♣ Feasibility report on crank shaft ♣

FEASIBILTY
REPORT
ON
crank shaft

S.T.B.S. COLLEGE OF DIPLOMA ENGG. SURAT.

♣ Feasibility report on crank shaft ♣

 AIM:-
 INTRODUCTION :-

The crankshaft is the part of an engine that translates reciprocating


linear piston motion into rotation. To convert the reciprocating motion into
rotation, the crankshaft has "crank throws" or "crankpins", additional bearing
surfaces whose axis is offset from that of the crank, to which the "big ends" of the
connecting rods from each cylinder attach.

It typically connects to a flywheel and to reduce the pulsation


characteristic of the four-stroke cycle, and sometimes a torsional or vibrational
damper at the opposite end, to reduce the torsional vibrations often caused along
the length of the crankshaft by the cylinders farthest from the output end acting on
the torsional elasticity of the metal.

 OVERVIEW:-

Our raw material is steel because, it is more preferable then material


because of it can easily forgeable. Then is cut by welding after than it is send to
grinding m/c for surface finishing.

 PROCESSES:-

Crank shaft is made by forging process


♣ Feasibility report on crank shaft ♣
 COST ESTIMATION:-
♣ Feasibility report on crank shaft ♣

 Material Cost :
● Weight of Material :- 1000 Kg

● Cost of Material :- Rs.30/kg

Cost of material: Rs. 30,000

 Labour Cost :

 Other Expenses :
● Taxes :- 830

● Insurance :- 1000

● Overhead :- 2080

● Power :- 8330

● Water :- 830

●Transportation cost :- 2200

Cost of Expenses : 15270

Total Cost : Fixed Cost + Material Cost + Labour Cost + Other Expenses
: 59,166 + 30,000 + 18,000 + 15,270

: Rs. 1,22,436
♣ Feasibility report on crank shaft ♣

Cost/ Piece : Rs.1,22,436 / 20,000 nos


: Rs.6.12

20 % Profit on mfg. cost : (20) / (100*6.12)


: Rs. 1.66 /piece

 Selling Prize : Rs. 6.12 + Rs. 1.66


: Rs. 7.88/unit

 CALCULATION OF BREAK EVEN QUANTITY:-

 Other Expenses : Rs. 15270

 Fixed cost ( F ) : Rs. 59166

 a : other expenses/ Units


: Rs.15270/20,000

: Rs 0.76/unit

Break even quantity (B.E.Q.) : F/ (b-a) (Where, b= selling price)


: 59166/ (7.88– 0.76)

: 8309 Units
♣ Feasibility report on crank shaft ♣

 References :

1. Maharaja watch tools Mfg.


Waghodiya G.I.D.C. , Baroda
Gujarat