Download as docx, pdf, or txt
Download as docx, pdf, or txt
You are on page 1of 4

Brief facts relevant to modification Proposition advanced Findings

It was contended that the proceedings Whether the appellant on the basis of
The court did not find any merit in
before the Arbitrator were without Section 34 (2) (5) contend that the
the argument. As the plea was raised
jurisdiction for want of arbitration arbitration clause as mentioned in the
for the first time only in
agreement which cannot be cured by contract did not constitute arbitration
Miscellaneous First Appeal filed
appearance of the parties, even if there agreement and the award was a nullity.
under Section 37(1)(b) of the
was no protest or even if there was a Arbitration Act before the High
consent of Jala Nigam, since consent Court. Also, Jala Nigam, on the
cannot confer jurisdiction and, contrary, had consented to the Chief
therefore, the impugned Award was Engineer, acting as an Arbitrator. For
null and void. the aforestated reasons and
particularly in view of the fact that
there has been considerable delay in
the litigation no useful purpose would
be served by keeping the matter
pending in this Court awaiting the
decision of the Constitution Bench.
The Arbitrator has meticulously
examined the claims of the contractor
under each separate Heads. We do
not see any reason to interfere except
on the rates of interest and on the
quantum awarded. The court found
the Award of the Arbitrator to be fair
and equitable.
1. KRISHNA BHAGYA JALA NIGAM LTD. V. G. HRISHCHANDRA REDDY AND
ORS.
2. M.P. POWER GENERATION CO. LTD. AND ORS. V. ANSALDO ENERGIA SPA
AND ORS.

Brief facts relevant to modification Proposition advanced Findings

It was submitted that the award of the Whether an arbitral award can be set The court observed the rights given by
Arbitral Tribunal suffers from aside for being in conflict with the Section 19 of the Indian Contract Act
fundamental flaws and requires public policy of India under Section are given only to a party whose consent
interference. Also, it was submitted that 34 of the Arbitration Act and whether to the contract was, in fact, caused by
a fault with the finding of the Arbitral the court has the power to modify the the fraud or misrepresentation therefore
Tribunal was found that there was offending part of the judgment if it is it was observed that the evidence on the
misrepresentation on the part of the severable from the rest. relevant records were not furnished by
Board. It was also contended that the the Board to enable the Claimants to
award is perverse and is vitiated due to ascertain the actual facts and therefore
patent illegality. the court held that it cannot agree with
the submission of the appellant on the
point of misrepresentation as it finds no
good reason to differ from the view
taken by the Arbitral Tribunal.
The court observed that that the award
of the Arbitral Tribunal is open to
challenge when the arbitrators fail to
draw an inference which ought to be
drawn or if they had drawn an inference
which on the face of it is untenable
resulting in miscarriage of justice. It
also has the power to modify the
offending part of the award in case it is
severable from the rest. The court
upheld the award of the Arbitral
Tribunal with the modification that the
Claimants are not entitled for the
amounts involved in the Bank
Guarantees.
3. OIL AND NATURAL GAS CORPORATION LTD. V. WESTERN GECO
INTERNATIONAL LTD.

Brief facts relevant to modification Proposition advanced Findings

The Respondent made a statement Whether the court under Section 34 The court while taking into consideration
before the High Court waiving pendente of the Arbitration Act can modify/set the importance of judicial approach
lite interest as the award by the Arbitral aside an award of pendente lite and observed that the importance of Judicial
Tribunal for the pendente lite and future future interest by the Arbitral approach in judicial and quasi judicial
interest was not justified. Tribunal. determination lies in the fact so long as
the Court, Tribunal or the authority
exercising powers that affect the rights or
obligations of the parties before them
shows fidelity to judicial approach, they
cannot act in an arbitrary, capricious or
whimsical manner. Judicial approach in
that sense acts as a check against flaws
and faults that can render the decision of
a Court, Tribunal or Authority vulnerable
to challenge.
It was also held that the requirement of
application of mind on the part of the
adjudicatory authority is so deeply
embedded in our jurisprudence that it can
be described as a fundamental policy of
Indian law. This Court further observed
that the award of the Arbitral Tribunal is
open to challenge when the arbitrators
fail to draw an inference which ought to
be drawn or if they had drawn an
inference which on the face of it is
untenable resulting in miscarriage of
justice. The Court has the power to
modify the offending part of the award in
case it is severable from the rest
4. THE TATA HYDROELECTRIC POWER SUPPLY CO. LTD AND ORS. V. UNION
OF INDIA.

Brief facts relevant to modification Proposition advanced Findings

The respondents contended that the Whether the court has the power to The court observed that if there is no
dispute, since it related to a defective modify the award on the ground of an dispute as contemplated by Sub-
meter and consequent under error of law apparent on the face of the section (6) of Section 26 of the Act,
registering of electricity supplied, such Award under Section 34 of the there is nothing which prevents the
a dispute could be resolved only by the Arbitration Act. parties from referring their other
Electrical Inspector. A statutory disputes to arbitration for determining
arbitration provided in the aforesaid the liability of the consumer in such
sub-section ruled out any private cases.
arbitration and therefore the Umpire The court also noticed that the Umpire
had no jurisdiction to pass an award in took into account the readings of the
respect of such a dispute even if meters maintained by the Railways
referred to it by the parties. themselves, but did not give to the
appellant the full benefit thereof. It
appeared unfair and inequitable that
the Union Government should deny
paying the amount for the electricity
consumed as per their own record.
Therefore, the court held that the High
Court erred in setting aside the award
of the Umpire and also held that the
award is required to be modified to the
extent that interest be awarded at the
same rate, but with effect from the
date of the award.

You might also like