Professional Documents
Culture Documents
Surveying and Setting Out
Surveying and Setting Out
1.2. Safety
Many Road maintenance operations are potentially dangerous, both to the maintenance
workers and to the road users.
It is the responsibility of the maintenance foreman or supervisor to insist that all risks are
minimized by:
Ensuring that the necessary temporary traffic signs. Where necessary, traffic should be
stopped during the placement or removal of temporary signs,
Arranging personal safety to be worn in appropriate circumstances,
Ensuring that all plant and vehicles are parked off the carriageway or behind protective
barriers and signs, when not in use,
Ensuring that no materials are left in a dangerous location and worksite is kept clean
and swept of any debris arising from the maintenance work,
Ensuring that proper precautions are taken when handling dangerous substances
Ensuring that all operators are trained in the operation of their equipment. If they are
not adequately trained when they are assigned to the foreman or supervisor, he should
himself provide, or arrange for, the necessary instruction. Operators and labourers
alike must be informed of the potential risks of and procedures for working with or
close to machinery,
Ensuring that traffic control operations are properly carried out and that road users are
not unnecessarily delayed,
Ensuring all ladders or scaffolding used in bridge maintenance are securely fixed,
Ensuring that where work on the carriageway or shoulder remains unfinished
overnight, then proper warning lights are arranged and, if necessary, protected,
Ensuring that all sites are left tidy and cleared of debris when the work is completed.
1. Objectives:-After completing the learning element the trainee will be able to wear
safety working clothes, shoes and etc in the working place.
2. Examples of PPE are:
╠ Overall clothes
╠ hard hate/ helmet
╠ safety shoe
╠ Rubber boot
╠ Mask
╠ Goggle
╠ Glove
╠ Hand guard
3. Hazardous Materials or Waste: Hazardous materials or waste include but are not
limited to explosives, compressed gas, flammable liquids, flammable solids,
combustible liquids, oxidizers, poisons, radioactive materials, corrosives, etiologic
agents, and other material are classified as hazardous materials.
4.
1.3. First Aid
A building site should have a first aid box which as minimum contents: -
Plasters
Bandages
Ointments
Disinfectant
Chapter-Two
2. Terms and Definitions
2.1. Survey & Setting out terms
Identification: Identification step is the preparation of a list of proposed roads to be
improved or maintained.
Screening: Screening of routes is carried out to identify roads in order to disqualify
those projects that do not meet certain criteria, are not technically or economically
feasible, or are not likely to have the expected impact.
Appraisal: Appraisal is a more detailed assessment for supporting an investment in
a certain road, often, a cost benefit analysis.
Ranking: Ranking is the ordering of all selected roads which have passed the
screening and appraisal stages.
Approval: Approval is a final step; the roads selected according to this process will
need to be approved by the relevant authorities.
Route survey: Route surveying to be used includes all the surveying mapping activities
(the field and office works) required to plan, design, and lay out (construct) the road for low
volume traffic roads.
Initial survey: Initial survey means gain information about the area where the road
will pass through.
Detailed survey: Detailed survey means setting out the exact location of a road and
its components.
Survey: Survey of a road alignment means inspection or investigation of the
condition of the terrain where the road (will) pass through an area.
Setting out: Setting out is the first application of the road measurement marking on
the ground of what is to be built.
Reconnaissance: c
Accuracy: Accuracy relates to how close a measurement is to the true value.
Precision: Precision is a measure of consistency and how close measurements are to
each other.
Tolerance: Tolerance can be defined as how much a field measurement or point set
in the field can vary from the true angle, distance, or location.
Vertical alignment: Vertical alignment means set out vertical levels on the center
line.
Straight grade: A straight grade is a section of road where the longitudinal
gradient of the road centerline is constant.
Gradient: Gradients are expressed as percentages, with a negative for a downgrade
and a positive for an upgrade.
Vertical curve: Vertical curve is provided at the point where the two straight lines
at different gradient intersect in the vertical plane.
Crest curve: Crest curve is a curve having convexity upwards.
Sag curve: sag curve is curve having concavity upwards or convexity downwards.
Point of vertical curvature (PVC): PVC is a point where parabolic curve begins.
Point of vertical Intersection (PVI): PVI is a point where the back tangent and
forward tangent intersects.
Point of vertical Tangency (PVT): PVI is a point where parabolic curve ends.
Leveling: Leveling is the most widely used method for obtaining the elevations of
ground points relative to a reference datum.
Reduced level (level): Reduced level is the vertical height of a point above or below
a reference datum.
Datum: Datum is a reference surface of constant potential, for measuring the
elevations of the points.
Level line: Level line is a line lying in a level surface.
Height of instrument (HI): HI is the elevation of the line of sight from the datum.
Gradient: Gradient is the rate of rise or fall in relation to the horizontal along the
length of the road or other structure (e.g. a drain).
Level: A level is a measurement in the vertical (Up and down) direction between two
points.
Roadway: The area normally used by the traffic, consisting of the carriageway and
shoulders.
Shoulder: The shoulder provides side support for the pavement and allows vehicles
to stop or pass in an emergency.
Ditch (Side drain): A long narrow excavation designed or intended to collect and
drain off surface water.
Back slope: Back slope is the portion of the side drain from the ditch invert to the
intersection with the natural terrain.
Crown: Crown is the highest point of the road, located on the centre line when the
surface is shaped with a camber.
Ditch Invert: Ditch invert is the cross-section profile of the side drain from the side
slope to the back slope.
