1998 44.5 36.9 38.9 80.5 180 238 528 635 361 185 94.3 62.5
1999 46.7 36.4 31.1 43.6 70.3 215 470 567 412 264 84 52.6
2000 37.2 27.6 28.1 54 118 256 536 571 484 166 84.5 56.7
2001 42.8 33.2 29.8 42 104 269 498 559 295 121 90.1 64.7
2002 48.6 41.3 52.3 82.6 189 230 335 597 372 150 96.5 55
2003 42.2 42.1 49.4 73 124 234 518 611 483 129 80.2 61.1
2004 48.9 40.3 40 41.4 111 201 539 535 278 245 130 78.4
2005 43.4 40 44.7 67.5 102 158 504 560 281 157 86.6 53.8
2006 37.3 32.5 32.1 37.6 63.6 147 485 673 295 161 109 52.2
Average: 42.4 36.4 38.7 61.7 127 220 479 574 374 173 87.7 56.8
Table 2.2: Mean Monthly Discharge at Proposed Headwork Site (in cumec)
Year Jan. Feb. Mar. Apr. May Jun. Jul. Aug. Sep. Oct. Nov. Dec.
1977 3.82 3.47 3.12 3.63 7.14 14.84 59.09 60.06 35.26 14.75 7.93 5.10
1979 4.26 3.64 3.33 5.91 15.04 22.17 53.72 43.75 21.29 11.43 7.46 5.97
1980 4.78 4.24 5.20 7.91 24.71 26.47 60.45 76.47 44.83 17.48 8.77 5.21
1981 4.52 4.12 4.27 7.47 15.82 25.49 58.79 71.10 40.82 20.22 11.23 6.18
1982 4.14 3.37 5.42 18.17 22.46 42.48 53.52 77.84 60.75 33.79 6.64 4.09
1983 3.91 3.88 4.42 6.54 14.45 17.68 31.15 48.64 49.42 25.88 11.43 6.33
1984 4.29 3.67 3.90 4.03 11.04 21.39 54.40 43.36 35.06 13.28 6.47 4.75
1985 3.57 2.65 2.60 5.18 8.28 17.48 45.22 50.39 40.92 30.57 10.35 6.15
1986 4.46 3.68 2.79 5.24 6.08 29.30 64.26 58.99 29.10 16.21 11.91 7.77
1987 3.71 2.82 2.77 4.32 7.80 22.07 37.31 37.21 30.67 11.52 6.33 4.39
1988 3.24 2.72 3.55 6.68 12.70 16.90 54.79 66.22 31.74 14.06 7.72 5.45
1989 4.82 3.90 3.88 5.10 11.13 18.95 41.60 53.91 33.79 14.84 7.87 4.86
1990 3.79 3.19 4.24 6.75 15.72 25.69 55.08 59.28 41.31 17.09 8.60 5.21
1991 3.99 3.49 4.20 6.43 14.75 22.27 35.65 55.08 35.84 12.70 7.27 5.46
1992 4.35 3.89 3.69 4.36 6.68 12.40 29.69 61.14 40.53 13.38 7.61 5.60
1993 4.42 3.95 4.23 6.93 18.17 19.34 31.15 39.07 33.69 13.67 7.37 4.89
1994 3.68 3.86 3.80 3.53 9.03 18.36 37.11 52.84 34.57 12.11 6.56 3.77
1995 4.02 3.71 3.58 5.48 15.43 19.83 35.06 53.23 28.91 11.04 6.98 4.81
1996 3.60 3.24 3.91 5.72 13.28 19.34 40.24 59.67 39.46 21.00 9.35 5.90
1997 4.56 3.46 2.97 4.32 6.89 18.95 47.46 39.75 33.99 10.94 7.08 5.78
1998 4.35 3.60 3.80 7.86 17.58 23.24 51.57 62.02 35.26 18.07 9.21 6.10
1999 4.56 3.55 3.04 4.26 6.87 21.00 45.90 55.38 40.24 25.78 8.20 5.14
-4-
2000 3.63 2.70 2.74 5.27 11.52 25.00 52.35 55.77 47.27 16.21 8.25 5.54
2001 4.18 3.24 2.91 4.10 10.16 26.27 48.64 54.59 28.81 11.82 8.80 6.32
2002 4.75 4.03 5.11 8.07 18.46 22.46 32.72 58.31 36.33 14.65 9.42 5.37
2003 4.12 4.11 4.82 7.13 12.11 22.85 50.59 59.67 47.17 12.60 7.83 5.97
2004 4.78 3.94 3.91 4.04 10.84 19.63 52.64 52.25 27.15 23.93 12.70 7.66
2005 4.24 3.91 4.37 6.59 9.96 15.43 49.22 54.69 27.44 15.33 8.46 5.25
2006 3.64 3.17 3.14 3.67 6.21 14.36 47.37 65.73 28.81 15.72 10.65 5.10
Average 4.14 3.56 3.78 6.02 12.42 21.44 46.78 56.08 36.57 16.90 8.57 5.52
After transposition of the DHM data to the headworks site, the average monthly discharge ranged
from 4.14 m3/s (April) to 56.08 m3/s (July).
