The maintenance team conducted a campus visit of the Roots Millennium School Wahid Campus to address issues and improve facilities. They met with campus management to discuss key concerns. The team found that a newly constructed shed was leaking due to gaps in the roof. They also noted the campus only had one functioning water bore and recommended installing an emergency backup. In the science lab, they observed water damage due to improper roof sloping and lack of waterproofing. The team addressed minor electrical, plumbing, and water cooler issues on site.
The maintenance team conducted a campus visit of the Roots Millennium School Wahid Campus to address issues and improve facilities. They met with campus management to discuss key concerns. The team found that a newly constructed shed was leaking due to gaps in the roof. They also noted the campus only had one functioning water bore and recommended installing an emergency backup. In the science lab, they observed water damage due to improper roof sloping and lack of waterproofing. The team addressed minor electrical, plumbing, and water cooler issues on site.
The maintenance team conducted a campus visit of the Roots Millennium School Wahid Campus to address issues and improve facilities. They met with campus management to discuss key concerns. The team found that a newly constructed shed was leaking due to gaps in the roof. They also noted the campus only had one functioning water bore and recommended installing an emergency backup. In the science lab, they observed water damage due to improper roof sloping and lack of waterproofing. The team addressed minor electrical, plumbing, and water cooler issues on site.
Maintenance & Development Visit November 04, 2020 – Roots Millennium School
Wahid Campus F-10/2
Debriefing Notes Introduction: RMS Maintenance team conducted campus visit of the F-10 Future World Wahid Campus Branch on 4th November, 2020. The team comprised of Resident Engineer M. Ammad Hassan, Inspector Mr. Imitiaz and rest of the maintenance team including an electrician, a plumber and an AC mechanic. The team met the campus manager Mr. M. Iqbal as well as the campus supervisor to discuss issues. Objective of the Visit: The objective of the visit was to provide facilitation and support to the campus staff to maintain the campus operations as well as provide assistance and guidance regarding major and minor civil works, to listen to and inspect the issues highlighted by campus staff first and then inspect the building ourselves to identify the issues that need our utmost and urgent attention so that we can improve the campus experience for the students and staff. Observations, Remedies and Recommendations: The issues observed on campus site by the team and their recommendations are as follows:
1. Newly constructed shed in Block C is leaking on a few points according to the
campus supervisor. On the visual inspection of the roof and the shed, several gaps were seen on points of connections where two different sections of shed meet. The bill of the contractor has not been cleared so it is pertinent that this issue is taken up as soon as possible and the contractor is asked to resolve the issue before he is paid his dues. 2. The campus has 2 big water tanks but only one water bore to fill them. Previously there was another water bore as well but it was damaged some time ago and cannot be used. In case the one working water bore is damaged the whole campus would be deprived of water because the water tanks can’t be filled with the help of a rented water tanker as well. To avoid such inconveniences in the future, a 2 nd emergency water bore has to made on site. 3. In Block C science lab, the back wall and the left side walls have seepage and water damage issues. Upon inspection of the roof top it was observed that there was a rainwater drain right at the point where there was water damage on the back wall, the issue is most probably due to improper slope of the roof top and the rain water ponds near the edge of the roof near the rainwater drain. On the left side wall issue, it was observed that there was no waterproofing layer applied on the roof of left side room (1 st class room on right row of Block C) and clear spaces were seen on the roof and wall connection place. The water proofing layer should be applied on the critical sections as soon as possible. 4. Several minor electrical, plumbing and water cooler issue were inspected and rectified on site.