Side Slope: Side slope is the portion of the side drain from the shoulder break point
to the ditch invert.
Road Reserve: Road reserve is the cleared portion of land where the road and all its
components will be built.
Culver: Culvert is a drainage structure which is allowing water to pass under the
road pavement to be discharged on the lower side of the road.
Nearside: This is the left hand or kerb side of a vehicle, relative to the direction of
travel.
Offside: This is the left hand or median side of a vehicle, relative to the direction of
travel.
Parking lane: Lane primarily used for vehicle parking.
Turning lane: An auxiliary lane reserved for turning traffic.
2.5. Related Terms
Capacity: The maximum rate of flow at which vehicles can traverse a point or
segment of a lane or roadway during a specified time under prevailing roadway and
traffic conditions, expressed as a vehicles per hour.
Labour based Technology: Is construction technology that utilizes locally
available materials and maximizes opportunities for the employment of labour
(skilled and unskilled) together with the support of light equipment.
Labor-intensive approach: Labor-intensive approach seeks to maximize the use
of labour with minimum use of mechanized equipment.
Equipment-Intensive approach: Maximizes the use machines with minimum use
of labour. The use of heavy equipment requires high initial capital investments.
Chapter-Three
3. Tools for Surveying and Setting Out
3.1. Introduction
Surveying and Setting out | . 9
Ethiopian Roads Authority
March 18, 2016 Chancho Labour Based Technology Training Center
There are a number of appropriate methods for setting out a road alignment. The choice of
surveying equipment is based on the required level of accuracy and the applied setting out
methods. When surveying rural road s, it is important to bear in mind the required level of
accuracy for the works. Obviously, the level of detail for a rural road is not the same as for
major highways or city streets.
Bearing this in mind, the following section describes some low-cost and easy to use but still
sufficiently accurate methods of surveying and setting out rural road work.
made of steel or linen. Although the former is stronger, the numbers and marking on the tape
becomes unreadable after a period of use.
Tapes are vital for setting out lengths and widths as well as setting tasks and measuring
completed works. The smaller tapes, 2m, 3m or 5m in length, are useful for small construction
elements, such as profiles of ditches, cambers, trenches, etc. It is important to keep them clean
and avoid dirt entering the case.
Both profile boards and ranging rods are inexpensive and can easily be manufactured
by a local metal work business. Before commencing setting out works, make
sure that a sufficient amount of ranging rods and profile boards is available. A
supply of 20 rods and profile boards is regarded as a minimum to effectively
carry out the job.
The line level has a range of up to about 50 meters. It is easy to carry around and with care
it can be used for setting out levels and slopes not less than 1 in 300.
Points to remember when using a line level:
The line level should be placed halfway between the two ranging rods. Use a
measuring tape to find the exact middle point.
Keep the string tight - do not let it sag.
T he line level is a delicate instrument, look after it – do not throw it around and
treat it roughly.
Check the accuracy of the line level regularly.
It is always useful to turn the line level around every time it is used, and take the middle of
the two marks as the horizontal level.
The same exercise can be carried out using profile boards. Often, a single boning rod is
then used to check the surface levels between profile boards. This exercise is commonly
applied to secure the correct levels of earthworks layers when building up fills or when
spreading gravel.
(i) Triangles
Triangle sets can be manufactured by a carpenter and are used for various purposes:
To set out a right angle to the centre line (necessary when cross-sections are set out)
To control or estimate the steepness of gradients - in this case a spirit level or a plumb
line is also required.
The steepness of gradients is described as a ratio. For example, a gradient of 1:2 means that
over a horizontal stretch of two meters, the terrain will rise one meter vertically. Alternatively,
the gradient can be expressed as a percentage increase in elevation. A 6% gradient would
describe a 6m rise over a 100m horizontal stretch.
When measuring existing gradients using a triangle, a spirit level is required to secure the
horizontal line. The joints of the triangle are then adjustable with pinned joints rather than fixed.
The most common use of the triangle is to quickly establish a right angle to the road centre
line.
The straight edge is usually 3 meters long and set horizontally with a spirit level. This
method is used for the measurement of gradients which continue only for short distances, e.g.
culvert beds, drain slopes and road camber. The figure above shows how a gradient of 1:15 is
measured.
This level consists of a length of clear plastic hose attached at each end to a wooden leveling
staff, as shown in the figure below. The two leveling staffs should be of the same length, about
1.5 m long. A graduated tape is attached to each staff, with the zero level at the top end of the
staff. The tube is filled with water until the level is about one meter high from the ground. Both
ends of the tube are fitted with rubber stoppers to prevent loss of water. The total length of the
tube, which defines the range of the instrument, is variable, but is usually limited to about 15 m
by the difficulty of moving the level around.
The two ends of the pipe are brought together at the starting point, the stoppers
removed and the readings taken level with
the bottom of each meniscus. The
readings should be the same (e.g.
reading A = 50 cm, reading B = 50
cm). The surveyor takes the pipe to
the point being measured and
takes another reading. The
difference between the two readings
is the difference in level (e.g. if reading A =
30 cm and reading B = 70 cm, the difference in level is
then 70 – 30 = 40 cm). The range is limited only by the convenience of
being able to carry the hose. The two points where the difference in level is being measured do
not need to be in sight of one another. The level gives accurate results and can be used for setting
level lines or slopes not less than 1 in 1,000.
measure height differences, used in combination with a leveling staff. The dumpy level is the
classic instrument used for setting out levels in road works projects. Levels can be transferred
from a benchmark and new levels can be established very accurately over distances up to 100
meters. There are several types of dumpy levels on the market, each with its own design.
