STEVE TSHWETE LOCAL MUNICIPALITY

CONSTRUCTION OF KWAZAMOKUHLE SWITCHING


STATION W3: WIP

PROGRESS REPORT

08 October 2020

Prepared for: Prepared by:

Water and Waste Water Technologies


Steve Tshwete Local Municipality
The Willovale Office
PO Box 14
Park, Suite 2, Pretoria
Middelburg
2076
1050
1. PROJECT DESCRIPTION
 
Project Name  MV KWAZAMOKUHLE SWITCHING STATION 
W3:WIP 
Engineering Consultants  Hoxana Consulting Engineers 
 
Contractor  Water and Waste Water Technology 

Official Starting Date as per the Contract  27th August 2020 
Construction Start Date  24 September 2020 
Completion Date.  30th  of June 2021 
Revised Completion Date  N/A 
Original Contract Amount (Contractor)  R 8,816,912.00 
Variation Order (s)  R0.00 
Revised Contract Amount  R 8,816,912.00 
Expenditure to Date  R 1,687,715.73 (25%) 
Progress to Date  10% 
 

2. SCOPE OF WORK
 
Water and Waste Water Technology was appointed on the 20th of August 2020 for the 
construction of Kwazamokuhle Switching Station: 
1) Civil Works 
I. Construction of 2.4m concrete walling 
II. Construction of switching station building 
III. Connect water and sewer to the switching station 
2) Electrical Works 
I. Purchase and install switchgear panel and control panels 
II. Purchase and install auxiliary transformer 
III. Electrical wiring for the switching station 
 
 

3. PROGRESS REPORT
 
 
3.1 MATERIALS 
 Purchasing of all foundation materials and brickwork materials up to wall plate level. 
 Purchasing of palisade concrete walling. 
 Purchase of G5 material 
 Hiring of excavator 
 
3.2 PROGRESS ON SITE 
 Preparation of site and site clearance.  
 Site establishment with storage container. 
 started trenching for 120m2 ×750 deep as per the drawings. 
 Backfilling with layers of 150 @95% as per the drawings . 
 Backfilling with G5 materials 150 layer as per the drawings. 
 
3.3 CHALLENGES 
 Due to weather conditions we are waiting for final compactions then instructions to proceed 
with foundation trenches from the engineer photos will follow 
 The councilor is imposing some of the sub‐contractors that we have to work with, their rates 
are unreasonable, some of these sub‐contractors are incapable and unqualified to carry out 
the works. 
 

 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 

 
 
 
 
 
 
APPENDIX: SITE PHOTOGRAPHS
 

 
 
Fig 1: Site clearance 
 

 
 
Fig 2: Site camp 
 
 
 
Fig 3: Cement on site 
 

 
 
Fig 4: Bricks on site 
 
 
 
Fig 6: G5 Material compaction 
 
 
 
Fig 7: Surveyor on site 
 
 