Professional Documents
Culture Documents
MOD 109 Process Piping B31-3
MOD 109 Process Piping B31-3
Basics of
ASME B31.3
Process Piping
To second half
The Faculty
Process Piping
THIS GUIDE IS EXCLUSIVELY PREPARED FOR TRAINING PURPOSE. RELEVANT SPECIFICATIONS, CODES
& SPECIAL REQUIREMENTS OF SPECIFIC PROJECT ARE TO BE REFERRED FOR MORE DETAILED
INFORMATION DURING CONSTRUCTION. EXAMPLES PROVIDED ARE ONLY FOR THE PURPOSE OF
ILLUSTRATION.
THE OBJECTIVE IS TO BE FAMILIAR WITH BASIC / FUNDAMENTAL CONCEPTS OF THE CODE.
1
10/13/2011
Program
• Historic Development
• Discussions
Failures
2
10/13/2011
Failures
Failures
3
10/13/2011
Failures
4 Feet
Failures
4
10/13/2011
Problem ?
Data Conclusion
Data Analysis
Collection wwwh
5
10/13/2011
Macro Cause
Test
Build
Design
Cause of Failures ?
Design Fabrication
(Welding..) Examination
Material
Testing
Relief CERTIFY
Inspection
6
10/13/2011
History of Development
ASA B31.3-1962
Code Case 49
ASA B31.3-1966
Q: Is there a code section of ASA 31 by which chemical Process
Industry piping may be designed, fabricated, inspected and
tested?
History of Development
1976 - ANSI B31.3 Chemical & Refinery Piping 1978 Committee B31 was re-
organized as ASME
Pressure Piping,
accredited by ANSI.
1981 – B31.10 (Cryogenic Piping) was withdrawn and included into B31.3
2002 , 2004, 2006, 2008, 2010 - ASME B 31.3 (scheduled to 2012 issue)
7
10/13/2011
Definitions:
Application !!!
8
10/13/2011
UTS
SMYS
UTS
60 000 PSI
35 000 PSI Test Pr = 1.5 x 20000 = 30000 (30/35 = 0.857 = 90% app)
9
10/13/2011
Allowable stress
B 31.3
Allowable
stress upto B 31.1
400ºF Allowable stress
20,000 PSI upto 650ºF
F.S 3 on UTS 15,000 PSI
F.S = 4 on UTS
B31.1 Vs B31.3
-20
Temp
to 150 200 250 300 400 500 600 650 700 750 800 850 900 950 1000 1050 1100
F
100
BPVC 17.1 17.1 17.1 17.1 17.1 17.1 17.1 17.1 17.1 15.6 13 10.8 8.7 5.9 4 2.5
B31.3 20 20 20 20 20 20 18.9 17.3 17 16.5 13 10.8 8.7 6.5 4.5 2.5 1.6 1
10
10/13/2011
B31 Codes
11
10/13/2011
Failure Theory
or thin
in which stress concentration is negligible.
Other differences are:
Thin Thick
Limiting proportions t < Do/6 t ≥ Do/6 or
By B31.3 P/SE > 0.385
Failure Theory
Failure Theory
Example:
Pipe OD= 30”; SA 106 Gr B Pipe
Pressure = 600 psi
Thickness = 0.5”
12
10/13/2011
Failure Theory
Failure Theory
Other Factors:
Primary Stress:
Design Pressure
Secondary Stress:
Thermal Expansion
Fatigue
Wind, Seismic Loads etc
13
10/13/2011
Conclusion:
Cir seam weld is TWICE stronger than
Long seam
or
Thickness Calculation
P=Pressure
S=Allowable stress
14
10/13/2011
Interpretations:
Code Cases:
ASME B31.3:2010
15
10/13/2011
SCOPE
SCOPE EXCLUSION
16
10/13/2011
The Give up
Fluid service-300.2:
Term concerning application of piping system, considering the
combination of
fluid properties, operating conditions, and other factors that
establish the basis for design of the piping system. (App M.)