The figure below shows a 2.5 meter long camber board showing a gradient of 5 percent
(1:20). The camber board is built with a length and gradient that suits the required profile.
The camber board is used in combination with a spirit level as shown below. Camber boards
are useful for checking the cross-slope on existing roads however; it should not be used when
building a new camber. The use of profile boards and a line level will provide more accurate
results.
The table below shows the appropriate quantities of tools required for carrying out the
regular setting out activities relating to rural road construction works. As demonstrated in the
following sections, surveying and setting out for rural road works can be carried out using fairly
simple and inexpensive equipment. These quantities are adequate for a work site involving 300
workers.
Chapter-Four
4. Surveying and Setting Out
4.1. Objectives
After you have learned this chapter you should:
Know how to determine the most suitable alignment of a road.
Describe why survey and setting out the construction works well in advance is
important.
Know the types of route survey.
Understand why the realignment of the existing road will important.
Setting out
Setting out is the first application of the road measurement marking on the
ground of what is to be built.
Standard methods have been developed for setting out road works and these
fall into the following main areas:
Setting out the horizontal alignment
Setting out the vertical alignment
Setting out the cross section
Setting out drainage structures
Setting out of tasks
After all the above have been investigated and surveyed the engineer will take his
decision based on an estimate of:
Construction costs
Maintenance costs
Costs to future traffic
Social costs and benefits
Construction costs: Example an alignment of a certain length passing through a
swampy area will cost more than of the same length passing
through grassland.
Maintenance costs: Example the cost to maintain steep gradients are higher than the
costs to maintain gentle gradients.
Cost to future traffic: Example more energy or engine power is required to climb a
steep gradient than a gentle gradient which means more fuel
consumption and also more wears to brakes when descending.
Social costs and benefits: In many cases the higher construction costs of a longer
alignment may be justified if the road would serve a public facility
(e.g. school, health center, etc.).
Rural roads are built to improve access and will usually not have stringent requirements in
regards to road curvature. Prior to the construction of the road, the community has most
probably been relying on a track or a trail. Following the alignment of existing tracks will
in most cases have the least effect on the surrounding environment. Often, the alignment of
existing tracks also provides the best solution in terms of reducing the amount of
earthworks.
It is sensible to make sure that all interested parties agree on the route and places to be
linked by a new or improved road. During the early planning stages, it is therefore useful
to carry out a process of consultation with the communities and beneficiaries of the road
works project.
4.6. Check List for route selection
╠ Locate the best sites for river crossings
╠ Avoid rocky areas
╠ Avoid areas with heavy bush clearing
╠ Try to avoid areas requiring complicated drainage solutions
╠ Follow existing alignments
╠ Avoid steep gradients (max. 10%)
╠ Keep earth moving to a minimum
╠ Be considerate with existing farming activities in the area
╠ Avoid triggering soil erosion
Costs to future traffic are greater when the road is designed with steep gradients. More
energy is used to climb and descend steep hills, causing more wear to the vehicles. More
powerful means of transport are required for steep curvatures. Animal drawn carts will
only be able carry reduce loads on such roads.
Vertical alignments requiring excessive cuts and fills along the road line should be avoided.
By adjusting the horizontal alignment to the existing terrain, there is a large potential for
reducing earthworks. Avoiding large side cuts also reduces the risk of soil erosion and
landslides.
Equally, steep side-sloping ground should be avoided even if the existing road or track is
cut into it. If possible, relocate the line lower down the hillside where the ground is flatter.
Surveying and Setting out | . 23
Ethiopian Roads Authority
March 18, 2016 Chancho Labour Based Technology Training Center
Cross drainage structures are expensive and can to a certain extent be avoided when the
road follows the line of the watershed. High ground such as watershed borders has natural
drainage and if the road is located in such terrain, the amount of drainage works is
significantly reduced.
4.8. Good road alignment
Crossing ridges at their lowest point or through the lowest pass;
Circumventing (avoid) hills rather than going straight over;
Avoiding deep cuts, thereby reducing earthworks and avoiding to destabilize side
slopes;
Avoiding excessive fills by realigning the road, preferably to locations where a
cut-to-fill is sufficient;
Finding the highest lying ground when passing through flood prone terrain;
Avoiding steep road gradients;
Avoiding rocky terrain or areas with difficult soils;
Locating good river crossings where there are limited risks of future scouring and
erosion.
specifications for work crews to follow. Teams may spend days or weeks in the field,
depending on the nature of the project.
A route survey supplies the data necessary to determine alignment, grading, and
earthwork quantities for the design and construction of various engineering projects.
The general route survey and location principles and guide listed below applies also for
the labour- based road construction roads. Route surveying to be used includes all the
surveying mapping activities (the field and office works) required to plan, design, and
lay out (construct) the road for low volume traffic roads. The following are types of
surveys:
Initial survey
Detailed Survey
the choice of alignment should reflect this. A high speed alignment and design is expensive
and irrelevant to a low volume rural road. Undulating vertical curvature and comparatively
sharp curves are more compatible with local roads with limited traffic.