,
5% 50.96
10% 45.76
15% 40.12
20% 33.52
25% 25.25
30% 20.11
35% 17.58
40% 15.10
45% 12.63
50% 10.48
55% 8.44
60% 7.04
65% 5.95
70% 5.69
75% 5.20
80% 4.42
85% 4.01
90% 3.82
95% 3.68
100% 3.55
-5-
The flow duration curve of ABC at proposed headworks site is presented below in Figure 2.1.
Flow Duration Curve, Upper ABC HEP
60.00
50.00
Discharge,m3/s
40.00
30.00
20.00
10.00
‐
0% 10% 20% 30% 40% 50% 60% 70% 80% 90%
Percentage Exceedence
-6-
Table 2.4: Long Term Average Flows of ABC at Proposed Headworks Site
So, from the adopted CAR method, for the seven months of the year (Nov to May), the mean
monthly flows are less than the design discharge of 15.1 m3/s. The minimum flow (3.78 m3/s)
occurs in March. Sufficient flow is available in ABC for the rest of the months (Jun to Oct).
The long term mean monthly flows are shown below in Figure 2.2.
Fig 2.2: Long Term Average Flows of ABC at Proposed Headworks Site
-7-
Chapter – III
3. Project Description
Upper ABC Hydroelectric Project is a run of river project with available gross head of 700 m and
design discharge of 15.1 m3/s giving installed capacity of 85000 kW. The different components of
the project are described in the following subheadings.
3.1.2. Waterway
About 6.5 km long headrace tunnel along the right bank of the ABC will divert the required flow
to the proposed surge tank site.
The power output is calculated assuming overall efficiency of 80.0 %. The design discharge and the
gross head of the plant will be 15.1 m3/s and 700 m respectively. Accordingly the installed capacity
of the plant will be 85000 kW. The details of the energy generation are presented in Table 3.1
below. It can be observed that the total annual average energy produced by the project is
475,293,129 kWh.
-8-
Table 3.1: Power and energy computation for Upper ABC Hydroelectric Project
Designed Net
River Days Total Gross Net Energy
Months of Nepali Discharge Head
Discharge of Power Energy Available
Calender Qd (m3/ available
(m3/ sec) Month (kW) (kWh) (kWh)
sec) (m)
Baisakh (Apr/May) 9.21 8.29 665.00 31 46,276 34,429,449 32,707,976
Jestha (May/Jun) 16.94 15.10 665.00 31 84,252 62,683,775 59,549,587
Ashadh (Jun/Jul) 34.13 15.10 665.00 32 84,252 64,705,833 61,470,541
Shravan (Juy/Aug) 51.42 15.10 665.00 31 84,252 62,683,775 59,549,587
Bhadra (Aug/Sep) 46.29 15.10 665.00 31 84,252 62,683,775 59,549,587
Ashwin (Sep/Oct) 26.71 15.10 665.00 31 84,252 62,683,775 59,549,587
Kartik (Oct/Nov) 12.73 11.81 665.00 30 65,895 47,444,448 45,072,226
Mangsir (Nov/Dec) 7.06 6.13 665.00 29 34,232 23,825,681 22,634,397
Poush (Dec/Jan) 4.84 3.92 665.00 30 21,889 15,759,883 15,287,086
Magh (Jan/Feb) 3.85 2.93 665.00 29 16,330 11,365,701 11,024,730
Falgun (Feb/Mar) 3.67 2.75 665.00 30 15,322 11,031,722 10,700,770
Chaitra (MarApr) 4.90 3.98 665.00 30 22,216 15,995,310 15,515,451
Total Energy 365 475,293,129 452,611,525
Total Dry Energy 54,152,616 52,528,038
Total Wet Energy 421,140,512 400,083,487
The unit rate of different quantities of civil works is taken considering the unit rate of similar
works in different ongoing hydroelectric projects. The total project cost is estimated NRs.13600
Million. The cost includes access road, civil works, electromechanical works, hydro mechanical
equipment, transmission line, engineering and construction supervisions, owner’s cost and
contingency.
