Royal Government of Bhutan Ministry of Works & Human Settlement
Royal Government of Bhutan Ministry of Works & Human Settlement
As per the letter from the site engineer, Chali Section vide letter no: DoR/CS/2019-2020/F-01/62
dated 24/03/2020, appraised RO team to inspect the bridge immediately.
There is numerous horizontal crack formed on both the abutments and deflection in left
abutment.
There is damage to the wing walls.
The gap has been formed between RCC slab and the abutment.
As a temporary solution, Autsho Sub- Division had initiated and sealed the cracks formed on the
abutments and repaired the damaged wing walls but we found it risky for the plying of the
vehicles.
Recommendation:
As a temporary measure we would like to propose to divert the traffic by construction of bypass
road and bailey bridge at upstream till the concrete solution found.