4.9.3. Stationing
Stationing shall be provided for all points set in the alignment survey. This includes
stationing for the PC, PI, PT and for all intermediate control points. Stationing shall be in
English units. English stationing shall be increased every 100ft, unless otherwise noted in the
request for a survey. Therefore, a station of 3+56.00 represents a point 356.00ft from the
beginning point. When using metric units for stationing the kilometer is the basic unit. Thus a
station of 2+050.022 represents a point 2,050.022m from the beginning point.
Chapter-Five
5. Horizontal Alignment
5.1. Objectives
After you have learned this chapter you should
Be Describe what is meant by a “horizontal alignment”
Know how to establish chainages.
Be able to describe how a road is set out in different types of terrain.
Know how to set out horizontal alignment.
Be able to sighting invisible points to make a straight.
Be able to describe how horizontal curves setting out.
Know how to determine the most suitable alignment of a road.
5.2. Introduction
Horizontal alignment of a road is usually a series of straights (tangents) and circular
curves which may or may not connected by transition curves. There are different
activities under the horizontal alignment, such as setting out straight alignment (visible
and invisible points), stationing, chainage establishment, and setting out of horizontal
curves. In addition, the horizontal alignment must be designed in conjunction with the
vertical alignment and both properly coordinated.
finding a suitable alignment in the terrain, using simple tools such as ranging rods,
profile boards and a line level.
When surveying the alignment, the exact location of the road is established by marking
the centre line with pegs located every 20 meters on straight sections and every 5 to 10
meters along curves. A mark is also placed on each of these stakes defining the distance
(up or down) to the finished formation level of the road surface. Horizontal alignment is
setting out the centerline of the road.
5.4.1. Interpolation
Interpolation is the estimation of unknown section from two known adjacent sections. The
two end points of the straight line to be established are each marked with a ranging
rod. The intermediate points can be found by sighting from one end rod to the other
and moving a third rod until it is aligned with the two end rods.
5.4.2. Extrapolation
The same procedure can be used to extend a straight line. Place two ranging rods at a
certain distance, e.g. 20m, along the line you would like to establish. Walk with the third
rod to the next point of the line, e.g. another 20m ahead. Sight the first two rods and shift
the third rod until all three rods are in a straight line. Mark this point with a peg and
repeat the same procedure every 20m until you have reached the end of your straight line.
Check the entire line again.
The solution is to find two locations on the hill which meet the following conditions:
╠ From point A, ranging rods placed at points B and C should be visible, and
╠ From point D, ranging rods set at points C and B must be visible.
From point A, set out points B and C in a straight line which is roughly heading towards
point D. Repeat the exercise from position D and ensure that point C is in line between
points D and B. Then go back to position A and move the ranging rod at point B so it is in
line between the point A and C. Repeat this procedure until A-B-C and D-C-B are straight
lines without the need for further adjustments.
Where the straights change directions, they are joined by circular curves to allow for
smooth vehicle operation at the design speed selected for the roadway. The design and
construction of curves is an important aspect of route surveying of roads.
A horizontal curve is provided at the point where the two straight lines intersect in the
horizontal plane. The horizontal curves are generally circular. Horizontal curves are of
four types namely:
Simple circular curve
Compound curve
Reverse curve and
Transition curve.
To avoid abrupt changes of direction in the road alignment, these straights are joined by
curves thus creating a more smooth curvature.
The distance between the intersection points can easily be measured and used as a first
estimate of the length of the road to be constructed.
Compound and reverse curves are unsuitable for modern high-speed highway, rapid transit, and
railroad traffic and should be avoided if possible. However, they are sometimes necessary in
mountainous terrain to avoid excessive grades or very deep cuts and fills.
a) Simple Curve
A simple circular curve consists of a single arc of a defined radius of the
circle.
The curve is tangential to two straight lines of the route
centerline.
A simple curve is a circular arc connecting two
tangents.
It is the type most often used.
b) Compound curve
Compound curve is composed of two or more circular arcs of different radii tangent
to each other, with their centers on the same side of the alignment.
c) Reverse Curve
A reverse curve consists of two circular arcs tangent to each
other, with their centers on opposite sides of the alignment.
The radius of the opposing curves may or may not equal.
d) Spiral curves
A transition curve is a horizontal curve of varying radius.
It provides a gradual change from the straight line to
the circular curve and again from the circular curve
to the straight line.
Transition curves are required on roads to
lessen the discomfort at sudden change in
curvature at the junction of a straight line
and a curve.
A spiral makes an excellent easement curve
because its radius decreases uniformly from infinity at
the tangent to that of the curve it meets.
( ∆2 )
(a) Tangent: T =Rx tan
∆
(b) Long chord: C=2 Rsin ( )
2
πR ∆
(c) Length of curve: L=
1800
(d) External Distance: E=Rx ¿
In the English system, staking is usually in full stations (100ft apart), although half-
stations (50ft apart) or even quarter stations (25ft apart), can be set depending on
conditions. In metric stationing, full stations are generally 1km apart, but stakes may be set
at 40, 30, 20, or even 10m apart, depending on conditions. Staking at the closer spacing is
usually done in urban situations, on sharp curves, or in rugged terrain, while the stakes are
placed farther apart in relatively flat or gently rolling rural areas.
After the tangents have been staked and stationed, the intersection angle ( ∅)is
observed at each PI and curves computed and staked. The station locations of points on
any curve are based upon the stationing of the curve’s PI. To compute the PC station,
tangent distance T is subtracted from the PI station, and to calculate the PT station, curve
length L is added to the PC station.