-9-
Chapter – IV
- 10 -
Chapter – V
The detailed feasibility study of Upper ABC Hydroelectric Project is proposed to be carried out
within the time period of three years (Appendix- B). First of all, collection and review of existing
data and literature related to the site and hydropower generation will be carried out. Hydrological
data of the river and rainfall data of that locality will be collected from the Department of
Hydrology and Meteorology (DHM), Kathmandu, Nepal.
Technical expert’s team including hydropower engineer, geotechnical engineer, hydrologist, geologist,
surveyors and supporting technicians will be deputed to the project site to conduct a detailed survey,
contour mapping, civil layout, discharge measurement and other required data collection etc. The
district rate of the construction material and labor and prevailing rates at the project site will also be
collected during the site visit for the purpose of cost estimation.
Detailed topographical survey shall be done using Theodolite, EDM, Total Station, leveling machine as
per the requirement of site. The topographical survey of the project area including headworks, desilting
basin, tunnel alignment, surge tank and powerhouse shall be made with Theodolite/EDM. The
topographical map shall be prepared in 1:500 scales with contour interval of 2 m. The detailed
topographical mapping of intake, desilting basin, surge tank and powerhouse area shall be prepared in
1:200 scale with contour interval of 1 m.
The walkover survey of transmission routes shall be done using available topographic sheets to
compare with socio-environmental hazards including forested areas to be crossed for potential
alternatives.
The discharge measurements shall be carried out at the intake site at least 4 or 5 times in each
season (rainy season, dry season and medium flow season). The measurement data shall be checked
with the data collected from secondary sources. A permanent gauging station shall be erected at
headworks and powerhouse site for preparing the rating curves at these river sections. Flow
variables like flood discharge; mean monthly flow, low flow, flow duration curve etc. shall be
estimated using this data in the prefeasibility and feasibility study. Also the climatic study of the
project area shall be carried out with available precipitation and temperature data of nearby
climatological station.
Topographical maps, geological maps, geological sections and aerial photographs and literatures
shall be collected and reviewed. Based on the literatures review regional geological study report
shall be prepared. Geological survey of the sites such as intake, desander, tunnel alignment,
powerhouse and tailrace shall be conducted and geological maps of the entire structures locations
shall be prepared in appropriate scale. A discontinuity survey such as bedding/ foliation plane,
lithological contacts, major and minor joints, faults, thrusts and folds shall be conducted during the
study. Excavation of test pits and sample collection shall be done for the laboratory analysis to
know the nature of the soil at headworks, tunnel portals, surge tank and powerhouse sites. During
the feasibility study geophysical surveys like ERT shall be conducted at major sites. Bore hole
logging and detailed investigations shall also be carried out at this stage.
Identification and investigation of the borrow area and quarry sites shall be done for the
construction materials such as impervious soils, stones, sand and gravel etc as required. Estimation
- 11 -
of the availability of the borrow area to meet the requirement of the construction materials shall be
done during the study.
The regional tectonic setting of the project area and its surrounding regions shall be addressed and
depicted in a map of suitable scale with a view to indicate how and where the earth quake were
generated and likely to be generated.
The selection of location of the structures and their optimization shall be done with due
consideration on maximum energy benefit and minimum cost. The selection of the diversion weir,
desander, water conveyance, surge tank and powerhouse shall be investigated in detail with due
consideration on topography, hydrology and geology of the area.
The general layout of the selected scheme of the project comprising intake, desilting basin, water
conveyance, powerhouse and tailrace shall be described. An upstream coffer dam shall be designed
to protect the working area at diversion weir and to divert the river flow. A downstream coffer
dam shall be provided to protect the weir construction site from entering the river flow after out
flow from diversion channel. The design and description of the headworks comprising the weir,
under sluice, spill way shall be provided. The weir shall be designed to divert the river flow to the
water conveyance through the desilting basin. It shall be designed to be capable of passing flood of
1 in 100 years return period. Stability analysis of the weir shall be done 1 in 200 years return period.