17
10/13/2011
Category D
[UTILITY]
Lowest cost
Usually - not fire resistant
- not blow out resistant
Category M
[LETHAL]
High cost
Usually - fire resistant
- blow out resistant
18
10/13/2011
Category K
(b) High Pressure (K) Fluid Service: a fluid service for which
the owner specifies the use of Chapter IX for piping design
and construction; see also para. K300
[HIGH PRESSURE]
High cost
Usually - fire resistant
- blow out resistant
19
10/13/2011
DRAWING PROCESS
DESIGN
20
10/13/2011
DESIGN
Material
A component ordinarily is not marked to indicate the edition date of the standard to which it is manufactured. It is
therefore possible that an item taken from inventory was produced in accordance with a superseded edition, or an
edition not yet approved by the Code (because it is of later date than that listed and is in use). If compliance with a
specific edition is a requirement of the intended service, it usually will be necessary to state the specific requirement in
the purchase specification and to maintain identification of the component until it is put in service.
21
10/13/2011
Fatigue !!!
Fluid Service
22
10/13/2011
Fabrication (Welding)
Fabrication, Assembly, and Erection
328.2 Welding Qualifications
328.2.1 Qualification Requirements
(a) Qualification of the welding procedures to be used and of the performance
of welders and welding operators shall conform to the requirements of the
BPV Code, Section IX except as modified herein.
(b) Where the base metal will not withstand the 180 deg guided bend
required by Section IX, a qualifying welded specimen is required to
undergo the same degree of bending as the base metal, within 5
deg.
(c) The requirements for preheating in para. 330 and for heat treatment in
para. 331, as well as such requirements in the engineering design, shall
apply in qualifying welding procedures.
(d) When impact testing is required by the Code or the engineering design,
those requirements shall be met in qualifying welding procedures.
……………..>>
PQRs
Pre Heat
PWHT
Bending / Forming
……….>> etc
23
10/13/2011
The Inspection
Inspection, Examination and Testing
340: Inspection applies to functions performed for the owner by the owner’s
Inspector or the Inspector’s delegates.
Inspector shall have not less than 10 years experience in the design, fabrication,
or inspection of industrial pressure piping. Each 20% of satisfactorily completed
work toward an engineering degree recognized by the Accreditation Board for
Engineering and Technology (Three Park Avenue, New York, NY 10016) shall be
considered equivalent to 1 year of experience, up to 5 years total.
(a) two additional samples of the same kind (if welded joints, by the same welder,)
shall be given the same type of examination
(b) if the items examined as required by (a) above are acceptable, the defective item
shall be repaired or replaced and reexamined as specified in para. 341.3.3, and all
items represented by these two additional samples shall be accepted, but
(c) if any of the items examined as required by (a) above reveals a defect, two further
samples of the same kind shall be examined for each defective item found by that
sampling
(d) if all the items examined as required by (c) above are acceptable, the defective
item(s) shall be repaired or replaced and reexamined as specified in para. 341.3.3,
and all items represented by the additional sampling shall be accepted, but
(e) if any of the items examined as required by (c) above reveals a defect, all items
represented by the progressive sampling shall be either (1) repaired or replaced
and reexamined as required, or (2) fully examined and repaired or replaced as
necessary, and reexamined as necessary to meet the requirements of this Code
24
10/13/2011
Examination Types
REPAIR in SPOT RT
Repair
A A
Repair
Repair
Rectify the
OR repair – all
welds
A R R accepted
R
A A A A
A A
25
10/13/2011
Hydro test
Tp=1.5 Dp x (ST/S)
For 950 F design Tp=1.5 x 600 (20000/4500) = 4000 psi (4.2 times)
For 1000 F design Tp=1.5 x 600 (20000/2500) = 7200 psi (7.5 times)
Documentation
26
10/13/2011
Documentation
Interpretation
• Interpretation: 20-20
27