Equations:
Example: Assume that the deflection angle; ∆=450 00' 00 ¿ , the stationing 12+20.55, and
terrain conditions require the minimum radius permitted by the specifications
of, say, 2,864.79 ft (arc definition).
Calculate:
(a) The PC stationing.
(b) The PT stationing
(c) The external distance
(d) Middle ordinate distance
The stationing of the PT cannot be obtained by adding the tangent distance to the station of
the PI, although the location of the PT on the ground is determined by measuring the
tangent distance from the PI. Points representing the PC and PT must be carefully marked
and placed exactly on the tangent lines at the correct distance from the PI so other
computed values will fit their fixed positions on the ground.
If route surveys are originally staked as a series of tangents having continuous stationing,
as described above, then an adjustment has to be made at each PT after curves are
inserted. This is necessary because the length around the curve from PC to PT is shorter
than the distance along the tangents from the PC to the PI to the PT.
PI
PC PT
The intersection method is an effective method to set out a curve. It requires simple
equipment and is easily managed by the technical staff on site.
The figure below shows how a circular curve with a 30-metre radius is set out. Having
decided on the appropriate radius, set out an off-set line at the same distance from the
centre line as the length of the radius (off-set lines 1 and 2).
The point at which the two off-set lines intersect (PI) is the centre from which the circle is
defined. Having established the centre of the circle, any point along the curve can be set out
using a measuring tape or a string with the same length as the curve radius. Equally, once
the intersection point for the off-set lines have been established, it is possible to locate the
tangent points, i.e. where the curve starts and ends (points A and B). This is where the tape
or string is at right angles to the centre line.
Note : that this method should only be used for gentle curves with deflection angle less than
20°. For curves with deflection angle greater than 20° for tangents longer than
tabulated, another method as explained above should be used.
√
Y = √ ( R −X ) − R −
2
2
( )
If it is not possible to reach the other tangent satisfactorily, you will have to select another
starting point BC and repeat the setting out.
Procedure:
1.
Establish two points M and N on tangents which are inter-visible.
Find angles α ∧β
2.
3.
Measure the length MN accurately
Deflection angle ∅=α + β
4.
5.
Calculate the lengths MV and NV by solving the triangle MNV (using the Sine
Rule)
i.e.
MV MN NV
= =
sin β sin ( 180−∅ ) sin α
sin β
∴ MV =MN
sin ( 180−∅ )
sin α
∴ NV =MV
sin β
sin α
∴ NV =MN
sin ( 180−∅ )
6. Calculate the tangent lengths VT1 and VT2
∅
VT 1 =VT 2=R tan ()
2
7. Determine the lengths MT1 and NT2:
MT 1=VT 1 −MV
NT 2=VT 2−NV
8. Locate the points T1 by measuring a distance MT1 from M. Likewise locate point
T2.
9. Use the Quarter method to set out the curve.
3. Select another point N on the line VT2 produced beyond the obstruction T2.
4. Select another point Q on one side of the line MN, such that NQ and MQ are
perpendicular, and measure distances MQ and NQ. Determine the length MN using
Pythagoras theorem:
MN =√ (MQ)2 +( NQ )2
5. Determine the chainage of N:
Chainage of T 2 =Chainage of T 1 + Length of Curve
Chainage of N =Chainage of T 2+ MN −MT 2
Once R has been determined; the curve can be set out using any of the methods described
earlier.
Tangent Length of horizontal curves for various low volume road standard
Curve angle in degree
5 7 6 3 6 4 -- -- -- -- -- -- -- -- -- --
10 14 12 5 11 8 3 7 5 3 6 3 2 5 -- --
15 21 17 7 16 12 4 11 7 4 8 4 3 7 3 --
20 28 23 9 21 16 5 14 9 5 11 5 4 9 4 --
25 35 29 11 27 20 7 17 11 6 13 7 5 11 5 4
30 43 35 14 32 24 8 22 14 7 16 8 6 14 6 5
Surveying and Setting out | . 44
Ethiopian Roads Authority
March 18, 2016 Chancho Labour Based Technology Training Center
35 50 41 16 38 28 9 25 16 8 19 10 7 16 7 5
40 58 47 17 44 33 11 29 18 9 22 11 8 18 8 6
45 67 54 20 50 38 13 33 21 11 25 13 9 21 9 7
50 75 61 23 56 42 14 38 24 12 28 14 10 24 10 8
55 83 68 26 63 47 16 42 26 13 32 16 11 26 11 9
60 93 75 29 70 52 17 46 29 15 35 18 12 29 12 9
65 102 83 32 77 58 19 51 32 16 38 19 13 32 13 10
70 112 91 35 84 63 21 56 35 18 42 21 14 35 14 11
75 123 100 38 92 69 23 62 39 20 46 23 15 39 15 12
80 135 109 42 101 76 25 67 42 21 50 25 17 42 17 13
85 147 119 46 110 83 28 74 46 23 55 28 19 46 19 14
90 160 130 50 120 90 30 80 50 25 60 30 20 50 20 15
95 175 142 55 131 98 33 88 55 28 66 33 22 55 22 16
100 191 155 60 143 107 36 96 60 30 72 36 24 60 24 18
105 209 170 65 157 118 39 105 65 33 78 39 26 65 26 20
110 229 186 72 172 129 43 115 72 36 86 43 29 72 29 22
115 252 204 78 189 142 47 126 79 40 94 47 31 79 32 24
120 277 225 86 208 156 52 139 87 44 104 52 35 87 35 26
125 308 250 96 231 173 58 154 96 48 116 58 39 96 39 29
130 343 278 107 257 193 64 172 108 54 129 65 43 108 43 32
Tangent Length of horizontal curves for various low volume road standard
Curve angle in degree
For normal values of super elevation, side friction and radius, the following formula is
accepted:
V2
e +f =
127 R
e=Superelevation(m/m). This is taken as positive if the pavement falls towards
the center of the curve.
f =Coefficient of side friction. This is taken as positive if the frictional force on
the vehicle acts towards the center of the curve.