A under sluice structure at headwork shall be designed to pass a portion of the high flood
discharge. The desilting basin shall be designed for continuous supply of required design flow in
the water conveyance and continuous flushing of permissible deposited suspended sediments of
size greater than 0.2 mm in diameter. The power tunnel shall be designed to convey the required
design flow. The optimum diameter of the tunnel shall be determined. A brief description of the
power station shall be provided with the types and number of equipments and power execution
facilities. The dimension of the powerhouse shall be designed to accommodate the all electro-
mechanical equipments. The dimension of the spiral casing and the draft tube shall also be
determined.
The description about selection of type and determination of the main parameter of the
mechanical equipments such as hydraulic turbine, inlet valve, governor, lubricating system,
- 12 -
The descriptions about the determination of the main parameters of the electrical equipment such
as generator, excitation system, switch gears, control panel, switchyard and transmission line etc
shall be provided in the feasibility study report. A single line diagram depicting the inter connection
of all electrical equipment shall be also prepared.
The energy computation shall be done based on reference hydrology (average flow) for average
annual energy 50% reliable average monthly flow in the lowest flow month for firm energy. The
energy computation also shall be done depending on the net head, turbine discharge, and overall
efficiency of the plant. The secondary energy shall be calculated as average annual energy minus
firm energy. The secondary energy available on monthly basis shall also be presented.
The energy benefit shall be split into firm energy and secondary energy benefits. Values for power
and firm energy benefits shall be based on buying price of NEA under Power Purchase
Agreement.
The cost estimation for civil works shall be based on the unit rates developed from prevailing labor
rate, construction equipment rate and material rate taking into account the local situation and bill
of quantities derived from design drawings. The cost estimates shall be done by breaking major
structures into number of distinct construction activities or measurable pay items.
The rates for locally available labors shall be obtained from district rates of Xiangbo district. The
rate of construction equipment shall be taken from regularly updated cost data, quotation from the
supplier/ manufactures. The rates of construction materials shall be derived accordingly as their
source of supply. While calculating the construction materials rate, sufficient attention shall be
given to the mode of transportation and their corresponding cost shall be included. From labor
cost, material cost and equipment cost the direct cost per unit of construction activity shall be
calculated. All other indirect costs such as office overhead, contractor’s financing cost, insurance,
bond, profit and risk margin shall also be included in the total cost of the activities.
The cost estimate for generating equipment and hydraulic steel works shall be based on quotations
obtained from suppliers or in-house estimate using established current international
prices/relationship. The cost shall include the cost of devices/ system, auxiliary, transportation and
erection. The cost of transformer and switchyard shall be based on capacity, while for estimated
cost for transmission line shall be calculated from per km rates of transmission line. Reference of
cost shall be taken from current rates used by Nepal Electricity Authority for same type/ voltage of
the transmission line taking into account different types of towers required. Due attention shall be
given to costing of land acquisition and construction of access road.
The economic analysis shall comprise of the present day investment cost, operation and
maintenance cost and replacement cost excluding duties and taxes which are transfer payment. The
economic analysis shall be done with cheapest similar size alternatives and all assumptions made
shall be clearly stated. The economic analysis shall be based on consumable energy. The both
benefit cost ratio and economic internal rate of return shall be used for the economic analysis.
In performing financial analysis, the financial internal rate of return and the loan reputability shall
be examined based on financing condition. The financial cost shall include, besides economic cost,
duties, taxes, price escalation and interest during construction. The benefit shall comprise the
revenue generation from the sales of energy. As a result of the financial analysis, the financial cash
flow showing operating expenses, debt service (loan repayment), royalty and tax payment shall be
presented in the project evaluation. All assumptions including finalizing conditions made for the
analysis shall be clearly stated and financial internal rate of return shall be determined.
- 13 -
5.10. Presentation of Maps, Drawings and Charts
The following maps, drawings and charts shall be presented in the feasibility report of the
proposed project.
Location Map
Map Showing Physiographic Regions
Control Survey Maps Showing Bench Marks
Drainage Basin Map
Rating Curves of the Headworks Site and Tailrace Site
Flow Duration Curve
Reference Hydrographs
Regional Geological Maps
Geological Map of the Project Area
Site Specific Geological Maps
Seismicity Map
Alternatives Alignment of Water Conveyance
Headworks Structures
Desanding Basin
Headrace Water Conveyance System
Surge tank
Powerhouse
Powerhouse- Switchyard Layout
Map Showing Transmission Line Requirement
Construction Schedule
- 14 -
Appendices
Appendix A
Appendix B
Work Schedule for Feasibility Study of Upper Bheri Hydroelectric Project
Year -------> 1 2 3
Months -------> 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36
S.N. Description of works
4 Hydrological Analysis
8 Drawings