V =Speed of vehicle (km/hr )
R=Curve radius(m)
Where f is zero in the formula, all of the centripetal force is provided by the super
elevation. This condition can occur on large radius curves with positive super elevation or
for slow moving vehicles on curves of any radius. At low speeds, f can be negative, and the
curve is then over- super elevated for that speed. Curves are generally designed, however,
so that a positive f is required for the range of vehicle speeds likely occur.
On short length horizontal curves, the radius of the vehicle path can be considerably larger
than the centerline or edge line radius. In these cases, the curve radius “R” can be
arranged as follows:
V2
R=
127( e+ f )
It then follows that:
V2
Rmin =
127(e max + f max )
Maximum design values of side friction demand for cars on sealed pavements
Design Absolute maximum Desirable maximum
speed coefficient of side coefficient of side
(km/hr) friction friction
40 0.35 0.30
50 0.35 0.30
60 0.33 0.24
70 0.31 0.19
75 0.29 0.18
80 0.26 0.16
85 0.22 0.15
90 0.20 0.13
95 0.18 0.13
100 0.16 0.12
105 0.12 0.12
110 0.12 0.12
120 0.11 0.11
130 0.11 0.11
70 0.23 0.14
80 0.20 0.13
90 0.15 0.11
100 0.12 0.12
110 0.12 0.12
120 0.11 0.11
80 1250
90 1500
100 2000
110 3000
120 4000
130 5000
Minimum horizontal curve radii with adverse super elevation for urban roads,
temporary roads, and side tracks and temporary connections on rural roads or
motorways:
Curve deign speed Minimum Absolute maximum
(km/hr) radius (m) coefficient of side friction
40 85 0.18
50 130 0.18
60 200 0.17
70 295 0.16
80 505 0.13
90 910 0.10
100 1575 0.08
120 3780 0.06
130 4435 0.06
5.17. Curve widening
On smaller radius horizontal curves, traffic lanes may need to be widened in order to
maintain the lateral clearances that apply to vehicles on straight sections of road.
2
nL 0.1 V
+¿= + ¿
2 R √R
w
Where:
w +¿=Total wideningrequired ¿
n=No. of lanes
V =Design speed , km/hr
R=Radius of horizontal curve (m)
L=The longest length of the wheel base
2) Compute R x to fit requirements of the figure and make the tangent distances of the
two curves equal.
Chapter-
Six
6. Vertical Alignment
1.60
1.40 1.40
f(x) = 0.02 x + 0
1.20 R² = 1 1.20
1.00 1.00 1.00
0.80 0.80 0.80
0.60 0.60 0.60 0.60
0.40 0.40 0.40
0.20 0.20
0.00 0.00 0.00
0 10 20 30 40 50 60 70 80
7.1. Objectives
After you have learned this chapter trainees should able to:
Describe what is meant by vertical alignment.
Describe the different types of vertical alignment.
Establish how straight grade set out.
Understand Maximum length of steep grade
Describe what a sag curve is.
Know how to set out a sag curve.
Describe what is meant by crest ( or hump)
Know how to set out a sag curve.
7.2. General
The vertical alignment defines the exact level of the road and how the road is placed in
relation to the surrounding terrain. As with the horizontal alignment, most road works agencies
have developed appropriate standards for how the vertical alignment is designed.
Rules concerning the allowed curvature and gradients greatly influence the alignment of the road
and the amount of earthworks required. Still, the final quality of the road alignment is dependent
on a thorough field survey and having made a careful assessment of the various alternatives
available.
In flat or slightly rolling terrain, the design of the vertical
alignment is fairly straightforward. The main concern in this
type of terrain is to ensure that water is efficiently drained
away from the road and that potential floodwater remains
well below the road surface levels.
When the road passes through hilly or mountainous
terrain, the choice of alignment is more critical in terms of
arriving at a durable design, which stands up to t he
environment in which it needs to perform. In order to reduce
Surveying and Setting out | . 51
Ethiopian Roads Authority
March 18, 2016 Chancho Labour Based Technology Training Center
future maintenance works, it is important that the road follows the shape of the existing terrain,
avoiding steep gradients and large cuts and fills. Heavy earthworks will often have a detrimental
effect on the stability of slopes, and can easily trigger landslides.
Side cuts and fills are also more prone to erosion, with the eroded material often falling into
the drainage system or causing damage to surrounding areas. It is therefore always recommended
to minimize the earthworks by trying to follow the contours of the terrain.
This can often be done in the case of rural roads since the geometrical standards allow for
smaller radiuses on the horizontal alignment for such roads. The main purpose of rural roads is to
provide basic access. As compared with highways, for which design speeds are a more
important design parameter, the main emphasis of rural roads is to maintain all-weather
access throughout the year to the rural communities.
Maximum allowable gradients should not be exceeded except in very exceptional
circumstances. Roads with steep longitudinal gradients are exposed to increased erosion
from surface water. Experience clearly shows that roads with gradients above 8 percent are
difficult to maintain unless a durable pavement is installed on the road surface as well as in
the side drains.
Therefore, the option of alternative horizontal alignment should be explored to avoid
excessive amounts of earthworks and steep gradients. Although this may result in longer
alignments, such choices will most probably provide better design solutions as the risk of
major damages to the road during the rainy season is reduced.
Vertical alignment (referred to as, and geometrically represented by the grade line or
longitudinal section) consists of straight grades joined by vertical curves. The final design
location of the vertical alignment is principally the fit to the natural terrain but
consideration also needs to be given to the maximum allowable grades, the minimum
radius vertical curves, economical balancing of the earthwork, environmental impacts, ,
and co-ordination with the horizontal alignment.
The design criteria which dominate in deciding on the appropriate alignment vary with the
type of road being considered. The vertical alignment must be designed in conjunction with
the horizontal alignment and both coordinated in accordance with the principle stated.
Once the horizontal alignment of the road centerline has been established it is necessary to
set out the vertical alignment of this road centerline. This vertical alignment sets out the
level of the road and this level is called the longitudinal gradient.
Vertical alignment is set out the level of the road on the centerline.
Vertical alignment consists of grades joined by vertical curves.
As with the horizontal alignment, it is seldom possible to join two places with a
straight line from the lower place to the higher place.
The longitudinal gradient is very important and so setting out the correct levels of the road will
ensure that:
The road is not too steep
The road is not too flat
The road is smooth and does not have any dangerous crests or sags.
The road is protected from water and has adequate drainage.
When setting out the vertical alignment of the road there are three basic situations that you have
to take in to account.
Setting out “straight grades”.
Setting out “sags” (dips).
Setting out “crests” (or humps).
Several methods can be used for setting out the vertical alignment of rural roads. Similar to the
setting out of the horizontal alignment, the methods described in this section rely on the use of
string line levels and profile boards.
This method can be effectively used for setting out most levels on a rural road, including the
levels of excavation works and f ills, surface layers and drains.
Using profile boards and a line level is also a quick and effective method of establishing the
quantities works in the initial surveys during the planning stage. The basic principle is to place a
series of profile boards that show the exact level 1m above the completed construction levels.
The method is best described by imagining the excavation of a ditch from point A to point B at
the level of the dotted line as shown in the figure below.
To ensure a correct and uniform level of the ditch, ranging rods are placed at positions A
and B. Profile boards are mounted on the rods 1m above the level of the excavated ditch.
A third profile board with a fixed height is used for controlling earthworks levels between
the two profile boards. It is known as the travelling profile or traveller. A boning rod is
effectively used as a traveller. During excavation along the line from points A to B, the
traveller can be used to control that the correct levels have been achieved.
By placing the traveller in the sightline between A and B, it is easy to determine whether
the excavation has been carried out to correct levels.
When the top of the traveller is below the sight line between the two fixed profile boards,
the ditch has been excavated to a too low level. If the traveller sticks up above the sight line,
the ditch needs to be dug deeper.
To provide good guidance, it is useful to dig slots at regular intervals of 4 to 5m along the
sight line. With sufficient slots, the workers can start excavating the ditch by removing the
soils between the excavated slots. The traveller is then used once again to control that
the finished work is to the correct level and that there are no high or low spots.
A traveller is also useful for establishing levels beyond the sightline between to profile
boards, as shown in the figure below.
When the correct levels have been set out with profile boards, the traveller will give an
indication of the finished construction levels anywhere along the sight line.
This is useful for the site supervisor when setting out. The most frequent use of a traveller
is to mark levels on setting out pegs. In addition, it can be used for activities, such as:
To guide and check excavation below earthwork levels (e.g. for excavation works
during construction of foundations for structures),
To find out whether solid rock or large boulders are above or below the level of the
road before deciding on the final vertical alignment,
To estimate the amount of fill needed if the level of the road is "lifted", or when the
road crosses low areas - this will assist in estimating the quantities of work involved
and help decide on the optimal road levels.
To locate the end of drains and approaches, and to provide a quick check on
excavated or filled levels.
7.3. Gradients
A rate of inclination or declination of a slope.
The rate of rise or fall of the road surface along its length.
The road is never dead flat and will have rise and fall along the length.
Vertical difference
Gradient (%)=
Horizontal distance
x 100
Example: If the difference of levels is 0.5m between two profiles with a distance of 20m
between them, the gradient is___________________.
+5.5%
excavations. The exceptional gradient should not be provided in a length more than
100m, in any case.
Worthwhile design feature to avoid horizontal curves, at least sharp curves, at the
bottom of steep grades, where speeds may develop to the point of difficult vehicle
control.
Slope
Chainage Distance PCH PR Fill (-) Prop. Elev. Elev.
0+000 0 1.00 1.00 0.00 2% 0.00 0.00
0+010 10 1.00 1.20 -0.20 2% 0.20 0.00
0+020 20 1.00 0.80 0.20 2% 0.40 0.60
0+030 30 1.00 0.60 0.40 2% 0.60 1.00
0+040 40 1.00 1.40 -0.40 2% 0.80 0.40
0+050 50 1.00 1.20 -0.20 2% 1.00 0.80
0+060 60 1.00 1.60 -0.60 2% 1.20 0.60
0+070 70 1.00 1.00 0.00 2% 1.40 1.40
Note:
Cut (+), above the give and take line and Fill below the give and take line.
If PCH −PR is positive , it needs cut .
If PCH −PR is negative , it needs fill.
Whenever roads change gradient, a vertical curve is required to take traffic smoothly from
one gradient to the other. Roads made up of a series of straight lines (or tangents) are not
practical. To prevent abrupt changes in the vertical direction of moving vehicles, adjacent
segments of differing grade are connected by a curve. This curve in the vertical plane is
called vertical curve. Generally, the vertical curve is the arc curve of a parabola.
A vertical curve is a parabolic curve in a vertical plane which is used to connect two
numerically different grade lines. The two grade lines are called the back tangent and forward
tangent, respectively.
Surveying and Setting out | . 60
Ethiopian Roads Authority
March 18, 2016 Chancho Labour Based Technology Training Center
General guidelines
Provide a smooth grade line with gradual changes, consistent with the terrain and type of
the road.
Avoid hidden dips, that is, dips that the driver of a vehicle cannot see.
Whenever possible, flatten the grade near the top of the ascent (An upward slope) on
long, steep grades.
Mountainous
Lowland Rolling Hilly With reduction Without reduction
K=20 K=13 K=8 K=5 K=6
Mountainous
Lowland Rolling Hilly With reduction Without reduction
K=30 K=20 K=20 K=10 K=10
Example: Calculate
(a) Length of crest vertical curve
(b)Length of crest vertical curve
Upward gradient; g1=6 %
Downward gradient; g2=−4 %
Assume the road to be built on rolling terrain.
[Answer: (a) L=200m and (b) L=130m]
Procedure:
1. Measure the longitudinal slopes g1∧g2 of the two intersection gradients.
8. Measuring the vertical distance z down the ranging rod from the level of each
lowered profile board will determine the extent of earthwork (cut or fill) at every
distance x =10m (say).
Example: A grade g1=−3 %intersects grade g2=+ 6 % at a vertex whose station 2+240. An
equal-tangent parabolic curve 300m long has been selected to join the two tangents.
Compute the:
(a) Offset from the vertical tangent to make the curve smooth.
(b) Total cut or fill at each point.
Chapter-Seven
8. Cross sectional Alignment
8.1. Objectives
After you have
learned this element you should be able to:
Describe what it means by cross section
set out cross section for different terrain types
know elements of cross section
8.2. General
The cross section of a road is a vertical plane; at right angles to the road control
line, viewed in the direction of increasing chain age, showing the various elements that
make up the road’s structure. A cross section can show transverse detail from
boundary to boundary, detaining the various road components.
Cross section is set out the width of the road and position of the drains from the
centerline and set out levels. Set out necessary pegs perpendicular to the centerline of
the road. Normally, cross sections are set out at 20m intervals on straight sections of
the horizontal alignment and at about 10m interval through horizontal curves.
Once the position and level of the centre line has been established, the next step is
to install the entire road including its drainage system. This work is normally carried
out in two stages. A preliminary survey is done when preparing the detailed design
drawings, which form part of the bidding documents. This survey exercise is essential
for estimating the exact quantities of work.
A second surveying exercise is carried out at the time when civil works commence. At
this stage, the setting out of the road cross section provides the detailed directions for
civil works activities such as clearing, excavation and fills works, and drainage
construction. A similar exercise is carried out when works on a road section have been
completed, for the purpose of reporting and payment of the actual quantities of work
carried out.
Using the established centre line for the road, this setting out exercise will result in
details relating to:
the exact location and amount of excavation works,
detailed measurements of fills and embankments,
all road levels including shape of road camber,
location and shapes of the drainage system, including side and mitre drains,
cut-off drains, drifts and culverts, and
Exact location and dimensions of any other structures.
Stakes are place on the existing ground surface, one on each side of the centerline stake. These
stakes are placed where the edge of a cut or the toe of a fill will come when the earthwork is
completed. The centerline stake is in place and the stakes on each side are slope stakes. They are
place where the limits of the earthwork must be located. Each slope stake must be marked with
its horizontal distance to the right or left of the centerline and the vertical distance from the
ground at the stake down to the elevation of the bottom of a cut or up to the elevation of the top
of a fill, i.e., the elevation of a line known as the base. All stakes must be marked with the station
number.
Original ground
Cut
F ill
Ori ginal gr ound
Original ground
Mixed
Side slope improvements include measures to reduce the gradient of the embankment
or roadside slope adjacent to the carriageway and also the removal of any hazardous
objects that are located within the area.
Side slope improvement will reduce the likelihood of a vehicle rollover in run-off road/
loss of control crashes and may also reduce the severity of these types of crashes.
Generally flatter side slopes are safer. A side slope is considered to be traversable if an
errant vehicle can recover and return to the roadway while keeping all wheels in
contact with the ground.
Side slope is defined as the slope of the cut or fill expressed as the ratio of horizontal
distance to the vertical distance.
1 1
3 4
Example
1. A 2:1 side slope indicate that for every horizontal distance of 2m, the corresponding
vertical distance is 1m as indicated in the following diagram.
CL=Ce n te rlin e
Ele v , 2 2 5 . 5 5 0
Ele v , 2 0 0 . 5 5 0 50m
6m 6m
2) Set out the same distance on both of the two lines (L) starting from the intersection
point B, e.g. 3m, and fix pegs A and C.
3) Span a string line between points A and C and measure this length A to C.
4) Divide the length A to C by two and set peg D exactly in the middle of this length.
5) Establish the new line B to D with a string line and extend beyond peg D if
necessary.